Hamilton County Facilities

2020-A

2020 Auburn
Archive

2020 – WiFi System Study

PM = John Nester – Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO.
01/29/25 – TEI and HCFD to conduct study walk thru of building in next 2 weeks.
02/26/25 – TEI requests time with HCFD to perform study walk thru
03/26/25 – TEI and HCFD walk the building to locate/document the existing WiFi system devices. Report is in progress.
04/23/25 – TEI to have draft report for review by HCFD/2020 staff by mid May.
05/28/25 – TEI has a draft review meeting with the HCFD/2020 staff. TEI finalizing a few modifications to the draft and will distribute to team for review/comments.
08/27/25 – DEG sends final report with HCJC comments included.
10/29/25 – DEG addresses C Walsh questions via email
12/10/25 – No updates this month

2020 – WiFi System Study Read More »

2020 – Sewer Deduct Meter

PM: Tony Matre, Terry Cannon
05/28/24 – Cooling tower makeup water reviewed and approved by GCWW and should be on bill next billing cycle.
06/27/24 – Irrigation sewer deduct ready to review by County. It’s ready to send to GCWW.
07/24/24 – Second deduct meter sent to County for review. TTC followed up by email.
08/28/24 – Received Tony signatures on final paperwork, ready for submission to GCWW.
09/24/24 – Second application has been given to GCWW and MSD, they confirm they have it but it has not been reviewed or processed yet.
10/30/24 – Additional data requested and sent last week to MSD.
12/12/24 – MSD and GCWW have all the data they need, we are waiting on their approved and meter review. The first meter has been on the bills since June, and we are getting a deduct for it. Meter number S03787, so far, they have saved a little over $1,000 in sewer charges in the first few months with the meter online.
01/02/25 – We have the meter and the transmitter has been located. We are moving towards installation in the near future.
01/27/25 – HC has installed the meter and transmitter. ThermalTech is coordinating the final inspection with MSD.
02/26/25 – Meter has been installed and approved. We will check water bills to see when it shows up on the GCWW bill.
03/25/25 – Sewer deduct meter not on water bill yet.
04/23/25 – March water bill has both sewer deduct meters logged on the bill but the irrigation meter has no usage usage yet. This project is ready to archive.
05/28/25 – Archived.

2020 – Sewer Deduct Meter Read More »

2020 – Slab and Masonry Repairs (F001)

PM: Rycca Thacker, Paul Bellman
02/01/24 – Hamilton County requested slab project be rebid based on previous project.
02/12/24 – THP published review documents to the County.
02/16/24 – Hamilton County provided review comments to the documents.
02/16/24 – THP published bid documents to Hamilton County.
02/20/24 – Hamilton County advertised project for bid.
02/27/24 – Prebid meeting occurred.
03/11/24 – Addendum 1 issued to Purchasing.
03/14/24 – Addendum 2 issued to Purchasing.
03/15/24 -Addendum 3 issued to Purchasing.
03/28/24 – Bids due date April 8, 2024.
04/12/24 – Reviewed Bid with Browning Chapman.
04/19/24 – THP issued Bid Summary Letter to Hamilton County.
05/02/24 – Hamiliton County issued Contract Documents to Browning Chapman.
05/10/24 – Browning Chapman returned signed documents.
05/30/24 – Hamilton County Board review on 06/06/24.
07/19/24 – Browning Chapman working on pricing estimates for floor finishes, submittals, and background checks.
07/23/24 – Hamilton County requested to schedule a kick-off meeting.
08/15/24 – Preconstruction meeting completed.
08/19/24 – THP issued meeting minutes.
08/28/24 – Browning Chapman issued revised flooring options estimates. Browning Chapman’s submittals approved. Project to be scheduled.
09/25/24 – Browning Chapman submitted new flooring proposal for polished concrete. Approved and BC will need to develop Change Order.
10/28/24 – THP returned submittals to Browning Chapman.
10/31/24 – Final Pre-Construction meeting scheduled for Friday 11/01/2024.
11/01/24 – Kick-off meeting.
11/04/24 – HC sent Notice to Proceed.
11/07/24 – Progress Construction meeting.
11/14/24 – Progress Construction meeting.
11/20/24 – Progress Construction meeting.
11/20/24 – THP Signed Pay App #1 and sent to HC.
11/27/24 – Progress Construction meeting.
12/05/24 – Progress Construction meeting.
12/10/24 – THP signed Change Order #1.
12/12/24 – Progress Construction meeting.
12/13/24 – THP Signed Pay App #2 and sent to HC.
01/09/25 – Progress Construction meeting.
01/16/25 – Progress Construction meeting.
01/23/25 – Progress Construction meeting.
01/23/25 – THP Signed Pay App #3 and sent to HC.
01/30/25 – Progress Construction meeting.
02/13/25 – Progress Construction meeting.
02/20/25 – Punchlist Walkthrough.
02/26/25 – Browning Chapman finalizing punch list items. Final walkthrough scheduled 03/06/25.
03/06/25 – Final Walkthrough and signoff of completed items.
03/07/25 – THP signed Pay App #4 and sent to HC.
03/26/25 – Email sent to Browning Chapman requesting Closeout documents. BC indicated Closeouts will be ready for review on 3/28/25.
04/11/25 – BC sent closeout documents to THP for review.
04/18/25 – THP sent reviewed closeout documents and comments back to BC.
04/22/25 – THP sent HC signed Pay App #5 – Final Retainage.
04/24/25 – BC sent HC Final Closeout Documents.
05/29/25 – Can THP archive project?
06/25/25 – Project Archived.

