Hamilton County Facilities

Champlin

TPC 9th Floor JFS and CoC Renovation

County: PM Rycca Thacker – Champlin PM: Sam Hofmann

02/26/26 – SOSS received for JFS portion of work. Design team verified existing conditions. SD plans and estimate in progress.
03/26/26 – SD plans and estimate in progress.
04/30/26 – SD plans and Estimate to be submitted to County next week.
05/28/26 – SD plan and estimate submitted to county for JFS work. CoC work is put on hold until further notice.
06/25/26 – No Update.
07/30/26 – No Update.
08/28/26 – CoC approved. SD plan and estimate to be uploaded to Archibus.
09/24/26 – Re-kick off to be scheduled.
10/29/26 – No Update.

TPC 9th Floor JFS and CoC Renovation Read More »

Winton – New Animal Shelter Building

PM: Rycca Thacker, Mike Murphy, Terry Cannon
12/11/25 – Land purchase is complete. The new building should be online by September 2029-ish.
02/26/26 – SOSS and PO received. Site investigation has begun. Kickoff to be scheduled sometime in March.
03/26/26 – Kick-off held with County, Cares and design partners. Geotech will begin investigation shortly. SPoA to send out programming survey shortly.
04/30/26 – Geotech beginning their scope. Needs assessment confirmation meeting on the calendar for 6/3.
05/28/26 – Data collection teams meeting held on 5/12. CARES needs to confirm some operational questions to prepare for the needs assessment on 6/3.
06/25/26 – Programming verification meetings complete. CARES will review and compare data to existing concept plan.
07/30/26 – SPoA to provide final program report.
08/28/26 – Programming report provided to CARES for review. Add services for Geotech approved. Additional testing scheduled for first week of september.
09/24/26 – Additional clearing needed for geotech. Approval pushed new borings until October. Program verification meeting held and concept plans incoming.
10/29/26 – Concept plan presented. CARES provided comments. SD plan in progress.

Winton – New Animal Shelter Building Read More »

CH – B95 Office Suite Renovations

PM: Megan, Sam
10/30/25 – This project went out to bid this week. Sam will send out invites for prebid and bid opening.
12/11/25 – Triton is low bidder. Project in contract phase.
12/12/25 – Furniture and two drawer cabinets can be located close to the hot water radiators, they just have to be moved if we ever need to service the units.
01/28/26 – Contract goes in front of the board today. Bulletin #1 will go out next week with the changes requested from Rycca.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. Project mobilization to be scheduled by County.
05/28/26 – Project tentative start on 8/10/26.
06/25/26 – No update.
07/30/26 – Submittals are being returned. Project start has adjusted to 8/31.
07/30/26 – RT said we may get new direction on final design for this space. We may need another Bulletin for this project.
08/28/26 – Mobilization on hold until scope changes are settled.
09/24/26 – Scope changes received. Bulletin is being prepared.
10/29/26 – Bulletin will be issued to Triton upon approval

CH – B95 Office Suite Renovations Read More »

TPC – Mechanical Room Door Replacement

PM: Jesse Estes, Sam Hofmann

08/28/25 – Field visit to confirm scope.
09/25/25 – Review set submitted to county. Project will be going out to bid next week.
10/30/25 – Project in Bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. County to schedule mobilization.
05/28/26 – Tentative start date of 7/6/2026.
06/25/26 – No Update.
07/30/26 – Tentative start has been pushed back to 9/8.
08/28/26 – No update
09/24/26 – Project has not started yet.
10/29/26 – 16 doors and frames have started. Project ongoing.

TPC – Mechanical Room Door Replacement Read More »

RSC – Regional Safety Complex Phase 2

PM: Rycca, Murphy, Toombs
09/25/25 – Design schedule has been updated such that final CD documents to be completed and bid in November 2025. Design documents are about 60% complete at this time.
10/29/25 – 90% Drawings, specifications, and cost estimates sent to Owner this week.
12/12/25 – Phase 2 drawings are in for owner comments. Bert said that he would get those back later this week. We are shooting for bidding first of January.
01/25/26 – MEP drawings and specification sent to Champlin Issued for Bid. They are stamped and signed. The targeted bid date is 02/02/26, Champlin reviewing all final documents in the set now. DEG is trying to onboard an AV and IT specialist for this job. We have not received his PO yet, Bright Technologies.
1/28/26 – THP submitted Bid & Permit set 1/21/26. will go out 2/3. Construction is expected to start in April.
02/26/26 – Budget has been approved and sent to Robert Bell for approval. Waiting on Cincy approvals to go out to bid. We are shooting for mid March issuance.
03/26/26 – Project is out to bid. Pre-bid scheduled for 4/2.
04/30/26 – Bid opening pushed back to 5/21. Sniper tower scope was pulled out as an alternate.
05/28/26 – Graybach was apparent low bidder. Bid vet to be scheduled in near future.
07/30/26 – A305’s requested from bidders. Waiting on direction from County. Not sure we have received them yet.
08/28/26 – Graybach awarded the project.
09/22/26 – THP – CA on going, reviewing RFI’s/Submittals.
10/29/26 – Permits submitted and almost ready. Dave commented that general waiting on fire inspector. Driveway permit is expiring next month. Plumbing submittals received and returned. Mechanical submittals received and returned.

RSC – Regional Safety Complex Phase 2 Read More »

JC – Cell Door and Frame Replacement (Phase 5)

PM: Matt Butz, Sam Hofmann

08/28/25 – Sheriffs provided scope of doors to be included in phase 5. Review set will be complete shortly.
09/25/25 – Review documents provided to county. Project will go out to bid on monday.
10/30/25 – Alpha is apparent low bidder. Bid vet occured 10/29. Alpha subbing out majority of the work to Cornerstone.
12/11/25 – Cornerstone is awarded the bid after contradictions in Alphas LOIs and Bid Vet statements came to light. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract signed. Kick off to be scheduled in near future.
03/26/26 – Cornerstone has taken field measurements. Submittals incoming.
04/30/26 – No update.
05/28/26 – Submittal received and returned. Schedule needs to be determined by Sheriffs.
06/25/26 – No update. Tentative fall start.
07/30/26 – Delivery scheduled for end of August.
08/28/26 – Mobilization in 2 weeks.
09/24/26 – two phases complete. Work ongoing.
10/29/26 – Project ongoing.

JC – Cell Door and Frame Replacement (Phase 5) Read More »

JC – Polished Concrete – Phase 2

PM: Jesse Estes, Sam Hofmann

09/25/25 – Project kickoff held and scope determined. Review documents will be ready for County next week.
10/30/25 – Project in bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – Bulletin #1 issued to include emergency L31 scope. Triton to provide schedule to begin work asap.
04/30/26 – Submittals approved. Triton to provide schedule.
05/28/26 – Triton mobilized 5/26. Epoxy demo ongoing.
06/25/26 – Half of South 3rd floor pods are complete. 5th floor Hall is next.
07/30/26 – First phase grinding and polishing is complete. Furniture will be installed next week.
08/28/26 – Furniture install ongoing. Backpunch scheduled for next wednesday.
09/24/26 – Phase 2 in progress.
10/29/26 – 2 pods complete in phase 2. Work ongoing.

JC – Polished Concrete – Phase 2 Read More »

TPC – 3rd Floor Auditor Breakroom

PM: Megan, Sam Hofmann, Terry Cannon
05/29/25 – Added as new project.
06/25/25 – Checking dates for meeting.
07/24/25 – Design meeting conducted on site.
08/26/25 – Design continues, updated floor plans received from Champlin today.
09/24/25 – Prices and owner review documents submitted to Champlin. County to review budget and scope to determine if they have enough money to bid as is.
10/30/25 – Scope and Budget confirmed. Project will be issued for bid today.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No Update.
04/30/26 – Submittals are in process. County to schedule mobilization.
05/28/26 – Triton mobilized on 5/6. Construction and Bi-weekly meetings ongoing.
06/25/26 – Demo complete. Framing complete. Roughin inspections ongoing.
07/30/26 – Construction ongoing.
08/28/26 – Project nearing completion. Punch scheduled for next week.
09/24/26 – Punch walkthrough completed. Closeouts in progress.
10/29/26 – Backpunch complete. Closeouts received and being reviewed

TPC – 3rd Floor Auditor Breakroom Read More »

Record Center – Animal Shelter Renovation

PM: John Nester, Sam Hofmann, Terry Cannon

02/27/25 – SOSS returned. Kickoff to be scheduled in near future.
03/25/25 – Preliminary HVAC and plumbing calculations started.
03/27/25 – Kick off meeting held. SD in progress.
04/24/25 – Follow up programing meeting held. SPoA is working on plans to be provided in next couple of weeks.
05/29/25 – Programming meetings in progress.
06/26/25 – Programming meetings still in progress. Finalizing schematic plan with SPoA.
07/24/25 – TTE sent SD cost for MEP work to Champlin for use on this project.
07/31/25 – Schematic design plan finalized. Site and DD developing.
08/28/25 – Last schematic meeting to be scheduled. County needs revised estimate for next steps. Keep Rycca looped in. TTE cost up near $2M so far.
09/25/25 – Estimate provided to county based on finalized SD Plans. County to determine feasibility of moving forward.
10/30/25 – Final schematic design meeting held to determine next steps with 7-9 million dollar budget gap. County to discuss with Cares to determine the minimum amount of renovation they need to use record center.
12/11/25 – Murphy met with Caroline to discuss scope and possible reductions. County to provide direction on funding of the project. No movement until budget is set.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – No Update. OK to Archive.

Record Center – Animal Shelter Renovation Read More »

TPC – NFPA Fire Door Upgrades

PM: Sam Hofmann, Jesse Estes

02/27/25 – SOSS returned. Kick off to be scheduled in near future.
03/27/25 – Drawings have been started. Kick off to be scheduled.
04/24/25 – Drawings in progress. To coordinate with Elevar on format.
05/29/25 – No update.
06/26/25 – Field visit to walk through all buildings to be scheduled.
07/31/25 – Field visit complete. Drawings to be finalized.
08/28/25 – Final review meeting to be scheduled.
09/25/25 – Door Hardware Consultant to visit doors on site to provide feedback and cost.
10/30/25 – Assa Abloy is working on specs and estimate.
12/11/25 – Assa abloy is finalizing scope.
01/28/26 – Finalizing cost estimate and base bid scope
02/26/26 – Completing bid set and project manual.
03/26/26 – No Update.
04/30/26 – No Update.
08/28/26 – County is cleaning paint off labels and will report back which locations will still need to be replaced.
09/24/26 – Confirmation required on labels able to be cleaned.

TPC – NFPA Fire Door Upgrades Read More »

Hillcrest – Campus Repairs Phase 2

PM: Megan, Sam, Hofmann, Terry Cannon

01/27/25 – Create new project for tracking.
02/26/25 – ThermalTech has preliminary started creating the second phase floor plans for MEP.
02/27/25- Because this is tied to Federal Grant money, Phase 2 may not proceed and potentially fall back to Trades to do the work hodgepodge in the future. CCF Grant Funding in summer 2025 at state level and make give us some indication of what we are doing future.
03/25/25 – Project on hold until further notice.
04/23/25 – Project on hold.
05/28/25 – Project on hold.
06/25/25 – Project on hold.
07/30/25 – Project on hold.
08/28/25 – Project on hold.
09/24/25 – Project on hold.
10/30/25 – Project on hold. High level cost was sent to Rycca for grant purposes include the updated cost for design partners. updated Kitchen cost also sent to County.
12/11/25 – No update.
12/12/25 – Some items in Phase 1 being moved to Phase 2 for example school sink solids interceptor, repairs in Maple cottage, dining rec RCP.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – Grant is pending. Scope will be reduced to fit budget of grant. SOSS incoming to right size fee for reduced scope.
05/28/26 – No Update.
06/25/26 – 1.5 million grant awarded. Phase 2 scope meeting held. County to determine budget and design partners to provide updated SOSSs.
07/30/26 – No Update. Remove from list.

Hillcrest – Campus Repairs Phase 2 Read More »

JC – Polished Concrete – Phase 1

PM Jesse Estes, Sam Hofmann

09/26/24 – Project to go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project went back out to bid and is opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract in progress.
03/27/25 – Kick-off scheduled for 4/2.
04/24/25 – Kick-off held. Submittals received. Mobilization to be scheduled.
05/29/25 – No update.
06/26/25 – No update.
07/31/25 – No update.
08/28/25 – Waiting on background checks to clear to begin.
09/25/25 – Concrete grinder sub walked out on project. Alpha is searching for replacement.
10/30/25 – Alpha found replacement grinder sub. Alpha discovered that all furniture on the 5th floor of the north building has been tack welded to the bolts. all furniture in the day space area will be removed and re anchored. All cell furniture will be grinded around as best as possible.
12/11/25 – Pods are complete. Alpha to begin central hallway.
01/28/26 – Scope Complete. Waiting on closeouts.
02/26/26 – Closeouts received and missing items requested.
03/26/26 – Items still outstanding.
04/30/26 – Items returned. Hard copies outstanding.
05/28/26 – No Update.
07/30/26 – Closeouts delivered to County.

JC – Polished Concrete – Phase 1 Read More »

Central – Office Consolidation Phase 1 & 2

PM: Bert, Mike M, Terry, John Millar
05/30/24 – ThermalTech submitted SOSS to Champlin for SD & Cost.
05/31/24 – Champlin sends TTE background material to start working on this project.
06/26/24 – Design Meeting started, Champlin sent agenda and latest drawings.
07/02/24 – Board Presentation Day.
07/10/24 – Fieldwork at site.
07/17/24 – Fourth Floor layout sent from Champlin to TTE.
07/25/24 – JFS Computer Room fieldwork setup for TTE.
07/31/24 – Bond Hill Due Diligence SOSS request sent.
08/01/24 – SD & Cost sent to Hamilton County for this project.
08/21/24 – Due Diligence SOSS questions came back from Champlin. Be ready to move on due diligence quickly if approved.
09/19/24 – THP update – Champlin/County request THP provide building envelope and garage restoration due diligence assessments.
09/26/24 – Due Diligence kicked off. Architectural, MEP and environmental site visits complete. Survey happening today. Structural and civil scheduled.
10/02/24 – Due Diligence – THP update – THP published proposal to Champlin.
10/03/24 – THP update – Champlin/County request THP provide structural footing design for the garden fencing as part of the larger project.
10/07/24 – Due Diligence – THP update – THP field teams completed building envelope and garage surveys.
10/10/24 – Due Diligence – THP update – THP completed roof thermal scans.
10/11/24 – THP update – THP published proposal to Champlin.
10/23/24 – Met onsite with Facilities, Environmental Services, Ameresco and ThermalTech on Netzero energy opportunities.
10/25/24 – Due Diligence – THP update – THP published building envelope and parking garage due diligence assessment to Champlin.
10/31/24 – Due Diligence draft submitted to county. SOSS for DD-CA submitted. DD review meetings have begun. Documentation ongoing.
12/12/24 – DD to be submitted for review on 12/23. Estimate to be submitted 1/6. Meetings ongoing.
12/23/24 – THP update – THP issued DD fence and moveable wall structural details.
01/27/25 – ThermalTech finalizing fieldwork at the site to continue design for HVAC, Plumbing, Electric, and Fire Protection beyond the DD phase into CD. We have received the server survey from Telecomm and have updated our calculations for each IDF and MDF room, we hope to have floor plans updated by end of this week with proposed rack locations and HVAC needs. We are on pace to make the CD deadline of February 28, 2025.
01/30/25 – Final meetings with each department ongoing. CD’s being developed. Bid review set to be submitted for review on 2/21.
02/27/25 – Review set submitted to county. Tentative bid issuance date is 3/6. DDS has been removed from bid package to be issued as a separate project.
03/27/25 – Drawings are ready for bid. Updated Estimate to be submitted this week.
04/24/25 – Bid phase ongoing. Pre-bid had light attendance. Bids open May 23.
05/29/25 – Graybach is apparent low. Bid vet to be scheduled when bid is determined acceptable.
06/26/25 – Bid vetting in process. A305s provided to county for consideration.
07/31/25 – Graybach will be awarded the bid. bid vet meeting held. contract has been signed and will be going in front of the board next week. Const meetings start week of August 11.4
08/28/25 – Graybach has mobilized and began demolition. Furniture move services bid issuance on 8/26. RFI received on plumbing and HVAC are being answered as they come in. We have officially access controls, but it has been resubmitted as individual components and AV cable, fiber and Cat6 is approved. Now we need to discuss what to do about the security camera system. We reinforced with the field foreman that we are pulling every cable back to the IDF rooms so it landed by floor. TTE to send IDF coordinate drawings to John for ordering and coordination ASAP.
09/23/25 – TTE met with DK yesterday on proposed HVAC changes at Bond Hill. DK has already performed all the work on the first floor, we negotiated changes and discuss field engineering changes methodology with Dustin and Dave. We agree on the material cost but feel strongly that the labor is more than what is needed to make the requested changes (as it was estimate at three additional men for one month). TTE suggested that this change order is enough to cover not only the 1, 2, 3 floors, but the entire building.
10/02/25 – THP – Champlin requested field support for cutting holes in precast panels.
10/23/25 – THP – after site trips and coordination with Champlin, THP issued field sketch for precast hole support.
12/11/25 – Graybach still confident they will get done by mid January with TCO in mid January for Phase 2. TCO expected next week for Phase 1 as most inspections are done for the TCO work. Design team still issuing Bulletins for changes for GC, EC, and low voltage. AT A&D they are getting ready to move to the new building. HC has weekly move meetings for coordination, Veteran Services move being coordinated. Osterman working with HC and Graybach coordinate move items. HC seeking additional funding for extra asks at the building and the low voltage items.
01/28/26 – Punch walk through completed. Exit sign issue has been solved.
02/26/26 – JFS has moved in to the first 3 floors. minor punch work ongoing. Floors 4 and 5 are ongoing. DDS awarded to Triton. Demo is complete for DDS.
03/26/26 – Floors 4 and 5 in progress. Punch tentatively scheduled for 3 weeks from now. Furniture scheduled to be compete 5/1. DDS portion is ongoing.
04/30/26 – Project to be complete in 2 weeks. Punch scheduled for next week. Move in mid may.
05/28/26 – Punch work nearly complete on 1, 2, & 3. Punch walk through on 4 & 5 minus DDS happened last week. Everyone (minus DDS) should be moved in by end of next week.
10/29/26 – Closeouts ongoing.

