10/25/16 – TEI issues SOSS for project to provide surge protection for the fire alarm system. Project pending approved SOSS and PO.
01/25/17 – Project pending approval of SOSS and PO.
02/22/17 – Project pending approval of SOSS and PO.
03/22/17 – Project pending approval of SOSS and PO.
04/26/17 – Project pending approval of SOSS and PO.
05/22/17 – Project pending approval of SOSS and PO.
06/27/17 – TEI receives signed SOSS and PO. Drawings issued to Bill Scholl and Tony Matre for review and comments. Package to be issued (small projects bid) upon receipt of comments.
07/25/17 – Pending review comments from Bill Scholl and Tony Matre.
08/28/17 – AKM asks TEI if this can wait and be installed as part of the fire alarm system replacement project. TEI spoke with Bill S and Bill is concerned with all of the electrical storms that happen at the facility that there would be a surge that could be catastrophic to the existing system if the protection was not put in place now. TEI and AKM have a discussion, and AKM said to get pricing on drawings that were developed and he will evaluate pricing and issue contract for work if he has $$ in his budget at towards the end of the year.
09/26/17 – Project released for bids from Cincy Electrical, DK and Phasor. Bids due back the ThermalTech by 9/29/17 and noon.
10/25/17 – AKM tells TEI that he is going to have DK install the system for their bid of $1,591 for the surge protection. Install to proceed upon approval of submittals.
11/29/17 – DK receives PO for the work and is instructed to schedule work with Building Manager.
01/22/18 – DK has completed construction. ThermalTech requested closeout document from contractor.
02/20/18 – Closeout pending receipt of closeout documents from DK.
03/27/18 – Closeout pending receipt of closeout documents from DK.
4/25/18 – Closeout pending receipt of closeout documents from DK.