JC RTU Fall Protection

Partner Lead: THP

08/27/12 – County requested an SOSS for the design services for RTU fall protection.
09/12/12 – THP had a meeting with Rodney. After meeting Rodney not sure of specific needs for fall protection. Rodney plans to review internally.

09/25/12 – County update: HC and CMI met to review equipment and operational access. CMI will review the condition and make recommendation; but currently a direction has not been determined. THP will be notified once a direction from HC and CMI has been determined.

03/12/13 – THP received and reviewed safety report recommending a platform without a ladder to access the RTU. Does the County want THP to submit a SOSS?

10/31/13 – Project on hold. Hamilton County reviewing need and scope.