Central – Office Consolidation Phase 1 & 2 Read More »

JC – Selective Cell Door Replacement 2024 (Ph. 4)

PM: Matt Butz, Sam Hofmann
03/28/24 – SOSS received. Sheriffs to locate doors included in this project.
04/25/24 – No update.
05/30/24 – Sheriffs provided doors to be included. Work in progress.
06/27/24 – Work in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. project to be bid in next couple weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Cornerstone is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project in contract phase.
01/30/25 – Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 3/31.
04/24/25 – No Update.
05/29/25 – Submittals received.
06/26/25 – Submittals to be returned and a schedule provided by Cornerstone.
07/31/25 – Submittals returned. Cornerstone to schedule mobilization.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Cornerstone to mobilize Monday to finish phase 3 work and begin phase 4.
12/11/25 – Phase 1 complete. Moving to phase 2 after the new year.
01/28/26 – Project ongoing.
02/26/26 – Project is ongoing. 2 pods left until completion.
03/26/26 – Project ongoing. second to last phase has been started. Final phase to pause for 1 month until Triton completes phase 2 work.
04/30/26 – No update.
05/28/26 – Cornerstone to complete this project after tritons project is complete.
06/25/26 – No update.
07/30/26 – Final pod is ongoing.
08/28/26 – Work is complete. Closeouts in progress.
09/24/26 – No update

JC – Selective Cell Door Replacement 2024 (Ph. 4) Read More »

TPC – Auditors Breakroom Renovation

PM – John Nester, Sam Hofmann

05/30/24 – Kickoff meeting held. Several options are ready for review. Meeting to be scheduled for mid June.
06/27/24 – Meeting held with Paula to go through options. More direction given. A revised plan is in progress.
07/25/24 – Updated options have been sent to Paula. Waiting on her response to finalize plans. Estimate complete and submitted.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update. OK to Archive.

TPC – Auditors Breakroom Renovation Read More »

JC – CARE Pod Counseling Rooms

PM: Matt Butz, Sam Hofmann
04/25/24 – Project update at Partner Meeting
5/29/24 – Field verification confirmed. CDs in progress.
06/27/24 – Final floor plan given to Matt for confirmation of scope from sheriffs.
07/25/24 – Bid set in progress. scheduled for owner review on 8/9.
08/29/24 – Owner review set submitted. Project to be out to bid in next couple weeks.
09/26/24 – Project is out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Only bid received was non responsive. Project is back out to bid today.
12/12/24 – Bid opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract finalized. Kick off to be scheduled in near future.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals returned. Change order #1 processed. Mobilization to be scheduled.
05/29/25 – Project scheduled to begin 6/30.
06/26/25 – Start date delayed due to hollow metal frame manufacturer issue.
07/31/25 – All issues solved. Waiting on Alpha to schedule mobilization.
08/28/25 – Waiting on confirmation for glazing ship date. Alpha has reached out numerous times to McAndrews and has not gotten a firm response.
09/25/25 – Glazing will be delivered by end of november. Alpha will mobilize next week and install temporary glazing until the BR rated glazing comes in. Frames were delivered in one single piece which are too large to fit into any elevator. Frames will be cut in half in the field and welded back together once in place.
10/30/25 – Alpha’s mason walked out on the job. A couple masons reviewed the project before they settled on one. Electrical work is complete. Alpha is convinced that the mid November deadline will still be met.
12/11/25 – Punch walk through tenatively scheduled for week of 12/22. Mason work is almost complete.
01/28/26 – Back punch complete. Waiting on closeouts.
02/26/26 – Waiting on closeouts.
03/26/26 – Closeout items missing sent to Alpha. Awaiting final submission.
04/30/26 – Waiting on hard copies.
05/28/26 – No Update.
06/25/26 – Hard copies delivered. Final pay app approved.

JC – CARE Pod Counseling Rooms Read More »

CH – Parking Lot Security

PM: Matt Butz, Sam Hoffman, Mike Barth
04/25/24 – Champlin has submitted SOSS, ThermalTech submitted SOSS recently.
05/30/24 – SOSS returned. Project kickoff to be scheduled in near future. BW said that this project on the fast track due to a recent incident in the parking lot.06/27/24 – Kickoff to be scheduled.
07/25/24 – Meeting held on site with County, Champlin, and several judges. Champlin is investigating fencing options and guard booth options for review. Plan will be modified based on comments in the field.
08/12/24 – THP completed a cursory field measurements for review of the proposed fencing.
08/12/24 – THP sent proposal to Champlin for review.
08/27/24 – THP sent SOSS to County for review.
08/29/24 – THP working on design with Champlin.
08/29/24 – Second meeting held for more investigation. THP found that additional structure will be needed for fence and guard booth.
09/25/24 – THP issued bid documents 9/20/24.
10/31/24 – Project is out to bid. Opening on 11/8.
01/30/25 – Tumlin was awarded the bid. Kickoff held. Permit submitted 1/29. Pending zoning and historical society approval. Submittals incoming.
02/27/25 – Submittals in progress. Tentative schedule received. Rejection received from the historical society.
03/27/25 – Submittals in progress. Zoning hearing scheduled for 4/2 for historical variance.
04/24/25 – Historical approval provided given some aesthetic changes to the project. Tumlin to provide pricing on the changes.
05/29/25 – Working with guard booth manufacturer to meet energy code requirements.
06/20/25 – THP submitted Bulletin #1. This covers the revisions that resulted from historic review board comments.
06/25/25 – THP received preliminary pricing from KT Holden for resurfacing lots: 250k.
07/31/25 – County approved moving forward with the Resurfacing project.
08/26/25 – THP modified the footing design to accommodate a continues concrete curb. THP preparing final sketch to be published on 8/30 with Bulletin No. 4.
09/24/25 – THP issued bulletin #4 on 8/29/25 to add grade beam for field conditions and new parking lot resurfacing work. Project in CA
10/30/25 – Grade beams installation onging. Guard booth will be lowered into place this weekend. Progress continues.
01/28/26 – Steel for door installed. Work ongoing.
02/26/26 – Cold formed steel going up in the next couple weeks. Fence material delivered. Phase 2 is pushed back slightly to align work.
03/26/26 – Phase 1 nearly complete. Cladding structure to begin weather dependent. Phase 1 fence installed. Phase 2 tentative date is 4/13.
04/30/26 – Phase 1 complete this week. Following for punch and commissioning. Phase 2 to begin 5/11. Parking on e court street and bus stop coordinated with city to prep for phase 2. Rycca, Mike and Derrick met onsite for security plants. SOSS incoming.
05/28/26 – SOSS for security plant beds submitted. Sheriffs have solved their booth connection issue and kicked off phase 2.
06/25/26 – Phase 2 to switch over mid July. Doors and booth to be tested to ensure seamless transition.
07/30/26 – Phase 2 has begun. Demo exposed some underground conditions that are being resolved. Phase 1 issues have been worked out, including new controls after being struck by lightning.
08/28/26 – Issues discovered below grade have been solved. Grade beams almost complete. Steel has been erected.
10/29/26 – Finishing fence this week. Programming second door. Ready for turn over next week.

CH – Parking Lot Security Read More »

JC – Lobby Ceiling Replacements

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. Project in progress. ThermalTech has been onsite and updated mechanical drawings for the potential future pans. Sam to setup kickoff project for this job.
06/27/24 – Kickoff to be scheduled in near future. BW asked to add the North Bldg Lobby to be added as an Alternate to this job, lower ceilings etc.
07/25/24 – Meeting held to discuss scope. Field visit to North building will take place soon. Bid set will be ready for owner review by end of August.
08/29/24 – Owner review set submitted. Project will be issued for bid in the next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kickoff to be scheduled in near future.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Submittals still in progress.
05/29/25 – No update.
06/26/25 – No Update.
07/31/25 – Submittals returned. Triton to schedule mobilization.
08/28/25 – Pre-mobilization meeting to be scheduled. Duration schedule received.
09/25/25 – Background checks approved. Triton mobilized this week. Demo to begin next week.
10/30/25 – Demo complete in both buildings. Installation has started.
12/11/25 – Plumbing and drain pan rework saved cost and simplified the system. Ceiling grid and pads to begin in North Lobby next week.
01/25/26 – Diffuser RFI answered earlier this month, should be an easy install. DEG reminded the county that they were working on Geiler replacing bad p-traps at ceiling before new ceilings are going back in. Fire dampers accessible only through this ceiling should be getting done by NKYHC (see Tony).
01/28/26 – North Building insulation tested for asbestos and came back negative. Triton providing pricing for insulation and mastic removal.
02/26/26 – CO#1 approved to remove insulation and mastic. Work is ongoing. Scheduled to be complete March 5th. Fire damper work is complete. Plumbing repairs being finalized. Fire alarm worker can use Triton lift to facilitate progress.
03/26/26 – Ceiling installation ongoing. CO Trap work to begin next week. Project tentatively to be complete mid april.
04/30/26 – Electric sub never got plan review approval. Issue has been resolved and inspections can be scheduled. Once inspections are passed, padding out ceilings will be final step.
05/28/26 – Final inspection passed. OKI to be on site for pad installation this week. Punch to be scheduled week of 6/8.
06/25/26 – Punch complete and final work to be complete this week.
07/30/26 – Punch work complete. Closeouts ongoing.
08/28/26 – Back punch complete. Closeouts received.
10/29/26 – No Update.

JC – Lobby Ceiling Replacements Read More »

TPC – Atrium Glass Replacement

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. work in progress.
06/27/24 – CDs in progress.
07/25/24 – No Update.
08/29/24 – Project will be issued for bid in next couple of weeks. Send to JN for review including the base bid and three alternates (bullet glass).
09/26/24 – Project is out to bid. Pre-bid scheduled for 9/30.
10/31/24 – No bids received. Project is back out today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future.
2/27/25 – Contracts finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals to be submitted.
04/24/25 – Submittals in progress.
05/29/25 – Pricing for frosted glazing received. We need to decide if spandrel glazing is remaining in the project.
06/26/25 – Change order cost to remove spandrel glazing and add frosted glazing to project received. Jesse to confirm.
07/31/25 – Changes confirmed. Scope will potentially be added to make use of deduct funds.
08/28/25 – Provided confirmation of scope change and permission to start. An offical cange order will be settled at the end of the project after any additional scope is added.
09/25/25 – No update
10/30/25 – Work is complete. Scaffolding removal and final cleaning to take place next week.
12/11/25 – Scaffolding removed and punch items addressed. Closeouts in review.
01/28/26 – County to provide scope for additional change order work.
02/26/26 – Field visit to determine additional work attended by Sam and Rycca. Bulletin #1 to be posted shortly.
03/26/26 – Bulletin #1 sent to Alpha to include glazing replacements on floors 5-10 and window cleaning of first floor windows.
04/30/26 – Alpha provided pricing. Waiting on clarification on pricing.
05/28/26 – No update.
06/25/26 – Change order approved. Schedule to be sent after submittals are approved.
07/30/26 – No firm delivery date yet.
08/28/26 – Tentative delivery date of 9/14
10/29/26 – Glazing installed. Windows washed this weekend.

TPC – Atrium Glass Replacement Read More »

TPC – Reentry Expansion

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in. We need the PO by mid-November and the project must be complete by 11/1/25, they are moving out of the lease space.
05/30/24 – Kickoff held with Thermaltech, County, Reentry and Champlin. Some minor redesign will be explored.
06/27/24 – New options will be provided to Trina this week.
07/25/24 – New options presented. Final plan confirmed. CDs in progress. Owner review scheduled for 8/14.
08/29/24 – Final owner review meeting held. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Submittals in progress. Kickoff meeting scheduled for next Wednesday.
06/26/25 – Demo for Phase 1 in progress.
07/31/25 – Demo complete for Phase 1. Re-entry to move to 4th floor space to give Triton full access to project area.
08/28/25 – Phase 2 demo is complete. Triton met with County and Champlin to discuss change orders. Adjusted COs provided. HC reported today that they would like to Triton to be completed in October 2025.
09/25/25 – Project on schedule to finish end of October. All change orders settled. Work continues.
10/30/25 – Project nearing completion. Furniture delivered to site. Triton will most likely get TCO approval early next week. Fire sprinklers are being added in a couple of pockets. We are keeping the window washing sprinklers heads as-is but Preferred will have to update their permit drawings after the TCO is approved.
12/11/25 – Fire protection work took longer than expected. Inspection to be scheduled for next week. Final CO expected before Christmas.
01/28/26 – Inspector will not provide CO until the exterior stair door is fixed. Trades is fixing the door starting on 2/2. Bulletin 2 for window shades and power issued and waiting pricing.
02/26/26 – Bulletin 1 pricing received. Work outstanding.
03/26/26 – Bulletin #2 pricing has been received and approved. Triton to begin electrical work.
04/30/26 – Blinds installation outstanding. All other work complete.
05/28/26 – Closeouts received and returned. Triton to submit outstanding items.
06/25/26 – No update.
07/30/26 – Hardcopies to be delivered to County.
08/28/26 – Hardcopies delivered. Access control programming complete.
10/29/26 – No update.

TPC – Reentry Expansion Read More »

CH – Law Library Stained Glass Window Repair

PM: Megan, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Initial field verification complete. We will need a second trip to take dimensions.
06/27/24 – Second trip complete. CDs in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30. ITB sent to multiple stained glass vendors.
10/31/24 – Bids received. One vendor had a bond issue, one bidder did not fill out XBE paperwork properly. Purchasing to provide direction.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in progress. Kickoff to be scheduled in near future.
02/27/25 – Contract Finalized. Kickoff to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Phase 1 windows are removed and taken back to the shop for refurbishment.
06/26/25 – Progress meeting at the shop scheduled for mid July.
07/31/25 – Windows still in progress.
08/28/25 – Phase 1 windows to be reinstalled in september. Phase 2 windows will be removed during the same time. Tentive completion date of end of october.
09/25/25 – Reinstallation of phase 1 began this week. Removal of phase 2 in progress.
10/30/25 – All storm windows have been installed. Stain glass installation of phase 1 to begin shortly. Phase 2 to be complete by end of november. County to request change order related to the plaster repair at window jambs.
12/11/25 – One section of stained glass installed. Second half of windows are still under repair. Background checks for installers have been over 90 days. County allowed stain glass to be reinstalled all at once when phase 2 windows are ready.
01/28/26 – No update.
02/26/26 – No update.
03/26/26 – Breilmeyer to mobilize this week. Installing half of glass and taking the other half to their shop.
04/30/26 – Half of stained glass is installed. Tentative completion at end of may.
05/28/26 – Breilmeyer to mobilize 6/8 to install the second half of the glass.
06/25/26 – Second half install ongoing.
08/28/26 – Installation complete. 1 punch item outstanding.
09/24/26 – No Update.
10/29/26 – Punch item complete. closeouts outstanding

CH – Law Library Stained Glass Window Repair Read More »

CH – North and South Riot Door Refurbishment

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Project to start once first phase is complete.
06/27/24 – Field verification completed. Drawings in progress.
07/25/24 – No Update.
08/29/24 – Owner review submitted. Investigating one more option for interior vestibule doors. Project will be ready to bid in next couple of weeks.
09/26/24 – Project will go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project was put back out to bid and opens on 12/19. Olek intends on bidding.
01/30/25 – Olek was awarded the bid. Contract is still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Doors have been removed and refurbishment is in progress.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – Call to discuss potential additional scope scheduled. Doors still in progress.
08/28/25 – Olek to reinstall riot doors in mid september. Electrical work to be complete during this visit. Any items that need to be taken to their shop will be removed and brought back after refurbishment.
09/25/25 – Olek currently onsite prepping for installtion of riot doors and interior doors.
10/30/25 – Door hardware supply issues pushed installation of riot doors back.
12/11/25 – Olek has been back on site. Ran into issues with the thresholds and pivots. Olek will be back mid january to continue work.
01/28/26 – Olek did not come back on site as first promised. Olek not responsive or timely. Champlin gave them a notice to be on site 1/19 or they would be referred to the prosecuter. Olek agreed they were in breach of contract but would not be on site until 1/26. The snow storm pushed that visit back until acceptable weather. County to provide prosecuter with letter.
02/26/26 – Olek to be back on site on March 9th to complete all remaining work.
04/30/26 – All work is complete. Closeouts are nearing completion.
05/28/26 – Closeouts outstanding. DK to complete a couple punch items.
06/25/26 – Close outs reviewed and several items still needed.
07/30/26 – Final punch item to be complete by Olek in August.
08/28/26 – Olek on site to complete punch work.
09/24/26 – Punch work complete. Olek sent official request for multiple change orders. Champlin has recommended denying request.
10/29/26 – Olek sent official request citing the contract. Champlin to provide official response.

