Hamilton County Facilities

Hillcrest Training School Cottage Slab Review

Project complete and closed out.
Past Comments

L&T submitted closeout paper work. THP & L&T revising warranty language in submitted warranties; all other paper work acceptable.
L& T completing final project closeout paper work. (2/24/10)
L&T requested a project closeout, so additional grading work will not be accepted.(2/24/10)
All punch list work including additional interior repointing at interior/exterior wall joints reported to be complete. THP to review next week. (2/24/10)
All work complete except punch list. Punch list published and all work except grading except grading expected to be complete by February 19.
Contract was coordinated with the prosecutor’s office and final copies were sent to Hamilton County for review by the commissioners on September 14.
August 17 THP recommended Langenheim.
Bids received August 14 and Langenheim & Thomson was low bidder within the project budget.
Project in bid process with pre-bid meeting completed on July 28, 2009. Bid due August 11th.
Design development documents anticipated to County 6/26.
Partial front end specification sent to County for review on 6/22.
Kick off meeting completed and field survey’s complete.

Scroll to Top