2020 – Slab and Masonry Repairs (F001) Read More »

2020 – City Façade Monitoring 2023 (F086)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/06/23 – Rappelling of façades completed.
09/28/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update
08/29/24 – No repairs needed final report due next June.

2020 – City Façade Monitoring 2023 (F086) Read More »

2020 – Breakroom to Locker Room Renovation

PM: Sam Hofmann / County: John Nester

02/22/23 – SOSS received. Preliminary plan sent to John. Scope changed by new personnel.

03/30/23 – Kickoff held on site. Estimate in progress.

04/27/23 – Plans complete. Estimate to be complete in near future.

05/25/23 – Plans and estimate have been uploaded to archibus.

06/29/23 – No Update

07/27/23 – No Update

2020 – Breakroom to Locker Room Renovation Read More »

2020 – Security Camera System Upgrade

PM = Matt Butz, Mike Barth

09/26/22 – HCFD requests SOSS for the Project.  TEI Submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing in design.  Will schedule a 75% design review with HCFD and 2020 staff after the holiday break.
01/25/23 – TEI, HCFD and HCJC meet to review project design.   TEI schedules working “Mock up” with Vicon rep on 02/01/23 so the staff at 2020 can see the views that will be provided with new system.   Design will be finalized after Mock up meeting.
02/23/23 – TEI, HCFD and HCJC meet with rep for mock up.  Camera types selected.  TEI has documents 90+% complete for issuance.  All new camera locations have the view area inserted on plans.  Upon final review with HCJC, Project will be issued for ITB.
03/29/23 – Project will be sent to purchasing on 03/31/23 for a 04/03/23 Out to bid issuance.  Prebid meeting is scheduled for 04/20/23 at 2:00 PM.  Bids will be due on 05/04/23.
04/27/23 – Project in bidding phase.  Prebid meeting was 04/20/23.   Well attended prebid.   Addendum 1 already issued.   Addendum 2 to be issued 04/28/23.
05/23/23 – Bids received for project.  (2) bids, DK and Glenwood.  Glenwood Electric Apparent low bidder.  TEI vets the bid, and recommends contract with Glenwood.  Project is in contract approval phase.  Upon contract approval and PO issuance, the project construction can commence.
06/28/23 – Project was approved at the BOCC meeting on June 15.  Glenwood recieves PO and is now working on submittals for approval.  Upon submittal approval, construction schedule will be developed and mobilization will be scheduled pending product procurement.
07/26/23 – Project construction kickoff meeting to be scheduled week of 8/7.  Construction schedule to be issued from Glenwood at kickoff meeting.
08/24/23 – Glenwood electric scheduled to mobilize to project site on 8/28/23.  Construction to commence.
09/26/23 – Construction commenced on project.   Multiple meetings with IT to discuss the network configuration.   Glenwood continuing installation of backbone of system.
10/26/23 – Construction under way.   4th Floor New Cameras are installed, as well as POD 203.  Juv Crt IT has not confirmed Network architecture.  Meeting schedule for 10/30/23 with all parties to finalize decision.
12/06/23 – Construction ongoing.  Network architecture finalized and programmed.  Glenwood has been working in non-housing areas first so that building staff can learn and get used to new VMS system.
01/31/24 – Working on floors. They have a computer in the room and are working on parallel system now, testing on two systems including the Valerus system for training.
02/28/24 – Construction continues on project.  Training occurred on 02/28/24 on site with building staff.  Ready to work on the PODs and move the residents.
03/27/24 – Work continues.  Most of exterior cameras switched over.  Close to working on 3rd floor (final housing units).   Anticipated completion in next 30-60 days.
04/24/24 – Project nearing completion of original scope.  CO cameras being installed.
05/29/24 – Glenwood has a hand full of interior cameras that remain to be installed, and then a few on the exterior.
06/26/24 – Glenwood ready for punchlist on all remaining areas. All main project cameras installed. CO cameras being installed. Demo complete and painted. Encoders being removed now.
07/24/24 – TEI and HCFD to finalize punch and issues on site in August.
08/28/24 – Glenwood has Cornerstone update the PLC system on site with new cameras to endure call ups are correct and working. TEI and HCFD will perform final walk thru once notified by Glenwood that everything complete.
09/25/24 – No Updates. Glenwood and Cornerstone working on scheduling modifications to the PLC.
12/11/24 – Glenwood notifies HCFD and TEI that PLC integration is complete. TEI and HCFD to perform final punchlist.
01/29/25 – Final punchlist completed and issued. Project complete pending closeouts.
02/26/25 – Project complete pending closeout.
04/23/25 – Project complete pending closeout.
05/28/25 – No updates.
05/29/25 – Barth has redlines, updating as-built drawings
06/25/25 – Record drawings complete. Project ready to close out.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