CH – North and South Riot Door Refurbishment Read More »

Hillcrest – Campus Repairs Phase 1

PM: Megan, Mike Murphy, Terry Cannon
12/20/23 – THP – Champlin request SOSS for incidental structural support work.
12/21/23 – THP submitted SOSS to Champlin for review.
01/30/24 – Kickoff meeting with Facilities, Juv Court, Champlin and ThermalTech.
01/31/24 – Meeting notes distributed, TE started drawings packages for Phase 1.
02/28/24 – Scope for phase 1 finalized. Meeting scheduled for March 13, 10AM to review finishes and answer any remaining questions.
03/22/24 – ThermalTech Phase 1 drawings and cost estimates pretty close for final review. TTC working through individual items with Facilities. TTC requested meeting with Facilities to coordinate final scope of each building to nail down equipment repairs, replacement, upgrades. Verified that the four cottages are Elm, Evergreen, Hickory and now Maple is an Alternate.
03/22/24 – Champlin close to complete with review set as well. Final review meeting set for 4/3. Estimates to follow on 4/12.
04/24/25 – Final review drawings sent this month. Revised estimates were sent to Bert for review. Breakouts were formatted so they can see the assessment vs final design.
05/30/24 – County approved funding. Drawings modified accordingly. User requested a meeting to be scheduled in near future. BW said that the project can go out for bid as soon as we are ready to bid this project. TTC, MCB, and SH said the drawings and specifications are ready. BW and MM discussed the fence alternate around the building. Be ready to bid June 11-13 timeframe.
06/27/24 – Project is out to bid. Pre-bid scheduled for 7/9. Partners to invite local contractors for bidding on July 9.
07/25/24 – Project is still in bid phase. Final addendum to be posted by next Wednesday.
08/29/24 – Bids came in awardable. Accepting different alternates will determine lowest bid. County to decide what they are accepting.
09/26/24 – Project is in contract phase. County still finalizing alternates. Champlin to send recommendation letter for recommended bidder and note we have not finalized the accepted Alternates.
10/31/24 – Contract in process. Variance package for the fence is nearly complete.
12/12/24 – Contract awaiting on PO approval. Submittals incoming. HVAC and Plumbing submittal are done, TTC needs to approve and send along. BW said to go ahead and submit permit and fence variance for this job.
01/02/25 – ThermalTech starting on submittals this week for Phase 1.
01/30/25 – Kick-off held 1/29. Submittals are in progress. Zoning is complete. Permit has been submitted. Zoning application for fence to be submitted this week. Graybach ready to mobilize by mid February.
02/26/25 – We met with Aramark on Tuesday to review kitchen operational needs. TTE has been reviewing and working on HVAC, Plumbing and Electrical submittals on an ongoing basis. We are in good shape. Two AHU’s have delayed ship dates because the manufacturer is not producing R-454B refrigerant yet.
02/27/25 – Submittals in progress. Notice to proceed will be provided to allow Graybach to start on site work. Zoning application for fence to be submitted this week
03/27/25 – Submittals ongoing. Demolition ongoing. Permits approved and picked up. Fence application in HC lawyers hands.
04/24/25 – Bulletin #1 released. Already received a $25,000 add for the window changes. The rest of the pricing is outstanding.
05/21/25 – Met with Graybach, Champlin, Facilities on Change Order log, we do not have EC cost yet. Review deducts and approved a couple of them. Verbally approved Windows change order.
05/28/25 – ThermalTech regularly meeting contractors on site working on RFI and Change Orders for this project. The big items are the R-454B units for School and Dining, Water Closets on new tile walls, ductboard repairs and controls for the Admin building.
05/29/25 – Change order #2 for the windows is approved. Several potential change orders have pricing submitted. Rycca needs to finalize which will be approved or not. Change orders 3 and 4 approved. The remaining items have been priced and submitted to the board for a PO increase. Work may have to pause while this process takes place.
07/31/25 – Request for funding all change orders went before the board. No update on their decision yet. Work is in progress. Rycca reported that LaForce found a control key and it is getting cut and shipped to our site. The hope is to stay with the existing manufacturer. Rycca further said that they need final change order cost for all remaining COR so she can take final numbers to the BOCC. HVAC final cost, plumbing underground cost, electrical final change order needed. Sam is working on the frosted glass specs but must be ligature proof. TTC to confirm if County self performs repair if warranty is intact.
08/26/25 – Construction meetings continue. We agreed on the items to be included in Change Order 5 and now we are working on reconciling the cost associated with them. TTE sent two items for HC plumbers to fix, but while on site they had questions. TTC to meet them on site to review.
08/28/25 – County requested $800k for Phase 1 repairs. Plus CO#5 is approved and sent to Josh for approval.
09/24/25 – TTE sent a long list of field conditions to Graybach after last const meeting for them to address before the project gets to the punchlist phase. Graybach responded with action items and concerns over some of the comments. One item was that the County agreed to allow the return diffusers to remain as installed but they should be changed out before occupancy.
09/25/25 – Change order request goes in front of the board this week.
10/30/25 – Change order request was approved by the Board. Work continues in full force. No word on the fence yet.
12/11/25 – More change order requests came in. Scope removal to cover permit required work is being considered. Project competition is tentatively scheduled for end of February.
12/12/25 – DEG met onsite to review lighting change order and work out several nice compromises with the EE and GC. MCB to send Rycca and proposed update. Parks & Graybach to update and send in revised change orders for review.
01/23/26 – Const Mtg. DEG walked the site, check plumbing, heating, and electric. Chris Hofmeister called us back to the cottages to ask about external conduit adjacent to the receptacles. This turn out to be communication wiring not power wiring. Habegger will be out Tuesday to check temperatures in school, the two wings felt cold, but the core was warm. HVAC and plumbing are released to perform their punchlist.
01/28/26 – Campus is nearing completion. Bulletin to address change in fence scope to be issued in near future and variance submitted.
02/26/26 – Work ongoing. Waiting on approval for change in fence height to issue bulletin. Mechanical punch completed.
03/26/26 – Fence bulletin issued. Waiting on pricing to determine exact scope. Punch of school and admin building complete. Punch for remainder of buildings to be scheduled in near future.
04/30/26 – Punch work in progress. Fence application still in County hands.
05/28/26 – Variance application submitted. Hearing scheduled for 6/16. Owner punch walk through school. The rest of the buildings will be walked on 6/5.
06/25/26 – Variance approved. Survey to be scheduled in near future. Majority of punch work to be complete by mid July.
07/13/26 – TTC on site working on plumbing and HVAC items all week.
07/20/26 – TTC on site working on plumbing and HVAC trends all week.
07/22/26 – DEG on site doing back punchlist work.
07/23/26 – DEG on site doing back punchlist work.
07/24/26 – DEG on site doing back punchlist work.
07/30/26 – Final back punch complete. Minor items outstanding. Fence location needs final approval.
08/28/26 – Punch items have been progressing. Fence location not yet approved.
09/24/26 – 3 items remaining according to Graybach. Fence location has been approved, just waiting on confirmation of supposed easement.
10/29/26 – Back punch complete. Fence work ongoing.

Hillcrest – Campus Repairs Phase 1 Read More »

2020 – Locker Room Buildout

PM: Jesse, Sam, Terry
02/01/24 – Champlin to send SOSS to TE for this job for Design, Bidding and Construction.
02/29/24 – Kickoff Meeting to be scheduled in near future.
03/28/24 – Kickoff held. Project to be bid in the next month or two.
04/25/24 – Bid Schedule needs to be determined. Project ready to move forward with small project bid. At the Partner Meeting we decide to have Trades do the work, TTE and CHA will assist with permitting. No sprinkler work needed. minimal HVAC. We do need an IBI and General Permit.
05/30/24 – Estimate to be sent to John. CDs in progress.
06/27/24 – Drawings and Estimate sent to John. Permit can be submitted when necessary.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – Permit to be submitted next week.
01/30/24 – Electrical Permit returned. Building and Mechanical Permit in progress.
02/27/25 – Building and Mechanical permit approved.
03/27/25 – No update.
04/24/25 – County to submit trades as a certified contractor in City of Cincinnati.
05/29/25 – No Update. County is getting Trades registered, trying to get fellow government entity set for this work.
06/26/25 – Trades is registered with the city but the HVAC work would not be allowed to be self performed. HVAC scope will be removed and permit revision submitted. ThermalTech updating the HVAC for engineering revision.
07/31/25 – City is not allowing any work that even touches HVAC to be done without a licensed HVAC contractor. We will need to bid out at least the HVAC work. Follow up at meeting was to remove the ceiling from the permit set and any work not associated with the wall and door going in. Resubmit permit without additional work.
08/28/25 – All ceiling work has been removed from the project. Permit approved and ready for pickup.
09/25/25 – No Update.
10/30/25 – Trades have began work. In wall inspection complete and board can be put up.
12/11/25 – No update.
01/28/26 – Work is complete.

2020 – Locker Room Buildout Read More »

CH – Law Library Text Room Renovation

PM – Jesse Estes, Sam Hofmann, Terry Cannon
12/07/23 – Signed SOSS received. Kickoff meeting requested.
01/22/24 – Load calculations are complete, fieldwork is started and mostly complete. Initial findings for AHU and HVAC needs sent to project team. In subsequent discussions it was decide to upgrade the unit for what we need in this space and do not try to “make” existing unit work if its undersized. TTE will design with that in mind.
01/31/24 – Review drawings to be ready in two weeks. TE to finish MEP review for that issuance.
02/29/24 – Final review meeting ready to be scheduled.
03/28/24 – Review meeting to be scheduled for first week of April.
04/25/24 – Review meeting held. Notes from Library received and changes have been made. They need to approve budget.
06/27/24 – Budget is still being worked out. Mothers room to be listed as an alternate. CDs in progress. Pull Mother’s Room out as an alternate. Laura got more money but not all of it. RR Alternate #1, Mother’s Room Alternate #2.
07/25/24 – No Update.
08/29/24 – Voting on new budget today and it should go forward soon.
09/26/24 – Budget was approved. Project to continue in October.
10/31/24 – Project goes out to bid today.
12/12/24 – Bid opens today.
01/30/25 – Alpha was awarded the bid. Contract still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 4/2. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Pre-mobilization meeting held. Alpha to provide schedule.
06/26/25 – Demo in progress. Freight elevator is down and has stopped work. RTU submittals were returned and we are working on an electrical requirements on the submittal with the vendors now. We have had several meetings trying to lock this down. Lead times range from 6 to 10 weeks.
07/31/25 – Demo is complete. Abatement of flooring to begin this week. Alpha to submit PCO related to plaster repair. AHU submittals have been received and approved with a new manufacturer. It took a long time to get there and there may be a credit to the project when all is said and done (Carrier/CaptivAire to York).
08/28/25 – Abatement will begin 9/2. Work paused during abatement delay. County is requesting more funds for plaster repair CO. Alpha was released to work up to cost of deduct from flooring removal.
09/25/25 – Framing has begun. Bathrooms to be turned over by end of October.
10/30/25 – Bathrooms to be turned over before 11/4. Asbestos concern to be investigated by the county. Work continues.
12/11/25 – Abatement of above ceiling pipe is complete. Alpha to remobilize and continue work.
01/28/26 – Bathroom back punch complete. Several items outstanding. Mid february completion.
02/26/26 – Library punch complete. Punch work outstanding.
03/26/26 – Back punch complete and work verified. Waiting on closeouts.
04/30/26 – Minor additional backpunch items sent to Alpha. Waiting on closeouts.
05/28/26 – No update.
06/25/26 – Closeouts outstanding. Shelf collapsed and new pins are being installed.
07/30/26 – No Update.
08/28/26 – Trades to fix all shelves. Alpha to come fix damaged shelves and adjust doors.
09/24/26 – Alpha to fix damaged shelves and conceal fasteners. Dehumidifier running to remedy door issues.
10/29/26 – Alpha to fix shelves and plaster in conference room.

CH – Law Library Text Room Renovation Read More »

Hillcrest – Conditions Assessment 2023

PM: Bert Watts, Mike Murphy
07/12/27 – SOSS approved, kickoff meetings scheduled.
07/17/23 – Fieldwork started with Architect & MEP. Cottages will be first.
07/27/23 – All fieldwork is completed. Top 10 list has been shared. Champlin working on consolidated list. County will take control of site on 8/1/23 per email.
08/31/23 – Pavement condition report and tree maintenance report have been received. Architectural report nearly complete. MEP system report sample draft of some buildings has been received and acceptable. Other buildings in process. On target for mid September submission.
09/12/23 – Sent final reports to Champlin for Hillcrest including cost estimates for use on final report.
09/28/23 – Final report submitted to County
10/25/23 – Champlin to provide estimate for interior painting of cottages.
02/01/24 – Ready to Archive.

Hillcrest – Conditions Assessment 2023 Read More »

Dane – Phase 2 Renovations

PM: Bert Watts, Mike Murphy, Terry Cannon
06/29/23 – Opened for tracking.
07/27/23 – Cad plans are ready per request.
08/31/23 – New SOSS requested and will be submitted this week.
09/01/23 – Sent SOSS to Champlin for use on 152 and 157 Kennel options. TTE started working on a zoning and load calc for any future dehumidification unit we may need.
09/28/23 – Small Project flooring replacement ready for bid. Project will be sent out 10/3.
10/25/23 – Bids received for Epoxy Flooring Installation. Bid vetting in progress. Trench drain scope in progress.
10/26/23 – TTE requested design meeting with owner to review HVAC requirements for this space. Temporary vs new conditions, reusing existing equipment, locations of new equipment.
12/07/23 – User meeting held to discuss phase breakdown. Phase 1 = Epoxy Flooring. Phase 2 = Plumbing Improvements. Phase 3 = HVAC Improvements. Phase 3 = All other improvements. Phase 1 has contract signed and flooring installation scheduled for 1/29. Phase 2 to be submitted for owner review 12/15.
01/31/24 – TE submitted Plumbing and HVAC review drawings for this project concerning the trench drains and air conditioning systems for this phase of upgrades. We are still exploring most economical ways to build these trenches at the Dane St. site.
02/29/24 – Request for availability for final phase II meeting sent out. Waiting to hear back from Cares. We can be ready for bid end of March. Wait until next Wednesday and set the meeting with available data.
03/28/24 – Final review meeting held. Cares requested consultant to review the plan. Shelter Planners of America have been brought on and will conduct review.
04/25/24 – Consultant brought on board for industry standard advice. Updated plan presented to CARES. Champlin to incorporate changes and determine new phasing plan.
05/30/24 – Drawings have been updated to reflect plan changes for Phase 2. Final estimate to be submitted this week. BW said to go ahead and include the kennel cost in the Phase 2 work. Phase 3 cost due end of June to County as well. Coordinate with structural for final design and cost.
06/27/24 – Phase 2 and 4 cost submitted to Bert. THP investigated structure options for Phase 3. It was determined that the best option is to put the mechanical units on a platform behind the building that will later serve as the sallyport structure. Goal is to have Phase 2 & 4 ready for bidding by July 17. Phase 3 to be purely HVAC scope and okay to include platform & roof now in this phase. OK to pour slab during this phase. Stairs and ramps can be done later. TE will put power in for Portable HEPA to hold us over until the new units are installed on the new platform in Phase 2.
07/12/24 – Phase 2 & Phase 3 cost submitted to Champlin for rollup to County and Cares.
07/23/24 – Phase 2 + 4 Issued for Bid with additional work included as alternates with latest request from owner and tenant.
08/29/24 – Phase 2 bid opening 9/3. Acoustical vendor bids came in and Universal had the lowest bid for this project.
09/26/24 – Phase 2 bids awardable. Contract returned. First submittals received.
10/31/24 – Contract finalized. Scope may change slightly due to record center work. Holding off on permit submission until changes are finalized. JN said pick a new material for the walls and change them to something less permanent. We discussed phasing for Dane vs Records at this meeting and the fast timeline of preparing space for Phase 2 work for the dogs.
12/12/24 – Bulletin #1 issued addressing scope change requests. Submittals are in process. Kickoff meeting scheduled for next week.
01/30/24 – Bulletin #1 was rescinded. Bulletin #2 issued with minor changes to account for the cancellation of Phase 3. Applying for a change of use in Zoning is ongoing. Application has been sent to examiner for review. Once his comments are received, we can apply for a conditional use review. Permit will be held up until zoning is complete.
02/26/25 – Bulletin #2 and #3 have been issued. Zoning hearing scheduled for March 12. Work ongoing.
02/27/25 – City zoning link was sent to Rycca and Champlin and Nester, not allowed to share, but BW will join with JN. Other witnesses can request access 24 hours in advance.
03/27/25 – Zoning conditional use was approved. Building department has not issued the permit yet and the building department has ordered a halt on all work until a permit is approved.
04/24/25 – Permit has been approved and work resumed. Kennels were delivered on site. We are still on schedule to be complete by end of June.
05/29/25 – Phase 1 punch scheduled for 6/2. Phase 2 work complete by end of June.
06/26/25 – Fire alarm and electrical issues pushed back turn over of phase 1. Phase 2.1 punch complete.
07/31/25 – All punch work is complete. The exterior ramp begins next week. Closeouts to be submitted by Graybach.
08/26/25 – Project is complete. TTC working with Ian and Chris on Wi-Fi thermostats. RTU-7 does have issues but wasn’t part of project. Ian getting . Entrance ramp poured incorrectly. Corrected railing detail to be provided to Graybach.
08/28/25 – Ian getting prices to replace RTU-6,7 given the issues. JN said CVW met with CARES on the security camera, JN to get AIA, TTE to send XBE forms, keep this moving ASAP.
09/25/25 – Multiple issues with all washers. Supplier and plumber met onsite to discuss issues. They are being replaced. Railing work outstanding. Graybach to submit closeouts in next 2 weeks. Security Camera project to be in to John for review by Monday.
10/30/25 – Railings installed. Punch list sent to Graybach and work completed. Back punch to take place in near future. Closeouts received but have not yet been reviewed.
12/11/25 – Railing punch items addressed. Closeouts reviewed. Graybach to provide missing items.
02/26/26 – Closeouts delivered to County.
03/26/26 – No update. County to review closeout documents.
04/30/26 – Final items to be delivered to County.

