Hamilton County Facilities

JUSTICE CENTER Mobile Command Center

Partner Lead: TEI

09/28/16 – Kickoff discussion about electrical connections for mobile command center. They need a 50A double pole breaker for this mobile command center.

10/25/16 – TE met with trades, documents routing and connections. Project submitted to IBI for permitting.

01/25/17 – Installation complete. All inspections are complete. Project can be closed out and archived.