2020 – Security Camera System Upgrade Read More »

2020 – Floor Patching

06/09/20 – Site visit to see existing conditions. SOSS submitted. Waiting for authorization to proceed.
09/08/20 – Received authorization to proceed. CA to schedule site visit
10/29/20 – Site visit to confirm existing conditions. Broadloom carpet made it difficult to confirm extent of cracks. Bid package in process with reasonable assumption for scope of work.
12/9/20 – SD Drawings and Estimate uploaded into Archibus.
01/21/21 – Structural Allowance added to cost estimate.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

05/27/21 – No Update

06/25/21 – No Update

07/13/21 – SOSS submitted to County

08/26/21 – No Update

10/27/21 – Bid set sent to County for approval. Ready to bid.

11/10/21 – Pre-bid held on site. flooring replacement scope added to be alternate #1, #2 and #3.

11/19/21 – Bids came in. Triton was the low bid. Waiting for contract now.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

05/26/22 – No Update.

06/30/22 – Kickoff meeting held. Notice to proceed issued. Submittals received and returned.

07/28/22 – No Update.

08/25/22 – Kickoff meeting held. subcontractor to provide schedule.

09/29/22 – Ready to begin project when materials arrive

10/27/22 – Construction began.

12/15/22 – Construction ongoing. should be complete by end of next week.

01/26/23 – Punchlist conducted last week. Corrections to be fixed in the near future.

03/30/23 – Damaged doors discovered from flooring repair. Triton to correct.

04/27/23 – Triton to remove and replace wood veneer on doors.

05/25/23 – Doors have been refinished. They need a final sealant coat and will be installed next week.

06/29/23 – Doors installed. Closeouts received.

07/27/23 – Closeouts need final approval.

08/31/23 – Final pay app sent to county and closeouts approved. Waiting on Triton to provide hard copies.

2020 – Floor Patching Read More »

2020 – Fire Alarm System Upgrade

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for the project requested by Facilities.
02/26/20 – TEI receives PO and signed SOSS. TEI and Jessica Powell request design kickoff meeting with 2020 staff. Project kickoff meeting to be scheduled ASAP and design to commence thereafter.
03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project Pending COVID-19 restrictions.
05/27/20 – Project pending COVID -19 restrictions.
06/23/20 – Project Pending COVID-19 restrictions.
07/29/20 – TEI meets with Rycca and Joe Houlihan to re-kick off the project. TEI re-booted the design process. Design fieldwork to be scheduled in the next 2 weeks or so.
08/21/20 – TEI completes field work and is working on completing design. TEI reaching out to Darryl Meadows (CFD) to schedule 85% complete review meeting with CFD and Bldg Department to get buy in on design with the AHJs prior to sending to HCFD for design review.
09/23/20 – TEI meets with Darryl Meadows, at the facility to review the design documents. Darry indicated that there is no BDA in the building presently, and that the City Ordinance requires a 3rd Party company (i.e. MobilCOMM) perform a spectrum analyzation of the building. TEI contacted MobilCOMM to obtain a quotation for the analysis. TEI will schedule a meeting to review design documents with HCFD – discuss option of Mass Notification, and latest Code changes that have been issued by NFPA 72, but that have not been adopted by the City of Cincinnati to date.
10/27/20 – TEI receives quotation from MobilCOMM for spectrum analysis for the building. TEI to schedule the test at a date that is approved by building manager. Upon receipt of the results of the testing – documents will be finalized and a review set will be sent to HCFD once funding for the project is secured.
12/09/20 – Spectrum Analysis scheduled for 12/15/20 with MobilComm. Upon receipt of results of analysis, TEI can send 99% set to HCFD for review in preparation for a January 2021 issuance.
01/26/21 – MobilComm provides spectrum analysis of the building, and a BDA for the project is not required for the building. TEI requests final design review meeting, and upon notification that funding is secured for project, will finalize ITB and issue for bidding.
02/23/21 – Project has been issued for bidding as ITB# 029-21. Pre-bid meeting scheduled for 03/09/21 and bids are due to purchasing on 03/24/21.
03/24/21 – Bids opened on 03/24/21 – and apparent low bidder is DeBra Kuempel, Inc. ThermalTech is vetting bids at 1:30 on 03/25/21 and will make recommendation ASAP to facilities upon completion of vetting process.
04/28/21 – Construction pending approval of contract by BOCC.
05/26/21 – PO and contract sent to DK on 05/25/21 – kickoff meeting to start submittal process requested with DK.
06/23/21 – JCI/Simplex developing submittals for the project. Upon approved submittals, construction will commence.
07/28/21 – TEI rejects (revise/resubmit) original submittals for the project. TEI receives revised submittals on 07/28/21. TEI to re-review and send approved submittals to DK for project. Project construction kickoff meeting can be schedule in next 2 weeks.
08/26/21 – HCFD and TEI host pre-construction meeting at the project site with Bldg Mgr, Brian Bell and Wayne McFarland. DK has PO and permits have been submitted for at are pending review comments from JCI Simplex. Materials from JCI have been released and are pending mid September delivery. DK tentatively scheduling mid/late September mobilization to the project site.
10/26/21 – TEI requests timeframe from DK for mobilization. Accoriding to JCI and DK, nearly all materials have be shipped to DK and work can commence.
01/25/22 – Project is in construction.  Backbone installed and DK has been working to pull second conductor to the notification appliances.  Work continues and in the next couple weeks will be working in the housing areas where residents will need to be temporarily relocated.
02/23/22 – Construction continues.   There are issues with the current Siemens smoke control system that the building manager is working with Siemens to resolve.   by first of next week, will be ready to start cutting over the units to the new system.  Meeting scheduled on 02/28/22 with housing unit staff to discuss and plan for relocation of residents during the installation.
04/28/22 – Met this week on site to do more fieldwork, Project should be complete in June 2022.
05/26/22 – Project nearing completion.  Inspections will be scheduled mid-late June for CFD and building department.
06/28/22 – Pretesting of smoke control system scheduled on 06/29/22.  Upon successful completion of smoke control system, inspections to be scheduled.
07/27/22 – Inspections to start next week.  Smoke control system work completed and tested.
08/24/22 – Inspections going well.  Building Department on site 08/25/22 (during this meeting) finishing inspections.  Will need to return once sampling tubes are replaced with correct tubes.  Then training and closeout can occur.
09/26/22 – All inspections complete and passed!  Finalized.   Upon completion of installation of access panels in the ceiling, project will be complete.
10/26/22 – Project completed.  Project pending close out documentation.
12/15/22 – TEI performs punchlist.  Still pending closeout documents.
01/25/23 – TEI receives close out documents from DK and reviews.   TEI requests minor updates.   Upon receipt of minor updates, Closeout documents will be submitted and project will be complete.
02/23/23 – Project ready to archive next month.