Dane – Phase 2 Renovations Read More »

JC – Painting

PM: John Nester. Sam Hofmann
02/15/23 – Signed SOSS received. Painter to be hired by County.
03/30/23 – No Update.
04/27/23 – Meeting with Captain Wilson Scheduled for today.
05/25/23 – Meeting to finalize color selection to be scheduled in near future.
06/29/23 – Drawings will be ready by next week.
07/27/23 – Met with Sheriffs to finalize paint selections. Complete drawings to be given to county next week.
08/31/23 – 5th floor drawings provided. Final set to be complete.
09/28/23 – Final set to be sent next week.
02/29/24 – Final plans sent to County. Executive summary sent to Bert.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update. OK to archive.

JC – Painting Read More »

Comm Center – Lobby and Breakroom Renovation

PM: Rycca Thacker, Sam Hofmann
02/22/23 – Bid awarded to Alpha. Contracts are in progress.
03/30/23 – Contracts still in progress.
04/27/23 – Pre-construction meeting held. Submittals incoming.
05/25/23 – Some submittals received and returned. Permit approved. Construction is almost ready to begin.
06/29/23 – Construction ready to begin 2 weeks from notice from Rycca.
07/27/23 – Construction began this week. Most submittals complete.
08/31/23 – Construction ongoing. CO#1 in progress to add minor scope. TTE responded to the plumbing change order work with comments.
09/28/23 – Construction ongoing. CO#1 settled. CO#2 has not been agreed on.
10/25/23 – Construction ongoing. Change Order #2 rejected by TTE. Alpha to rework change and send back to us. Lights have been reworked in current ceiling configuration.
12/07/23 – Work is finishing up. Punch list held on 11/27. Back punch to be scheduled.
02/01/24 – Drinking Fountain cover still not acceptable, TE to work on better cover for the plumbing.
02/29/24 – Back punch items still unresolved. Closeouts in review.
03/28/24 – Waiting on hard copies from Alpha.
04/25/24 – Closeouts received. Check to see why its so large. Three hard copies still required with a thumb drive.
05/30/24 – Waiting on release of liens. TTC repaired the water cooler cover to give it more accessibility.
06/27/24 – No Update. TTC modified the EWC wrap so it’s better than it was.
07/23/24 – TTV replaced the pipe wrap again and it looks better than “better than it was”
08/29/24 – All closeouts received. Final pay app released. Ready to archive.

Comm Center – Lobby and Breakroom Renovation Read More »

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone)

PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/30/23 – Kickoff held on site. Sheriffs chose 7 doors for base bid and another 4 as an alternate. They will provide a few more doors to be added into the scope as alternates.
04/27/23 – Still waiting on additional doors from sheriffs.
05/25/23 – No update.
06/29/23 – List of doors and alternates has been provided. Drawings can be complete by end of month.
07/27/23 – Drawings will be complete by end of August.
08/31/23 – Drawings will be complete by end of September.
09/28/23 – Meeting held with Captain Wilson to confirm scope. Project will be out to bid 10/10.
10/25/23 – Project is out to bid.
12/07/23 – Bids returned. Cornerstone is lowest bidder. Bid review meeting held 12/5. Project now in contract phase.
02/29/24 – Cornerstone to send submittals in near future.
03/28/24 – Still waiting on submittals from Cornerstone.
04/25/24 – No Update.
05/30/24 – Submittals received and returned.
06/27/24 – Cornerstone field verification completed this week. Doors to be ordered.
08/29/24 – No Update.
09/26/24 – Cornerstone placed order. Pre-con meeting to be scheduled in near future.
10/31/24 – No Update.
12/12/24 – Cornerstone has material in hand. Coordinating best time with sheriffs and ongoing lock project work.
01/30/25 – Work to be scheduled in line with lock project corrections.
02/27/25 – No update.
03/27/25 – No Update.
04/24/25 – First Pod began. All frames installed but doors did not fit. New doors shipped immediately to finish the first pod. The rest of the doors will ship end of May.
05/29/25 – Pod complete and back punched. Next pod to begin next week.
06/26/25 – Next phase punch scheduled for tomorrow. Final phase to begin in 3 weeks.
07/31/25 – Next set of frames and Phase 4 frames to be manufactured together. 12 week lead time for delivery.
08/28/25 – Frames to be delivered mid september.
09/25/25 – Frames will be delivered next week.
10/30/25 – Cornerstone to remobilize monday.
12/11/25 – Phase 2, 3 and 4 have effectively merged into one project. All material is on site. Scope has been scheduled per unit with phase 2 and 4.
01/28/26 – Work Complete. Closeouts outstanding.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – Closeouts reviewed and missing items requested.
08/28/26 – No update.
09/24/26 – No update.
10/29/26 – No update.

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone) Read More »

JC – Sally Port Door Replacement

PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/28/23 – Kickoff held on site. design in progress.
04/27/23 – Overhead doors have been on site to assist with design. Bifold doors to be replaced with new bifold doors. Research needed for physical barrier to stop trucks from hitting garage doors.
05/25/23 – Two bifold door manufacturers are working on quotes. One has been out to site. Drawings in progress.
06/29/23 – Still have not received a quote. Followed up with manufacturers. Drawings in progress.
07/27/23 – Drawings can be complete by end of August.
08/31/23 – Drawings in progress. Nearly complete.
09/28/23 – Project will be out to bid 10/10.
10/25/23 – Project is put on pause until budget information is worked out.
12/07/23 – No update
02/29/24 – Submitted to ODRC for approval.
03/28/24 – State approval received. Final review set to be submitted 4/5.
04/25/24 – Request from the state requires additional design and funding. Waiting for further direction.
05/30/24 – No update.
06/27/24 – State approved the sally port door installation without the mini PLC system. Project to be bid out in near future.
07/25/24 – Project is out to Bid. Pre-bid scheduled for 7/30.
08/29/24 – Bids came in awardable. Robert Bell to review acceptable bids. Bid vet to be scheduled pending ok from Robert.
09/26/24 – Project in contract phase.
10/31/24 – Project still in contract phase. Preliminary site visit held for measurements.
01/30/24 – Submittals returned. Change order to receive hydraulic four-fold doors instead of electrical doors incoming. Kickoff to be scheduled closer to delivery of doors.
02/27/25 – Submittals returned. All doors by 4-fold are ordered and being delivered end of march. Change order #2 approved. Resubmittal for 4-fold door outstanding.
03/27/25 – All doors ordered. Alpha has mobilized to begin electrical work.
04/24/25 – Grant extension was approved. High-speed doors have been installed. North Sallyport doors are next. Trash compactor door has been added to the scope.
05/29/25 – Issue related to door and barrier arm connection has been solved. Overhead door to correct the issue next week. Bifold doors and trash compactor door to be delivered next week.
06/26/25 – North building complete. Change order to paint existing frames approved. Trash compactor door installation ongoing. Bi-fold door control units were delayed. installation to being next week.
07/31/25 – Doors punched yesterday. Multiple change orders requested on small items. Change order frame painting still outstanding.
09/25/25 – Pricing for various items still outstanding. Multiple issues with doors over the last month. Back punch to be scheduled.
10/30/25 – Back punch has yet to occur. Multiple failures this month have been recorded. Closeouts outstanding.
12/11/25 – Change order work outstanding. Meeting with Alpha and Overhead Doors to address continual failure of doors.
02/26/26 – Closeouts outstanding. Doors still having issues.
03/26/26 – No update.
04/30/26 – No update.
06/25/26 – Final closeout review complete. Pay app deadline of this friday.
07/30/26 – Closeouts delivered to County.

JC – Sally Port Door Replacement Read More »

2020 – Breakroom to Locker Room Renovation

PM: Sam Hofmann / County: John Nester

02/22/23 – SOSS received. Preliminary plan sent to John. Scope changed by new personnel.

03/30/23 – Kickoff held on site. Estimate in progress.

04/27/23 – Plans complete. Estimate to be complete in near future.

05/25/23 – Plans and estimate have been uploaded to archibus.

06/29/23 – No Update

07/27/23 – No Update

2020 – Breakroom to Locker Room Renovation Read More »

SPHQ – Academy Building Repurpose

PM: Sam Hofmann, Matt Butz
02/22/23 – SOSS received. Kick off to be held soon.
03/30/23 – Kickoff held on site with user. Matt to figure out budget and who pays for furniture. No movement until then.
04/27/23 – Design development on going. We will need one more meeting with users as we finish CDs
05/25/23 – Meeting held on site with users. Drawings in progress.
06/29/23 – Final review meeting held on 6/26. Discussed replacing clerestory windows. Window opening is not a glass block module so aluminum storefront and igu will be specified.
07/27/23 – Final review set submitted to county. Need to redo project manual with updated requirements.
08/31/23 – Project goes out to bid today.
09/28/23 – Bid opens today.
10/25/23 – Project was re-bid due to XBE paperwork not being filled out properly.
12/07/23 – Bids returned. Bid vet to be scheduled for this week.
02/29/24 – Projects kicked off. Submittals received and being returned.
03/28/24 – Construction to begin 4/1.
04/25/24 – Construction ongoing. Romex was found in the building not in conduit. We will get a cost to upgrade the electric to conduit on this job. We have removed the sink from the job and will take a credit for that work.
05/30/24 – Construction ongoing.
06/27/24 – Construction ongoing.
07/23/24 – Const Mtg onsite but little progress from last meeting.
08/29/24 – Progress being made. Tumlin removed wrong water fountain.
09/26/24 – Paint and casework mostly complete. Flooring getting installed next week. New wifi getting installed TTC to follow up.
10/31/24 – Punchlist issues, but additional work is needed. Deteriorated window sills needs to be fixed, EWC question sent today to TTE.
12/12/24 – Punchlist distributed. Sheriff are happy with new space. TTC replaced thermostats and put them on WIFI.
01/30/25 – Project complete. Closeouts to be submitted by Tumlin.
02/27/25 – Tumlin will be onsite for punch items. Closeouts outstanding.
03/27/25 – One punch item outstanding. Closeouts outstanding.
04/24/25 – Closeouts outstanding. Final pay app submitted by Tumlin will be held until closeouts are received.
05/29/25 – Parts missing. Tumlin to complete closeouts.
08/28/25 – No Updates.
09/25/25 – No Updates, we are still waiting on closeout documents.
10/30/25 – Closeout updates have been received from Tumlin. We will review to determine if they are acceptable.
02/26/26 – Closeouts given back to Tumlin to correct and return.
03/26/26 – Closeouts in Countys hands.

SPHQ – Academy Building Repurpose Read More »

525 – EMA/JFS/513 Office Renovations

PM: Bert Watts, Mike Murphy, Paul Bellman, Terry Cannon

01/25/23 – SD and Cost complete.  Created new category and started tracking EMA renovation.  CD documents have been started.  THP and TTE starting overhead door early project.  BW sent information for design.
02/22/23 – User meetings complete. DD in progress from user meeting changes.
03/30/23 – Met with JFS last week. Need to get approval on design from users.
04/27/23 – Meeting on site with JFS scheduled for 5/5. Design development to proceed after that. Update old estimate with new cost for revised design. Cost is due in two weeks. Champlin to send revised plans. Include owner required items in the new cost including blue brick screen wall that is coming down, new sidewalk, plus other owner items.
05/11/23 – Champlin requested updated opinion of probable cost with updated scope of work.
05/17/23 – THP provided updated opinion of probable costs for structural scope of work.
05/17/23 – THP provided SOSS for DD through CA services based on new scope of structural work.
05/21/23 – ThermalTech DD cost updated in Archibus and shared with the team. Drawings are being updated this week.
05/25/23 – Drawings and estimate have been uploaded to Archibus. Landlord improvements have been marked with a (C).
06/12/23 – THP – Champlin returned executed Contract for DD-CA Services.
06/29/23 – No updates from THP.
06/29/23 – Final plans have been approved by users. follow up information to be provided to County this week. CDs in progress.
07/27/23 – 95% Review set submitted to County. Page turn with users to be scheduled.
08/09/23 – THP updated structural work and fees to the Archibus project estimate.
08/31/23 – Updated department breakdown plans and estimate. User page turn to be scheduled in near future.
09/27/23 – THP waiting to hear from Champlin about the page turn meeting with Hamilton County.
09/28/23 – Review meeting held with EMA. minor changes to plans made. JFS and 513 meetings to be scheduled.
10/25/23 – THP sending bid set to Champlin. Meetings held with all users. Final owner review sent to County for landlord approval.
11/22/23 – Building owner has approved the Phase 2 renovation plans. THP to send Bid Set to Champlin once bid date has been set.
12/06/23 – THP to send Bid Set to Champlin for 12/15/23 issuance.
12/07/23 – Received final approval from landlord and County. Bid issuance on 12/15.
01/04/24 – Project advertised to Bid.
01/18/24 – Pre-bid meeting on site.
01/25/24 – Addendum #1 issued.
01/29/24 – THP sent stamped permit set to Champlin.
02/07/24 – THP Addendum #2 issued. Unit prices and details for CMU tuckpointing and CMU replacement were included.
02/22/24 – THP – Bid Opening. 4 bids received (Alpha Construction, John P. Tumlin & Sons, Leo J. Brielmaier, and Triton Services). Champlin to evaluate bids.
03/28/24 – Contract phase ongoing.
04/19/24 – THP – Approved construction contract approved by the Board of County Commissioners and sent to project team.
04/23/24 – THP – County issued PO for the project to the team. Pre-construction meeting tentatively scheduled for 05/03/24 afternoon.
04/25/24 – Contracts finalized. Project kickoff tentatively scheduled for 5/3.
05/03/24 – Pre-construction meeting with full team at project site.
05/30/24 – Kickoff held. Submittals in progress.
06/27/24 – Pre-mobilization meeting scheduled for 7/12. RTU submittals have been rejected, TEI trying to get submittals on approved manufacturers.
07/12/24 – THP reviewed front entry slab drainage issue with Hamilton County.
07/12/24 – Pre-mobilization meeting with full team at project site.
07/25/24 – Construction to begin Monday.
08/28/24 – THP returned structural shop drawings to Champlin.
08/29/24 – Construction ongoing. More abatement to be completed next week. Demo almost complete.
09/26/24 – Construction ongoing. Main sewer line underslab is damaged beyond use. Tumlin to report on extent of damage. CO2 is being discussed and finalized. THP will return approved Masonry Lintel shop drawings to Champlin on 9/26. Water test is complete and Fire Protection calculation underway.
10/29/24 – THP responded to Champlin regarding Masonry repairs. Hamilton County to determine extent of repairs.
10/31/24 – Construction ongoing. Change order 2 and 3 approved for sanitary line work and fire protection changes.
12/06/24 – THP visited the site to coordinate supplemental steel with Thermal Tech and Tumlin to help with the response to RFI 23. THP issued a field report for review by Thermal Tech.
12/12/24 – Work ongoing. Forest Park has provided report stating that any combustible material will need to be removed. We believe the wood studs would be grandfathered in compliance. Champlin to investigate.
01/27/25 – Work progressing, Tumlin stated they would be complete at the end of February. ThermalTech (TTC) trying to schedule a coordination meeting between Emcor, Bison, and KW about final controls scope between project and state term work. Rooftop units not onsite yet but should be arriving soon. Plumbing rough-in mostly complete. Forest part has approved our fire protection permit and Preferred Fire should mobilize soon to the site for sprinkler work. According to Tumlin, we will not have to move all the trucks parked in the warehouse for the sprinkler work (all sprinklers in the Northeast Warehouse must be replaced with 11.2 sprinkler head).
02/26/25 – Work continues in space. GC, MC, EC, FPC are all on site performing work daily. PC coming back soon when the fixtures will be installed. TTE bringing Wi-Fi plan to Friday meeting. Several COR have come in this week, HC asked for the Fire Pit cost too, the permit needs to be amended for the additional inspection. We will get a scheduled update this Friday.
03/11/25 – HVAC Engineering Change drawing sent to Tumlin for their submission to FP for the return air openings on the first floor.
03/23/25 – TTE returned another set of controls submittals to Emcor for the ALC controls. Bison has not confirmed if we can get BACnet thermostats or now. ALC planning on interfacing through the SystemVu controllers in the RTU units.
03/25/25 – Plumbing Engineering change drawing set to Tumlin to give to Carrigan to give to FP for the natural gas adjudication letter received last week. ThermalTech continues to answer questions from the contractors working towards permit approvals.
03/27/25 – Pricing for Bulletin#3 received. Substantial completion date set at May 9th.
04/24/25 – RTUs delivered a month ahead of schedule and have been installed. Fire pit work ongoing. Railings will not be delivered and installed before May 9. Signage quote approved.
05/19/25 – THP visited the site to review supplemental steel.
05/29/25 – Punch list sent last week. Railing scheduled for delivery this week. Tumlin to schedule final inspection. Signage to begin install tomorrow.
06/24/25 – ThermalTech onsite this week working on HVAC issues. We are scheduled to come back for troubleshooting with MC and CC Friday at 7am. Emcor video was sent out from Ben.
06/25/25 – Final inspection complete. CO will be signed when Rafic returns. Ribbon cutting tomorrow.
07/31/25 – Ribbon cutting ceremony held. Several punch items still outstanding. Tumlin to begin closeouts. As-Builts not received yet. Emcor controls out this week for finalizing the new DDC controls..
08/28/25 – Tumlin confirmed all work is complete. Back puch to be scheduled. Closeouts outstanding.
09/25/25 – Backpunch complete. As-builts received. closeouts outstanding.
10/30/25 – Closeouts outstanding. Official CO received.
12/11/25 – No update.
01/28/26 – Closeouts in review.
02/26/26 – Waiting on closeout corrections.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
08/28/26 – Tumlin provided update on missing items.
09/24/26 – No Update.
10/29/26 – Closeouts received

525 – EMA/JFS/513 Office Renovations Read More »

230 – Magistrate & Mediation Construction

PM: Matt Butz, Sam Hofmann
09/29/22 – Two projects combined into one Construction project. Some furniture will be reused.
10/21/22 – Contracts finalized and Pre-construction meeting held. Kick-off meeting to be scheduled when submittals are returned.
12/15/22 – Kick-off meeting to be scheduled
01/26/23 – Kick-off meeting held. Construction to start in near future. Waiting on all background checks to return.
02/01/23 – Notice to proceed issued.
02/22/23 – Construction on going. First progress meeting held.
03/30/23 – Construction ongoing.
04/26/23 – ThermalTech reviewed the HVAC and Fire RFI’s and discussed final design for these services.
04/27/23 – Construction on going. Will move onto 9th floor this month.
05/25/23 – Punch completed for 11th and 12th floor. Construction started on 9.
06/29/23 – 11 and 12th floor punched. Work is underway on 9th. Everything to be complete by end of month. HVAC and Electric change orders approved, TTE to cover these cost.
07/27/23 – 11 and 12th floor nearly complete. 9th floor to be complete mid august. Waiting on Alpha to provide pricing for potential flooring change order TTE provided a 10″ neck diffuser for Alpha to get installed. Trades will help clean up the 11th floor inefficiencies. Inspections are complete for MEP on 9, 11, 12 floors. 9th floor punchlist coming up soon. Barth talked to Delta and they may be able to provide two can lights for the Reception area from leftover stock.
08/31/23 – Added flooring on order. Install at end of September. Work on 9 is finishing up. a pre-punch list has been submitted to Alpha for less than satisfactory work.
09/28/23 – Alpha has not completed contract work yet. New flooring to begin on 10/3.
10/25/23 – Contract work is still not complete. Flooring has been pushed back until the space can be occupied. No firm install date scheduled.
12/07/23 – All work is complete. Minor punch list items outstanding.
01/31/24 – Closeout documents received. TEI noted there were not redline markups for as-built drawings received for this job.
02/29/24 – Punch list items complete. closeouts in review.
03/28/24 – Hardcopies from Alpha outstanding.
04/25/24 – Closeouts received.
05/30/24 – Waiting on release of liens.
06/27/24 – Closeouts still outstanding.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – Final pay app returned.
09/26/24 – Flooring still not great but ready to Archive.

