Hamilton County Facilities

MRDD – Franks Center Renovations

03/31/08 – Bids due 4/11/08

03/31/08 – Pre-bid meeting

03/21/08 – Addendum 1 issued

03/08/08 – Issued for bid

02/15/08 – CRA Add Service CR-084a $6,999.00 signed by MRDD on 2/12/08, forwarded to Bert Watts.

01/11/08 – SOCC CR-084a modified per WM email 1/11/08

12/20/07 – CRA add service requested by MT 12/20/07

11/09/07 – SD review meeting was held at Franks Adult Center. CRA presented Schematic Design drawings and color and finishes samples.

11/02/07 – Next review meeting is scheduled for 11/08/07 at Franks Adult Center at 3pm.

10/24/07 – Meeting was held at Franks Adult Center to discuss the scope of the project and verify existing conditions.

09/24/07 – CRA received signed and approved SOSS.

08/30/07 – CRA submitted the SOSS.