2020 – Fire Alarm System Upgrade Read More »

2020 – City Façade Assessment

08/22/19 – THP provided SOSS.
08/28/19 – County approved SOSS.
09/26/19 – THP schedule to complete work in October.
10/18/19 – THP visited site to perform visual inspection of façade from grade and from roofs.
10/25/19 – THP visited site to rappel façade and perform close-up inspection.
10/30/19 – THP finalized draft of façade review report for Owner’s review.
12/12/19 – THP met AFR at site to confirm façade repair locations.
12/13/19 – THP met AFR at site to confirm completion of façade repairs and document locations.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs.
02/27/19 – Refer to F117 for status.

2020 – City Façade Assessment Read More »

2020 – Arc Flash Modeling and Labeling

05/29/19 – Hamilton County requests SOSS for project.

06/26/19 – TEI submits SOSS to facilities. Project Pending SOSS approval and PO.

07/24/19 – Project pending SOSS approval and PO.

08/27/19 – Project pending SOSS approval and PO.

09/25/19 – Project Pending SOSS approval and PO.

10/30/19 – Project Pending SOSS approval and PO.

12/11/19 – Project Pending SOSS approval and PO.

01/28/20 – Project Pending SOSS approval and PO.

02/26/20 – TEI receives signed SOSS and PO for project. TEI contacts Jessica Powell and requests project kickoff with 2020 staff. Kickoff meeting to occur ASAP and project to commence thereafter.

03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.

04/30/20 – Project Pending COVID-19 restrictions.

05/27/20 – Project pending COVID-19 restrictions.

06/23/20 – Project pending COVID-19 restrictions.

07/29/20 – TEI meets with Bryan Collins to re-kickoff project. TEI contacts sub contractor to schedule field investigation to incorporate into the SKM model. field investigations to be coordinated with building manager.

08/21/20 – TEI has Phasor Electric perform field investigation of all of the gear and feeders at the building. Field work notes were sent to TEI on 08/20/20, and the data will now be entered into the model for running calculations.

09/23/20 – TEI processing data from Phasor – and will complete the modeling upon receipt of follow up data requested from Phasor.

10/27/20 – Phasor scheduling back visit to the building to get missed information and then the model will be completed and sent to Hamilton County Safety Consultant for review.

12/09/20 – Phasor returned to site to gather missed information. Finalizing model, and will send through internal review, and then forward to Charlie for his review.

01/26/21 – Model to be sent to Charlie at CMI for review by 01/29/21.

02/23/21 – Model completed and sent to Charlie at CMI for review and comments. Upon receipt of review comments from Charlie, labels will be printed and applied at the building.

03/24/21 – ThermalTech receives comments from CMI and incorporates into the model. Labels printed and building manager contacted to schedule installation of labels – proposed to be installed week of 03/29/21.

04/28/21 – Labels installed on all equipment. TEI to over report to HCFD and project complete.

05/26/21 – Project Complete.

