Hamilton County Facilities

800 – Juvenile Court and Domestic Court Relocation Study

06/06/17 – GBBN contacted by Facilities about authoring SOSS.
06/07/17 – Hamilton County Facilities requests some modifications to the SOSS including using #F052.
06/08/17 – Revised SOSS submitted to Facilities.
06/27/17 – Facilities sends approved SOSS to GBBN.
06/28/17 – Facilities and GBBN begin discussions for a Kick-off Meeting date.
08/02/17 – Meeting with Facilities and GBBN to discuss scope and approach for moving ahead with project.
08/05/17 – GBBN holds internal review meeting before meeting for presentation to Owner.
08/17/17 – Meetings at 800 Broadway with both Juvenile Court and Domestic Relations Court. Tour of Domestic Court Offices was conducted after meeting. Domestic Relations presented Programming List for GBBN’s use.
08/25/17 – GBBN internally produces meeting minutes and circulates for review.
09/22/17 – GBBN holds internal review meeting before meeting for presentation to Owner.
10/10/17 – Final presentation review set distributed in office for associated personnel to review and comment.
10/18/17 – GBBN communicates with Facilities and Administration related to timing for meeting for final presentation. A final Onwer review draft is sent to the Owner. Ralph Linne responded with corrected financial information.
10/20/17 – Corrected draft with updated financial information is sent by GBBN to all parties involved.