PM: Jesse, Sam, Terry
02/01/24 – Champlin to send SOSS to TE for this job for Design, Bidding and Construction.
02/29/24 – Kickoff Meeting to be scheduled in near future.
03/28/24 – Kickoff held. Project to be bid in the next month or two.
04/25/24 – Bid Schedule needs to be determined. Project ready to move forward with small project bid. At the Partner Meeting we decide to have Trades do the work, TTE and CHA will assist with permitting. No sprinkler work needed. minimal HVAC. We do need an IBI and General Permit.
05/30/24 – Estimate to be sent to John. CDs in progress.
06/27/24 – Drawings and Estimate sent to John. Permit can be submitted when necessary.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – Permit to be submitted next week.
01/30/24 – Electrical Permit returned. Building and Mechanical Permit in progress.
02/27/25 – Building and Mechanical permit approved.
03/27/25 – No update.
04/24/25 – County to submit trades as a certified contractor in City of Cincinnati.
05/29/25 – No Update. County is getting Trades registered, trying to get fellow government entity set for this work.
06/26/25 – Trades is registered with the city but the HVAC work would not be allowed to be self performed. HVAC scope will be removed and permit revision submitted. ThermalTech updating the HVAC for engineering revision.
07/31/25 – City is not allowing any work that even touches HVAC to be done without a licensed HVAC contractor. We will need to bid out at least the HVAC work. Follow up at meeting was to remove the ceiling from the permit set and any work not associated with the wall and door going in. Resubmit permit without additional work.
08/28/25 – All ceiling work has been removed from the project. Permit approved and ready for pickup.
09/25/25 – No Update.
10/30/25 – Trades have began work. In wall inspection complete and board can be put up.
12/11/25 – No update.
01/28/26 – Work is complete.