 

2020 – Arc Flash Modeling and Labeling Read More »

2020 AUBURN – BUILDING ASSESSMENT

05/03/07 – Hard copy report is finished and being delivered to Mark Donnelly.

04/26/07 – TTC told Mark that he would incorporate Don Benbow’s mark up and update the website and give him 6 new hard copies.

04/18/07 – The only comments that we have received are from Don Benbow. We will update the report for the items we are willing to concede and update and send down final copies to Mark Donnelly if he is okay with this approach.

04/13/07 – Issues in disagreement are being worked out.

04/04/07 – Matre forwarded some comments from Don Benbow. TE may incorporate his suggestions into the report. We however disagree with some of them.

03/30/07 – Email copy has been delivered to Mark Donnelly for markup. TEI will provide 6 hard copies upon receipt of HamCo comments.

03/23/07 – Awaiting notification to provide hard copy of report.

03/20/07 – TTC to input report on Wednesday. Report has been input to Archibus. Review set to be hand delivered on Thursday.

03/14/07 – NR created project journal and filled in back data from previous meetings. Report completed, information to be inputted into Archibus on 03/12/07. Hard copy will be delivered during the week of 03/12/07.

2020 AUBURN – BUILDING ASSESSMENT Read More »

2020 Boiler Replacement

01/24/11 – All punchlist and closeout documents have been sent to Bert for this project. Receptacle was moved by Ginter on water softener.

10/1/10 – All work is complete. Seco has not turned in final closeout paperwork yet.

09/22/10 – Peck has scheduled change order work to start at the end of September. ThermalTech has provided answers to the PHB questions on the Change Order work.

08/13/10 – Peck submittals are approved on water heater and all other change order work. Seco change order was sent out for signing. Seco payapps sent to Bert for payment. Siemens payapps sent to Bert for payment.

07/23/10 – Peck change orders are approved. Folck is working on Seco closeout documents and change order forms. Peck is to schedule change order work starting next week. Bert is trying to get PO for water softener.

06/02/10 – Siemens has provided pricing for OM-1 Actuator Option to convert 2-position valves to modulating. Isolation valves will need to be modulating to avoid damaging system shock.

05/28/10 – Boiler installation has been approved by IBI. There are a few minor issues which Seco will complete next week. PH+B has provided pricing to install blank off orifice plates to convert (3) 3″ flanged 3 way bypass valves to 2-way valves for AHU-1,2,3. Blank off plates are 1/16″ thick with a 1/4″ hole in the center for relief and will be installed between the existing valve gaskets and flanges. CB BLR-3 and BLR-4 have been successfully fired and will continue commissioning by Siemens next week.

05/26/10 – Boiler installation has been approved by the State/City and is ready for startup with CB Thursday and Friday (5/27-5/28).

05/24/10 – We had a construction meeting today for the project. All mechanical and electrical work has been completed. Siemens will be on-site all week to install control wiring and begin controls startup / commissioning. Boiler inspections are scheduled for Wednesday (5/26 – State/City) and Thursday (5/27 – Electrical). Boiler startup with CB is scheduled for Thursday and Friday (5/27-5/28).

05/21/10 – HWS/HWR and NG piping have been completed. Condensate drain line and relief valves will be installed Monday (5/24). Combustion air intake has been modified to eliminate 45 degree elbow around conduit rack. All electrical work has been completed including VFD’s, pump, and boiler feeds. Current transformer has been fixed temporarily until new transformer is installed on Monday (5/24). Control panel has been installed and conduit for control wiring was run to boilers and pumps. CC will be on-site all next week (5/24-5/28) to install control wiring, thermal wells, and begin programming with Chris Neff.

05/18/10 – Combustion air and exhaust have been installed for Boiler #3 & #4. (1) 45 degree elbow was used on intake air to avoid conduit rack. TTE recommends (2) 90 degree elbows vs (1) 45 degree elbow for a more appealing installation. To avoid compromising the security bars and make installation more simple, combustion air intake was not installed thru existing louvers. Boiler piping has been started and will be completed by Monday (5/24). Balancing valves or triple duty valves will not be used for this installation. Copper was considered for condensate drain lines to avoid damage by foot traffic, but is not an option due to possible erosion from acidic condensate. If problems occur in the future, condensate drain lines could be changed to sch 80 pvc or stainless steel. Electrician has moved (2) of (4) VFD’s near pumps and will complete installation Wednesday (5/19). Siemens will be on-site Thursday (5/20) for controls.

05/14/10 – Project schedule was updated and meeting notes were sent out from construction meeting on Monday (5/10). All demo has been completed for boiler #2. New Boiler #3 & #4 are currently in the assembly process and will be completed on Monday (5/17). Included boiler legs have been shortened 5″ to accommodate overhead clearance requirements. Boiler #3 & #4 have been positioned on existing concrete pad as shown on TTE drawings. Included boiler exhaust was installed opposite of drawings by factory and will be changed to match TTE drawings. Boiler piping will now be routed between boilers as approved by TTE. HWS valve has been relocated near existing HWS tie-in. TTE considering the addition of balancing valves or triple duty valves for Boiler #3 & #4. Boiler combustion air, exhaust, and piping will be installed next week (5/17-5/21). Electricians will be moving VFD’s near pumps on Tuesday (5/18) to satisfy line of site concerns. Replacement transformer is scheduled to arrive Wednesday (5/19).

