02/14/08 – Punch list submitted.
02/13/08 – CRA sent additional service signed 2/13/08 to Bert
02/13/08 – TEI attended the const mtg today for MRDD. EDI is almost complete. Additional concrete will be installed around the new air handlers.
12/07/07 – CRA job meeting held on 12/05/07
11/14/07 – CRA received and approved shop drawings and substitution request for automatic door operators.
11/10/07 – The construction has commenced.
11/01/07 – Pre-construction meeting was held. See Meeting Minutes below.
10/26/07 – GC/EC submitted revised insurance certificate. GC/EC contracts have been approved approved. HVAC contract is still pending.
09/28/07 – Awaiting GC/EC to submit revised insurance certificate for final executed Contract.
08/16/07 – Contracts submitted 07/31, CRA received comments, re-issued 08/16.
08/02/07 – C+RA and TE submitted the Building Permit Application to the Village of Evendale Building Department.
06/25/07 – Addendum issued. Bids are due 07/02/07.
06/15/07 – A pre-bid meeting was held on location yesterday, June 14, 2007. This project is set to open for bid on June 26, 2007.
06/08/07 – This project has been sent to Cole & Russell for review. TE is awaiting comments back.
04/27/04 – Final review meeting is scheduled for next week.
04/20/07 – Updated drawings are being sent out today, April 20 2007.
04/13/07 – Project is progressing as expected.
04/06/07 – Preliminary set of drawings were sent to Architect today, April 6, 2007. Awaiting review comments.
03/30/07 – Final field work has been assessed. TE working on design.
03/23/07 – Project is progressing as expected.
03/20/07 – Kickoff meeting complete. Check CRA for updates.