230 – Magistrate & Mediation Construction Read More »

Animal Shelter – Dane St Renovations

Project Managers: Mike Murphy, Bert Watts
05/26/22 – SOSS requested to move forward with design. BW provided updated scope for access to the Animal Shelter buildings.
06/30/22 – SOSS approved for Northside building to be converted to animal shelter. Preliminary schedule provided to County. Site visit to be scheduled.
08/25/22 – Site visit performed. Held user meetings to define scope. Work in progress.
09/25/22 – ThermalTech directed to submit their own SOSS’s for this project for regular and small scopes.
09/29/22 – Conceptual plan and estimate to be submitted 9/30
09/29/22 – TEI SOSS has been submitted to BW for approval.
09/30/22 – Conceptual plan and estimate submitted to County.
10/27/22 – ThermalTech electrical & mechanical cost estimates are done. We are working on drawings and plumbing estimates now.

12/15/22 – SD plans and estimates complete

01/26/23 –  No Update

02/22/23 – No Update

03/30/23 – No Update

04/27/23 – No Update

05/25/23 – No Update

Animal Shelter – Dane St Renovations Read More »

JC – Courtrooms A&B Upgrades

PM: John Nester, Derrick King
07/27/22 – Project created. SOSS is approved. Fieldwork started with Champlin and TEI. Champlin has updated & sent Revit model to TEI for design purposes. The ceiling in one of the rooms will be lowered 24″ in one Courtroom and will stay the same in the other Courtroom. We may need more fieldwork for the non-lowered ceiling for spacing below utilities.
08/22/22 – Review set sent to county
09/29/22 – Project out to Bid
10/27/22 – Triton awarded bid. Contracts in progress.
12/15/22 – Submitted for permit. Still waiting on contract.
01/26/23 – Contract finalized. Background checks submitted.
02/22/23 – Kick-off meeting scheduled for next week.
03/30/23 – Schedule updated, Triton to start next week on this job. Some submittals have been received and returned.
04/25/23 – ThermalTech met Triton onsite for plumbing routes and final connections in closet.
04/27/23 – Construction on going.
05/25/23 – Construction on going. Triton working on getting the steel sub on site.
06/29/23 – Drip pans are on site but not installed, we are waiting on sealing to be completed and reviewed. Construction is ongoing.
07/12/23 – Pans arrived, TTE rejected them due to size and configuration. Triton is taking back to fabricator for reforming. TTE suggested Triton go pick one up for immediate installation.
07/26/23 – Meeting cancelled and moved back one week.
07/27/23 – Construction ongoing.
08/31/23 – Construction ongoing. Courtroom B finishing up. Construction on A started.
09/28/23 – Punchlist for B to be scheduled soon. Drip pans to be installed in A next week.
10/25/23 – Drain pans installed. Finish work ongoing.
10/26/23 – Sprinkler contractor should be onsite this week to start moving and reworking sprinkler heads and systems. JW checking on final sealant for pipe penetrations from second to first floor for us (below and above). Drain pipe in hallway not complete as of last meeting.
01/31/24 – Both courtrooms at punchlist stage. Triton working on final details. New change order submitted for new pans for additional leaks discovered during first use. TE and JN agree new price is better than original submission. Bench refinishing change order work still ongoing. New anchors are being installed on benches when they are reinstalled. New bullet proof glass has been installed but needs to be cleaned by Triton for the full height of the glass. Need change order for back hallways.
02/29/24 – Change order approved for pans above magistrate benches. Triton needs to insulate domestic water piping repair and provide change order for work above ceiling tiles. John asked for construction meeting before demolition. TTC to check on electrical work.
04/25/24 – New leak found. Punch items in progress.
05/28/24 – Ceiling tile fell in Courtroom B. JN, Triton and TTE responded to see and cleanup the damage. An Acorn valve failed up on the third floor.
05/30/24 – Change order work wrapping up.
06/27/24 – Work to be completed this week. Closeouts in progress.
07/02/24 – Triton submitted air balance report today and it was rejected by TTC. Airflows were fine, project data was wrong and AHU data are missing.
07/08/24 – Balance report submitted and accepted by ThermalTech.
07/18/24 – Triton reported all the work in the back hallways was complete
07/19/24 – Nick reported that the plumbers will be back third shift to install the final plastic pan above the ceiling next week.
07/25/24 – Work complete. Closeouts received. Need to be reviewed.
08/29/24 – No update.
09/26/24 – No update.
02/27/25 – Final closeouts received. Need to be confirmed complete.
03/27/25 – No update.
04/24/25 – No update.
05/29/25 – No update. We need Triton subs Release of Liens and certified payrolls affidavit.
07/31/25 – John says closeout documents look good but they need final payment for this job.
08/28/25 – Ready to Archive.

JC – Courtrooms A&B Upgrades Read More »

125 – Public Defender Relo 3,4,5,8,9

PM: Mike Murphy, Rycca
07/20/22 – SOSS Approved. Site visit to be scheduled.
07/27/22 – TEI to send 230 PD from original renocation.
08/19/22 – Preliminary plans sent to HC for review.
09/7/22 – Kickoff meeting held with Users. Program survey sent out.
09/29/22 – Program sent to county. Scheduling next round of planning meetings in progress.
10/18/22 – Meeting held to confirm Program. One department remaining to confirm. Conceptual planning to begin.
12/15/22 – Work on pause until further notice
01/26/23 – No Update.
02/22/23 – 2 options of test fit plans sent to Rycca. One with Guardian Ad Litem in building, one with Guardian Ad Litem moved to another facility.
03/23/23 – ThermalTech performed fieldwork on the 5th floor this week for HVAC, electrical, fire protection and plumbing.
03/30/23 – Meeting with users. Plans as developed are generally ok. however, the building has signed a 2 year lease with a tenant on the 6th and 7th floor. Meeting scheduled for next week to re-phase the department renovations.
04/27/23 – Site visit to verify all existing conditions. SD development ongoing.
05/21/23 – ThermalTech SD Cost and markups uploaded to Archibus for mechanical systems.
05/25/23 – Champlin plans complete. Estimate will be uploaded to Archibus next week.
05/29/23 – Plans and estimate uploaded to Archibus.
06/29/23 – No Update. In meeting we found out the 8th floor won’t be early occupied. Cost seems high per square foot.
07/27/23 – Provided answers to minor questions and broke down cost estimate further.
08/31/23 – County provided some VE changes. Drawings and estimate to be revised by 9/8.
09/28/23 – Archibus estimate and drawings have been updated with the requested changes.
12/07/23 – No Update.
01/24/24 – Partners responded to Cushman email on lower build-out cost with a review of the design build estimate. Count to use as needed.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
06/27/24 – No Update.
06/27/24 – OK to archive, they will use the 8th floor with minimal renovation. Next steps leasing options.

125 – Public Defender Relo 3,4,5,8,9 Read More »

264/2611 – ADA Assessments

PM: John Nester, Mike Murphy
05/26/22 – Schedule site visit.

06/30/22 – Site visit complete. Report in progress

08/23/22 – Finalizing report.

09/29/22 – Report to be submitted by end of next week

10/27/22 – Adding cost estimate into report. To be finalized and submitted in near future.

12/15/22 – Report to be submitted soon.

01/26/23 – Report submitted county with final pricing.
02/23/23 – Ready to Archive.

264/2611 – ADA Assessments Read More »

230 – Magistrates Lobby Security Upgrade

02/08/22 – Signed SOSS Received.
03/29/22 – DD Kickoff meeting.
04/15/22 – Comments received from Scott and plans adjusted accordingly. 100% review meeting mid may.
05/17/22 – Review meeting with With Scott. Plans adjusted according to his comments.
05/26/22 – Project combined with Mediation. Review set due June 2 Arch and MEP.
06/30/22 – Project in bidding phase.
07/28/22 – bidder recommendation letter sent.
08/25/22 – Building Permit applied. Contracts in progress
09/29/22 – Contracts finalized. kick off meeting to be scheduled in the near future. Construction Project move to a combined construction project.

230 – Magistrates Lobby Security Upgrade Read More »

JC – 2022 Cell Door Replacement (Ph 2 Triton)

PM: Matt Butz, Sam Hofmann
01/21/22 – Signed SOSS Received.
03/23/22 – Meeting with Sheriffs to define scope. Number of doors defined. Hold pending door lock replacement project scope.
06/30/22 – Scope to be defined at project kickoff meeting for current set of doors.
07/28/22 – Scope to be defined at project kickoff meeting for current set of doors.
08/23/22 – Scope finalized. Plans to be sent and confirmed with sheriffs.
09/29/22 – Project out to Bid
10/27/22 – Triton won bid.
12/15/22 – Contracts signed and returned.
01/26/23 – No update.
02/25/23 – No update.
03/30/23 – Triton has subbed Jails Products again. Submittals to arrive shortly.
04/27/23 – No Update.
05/25/23 – No Update.
06/29/23 – No Update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – Kick off to be scheduled close to delivery.
03/28/24 – Triton asked question. Site visit to confirm to be scheduled for next week.
04/25/24 – Waiting on sheriffs to answer keying questions.
05/30/24 – Questions sent to Triton. Triton has not responded.
06/27/24 – New project manager assigned to project. Doors to ordered in near future.
02/27/25 – Doors are ordered and scheduled for delivery the last week of April.
03/27/25 – No update.
04/24/25 – Mobilization scheduled for early May.
05/29/25 – Delivery was delayed. mobilization scheduled for mid June.
06/26/25 – Mobilization scheduled for Monday.
07/31/25 – Frames came in with incorrect dimensions. They will all be modified by Triton and remobilized in a couple weeks.
08/28/25 – Modified frames were manufactured for thicker wall dimension. Triton to provide correct frames as soon as possible.
09/25/25 – Corrected frames will arrive with Cornerstones delivery.
10/30/25 – Frames to be delivered monday. Triton to mobilize and complete their scope.
12/11/25 – Triton discovered that the doors were the wrong thickness. Cornerstone doors can be used to cover all but one of their doors. The one door has been ordered and will be delivered shortly.
01/28/26 – Door delivery date has been pushed back. Work has been paused.
02/26/26 – Door still not delivered. Door suppossedly will be delivered tomorrow. two more doors in this project once the door delivered is completed.
03/26/26 – Final phase to begin next week.
04/30/26 – Frames came in the wrong size. Frames to be delivered next week. Project to be complete end of May.
05/28/26 – Cornerstone to complete final pod for Triton. 6/24 install date.
06/25/26 – Demo revealed damage to block walls. Change order accepted. Cornerstone to complete work. Mobilized this week.
07/30/26 – Work is complete. Closeouts ongoing.
08/28/26 – No Update.
09/24/26 – Change order to order new millenium pac units submitted. No update on closeouts.

JC – 2022 Cell Door Replacement (Ph 2 Triton) Read More »

TPC – Risk Management Renovation

PM: John Nester, Sam Hoffman, Mike Murphy, Terry Cannon
04/29/21 – TEI and Champlin on board with providing programming for this work for the current SOSS in place. Discuss with John and Bert after partner meeting.
05/19/21 – Kick-off meeting held to review scope.
05/20/21 – Champlin sent County preliminary layout of Scenario 1
05/25/21 – User meeting with Rodney Lofland. Review his stated program needs.
06/16/21 – Met with Risk Mgmt and reviewed Champlin proposed floor plans. Got input from the department and discussed needs for space from the Architectural Review. We also started the MEP needs of the space and settled on some basic requirements for HVAC zoning, plumbing use, and security requirements. They do want a kitchenette for a sink, coffee pot, microwave, and refrigerator.
06/25/21 – Sent updated floor plan to County.
07/29/21 – Two estimates will be done. One with 900 SF, one for 2500 SF. County will open the Archiubs estimate for us to put our numbers in. Put the small estimate in as a line item change in the larger estimate. Get number and get schedule.
10/18/21 – SD and Estimate uploaded to Archibus. Provided plans and estimate for a base, upsize and downsize option. ThermalTech drawings, cost and archibus updates also complete.
01/27/22 – Should have a decision on budget and option on Tuesday.
02/22/22 – DD-CA SOSS submitted.
03/31/22 – Signed SOSS received. Deadline of end of April to be Bid ready.
02/25/22 – Signed SOSS Received.
04/06/22 – Kickoff meeting scheduled, to be complete by the end of April.
04/28/22 – Requested Plan review confirmation meeting mid-May. TTC combined our version with Champlin version, we will continue with the Champlin version from here on out.
5/12/22 – Review meeting held. Revised layout approved. TTE to get started on design and Champlin to finalize finishes.
06/30/22 – Project issued for bid.
07/28/22 – Bids received. bid review 7/26
08/23/22 – Building Permit applied for. Contracts in Progress.
09/29/22 – Contracts finalized. Kickoff meeting to be scheduled in the near future.
10/13/22 – Pre-construction meeting held. Kickoff meeting to be scheduled once submittals are returned.
12/15/22 – Construction ongoing.
01/26/23 – Construction on going. Schedule pushed back to be substantially complete on 2/20/23.
02/22/23 – Construction not complete. Will need a couple more weeks.
03/30/23 – Punch list completed 3/29.
04/27/23 – Still waiting on various punch list items to be complete.
05/25/23 – Furniture installed. Triton to send signed off punchlist.
06/29/23 – Waiting on closeout documents
07/27/23 – Extra permit withdrawal paperwork sent to Triton Jeff to give to city. Check and make sure they done.
08/31/23 – No update.
09/28/23 – No Update.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – Closeouts received
03/28/24 – Hardcopies outstanding.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
07/24/24 – Additional request sent to Triton for closeout documents.
08/29/24 – No Update.
09/26/24 – No Update.
12/12/24 – Requested updates last month. No update.
01/30/25 – Meeting held with Triton and County to go over outstanding items for several projects.
02/27/25 – Final Pay app processed.

TPC – Risk Management Renovation Read More »

OMJ Accessibility Entrance Study

02/08/22 – Signed SOSS Received. Scope reduced to exterior entrance only.

03/31/22 – Field verification complete. Plan and estimate in progress.

04/28/22 – Work in progress.

5/26/22 – Civil Engineer to provide Champlin with drawings end of day friday 5/27. Final set can be ready to review the following week.

6/30/22 – Bid set and project manual submitted to County for final release.

07/28/22 – One bid came in above 50,000. Bid review to be completed to determine ITB advertised estimate.

08/23/22 – Project out to bid. Pre-bid meeting scheduled for 8/31.

09/27/22 – Bid awarded to Prus. Contracts in progress.

10/27/22 – Pre-construction meeting scheduled for 11/4

12/15/22 – Construction complete.  Punchlist by county and champlin complete. Punchlist by Kleingers to be scheduled.

01/26/22 – Punchlist sent to Prus. They are to fix items that need correcting and confirm slope conforms to code requirements.

02/22/23 – Punchlist completed. Waiting on closeout documents.

03/30/23 – Waiting on closeout documents.

04/27/23 – Close out documents received.

05/25/23 – Waiting on Prus to send final pay app.

06/29/23 – Close outs and final pay app received.

