Hamilton County Facilities

Fire Alarm & Sprinkler Testing

Partner: ThermalTech

Status: Active

Status:

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/29/15 – Two day prebids complete. Add01 is issued. Add02 will be issued tomorrow. Bid opening on schedule for August 27.

08/27/15 – Bid opening scheduled for today. 2 Addendums issued total on this project.

09/23/15 – Tony selected SA Comunale form base bid initial term as the recommended bidder for this project. ThermalTech to author the contract for Facilities.

10/28/15 – Contracts approved. Project can be archived.