05/10/10 – We had a construction meeting today for the project. Peck will begin demolition on Tuesday. Controls and Electricians will be reported next week to start their next phase of work. TTE will work on schedule and meeting notes this week.

05/07/10 – We setup a const mtg for next week on Monday to kick off the demolition on this job and to coordinate the construction issues. The permit has been approved by IBI and City. The real work begins.

04/29/10 – We continue to work on schedule with Peck. PHB came on Wednesday to begin coredrilling for the new vents. The city has the permit held up on 3 issues that TEI sent responses down for reconciliation. The electricians and Siemens are working on a disconnect issue with the VFD’s. Boiler is scheduled to be demolished on May 10 which has been approved by Don Benbow.

03/24/10 – Siemens payapp has been received but the schedule of values is not acceptable. TTC will contact Siemens. Peck payapp has been approved.

03/23/10 – All submittals have been received. All submittals have been returned. We clarified an issue with the boiler vent piping. It can be single wall with personnel protection on this job. A controls meeting is scheduled next week to work on sequences with 2020 and the Siemens. Gary Davies will attend for TEI.

02/22/10 – No word on Siemens. TEI created permit drawings sets for the contractors, as soon as they are stamped and signed, we will give to contractors. Small modifications to venting per the 02/12 visit.

02/12/10 – Met with Peck on site and reviewed project with Foreman. Contact all contractors for submittals. Neff said he could call Siemens for me to find out where their subs are.

01/19/10 – The preconstruction meeting was held on site. TEI has approved the boiler submittals but wants better paperwork. Siemens did not attend the precosnt meeting. PHB and Seco were in attendance and are working on submittals as TEI works on permit drawings for the project.

12/31/09 – Contracts are signed but the BOCC have to approve them before we start. Siemens state term contract is ready. Peck asked for and received an extension on the project completion date. Ballinger informed us through Peck that boiler prices will increase in 2010 if we don’t order in 2009. That is a problem since the contract won’t be approved because of winter hours for the BOCC.

10/19/09 – Bid came in for the project. Peck appears to be the lowest bidder. I confirmed the prices with Bernie. His labor looks low but they are willing to do the project for the price. I know have to look at the LCC for the boilers and see which is best and look at lead times on the equipment.

09/18/09 – Final bid documents were sent to Purchasing and Queen City. The Bid Opening is October 19th. The Prebid is Oct 1. Chris Neff called and wants to go over some drawing details. The controls contract will be given to Siemens under a state term contract. TEi turned over the pdf’s to Siemens but we have not heard any comments from the CC yet. Gary is in the office this week so we need to organize the final details.

08/25/09 – Control schemes are finished. SOSS is approved. TEI is working on design. We need to go back and do more fieldwork for verification and start the design on paper. We are bidding 3 alternates for boilers: Clearfire, Fulton, Sync.

07/28/09 – TTC & TZ visited the site and did the preliminary field work. TTC created and sent Tony an SOSS for the project. TTC will hand deliver the SOSS to Bert at the County Partnering Meeting.

2020 Boiler Replacement Read More »

2020 – Boiler Replacement Phase 2

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/25/10 – Contract for Peck has been sent to Tony for approval. Tony said he was going to pay for Boiler #1 repair this year and install the new boilers in Spring 2011.

01/24/11 – Contracts are in approval stages. Waiting for pre const mtg. Labor will start after heating season, March 2011.

02/22/10 – Pre Const Mtg Complete. Mtg notes being sent to contractors. PHB has submitted boiler paperwork for approval. The original rain caps have been removed on the boiler stacks to prevent ice puddling below the stacks. PHB is looking at installing thimble caps on all new vents. New venting and project schedule must be approved.

03/30/11 – Peck is working on boiler order and delivery. Boiler submittals and electrical submittals have been returned to Peck. We are currently trying to work out a change order on the control valves, actuators and flow meter. The project will begin in May-June 2011. We should be finished by the time summer is over.

05/12/11 – Peck is working on new background checks. All change orders have been sent through. Boilers are ordered.

06/07/11 – Boilers are at PHB and the flues should be there in a few weeks. PHB still needs to get background checks back from the State before they proceed.

06/20/11 – PHB is ready to start some sheet metal demo in the boiler room next week, also finalizing the project schedule for this job.

Item #2 – There are a couple of issues with the control equipment that we need to discuss. The acuator and valve by Keystone apparently is out of stock. They have offered a replacement that we can get, it is slightly bigger than the one we specified. The problem is TTC can’t find this model on their website. Asked Chris who they contacted locally for prices and model #’s.