OMJ Accessibility Entrance Study Read More »

A&D – JFS Furniture Redesign DD-CA

02/08/22 – Signed SOSS Received. Kickoff meeting scheduled for 03/22
03/22/22 – DD Kickoff meeting held. Weekly meetings scheduled for friday mornings for duration of DD phase.
04/13/22 – THP requested to review proposed cabinet layout on the fifth floor on the west side of the building.
04/14/22 – THP – Champlin approved THP proposal.
04/22/22 – Weekly DD meetings in progress.
04/26/22 – THP reviewed the cabinet location and analyzing the conditions.
04/28/22 – Kevin asked about dehumidification in the basement. ThermalTech to look at existing conditions and trending this area. Three months DD and three months CD; inclusion meeting during CD phase.
05/27/22 – Weekly DD meetings in progress.
06/30/22 – Weekly meetings complete. DD drawings to be submitted 7/1, DD estimate 7/8.
07/28/22 – Weekly CD User group meeting to start end of august.
08/23/22 – First weekly meeting scheduled for 8/26.
09/29/22 – CD ongoing. Last progress meeting scheduled for 9/30.
10/17/22 – ThermalTech conducted several field trips back to the building for final design
10/26/22 – LEED Checklist returned to Champlin from ThermalTech with comments and suggestions. Drawings, titleblocks, spec headers all being coordinated wth Champlin.
10/26/22 – Final Owner Review meeting scheduled for 10/28/22.
10/27/22 – Friday final owner review will be electronic review. Print three 11×17
12/15/22 – Project out to bid.
01/26/23 – Project still in bid phase. final addendum to be sent out next thursday. Bid opens 2/9.
02/14/23 – Bid opening – Universal is apparent low bidder
02/22/23 – Bid Review is scheduled for 3/3. Meeting rescheduled to two weeks from now. Furniture package is currently under review. Champlin has requested additional information from furniture vendor.
03/30/23 – Champlin sent Letter of Recommendation for Universal. County still deciding whether to move forward with contract with Universal.
04/27/23 – Universal answered several follow up questions. County is proceeding with awarding the bid to Universal. Contract is in progress.
05/25/23 – Monthly meetings with users scheduled.
06/29/23 – No update.
07/27/23 – No update.
08/31/23 – No update.
09/28/23 – No update.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – No update.
03/28/24 – No update.
04/25/24 – No update.
06/27/24 – No update.
08/29/24 – No update.
09/26/24 – No update.
10/30/24 – No update.
12/12/24 – No update.
01/30/24 – No update.
02/27/25 – OK to Archive.

A&D – JFS Furniture Redesign DD-CA Read More »

CH – Bronze Door Repair

PM: Matt

02/15/22 – Signed SOSS received.
03/31/22 – Field investigation completed. Preliminary drawings completed. We have been in contact with several historic door restoration companies.
04/28/22 – Drawings at 75% complete. Need to schedule a review meeting.
05/10/22 – Review meeting with Rycca. Determined more documentation per door is needed.
06/30/22 – Bid package to be finalized and submitted for final review.
07/28/22 – Additional site visit performed. detailed scope photographs added to drawing set.
08/24/22 – 95% check set sent to HC.
09/29/22 – Project out to Bid
10/27/22 – Olek won bid. West doors and Cleaning awarded. Contracts in progress.
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Call with Olek, County and Champlin to discuss details of kickoff meeting. kickoff meeting to be scheduled by end of February.
02/22/23 – Kickoff meeting to be scheduled in near future. Champlin has reached out to Olek twice for dates.
03/30/23 – Kickoff held on site. Preliminary schedule received. Olek to provide firm dates as we near demolition.
04/27/23 – Doors have been removed and sent to New Jersey for refurbishment.
05/25/23 – Doors have been taken apart and analyzed. Doors are in better shape than anticipated. Submittals to come soon.
06/29/23 – Photographs received. Work in progress.
07/27/23 – Restoration ongoing. restoration revealed that the door pulls were originally nickel plated. Change order to nickel plate the door pulls in progress.
08/31/23 – Olek to return to site 9/11. Test fit of closer complete.
09/28/23 – Olek cleaned existing bronze and prepped hardware installation. No crocs in sight.
10/25/23 – Construction ongoing. County requested pricing for additional bonze cleaning.
12/07/23 – Installation scheduled tentatively for march. Olek returned pricing for all items requested.
02/29/24 – Change orders approved. Several doors are complete. Still on schedule for late March Install.
03/28/24 – Doors to be installed first week of April. Site and prep work will continue into the following week.
04/25/24 – Doors to be installed in may. Firm dates to be determined.
05/30/24 – Olek is on site. Two doors are in. One Torchiere was blown over in a storm. Olek is shipping damaged parts to their shop.
06/27/24 – Work on site complete. Olek will need to come back for punchlist work. Matt ask Murphy to review final retainage payment submit.
08/29/24 – Olek needs to come back out to complete punchlist.
09/26/24 – No Update.
10/31/24 – Olek was back on site for the punch work. They did not complete the list and will need to come back.
12/12/24 – Olek came back for the back punch work but did not complete their work. They will be back for the punch and for a closer warranty issue.
01/30/24 – Olek still has punch work to complete. close outs to be submitted.
2/27/25 – Scott reached out to olek to request closeouts and a timeline for punch work. The closeouts are in progress. The punch work will be done in tandem with the first phase of the north and south doors.
03/27/25 – No Update.
04/24/25 – No Update.
05/29/25 – No Update.
06/26/25 – No Update.
10/30/25 – No Update.
12/11/25 – No Update.
01/28/26 – Olek to complete punch work when on site next.
02/26/26 – Olek onsite March 9th to finish punch work.
03/26/26 – Olek is onsite. Punch work is in progress.
04/30/26 – Work is complete. Closeouts nearly complete.
06/25/26 – No update.
07/30/26 – No update.
08/28/26 – No update.
09/24/26 – No update.

CH – Bronze Door Repair Read More »

JC – Cell Window Screen Project

PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received.
01/25/22 – Preliminary plans and schedule created. Will be discussed at JC Door replacement Kick-off.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress
06/30/22 – Documentation in progress
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Triton was apparent low bidder but their product did not meet specs. They are saying that they can provide the correct product for 1.6 million.
03/30/23 – Triton pulled their bid. Fabcor was the next lowest bidder. Contracts in progress.
04/27/23 – Contracts returned. Fabcor is starting the submittal process.
05/25/23 – Kickoff meeting held on site. Fabcor to finalize submittals for ORDC review. Fabcor to schedule site visit to field verify all dimensions.
06/29/23 – 4 Screens to be installed prior to the rest as a trial. submittal returned. Jails yet to schedule installation.
07/27/23 – Windows are on order. Jails has been on site to measure the remaining window sizes.
08/31/23 – 4 test screens to be installed next week. County to get approval from state for the rest of the screens.
09/28/23 – Test screens installed and reviewed. List of items from Champlin and Jails sent to Kane for review before the large install. Still waiting on State approval to return submittals.
10/25/23 –  State approved submittals. Sample from Kane that fixed mock up issues received. Review meeting scheduled with Captain Wilson 10/26.
12/07/23 – Comments from mockup returned to Jails. Jails to follow up with a schedule.
02/29/24 – Schedule provided by Jails. Install to begin in April.
03/28/24 – Install to begin 4/1.
04/25/24 – Installation ongoing. North 5th floor to be complete next week.
05/30/24 – Installation ongoing. South 5th floor to be complete next week.
06/27/24 – Installation ongoing.
08/29/24 – Installation ongoing.
09/26/24 – Installation ongoing. Lexan CO approved. Day space CO in progress.
10/31/24 – Installation ongoing.
12/12/24 – Installation ongoing. Day space CO approved. Quote to add Lexan to previously installed screens incoming.
01/30/25 – Installation ongoing. Lexan install in psych unit ongoing. Dayspace screens to be installed next.
02/27/25 – Original contract work complete. Dayspace area is ongoing. Second round of Lexan install ongoing.
03/27/25 – Dayspace mock up rejected. Revised submittal returned. Correct mockup to be installed prior to manufacturing of the remaining dayspace screens.
04/24/25 – Revised mock up also rejected. Kane to provide solution to prevent mesh damage.
05/29/25 – Kane provided solution. Mock up revision #2 to be installed.
06/26/25 – Mock up approved. Manufacturing of dayspace windows to begin.
07/31/25 – Delay from steel mesh manufacturer pushes install into October/November.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Jails will remobilize end of november.
12/11/25 – Day space installation ongoing.
01/28/26 – Scope to be complete by end of 2/6. Closeouts requested.
02/26/26 – CO work is complete. Additional screens in Med unit is requested. Awaiting pricing from Jails.
03/26/26 – CO approved for Med unit screens. Delivery date to be provided by Jails.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – Closeouts in progress. final change order screen installed.
07/30/26 – Closeouts reviewed. Missing items requested. OK to close out the project.

JC – Cell Window Screen Project Read More »

JC – Cell Door Lock Replacement (Cornerstone)

PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received
01/26/22 – Plans and Schedule created. Will be discussed at JC Door Replacement Kickoff.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress.
06/30/22 – Documentation in progress.
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Bid opening is pushed to 3/3. Final addendum to be issued before 2/28.
03/30/23 – The bid has been cancelled. An invitation for manufacturers to demo their products has been put out for 4/5.
04/05/23 – Manufacturer presentations held. Willo, Airteq, and Habersham displayed their products to the county and sheriffs.
04/27/23 – Revised bid sent to the prosecutors office for review. Once approved, the project will be ready to rebid.
05/25/23 – Project has been rebid. Pre-bid meeting is 6/2.
06/29/23 – Bids received. Project is awardable.
07/27/23 – Lowest Bidder – Jails – bid is under review with prosecutor to determine if bid is awardable. Second lowest bidder – cornerstone – vetted.
08/31/23 – PO is approved and contract has been sent. Kickoff meeting to be held in the near future.
09/28/23 – Kickoff meeting held. Site visit to measure existing conditions scheduled for week of 10/9. 4 cell mock up to be scheduled at site visit.
10/25/23 – Site visit occurred. Mock up submittal returned. Mock up installation to be scheduled in near future.
12/07/23 – Mock ups to be installed 1/9.
02/29/24 – Mock ups ran into trouble connecting with the PLC. Cornerstone could not figure it out onsite. They sent locks to be tested by Stanley. Locks have not been successfully programmed yet.
03/28/24 – Stanley determined that the locks can be used with modification to the PLC system. Cost of the upgrade is around $500,000. Conversation of next steps ongoing.
04/25/24 – Working mock-ups installed. Schedule to be determined for Securitas to be on site for upgrading power.
05/30/24 – Work to begin 6/17. Work is expected to take 2-3 weeks per floor.
06/27/24 – Locks delivery was delayed. The locks had to be re-programed. Cornerstone to overnight one re-programed lock to ensure functionality. Prep work on George 51 is complete.
07/24/24 – Matt punchlisted project last Sunday. They met the State on Monday. One door hitting the wall, so we need to add a new bumper.
08/29/24 – Installation ongoing. Cornerstone getting to a unit per 2 weeks.
10/31/24 – Installation ongoing. No issues have been resolved by airteq regarding quality control. Meeting to discuss issues with Cornerstone and Airteq will take place next week.
12/12/24 – Installation ongoing. Power upgrade is complete. Rewiring lock power is in progress. New switches to be installed at end of January.
01/30/24 – Last unit work ongoing. Cornerstone and Airteq VPs to attend a meeting in February to work out warranty issues.
02/27/25 – Meeting held with VPs of Airteq and Cornerstone to finalize warranty discussion. 5 year warranty agreed upon. Medical unit to be complete this week. outstanding work will be repairing damaged locks.
03/27/25 – All contract work complete. Closeouts to be submitted and correction work to be done.
04/24/25 – Replacement housing and attic stock to be delivered in near future. Cornerstone will begin correcting outstanding punch items.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – No Update.
08/28/25 – No Update.
09/25/25 – Attic stock and corrected housings delivered and replacement process has began. Closeouts outstanding.
10/30/25 – Still have a couple of things left to do. We need a list of lock boxes left to do.
12/11/25 – List of outstanding punch items provided. Closeouts under review.
01/28/26 – Punch work complete. Attic stock is outstanding. Closeout corrections requested.
02/26/26 – Closeouts will be delivered next week. Attic stock needs to be replenished from warranty work orders.
03/26/26 – Still waiting on closeout docs. Attic stock is still not on site. Warranty period has not began.
05/28/26 – No update.
06/25/26 – No update.
08/28/26 – Phillip onsite to review rust damage. Champlin to provide report.
09/24/26 – Report submitted. No update on solution.
10/29/26 – Roller bolts have been discovered missing on several doors. Sheriffs to provide report.

JC – Cell Door Lock Replacement (Cornerstone) Read More »

A&D – Accessible Employee Entrance

12/03/21 – Signed SOSS Received.
01/25/22 – Product research and preliminary brainstorming started. Field survey to verify existing conditions.
02/24/22 – Field verification complete. Products research complete.
03/31/22 – Options sent to County for review. Waiting on scope decision to price.
04/28/22 – Kevin Holt confirmed this project will not be moving forward. OK to Archive.

A&D – Accessible Employee Entrance Read More »

250 WHT – First & Second Floor Construction

PM: John Nester, Lead: Sam Hofmann

10/28/21 – Create project for tracking construction progress.
12/14/21 – Project waiting on contract finalization. Permit filed.
01/25/22 –  Construction Kick-off meeting held.
02/24/22 – Notice to proceed issued. CA in progress. RFI submitted on t-stat and answered to leave where is. HVAC submittals received and returned.
03/31/22 – CA on going. Demolition complete, framing in progress.
04/28/22 – CA on going.
05/26/22 – CA on going. Still on target to complete on schedule.
06/30/22 – CA on going. IBI inspections this week. City TCO next week. Move 2nd floor into new space in time for meeting.
07/28/22 – Second floor punchlist scheduled for 8/4. Door delivery for first floor is delayed. Triton to install temporary doors to receive occupancy.
08/04/22 – Second floor Punch list completed.
08/24/22 – First floor punch list completed.
09/29/22 – Second Floor punchlist completed. First floor backpunch to be scheduled.
10/27/22 – Back punches complete. waiting on confirmation that items have be12/15/22 – en completed.
12/15/22 – Second floor sign off received. Still waiting for cores for the first floor doors. PO being held open for TPC 6th floor ceiling work.
01/26/23 – Cores completed. Cypher lock had to be reordered. should be installed in next couple days which is the last item. Close out documents requested.
02/22/23 – Closeout documents and final pay app received.
03/30/23 – Still need physical binders from triton.
04/27/23 – No update.
05/25/23 – Have reached out to Triton several times regarding binders and final pay app, still have not received them.
06/29/23 – Closeouts and final pay apps received.

08/31/23 – No update.

09/28/23 – No update.

250 WHT – First & Second Floor Construction Read More »

EMA/Comm Center – SD & Cost

09/20/21 – Kick-off meeting with County, Champlin, Thermaltech, THP, and Cushman & Wakefield.
09/27/21 – Building Tour.
09/30/21 – SOSS received from County
10/13/21 – Programming Meeting held with Comm Center, County, Cushman & Wakefield.
10/15/21 – Programming Meeting held with EMA, Champlin, County, and Cushman & Wakefield.
10/20/21 – Draft Program sent to User groups for comments.
12/03/21 – Signed SOSS received for SD.
12/13/21 – SD Kickoff meeting held with Champlin. EMA and 911. SD to be finished by 1/7.
12/22/21 – progress meeting with Users.
01/06/22 – 90% review meeting with Users
01/07/22 – SD set and estimate submitted to County.
02/24/22 – The building purchased is moving forward. 4 teams made the short list, interview will be held in March 2022.
04/28/22 – Revised plans and estimate sent to County. Project is complete, ready to archive.

EMA/Comm Center – SD & Cost Read More »

TPC – Autotitle and BMV Combined Renovation

PM: Matt Butz, Mike Murphy
09/28/21 – SOSS received from County
10/27/21 – Champlin reached out to BMV contact to schedule programming meeting.
11/12/21 – Programming Meeting held with County, Champlin and BMV.
12/14/21 – Narrowed down potential layouts to two options. sending to BMV for comments.
12/22/21 – Met with BMV to finalize design. BMV to submit design to State. No response yet.
02/09/22 – Met with Greg Brush and Shawna Derencamp. Plan approved with small changes. SD and Estimate to be submitted by 3/4.
03/31/22 – SD plan and estimate submitted to County
04/28/22 – Estimate combined with Re-entry and sent to County.
05/26/22 – No update.
06/30/22 – No update.
08/25/22 – No Update.
09/29/22 – SOSS for DD-CA to be submitted in the near future.
10/27/22 – SOSS approved. DD meeting to be scheduled for week of 11/7.
12/15/22 – Final owner approval scheduled for 12/20
01/26/23 – Project will be posted for bid today
02/22/23 – Bid opening on 2/24.
03/29/23 – Graybach awarded the bid.
04/27/23 – RCF has met on site to provide furniture quote.
05/25/23 – Contracts finalized. Quote received from RCF. Kickoff meeting to be scheduled in the near future.
06/29/23 – Two separate kick off meetings will be held with each department. Design team to provide meeting options for next two weeks.
07/27/23 – Mid august start date. Meeting held with Autotitle. Meeting with BMV scheduled for next week. Plumbing and HVAC submittals have been received. TTE will send back this week.
08/31/23 – Construction began 8/14. Demo almost complete.
09/28/23 – Construction ongoing. Bulletin #1 issued for minor deduct work. Furniture for phase 1 ordered.
10/25/23 – Construction ongoing. Coordination between state and county data + telephone ongoing. State has been onsite to drop their data lines.
10/26/23 – The two large VAV boxes ductwork configuration has been modified to fit final wall construction installation. TTC met with NKYHC last week. Plumbing pilot holes reported to be filled, not verified by TTC yet. Drain pan in basement is being fabricated and should be here soon.
12/07/23 – Construction ongoing. phase 1 to be complete 12/22. Punchlist scheduled 12/21.
02/01/24 – Phase 1 is complete, Autotitle has moved into their temporary space. Toilets and restrooms are being installed now. City water tie-in next week. Triton begins demo of old Autotitle space and continues to work on Phase 2 work.
02/29/24 – Phase 2 began. Demo almost complete.
03/28/24 – Construction ongoing. Punchlist scheduled for 4/9.
04/25/24 – Punchlist items in progress. Autotitle moved into their space. BMV to be moved in two weeks after we make some additional changes in network infrastructure. Nick setting up meeting with Sonitrol to finalize new detail on how the new system is going to be monitored.
05/30/24 – Final punch items are in progress.
06/27/24 – Change order pricing outstanding.
08/29/24 – Pricing received. Waiting on materials for Triton to mobilize.
09/26/24 – Materials are in hand or arriving in near future. Triton to be on site this month.
10/31/24 – Triton back on site this week to finish last items.
12/12/24 – Triton has completed some punch items. Subs will be onsite to finish casework next week.
01/30/25 – Triton still has a couple items to complete on site.
02/27/25 – Punch work ongoing. Working on final connections to doors and get fire alarm tie-ins for FA system.
03/27/25 – Punch work still ongoing.
04/24/25 – Repair conducted on the auto operator. Fire tie in still outstanding.
05/29/25 – Access control have been on site a couple times. Problems are still not resolved.
06/26/25 – All items are not complete. Closeouts in progress.
08/28/25 – Closeout received. Ready to Archive.

