Hamilton County Facilities

Parkhaus Garage Assessment

September 7, 2011 THP sent assessment report to County

THP anticipates completing the report by August 5.

July 25, 2011 THP completed all field survey.

Assessment placed on hold until Ram completes stair tower work.

THP anticipates field work in next two weeks and report to be complete by June 30.

April 26, 2011 SOSS approved.

County reviewing SOSS.

April 18, 2011 THP provided requested SOSS to complete garage assessment for the Parkha