Hamilton County Facilities

250 – General Health Door Renovation

Project Lead: GBBN
07/28/17 – Hamilton County requested SOSS to investigate adding a new door and new Office Wall.
07/31/17 – GBBN visited the site and met with General Health to discuss scope of work. A hand drawn sketch was presented to GBBN. GBBN photographed and field verified the site. GBBN and TEI verified the proposed scope of work would require permitting.
08/03/17 – GBBN authored and issued SOSS for review.
08/21/17 – County requested a revised SOSS, based on a reduced scope to be compliant with no permitting required. A simple opening through the existing gypsum board partition is requested. TEI confirmed no added load to electrical service means no IBI permit required.
08/23/17 – Facilities clarifies the final scope of the project to GBBN and TEI.
08/25/17 – GBBN authors and delivers revised SOSS to Facilities.
09/18/17 – GBBN clarifies scope with Facilities to use hollow metal door frame in new opening for durability. Double studs and header will be used in expanded opening rough framing for frame installation and anchorage.
09/22/17 – GBBN confirms to Facilities the drawings are completed to the point of final field verification and owner review of drawings.
10/02/17 – Facilities requests final drawings from GBBN for issuance to Trades. GBBN sends drawings with inquiry about final Owner review meeting.