TPC – Autotitle and BMV Combined Renovation Read More »

Animal Shelter – Master Planning

PM: Mike Murphy, Bert Watts
07/29/21 – Master Planning meeting being scheduled for scope and SOSS creation.
08/23/21 – Meeting held with County and Animal Shelter representatives
08/25/21 – Animal Shelter CEO puts Champlin in touch with Animal Arts.
10/17/21 – SOSS submitted to County. Waiting Approval.
11/08/21 – Approved SOSS received.
11/29/21 – Kickoff meeting held. attended by Champlin, County and Cares.
12/06/21 – Programming meeting held. Attended by Champlin, County and Cares. Finalized schedule and future meeting.
01/17/22 – Concept plan approved.
01/26/22 – Bi-weekly meetings in progress. Floor plan and renderings begun.
02/24/22 – Final user meeting to confirm/present interior and exterior renderings
04/11/22 – Final deliverable submitted to County.
04/13/22 – SOSS submitted for analysis of two existing buildings.
04/21/22 – CH and County Meeting to review commissioner feedback.

01/26/23 – Fair grounds site evaluated for animal shelter location. Fit plans in progress.

02/22/23 – SOSS approved to review Winton road site for test fit.

03/30/23 – No update.

04/27/23 – No update.

05/25/23 – No update.

06/29/23 – No update.

Animal Shelter – Master Planning Read More »

125 – 8th Floor Public Defender Expansion

07/28/21 – Submitted SOSS to County.
08/02/21 – SOSS Received.
09/27/21 – Site visit to confirm existing conditions.
10/14/21 – Preliminary plans sent to County for comment.
10/26/21 – Review meeting requested
11/04/21 – Review meeting held. Attended by Champlin, Public Defenders and County
11/29/21 – New layout options sent to County and Public Defenders.
12/23/21 – User meeting to finalize plan.
02/04/22 – SD plan and estimate sent to County.
03/31/22 – No Update
04/28/22 – No Update
05/26/22 – No Update. New information at Partner meeting on project status, still in development.

06/30/22 – Site visit to discuss scope of increased expansion

08/25/22 – Work to be reported in the new project.

125 – 8th Floor Public Defender Expansion Read More »

230 – Court of Appeals Mediation Renovation

07/28/21 – Signed SOSS received by Champlin.
08/26/21 – No update.
11/04/21 – Meeting with County and User to review Mediation Renovation scope reduction.
11/15/21 – SOSS submitted for DD-CA work.
11/17/21 – SD Set and Estimate uploaded to Archibus.
12/14/21 – Signed SOSS received for DD thru CA.
01/12/22 – Design review meeting with new administrative judge. No design changes. waiting for wall covering scope of work to be finalized.
02/24/22 – Waiting on official confirmation of wall covering scope. (our understanding is that there will not be any)
03/31/22 – Scope confirmed. DD in progress. Deadline of 3rd week of April to be bid ready.
04/27/22 – Final review meeting to approve final bid issuance.
05/26/22 – Finalizing bid package will be combined with Magistrates now. Final review set due June 2.
06/30/22 – Project in Bidding phase.
07/28/22 – Bidder recommendation letter sent to county.
08/25/22 – Building permit submitted. Contract in progress.
09/29/22 – Contract Finalized. Kickoff to be scheduled in near future. Construction moved to combined project.

230 – Court of Appeals Mediation Renovation Read More »

CH – B-95 Facilities Accounting Renovation

PM: Mike Murphy
05/25/21 SOSS Submitted to County
06/25/21 Meeting Scheduled for 7/13
07/13/21 Meeting occurred.
07/16/21 SP-1 and SP-2 sent to county with two option.
07/29/21 Meeting scheduled to review options.

08/26/21 Layout settled. Waiting pricing from furniture vendor.

10/13/21 – Site visit to confirm existing conditions with Champlin, Thermaltech and County.

10/19/21 – Final SD set and Estimate uploaded to Archibus.

12/14/21 – Signed SOSS received for DD thru CA.

02/24/24 – Permit applications

03/31/22 – Building permit picked up and delivered to County.

04/28/22 – No update.

05/26/22 – No update.

07/28/22 – Building and IBI inspection scheduled for 8/4.

08/25/22 – Final building and IBI inspections preformed.

CH – B-95 Facilities Accounting Renovation Read More »

Comm Center – Building Masterplan

05/22/21 – SOSS Submitted to County
06/02/21 – Received signed SOSS
08/09/21 – Meeting held with users to review scope.
08/26/21 – County said to let THP look at floor loading for this work. OK to get them involved now. Previous work created a lot of penetrations in the existing floor and new furniture was heavy. THP to review. New furniture should be less substantial than existing spaces.
10/28/21 – Keep masterplan work in place because this building will remain in the county portfolio for repurposed training facilities.
12/14/21 – No Update.
02/24/22 – Combined Estimate required. need to schedule a meeting to resolve scope overlap.
03/31/22 – SD plan of Combined 2022 estimates created. Meeting is needed to confirm final SD scope.
04/28/22 – We discussed the scope in the Admin Office spaces? Were the Radio Room involved? and we decided that we have not. Should we include Mission Critical involved in this report? Kitchen and Locker room are included.
05/26/22 – Finalizing estimate.
06/30/22 – Combined scope plans provided to TEI for estimate. Finalizing estimate
08/25/22 – SD set sent to HC. Plans need further broken down and resent.
09/29/22 – Site visit scheduled for 10/11.
10/27/22 – Scope refined after field visit. Owner Review Issuance scheduled for 11/11.
12/15/22 – Masterplan drawings need to be changed to reflect current project. waiting until bids are accepted to update according to which alternate is chosen.
01/26/23 – Updated plans will be completed by end of next week.
03/30/23 – Updated plans and estimate uploaded to Archibus.
04/27/23 – No Update.
05/25/23 – No Update.
07/27/23 – No Update.
08/31/23 – No Update.
09/28/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update.
06/26/25 – No Update but keep on list per HC.
03/26/26 – Leave on list.
07/30/26 – OK to Archive, RT

Comm Center – Building Masterplan Read More »

TPC – Commissioners Conference Room Upgrades

04/30/21 – SOSS Submitted to County
05/11/21 – Signed SOSS received.
06/23/21 – Meeting on site to review scope. Champlin finishes scope removed. Light fixture selection and photometrics to be done.
07/29/21 – Sconce selection is made. acoustical selection is not required. Researching main light fixtures.
08/11/21 – Provided cutsheets for suggested fixture replacements.
08/18/21 – County provided feedback on fixture selections.
10/27/21 – Draft Rendering/Photo provided to County. Fixture cuts provided to Thermaltech for photometric calculations.
12/14/21 – No Update.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
05/26/22 – No Update. Ready to archive.

TPC – Commissioners Conference Room Upgrades Read More »

250 WHT – Public Health Lobby Renovation (2nd Flr)

03/31/21 – SOSS approved. Kickoff meeting scheduled for 5/6.
04/29/21 – Kickoff meeting schedule for 5/6/21.

05/06/21 – Kickoff meeting held

05/17/21 – Field visit to verify existing conditions

06/04/21 – Progress set sent to Greg Varner for review

06/08/21 – Updates from Greg received

06/10/21 – Updated plan sent to Greg

06/22/21 – HC, PH, and ES decided to combine project scopes of 2nd floor lobby and 1st floor lobby into one bid.

06/23/21 – Updated plan sent to Greg.

07/09/21 – 95% review meeting to review scope and budget. Raised questions related to code requirements. required additional research.

07/29/21 – Meeting scheduled for Final Review Set.

08/10/21 – Project Issued

08/23/21 – Pre-bid Meeting Held

09/09/21 – Bid opening – Triton was apparent low bidder.

09/15/21 – Zoom meeting with Champlin, Thermaltech and Triton to vet the bid. Sent Letter of Recommendation to County.

10/28/21 – Ready to archive.

 

 

 

250 WHT – Public Health Lobby Renovation (2nd Flr) Read More »

230 – 11th and 12th Floor Renovation

03/08/21 – SOSS approved.

04/06/21 – Kickoff meeting with users to go over scope.

04/20/21 – Field visit to confirm existing conditions. Working on selecting finishes and furniture.

05/20/21 – User meeting presenting initial room layouts

06/10/21 – Sent updated plans to further define scope

06/22/21 – User responded to refocus efforts in light of new funding. meeting scheduled 6/28

06/28/21 – Sent county plans and estimate for flooring replacement and wallcovering removal and paint. furniture estimate outstanding.

07/28/21 – John to remind users about need for additional information in order to finalize furniture estimate.

08/26/21 – Project part of 2022 Estimates.

10/28/21 – Ready to Archive.

 

 

230 – 11th and 12th Floor Renovation Read More »

RSC – Regional Safety Complex Phase 1

PM: Bert Watts, David Toombs, Terry Cannon
04/02/21 – SOSS approved. Waiting for contacts from County to begin programming.
05/27/21 – No Update.
06/17/21 – Toured City and County facilities.
06/23/21 – Site planning concepts sent to Bert for input. Input received the same day.
07/16/21 – Review meeting with County Commissioner, City Council Member, County Administrator, and representatives of Hamco Sheriffs and City of Cincinnati Police.
07/26/21 – Final rendering and diagram packet sent to Bert.
08/25/21 – SOSS Submitted to County
10/28/21 – No Update.
12/14/21 – No Update.
01/26/22 – No Update.
02/22/22 – Champlin presented at Residents Meeting in Colerain Township.
02/24/22 – Elected officials outnumbered the residents who were in attendance at the meeting and Champlin presented the project. 5 residents were in attendance, sheriff, county, other people were there. Concerns: Acoustic study, traffic study, and site environmental range. Even though it’s a firing range now.
04/27/22 – Champlin sent kickoff meeting invite for May 10.
05/10/22 – Kickoff meeting with County Cincy Champlin and Kleingers held. Reviewed program and concept
05/24/22 – Progress meeting with County Cincy Champlin and Kleingers to review floor plans and ancillary buildings.
06/30/22 – Progress meetings ongoing. SD package to be completed on schedule
08/25/22 – Final SD package sent to HC. Estimate breakdowns to be finalized.
09/29/22 – No Update.
10/27/22 – No Update.
01/26/23 – Meeting held with County and City to discuss funding. Estimate is being broken down by item to value engineer the project.
02/03/23 – THP – Champlin requested SOSS for structural services.
02/09/23 – THP provided an SOSS to Champlin for review.
02/22/23 – SOSS received for DD-CA.
03/08/23 – THP and Champlin have executed contract.
03/30/23 – Site survey is complete. Developing Topo basemap to be complete middle of next month. the Acoustical Engineer has completed existing condition sound testing.
04/27/23 – Draft of Acoustics report received. Champlin had questions and is finalizing a report. Topographic survey complete and base map received. Champlin and Kleingers are coordinating scope of work.
04/28/23 – Moved project out of Champlin General Services to Satellite Offices for future updates.
05/21/23 – TTE attended DD development meetings wiht Champlin & Kleingers for site work.
05/25/23 – Site package sent to County for review. Drawing to begin development.
06/29/23 – DD page turn held 6/23. Hud environmental assessment exhibit materials are due to Bert by friday June 30. Flood plane exhibit sent 6/27. Final acoustics report is ready to send upon request. Design team has reworked architectural site plan with the temporary building location moved.
06/28/23 – THP coordinating with Champlin on Phase 1 documents in July.
06/29/23 – Septic Engineer will be onsite Jully 6 for site survey and cores for their work. The Water Test from Veolia is on hold for supply issues with our test kit, but we hope they can also be on site the week of July 7.
07/20/23 – ThermalTech met SCS engineers onsite for septic design ground samples and septic tank locations.
7/24/23 – Champlin sent email: Phase 1 design coordination with structural (THP) is expected start this week for CD due end of August.
07/26/23 – Veolia water testing scheduled for August 1 with Ian, TTE, and Veolia.
07/27/23 – Meeting held with Sheriffs. Program and plan confirmation for temporary range and ancillary structures locations occurred at that meeting. Expect phase 1 CD submission for end of August. Geotechnical work is ongoing.
08/31/23 – Schedule for bid package 1 and 2 distributed to all consultants 8/28. Coordination is ongoing. Bid package 1 completion date is 9/22.
08/31/23 – THP no project updates.
09/28/23 – Meeting held with CPD. Cincinnati had scope requirements to continue involvement with the safety center. County is working on an agreement.
09/29/23 – THP issued Phase I bid review documents.
10/25/23 – Revised estimate submitted to County for review. Waiting on meeting to be scheduled with CPD to answer some outstanding questions. EPA issue has not been resolved.
12/07/23 – Meeting with Cincinnati, CPD, Sheriff, and Hamilton County held to discuss status on 11/6.  US EPA review comments continue and we are providing answers as required.
1/24/24 – THP – No update. Paused.
02/01/24 – EPA questions submitted answered. HC continues to have meetings with the EPA. We will most likely require some sort of testing wells for this site to monitor content in the aquafer. Currently this project is on a design hold until these administrative tasks are complete.
2/28/24 – THP – Phase 1 is on hold. Expected official response 3/1/24 and issue bid document 30-45 days. Design is done. Phase 2 is on hold with no date planned.
02/28/24 – Met with Morgan and Anson on Feb 23 to discuss approach to hiring engineering for water main extension. City of Cincinnati determined that GCWW was OK with not hiring the design as long as standards are met. All agreed it made sense to have Kleingers due the work because of head start on project understanding. USEPA verbal commitment to have a letter by March 1 has slipped to mid March.
02/29/24 – Bert asked for operational cost, environment, utility cost and lab test.
03/28/24 – Land swap negotiations nearing completion. Zoning variance for sniper lanes to be submitted in near future. Coordination between architectural and civil to wrap up this week.
4/23/24 – Phase 1 Bid Review set submitted on 4/12/24. Phase 2 on hold with no date planned.
04/25/24 – 95% review set submitted to the County 4/18. Cost estimates are being developed. Zoning meeting scheduled for 5/22.
05/30/24 – Board of zoning appeals voted to approve the required variance on 5/22. Bid set sent to purchasing 5/23. City comments on phase 1 received with no impact to phase 1 drawings.
06/27/24 – Project is out to bid. Pre-bid held, Addendum #1 is issued.
07/24/24 – Bids were opened and five underbudget bids were received
08/28/24 – Phase 1 Bids in. Phase 2 on hold with no date planned.
08/29/24 – Bid review complete. Project in contract phase.
09/23/24 – ThermalTech sent “Issued for Permit” drawings sent to Champlin for distribution and submission for this project.
09/25/24 – THP – Pre construction meeting with Monarch next week. Phase 2 still on hold.
10/31/24 – Groundbreaking ceremony held last Friday. Phase 2 to begin.
12/11/24 – in CA. submittal reviews. Phase 2 still on hold.
01/30/24 – Phase 1 – Site work to start ramping up due to weather. Zoning and Permit issues are close to resolved. Phase 2 – SD plan approval received from Cincinnati and Hamilton County. DD development ongoing.
02/26/25 – Phase 1 – we have returned adn submitted all the OEPA permits to keep the permitting phase of the job moving forward, the contractor is getting close to running out of work on Phase 1 I think, we need to get permitting on place. Phase 2 work for DD is due March 3. TTE working on Revit model updates and working on cost estimates as well. We have been meeting with David Toombs regularly on MEP updates.
03/25/25 – We have multiple DD design meetings with Champlin this month. Bluebeam studio being used for markups, DD drawings and cost due this week to Champlin for Final DD tear-off set. MEFP and Architectural design being tweaked for final DD adjustments. Phase 1 submittals are being received and returned as they come in, submittals are acceptable. The Septic permit is still elusive but we continue to work towards resolution, SCS says most of the paperwork is already submit, but he needs to fill out one more new electronic form.
04/24/25 – THP update – County requested changes to the design. THP provided pricing for additional services to be included in Champlin’s request.
04/24/25 – DD for phase 2 is complete. Revised estimate submitted to county. Phase 1 work ongoing.
05/29/25 – Project schedule shared for phase 2. Phase 1 work in progress.
06/25/25 – DD submittal in Apr. Team is waiting for approval to proceed into CD.
08/04/25 – We received an Anti-Degradation email from Bert and forwarded that to Dan Brennan SCS engineers to handle. SCS sent a memo to Glenn per their request but will call him back to make sure that is all they need. We also got the approval to send in the revised submittal drawings from the contractor for Monarch. TTC passed all this information on to Bert and David.
08/26/25 – Construction continues on site. Pilot holes are being drilled to assist in figuring out how to get under the roadway. Soils change order being developed. Bulletin 6 issued to Monarch for pricing and coordination.
08/27/25 – on Phase 1 the large retention system walls are nearly complete, and the Phase 1 temporary range was completed last week. The Ph1 grounds building cladding is in progress and the staging to raise the parking lot grading has also started. On Phase 2 the Design Team received DD approval and is proceeding with CD Phase. Over the last 3 weeks all remaining in-person owner meetings for Security, Technology and Interior Design have been completed.
10/30/25 – 90% documents for phase 2 will be submitted to county tomorrow. Phase 1 work continues and on target for January completion. Retaining wall movement has been rectified with additional wall in front of original retaining wall.
12/11/25 – 90% set is under owner review. Ohio EPA approval is still in process. Grounds building is complete and sheriffs are moving in. Existing building Demo to begin shortly. Phase 1 work on target for completion in January.
02/26/26 – Project complete. Punch work ongoing.
03/26/26 – One site issue still outstanding. Kleingers is working on a solution.
04/30/26 – Guardrail posts being installed next week. Closeouts outstanding.
05/28/26 – No Update.
07/30/26 – Monarch sent closeout documents, Partners have been commented on them this week. Concrete joints and curb issues being addressed.
08/27/26 – OK to Archive.

