Hamilton County Facilities

2014 GENERAL SERVICES GBBN

09/17/13 – Bert Watts requests Partners to submit SOSS for 2014 General Services.

09/18/13 – SOSS submitted to Bert Watts.

01/30/14 – GBBN attends monthly Partnering Meeting.

02/27/14 – GBBN attends monthly Partnering Meeting.

02/24/14 – Bert Watts indicates the JCC Mural project services will be billed to the General Services.

02/25/14 – GBBN and TEI meet with Bert Watts to discuss moving the Recorder’s File Storage to the CAB 10th Floor CLEAR area. Bert requests the services for the Schematic Design and Opinion of Probable Costs be billed to the General Services.

03/18/14 – GBBN delivers estimating binders to Facilities after review finds all printing and assembly of binders to be in order.

04/24/14 – GBBN attends monthly Partnering Meeting.

03/27/14 – GBBN gets new Partner ID Badge at Sheriff’s Office in Courthouse to replace lost badge.

04/24/14 – GBBN attends monthly Partnering Meeting.

05/29/14 – GBBN attends monthly Partnering Meeting.

06/23/14 – GBBN completes the CAB 8th Floor As-Built drawing layering standard review and reconciliation.

06/26/14 – GBBN attends monthly Partnering Meeting.

07/28/14- Facilites sends Master Service Agreement Admendment to GBBN for signatures.

07/28/14- Facilities sends three building (230 WHT Law Center/CAB Basement/A&D) existing As-Built drawings to GBBN for layering verification review.

07/31/14- GBBN attends monthly Partnering Meeting and delivers signed Master Service Agreement Admendment to Facilities.

09/02/14- Bert Watts contacts GBBN about a project to renovate an existing space in 800 Broadway, 6th Floor.

09/05/14- Sketch sent from Bert Watts about pop-up project at 800 Broadway.

09/15/14- GBBN attends kick-off meeting with Bert Watts, JFS and Juvenile Court.

09/16/14- ThermalTech sends the MEP Estimating Documents to GBBN. GBBN sends combined project Estimate to Bert Watts for review.

09/30/14- GBBN receives email invitation to visit Patrol Headquarters to investigate addition for a Kennel and to investigate an operable partition renovation to the Comm. Center.

10/16/14- GBBN receives email with Operable Partition quote, developed by OKI (7/7/14), from Bert Watts via John Nester.

10/07/14- GBBN receives email from Bert Watts about estimate project requests created in Archibus for estimating.

10/09/14- GBBN sends first iteration of Patrol Headquarters Kennel addition floor plan to Facilities and TEI for review.

10/15/14- GBBN completes estimate for Patrol Headquarters Kennel addition.

10/16/14- GBBN receives comments and suggested floor plan revisions for the Patrol Headquarters Kennel estimate.

10/17/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by email off the link from the website.

10/20/14- GBBN sends updated Patrol Headquarters Kennel floor plan to TEI and Facilities for review and estimating.

10/20/14- GBBN sends deflection criteria information to THP to review for roof joist loading. Structural drawings received from TEI are forwarded to THP for investigation.

10/24/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by telephone. Voice mail was left.

10/27/14- GBBN receives call from Valcom Enterprises related to inquiry about floor mounted operable partition system. Telephone memo forwarded from GBBN to Facilities and THP.

10/29/14- Bert Watts forwards final design criteria on Comm. Center operable partition for estimating (three separate estimating options) purposes. GBBN calls Valcom Enterprises for quotation on actual floor mounted operable partition.

10/30/14 – GBBN attends monthly partnering meeting. Next Meeting scheduled for January 2015 if GBBN awarded contract extension.