Item #3 – TTC asked if Siemens or someone else preferred make the paddles wheel flow meter needed. Bernie was looking for a local manufacturer that sells the Badger flow meter, but was not aware of any yet. Did Siemens offer the one we get easily?

07/07/11 – Peck is on site performing demo. Chris has been sharing controls and wiring with the Peck for purchase through Seco.

07/21/11 – Pipefitters are complete with their work. Sheet metal guys are waiting for a fitting for the flues, and will continue as soon as they get the rest of their materials. SECO Electric will be on site Monday 7/25. Start up is scheduled for August 12th, that will give enough time to get everything complete and the boilers inspected. ThermalTech has to provide a punchlist and discuss controls with Chris Neff.

08/05/11 – TTC sent out an email punchlist to Peck from a site visit last week. Bernie said they can get this done.

08/08/11 – Peck submitted payapp #1 but the change order paperwork is not signed yet. TEI asked them to modify their payapp so they can bill more quickly on this project.

08/25/11 – All work is complete except for metal pans on louvers. Boiler alarms not part of new boilers, Bill is working on a separate change order for that. Ready to closeout. Chris is writing sequences now.

09/28/11 – Pay App #1 was resubmitted by PH&B. Approved by TTC 3 copies were sent to Tony Matre on this date.

09/30/11 – We resolved Payapp #1 issues and asked PHB for closeout documents. Tony paid the $102,600 invoice already so we voided the later invoice and asked for a #2 for closeout. The change order was signed on May 13.

10/24/11 – Payapp 2 (labeled 3) arrive and was paid. Payapp 3 (retainer arrived and was held for closeout docs). TTC advised PHB the closeout documents are due before final payment can be made.

12/23/11 – This project will be archived for 2012.

02/22/12 – Chris reports all boilers are working great but there is still some programming left for him to change or update. This project is ready to be archived. All closeout and pay applications have been sent to Tony.

2020 – Boiler Replacement Phase 2 Read More »

2020 Entry Soil Stabilization

Lead Partner: THP

08/29/13 – County requested SOSS to provide repairs to the Terracotta at the first and second floors.

09/09/13 – THP surveyed the site to determine scope of work and possible solutions.

09/13/13 – THP met with Tony Matre to discuss scope of work and SOSS.
10/31/13 – THP issued Owner review documents.

11/01/13 – Jeffrey Allen Corporation was the apparent low bidder.

11/11/13 – THP sent AIA contracts to the County for review.

02/27/14 – Project on hold.

03/27/14 – Project on hold.

04/24/14 – Project on hold.

05/29/14 – Project on hold.

2020 Entry Soil Stabilization Read More »

2020 Masonry Investigation

Partner Lead: THP

02/03/16 – County staff reported masonry cracking throughout the building, and requested THP investigate.

02/25/16 – THP visited the site, confirmed the conditions, and is developing a SOSS.

03/24/16 – THP provided an SOSS for review.

04/04/16 – County approved the SOSS.

05/26/16 – THP completed field investigation of the facility. THP developing analysis and final recommendations.

09/09/16 – THP published draft report. County provided draft comments the same day.

09/28/16 – THP anticipates publishing final document 9/30/16.

10/11/16 – Final report published.

2020 Masonry Investigation Read More »

2020 – Cooling System Questions and Upgrades

05/19/16 – ThermalTech met with Bill Scholl and review the CT installation.

05/25/16 – TEI recommended to Tony to rebuild the towers and add an equalizer line for more efficient operation.

06/23/16 – Spoke with Bill Scholl and confirmed he is correct that the off chiller needs to be isolated from the chilled water system or else there are large inefficiencies in the chilled water system and a blending of cooling water return temperatures.

06/27/16 – Sent drawings to Tony and Bill for possible ECM project.

02/01/17 – Project on hold as far as I know.

2020 – Cooling System Questions and Upgrades Read More »

2020 Matrix Security System Upgrade

Partner Lead: TEI

09/28/13 – Mike Barth met with Bill Scholl about scope of upgrading the security system which may include the locks, cameras and maybe master clock systems. Currently developing the SOSS for Tony.

02/24/16 – Tony inquired about resurrecting this project today. Debra Kuempel provided a new estimate for replacing some parts of the head end.

03/29/16 – ThermalTech reviewed the estimate from DK and authored a letter to Tony Matre to describe what DK had included in their bid versus what was included in the Archibus complete system replacement. Tony to provide ThermalTech with direction to move forward. Project on hold pending direction from Tony.

04/27/16 – Project pending direction from HamCo. BW said this is on hold as it is part of a larger budget appropriations for this building. It may be incorporated into a larger project at the 2020.

05/25/16 – SOSS Submitted to Bert Watts – Pending approval and PO.

06/27/16 – SOSS approved and PO Issued. ThermalTech conducted Kick-off meeting on site with Facilities and building staff. ThermalTech provided field work to document the existing conditions. ThermalTech meeting with Vicon industries on 06/29/16 to discuss options and capabilities.

07/27/16 – ThermalTech met with Vicon to address issues with new system and to get answers for 2020 questions. ThermalTech scheduled a design progress meeting with the 2020 staff, meeting scheduled for Friday August 5th when 2020 IT department staff returns from vacation.

08/23/16 – TEI attended Design meeting at 2020. Final Design review meeting scheduled for 08/31/16, and scheduled to be issued for bidding on or before 9/9/16.

09/28/16 – Drawing package issued for Bids on 09/09/16. Pre-bid meeting occurred on 09/20/16. Addendum #1 has been issued with Pre-bid meeting notes and sign in sheet. Bid opening scheduled for 10/06/16 at 11:00 AM at the purchasing department.

10/25/16 – Bids received, opened, and qualified. TE drafts contract and is at the prosecutors office for review and comments.

01/25/17 – Debra Kuempel was awarded the contract. Shop Drawings were submitted and have all been returned. DK began construction on 01/17/17 and next const meeting is 1/31/17.

02/22/17 – Work is proceeding on the project. The new NVRs, Kollectors (encoders), and Matrix Computers are installed in new rack and are running (burn in period). Comtec scheduled to be on site for change over to new system beginning week of March 20, 2017.

03/22/17 – Work continues to progress on the project. Com-tec on site programming the PLCs and installing 4 work station in the second floor control room. Spare DVR (DVR4) installed and running as Archive DVR.

04/26/17 – Project nearing completion. All work on original bid complete, and DK indicated that the the changes (allowance usages) will be completed approx end of first week or two of May. DK was told to deliver close out docs and as-builts to ThermalTech. POE pricing to be determined, possibly paid through the allowance.

05/22/17 – ThermalTech completed Punchlist on 05/23/17. There are minor issues to complete project, and (4) additional cameras being priced by DK in the intake area of the building that has no camera coverage at this time.

06/27/17 – DK Completed punchlist and email to John Nester and ThermalTech. A few final glitches in the system to get worked out and project closeout pending closeout documents from DK.

07/25/17 – DK and Vicon conducted training on the system on 07/18. TEI received final pricing for allowances, and authored Change Order #1 (deduct change order) or unused portion of allowance. TEI delivers Training videos to Hamilton County Facilities.

08/28/17 – Project complete, pending final closeout documentation from DK.

2020 Matrix Security System Upgrade Read More »

2020 – Fire Alarm System Replacement Study

07/25/17 – Facilities department receives indication that the existing Fire Alarm system is beyond usable life and that parts are no longer available for the existing system. Requested an SOSS from TEI to provide an assessment of existing conditions and make recommendations. TEI issues SOSS for project to provide assessment of the fire alarm system and provide recommendations. TEI receives approved SOSS and PO.
08/28/17 – Report in progress. TE receives information from Siemens on existing system obsolescence dates and also conducts meeting and building walk through with John Nester and Bill Scholl.
09/26/17 – ThermalTech is completing to study. Will submit draft of Study to Facilities department by 10/06/17 for review and comment.
10/25/17 – ThermalTech submits final copies of report to Bert Watts for distribution.

01/22/18 – Next steps pending review of study.
02/20/18 – Next Steps pending review of study.

03/27/18 – Next Steps pending review of study…

04/25/18 – Next steps pending review of study.

2020 – Fire Alarm System Replacement Study Read More »

2020 – Fire Alarm Surge Protection

10/25/16 – TEI issues SOSS for project to provide surge protection for the fire alarm system. Project pending approved SOSS and PO.
01/25/17 – Project pending approval of SOSS and PO.
02/22/17 – Project pending approval of SOSS and PO.
03/22/17 – Project pending approval of SOSS and PO.
04/26/17 – Project pending approval of SOSS and PO.
05/22/17 – Project pending approval of SOSS and PO.
06/27/17 – TEI receives signed SOSS and PO. Drawings issued to Bill Scholl and Tony Matre for review and comments. Package to be issued (small projects bid) upon receipt of comments.
07/25/17 – Pending review comments from Bill Scholl and Tony Matre.
08/28/17 – AKM asks TEI if this can wait and be installed as part of the fire alarm system replacement project. TEI spoke with Bill S and Bill is concerned with all of the electrical storms that happen at the facility that there would be a surge that could be catastrophic to the existing system if the protection was not put in place now. TEI and AKM have a discussion, and AKM said to get pricing on drawings that were developed and he will evaluate pricing and issue contract for work if he has $$ in his budget at towards the end of the year.
09/26/17 – Project released for bids from Cincy Electrical, DK and Phasor. Bids due back the ThermalTech by 9/29/17 and noon.
10/25/17 – AKM tells TEI that he is going to have DK install the system for their bid of $1,591 for the surge protection. Install to proceed upon approval of submittals.
11/29/17 – DK receives PO for the work and is instructed to schedule work with Building Manager.
01/22/18 – DK has completed construction. ThermalTech requested closeout document from contractor.
02/20/18 – Closeout pending receipt of closeout documents from DK.
03/27/18 – Closeout pending receipt of closeout documents from DK.
4/25/18 – Closeout pending receipt of closeout documents from DK.

2020 – Fire Alarm Surge Protection Read More »