RSC – Regional Safety Complex Phase 1 Read More »

JC – 2021 Cell Door Replacement (Ph 1)

PM: Matt Butz, Sam Hofmann
02/22/21 – Received approved SOSS. waiting for more information to proceed with design.
03/18/21 – Design Kick-off meeting with County, Sheriffs, Champlin and ThermalTech.
03/22/21 – Site visit by Sam Hofmann and Jeff Cyrus. Further developing plans and gathering information.
04/29/21 – Several Manufacturers researched. Wrapping up DD set for review.
05/21/21 – User meeting to finalize scope. Shereen provided existing building door details for coordination purposes.
06/08/21 – Updated plans sent to manufacturers for pricing. still waiting on Door and frame prices. Requested county to investigate existing hardware.
06/15/21 – Received information on low voltage locks. still waiting on information on high voltage locks.
07/14/21 – Champlin identified current contractor in building and requested updated specs and estimates.
08/25/21 – Final meeting held. scheduled to go out to bid on 9/2
09/02/21 – Bid issued
09/23/21 – Bid opening. Triton is apparent low bidder.
10/15/21 – Zoom meeting with Triton, Champlin, and Thermaltech. Letter of Recommendation sent to County.
12/09/21 – Contract and PO Issued. Permit filed.
01/26/22 – Construction kickoff meeting scheduled for 2/7.
02/24/22 – Submittals starting to be received. Progress meetings will start in June when construction starts.
03/31/22 – CA ongoing.
04/28/22 – CA ongoing. Information required from the sheriffs in order for Triton to order locksets. phone call with vendor confirmed the information is in the sheriffs possession. Our attempts to contact Sheriff have not been successful.
05/26/22 – Information from Sheriffs received. Submittals returned. Triton to provide a construction schedule when determined.
06/30/22 – Submittals resubmitted and returned. Triton to provide schedule when materials are ordered.
07/28/22 – Triton selected new Project Manager. Jeff W to provide update.
08/25/22 – Final submittals returned. project kick off to be scheduled.
09/29/22 – Kick off to be scheduled in near future.
10/27/22 – Update from Triton puts project start in late January.
12/15/22 – No update.
01/26/23 – Project on schedule to start in February.
02/22/23 – Update from Triton stated doors wont be delivered until end of March
03/30/23 – Triton mobilized on site. Jails delayed some materials but shouldn’t impact schedule.
04/27/23 – Phase 1 and 2 to be complete by 4/29.
05/25/23 – Phase 1 and 2 complete. Phase 3 ongoing.
06/29/23 – Phase 3 and 4 complete. Final phase to begin next week.
07/27/23 – All doors installed. Punchlist items outstanding.
08/31/23 – Backpunch returned to Triton for final touch ups.
09/28/23 – Project complete. Triton to provide closeouts.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – Closeouts received. Need to be reviewed.
09/26/24 – Sam to continue closeout paperwork reviews.
12/12/24 – No update
01/30/24 – Triton and County held meeting to review all outstanding documents needed.
03/27/25 – Closeouts received.
05/29/25 – Final payment released. OK to Archive this project.

JC – 2021 Cell Door Replacement (Ph 1) Read More »

TPC – Lobby Renovation

PM: Mike Murphy, Mike Barth
01/08/21 – SOSS Submitted to county for approval.
01/28/21 – PO and SOSS approved.
03/10/21 – Field visit by Sam Hofmann and Tracy Pohl. Further developing plans and selecting finishes.
04/01/21 – Sent renderings and finish options to Bert. A review meeting to select finishes is necessary before continuing.
05/27/21 – No Update.
06/25/21 – Design review committee meeting scheduled for 6/28
07/21/21 – Design Committee review meeting #2.
07/27/21 – Revised rendering and light fixture cut sheets sent to Bert.
08/26/21 – No update.
10/28/21 – Drawings and rendering completed. Estimate in progress.
11/02/21 – Updated Renderings and executive summary sent to County.
01/26/22 – No Update. We should have an update next Tuesday.
02/24/22 – No Update.
03/31/22 – Deadline of end of April to be bid ready.
04/26/22 – field visit to review artwork to be replaced. Bert supplied some additional information. Champlin to provide a suggested strategy for owner approval.
05/26/22 – Final Review set submitted to county. Changes have been made according to Berts comments. To be determined if this project will be combined with the elevator renovation project.
06/30/22 – Project to be bid out separately from Elevator Modernization project on July 7th.
07/28/22 – Project in bidding phase.
08/25/22 – Triton awarded the bid. Contract in progress.
09/29/22 – Contracts in progress
10/27/22 – Contracts in progress
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Kick off meeting held. Submittals being returned.
02/22/23 – Submittals returned, ready to issue notice to proceed.
03/30/23 – Notice to proceed sent and schedule received.
04/27/23 – Preconstruction meeting held. Phase plan finalized. Mobilization to start 4/28.
05/25/23 – Construction ongoing. Triton has had issues with staffing and maintaining a properly maintained work area. Phase 1 and 2 complete. Phase 3 in progress.
06/29/23 – Abatement is complete. Triton submitted new schedule.
07/27/23 – Construction ongoing. Axis was on site to begin floor leveling and could not continue due to current state of the floor. Triton to further demo the floor to acceptable conditions. Sconces have been turned rightside up on one column. Mike in contact with King lighting to provide sconce solution.
08/31/23 – County to make decision on installing light kit themselves, sending back to the manufacturer or leaving the fixtures as is. Flooring to be complete early next week. Wall tile installation to begin next week. Reviewed tiling work with County and small changes in how it was tiled is okay. Streetcar scheduled was discussed and posted in the Admin.
09/28/23 – Construction ongoing. Flooring and wall tiles to be complete next week. Second Mural approved.
10/25/23 –  Construction ongoing. Murals to be hung this week. Floors to be polished the next week.
12/07/23 – Punch list complete. Additional signage installed. Back punch to be scheduled in near future.
02/29/24 – Triton to provide closeouts.
03/28/24 – No update.
04/25/24 – No update. Triton getting closeouts in place, discussing some extra from the work on the job.
05/30/24 – No update. Triton owes us about five closeouts for projects, this one included.
06/27/24 – No Update.
07/24/24 – Triton owes us closeout documents for this job.
08/29/24 – No update.
09/26/24 – No update.
12/12/24 – No Update.
01/30/25 – Triton and County held meeting to review all outstanding documents needed.
02/27/25 – No update.
04/24/25 – Closeouts requested from Triton. No response.
05/29/25 – No Update.

TPC – Lobby Renovation Read More »

TPC – Auto Title Office Renovation

01/26/21 – Received signed SOSS from county.
01/28/21 – SOSS and PO approved. We discussed project scope with the team and how to proceed with the new scope and schematic design. CHA and TEI to review proposed furniture layout and make sure their design is permittable and legit, update the cost estimate in Archibus. 19 staff members for new restroom, no men or women signage on new RR.
02/25/21 – TTE to provide opinion of most efficient location for restroom to continue with design
03/12/21 – Furniture meeting on-site attended by County, Autotitle, Champlin and ThermalTech.
03/19/21 – MEP Drawings and cost uploaded to Archibus #2022; extra cost for two bathrooms in comments Section, breakdowns uploaded as PDF.
04/07/21 – Received furniture quote from RCF
04/14/21 – User review meeting. SD estimate modified.
05/27/21 – No Update.

06/25/21 – No Update.

TPC – Auto Title Office Renovation Read More »

Animal Shelter – Exit Signs

01/06/21 – SOSS signed and received.
01/21/21 – Champlin and TTE walkthrough with John Nester to review existing locations and review scope.
02/09/21 – Champlin uploaded Estimate to Archibus.
02/25/21 – TEI needs to add cost to Archibus for this project.
03/02/21 – All estimates are uploaded. Final report to come.
04/29/21 – Estimates are in and final report uploaded to Archibus.
05/27/21 – No Update. OK to Archive

Animal Shelter – Exit Signs Read More »

250 WHT – First Floor Lobby and Delivery Closet Renovation

10/21/20 – Authorized to proceed with design and bid phase.
12/10/20 – two options sent to county and Public Health for review.

01/06/21 – Review meeting with Users – Finalized scope

01/22/21 – Received TTE sd documents

01/26/21 – Uploaded SD Drawing and Estimate to Archibus.

02/18/21 – Received comments from owner

01/25/21 – Champlin working on SOSS to take project through completion.

03/11/21 – SOSS approved.

03/25/21 – CD’s being developed. Review meeting with users to be scheduled in the near future.

04/06/21 – User Review Meeting. Finalized scope.

04/20/21 – Final CD documents and budget given to County.

04/28/21 – County approves final plans. Champlin to get ITB number from Purchasing.

05/11/21 – Project Posted by Purchasing

05/21/21 – Prebid meeting held at 250 WHT

05/24/21 – Addendum 01 posted.

06/03/21 – One bid received. Budget exceeded and bid had to be rejected.

06/14/21 – Rejection letter sent to John Nester after bid review and discussions with other pre-bid attendees.

06/22/21 – Email from John Nester suggesting to combine this project with Public Health Lobby for new bid.

10/28/21 – Ready to Archive.

 

 

250 WHT – First Floor Lobby and Delivery Closet Renovation Read More »

DDS – Group Homes Renovation

10/29/20 – Site visit to confirm existing conditions. Meeting scheduled for 10/29 with Kevin Maue for preliminary review. Meeting scheduled for 11/5 with Towards Independence.
11/05/20 – Meeting with Towards independence for review
12/11/20 – Submitting SD drawings and estimate to Kevin Maue for review.
01/20/21 – Email from Kevin Maue indicating decision by DDS on direction towards end of February.
02/25/21 – No Update
03/25/21 – No Update
04/29/21 – No Update
05/12/21 – Sent broken down cost estimate ( kitchen renovations for each building) to Kevin Maue
06/25/21 – No Update.
07/27/21 – Champlin spoke to Kevin Maue. Kevin expects approval to proceed on all three homes on 7/28.

08/12/21 – SOSS sent to County.

08/18/21 – Kevin Maue sent Champlin questions related to SOSS

10/28/21 – No Update.

12/14/21 – No Update.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

06/30/22 – SOSS approved for Geier renovation DD-CA. Kickoff meeting held to confirm scope.

07/28/22 – Kickoff meeting occurred. Program and scope changes were discussed. New plan in progress.

08/25/22 – Revised plan sent to Kevin Maue for review.

DDS – Group Homes Renovation Read More »

250 WHT – HCPHD Lobby, WM, WQ, Plumbing, HPE

10/29/20 – Furniture confirmation meeting held 10/28. HPE proceeding to furniture bid. Lobby, WM and Copy/Print/Conference room reconfiguration to be estimated for future funding. Plumbing and Water Quality modifications no longer being pursued.
11/23/20 – SD Drawings and Estimate sent to County for review.
01/27/21 – No update.
02/25/21 – No update.
03/25/21 – SOSS sent for 2nd Floor Lobby scope only. waiting on approval to proceed.
04/29/21 – Separating Public Health Lobby into new project. No Update for remaining spaces. Scope is complete, okay to archive.

250 WHT – HCPHD Lobby, WM, WQ, Plumbing, HPE Read More »

237 WHT – HCPHD – Disease Prevention TB Clinic

10/29/20 – Programming meeting held. Planning confirmation meeting scheduled for 11/5/20.
11/05/20 – Meeting to review scope. Proceeding with 2 options to SD and Estimate level.
12/08/20 – Site visit by CA and TTE to verify existing conditions
12/10/20 – ThermalTech has requested information on existing equipment and specifics for using for loads for new space.
12/14/21 – Cost estimate for emergency work needed, minimum renovation plan and minimum plus renovation plan sent to Greg Varner for Board Meeting.
02/25/21 – No update.
03/25/21 – No Update. OK to Archive.

237 WHT – HCPHD – Disease Prevention TB Clinic Read More »

CH – Additional Flagpoles

07/10/20 – On site review. Authorized to proceed on CH only.
08/27/20 – One and Two flagpole settings discussed.
09/09/20 – Estimate and cut sheets uploaded on to Archibus.
10/29/20 – Approved to proceed on adding two flagpoles at Courthouse. Need to measure actual height of existing pole.
11/20/20 – RFP sent to Megen Construction, James Hunt Construction and Triton Services.
11/24/20 – Prebid Meeting at Courthouse.
12/01/20 – Addendum 1 issued.
12/08/20 – Bids received. Triton is apparent low bidder.
12/09/20 – Zoom meeting with Triton to review scope and vet bid. Official Letter of Recommendation sent to County.
01/22/21 – John Nester sent signed contract to Josh Smallwood at Triton.

02/25/21 – Josh Smallwood to deliver Schedule of Values, Project schedule and Submittals mid week of 3/1

03/11/21 – Permit issued. Waiting on approval. Still need lighting submittal.

04/29/21 – Waiting on Triton to answer foundation question for permit response and physical samples for flagpole material.

04/29/21 – THP to provide structural drawing for footing design

05/10/21 – THP provided Champlin with structural sketch

05/21/21 – THP provided Champlin with official design.

06/08/21 – Construction kick-off meeting. still waiting on additional finish sample from Josh.

07/19/21 – Notice to Proceed issued to Triton.

08/24/21 – Submittal returned to Triton.

10/05/21 – Site visit attended by County, Triton and Admiral. led to confusion on total scope.

10/25/21 – Meeting with Triton confirmed scope and gave Triton direction.

11/27/21 – Boring for the hole started. Soil conditions were found to be unacceptable. Terracon was contacted by THP to analyze soil conditions. No schedule has been given for the analysis.

01/26/22 – Ongoing communication between Triton THP and Terracon. Pricing to be submitted for added services.

02/23/22 – Change Order #1 signed and returned.

03/31/22 – Triton waiting on sidewalk permit to restart construction.

04/28/22 – Triton has provided an install schedule from 4/30 to 5/7 with installation complete on the 7th.

05/26/22 – Project Completed. Punch to be scheduled soon.

06/30/22 – Reviewed on site. Official punch to be submitted to triton shortly.

07/28/22 – Punchlist to be issued.

08/25/22 – Punchlist items complete. Final pay app to be submitted.

09/29/22 – Waiting for Triton to submit closeout documents

10/27/22 – Close out documents missing warranties and O&M manuals. Triton working on it.

12/15/22 – Close out documents received.
02/23/23 – OK to Archive.

CH – Additional Flagpoles Read More »

Homeless Shelter COVID Mods

08/20/20 – SOSS signed and returned. Initial provider meetings starting this week.
08/25/20 – 09/15/20 CA, CMTA, GBBN visit all shelter sites.
09/17/20 – 09/22/20 CA, CMTA, GBBN zoom meetings with all property managers to confirm scope of work.
09/22/20 – GBBN provides CA with SD drawings for CA to proceed with implementation.
09/23/20 – CA provides Messer with preliminary drawings for pricing.
09/28/20 – Target date for getting Messer final drawings for pricing.
10/29/20 – Bid packages and Permit ready. Waiting for authorization to proceed.
12/10/20 – Waiting for Authorization to proceed
01/26/21 – Meeting with Lisa Webb and City of Cincinnati to reassign Champlin contract.
02/25/21 – No update. Final stages of dividing contract between county and city.

03/25/21 – No Update

04/29/21 – No Update

05/18/21 – Meeting with City to discuss scope and remaining fee.

06/07/21 – Final signed assignment agreement received.

07/27/21 – Contract transfer complete.

08/26/21 – Project no longer a County project.

Homeless Shelter COVID Mods Read More »

250 WHT – HC Public Health Dept. EPI & IT/PHEP Interior Renovations

08/20/20 – SOSS signed and returned. Champlin notified ThermalTech. Working to schedule field work.
08/27/20 – Champlin sent several floor plans for review and asked about electrical impact. Barth responded that it is really pretty much the same electric scope except one layout requires an additional power pole and data jack which is not a big deal.
09/08/20 – CA site visit to see existing conditions
09/23/20 – CA SD drawings and estimate uploaded to Archibus
10/22/20 – Drawings updated to reflect scope change
10/29/20 – RCF pricing in process with the inclusion of prevailing wage.
11/23/20 – Haworth unable to meet furniture delivery deadline due to covid. Haworth sent a letter to explain the issue for Cares Act Funding. Furniture to be delivered early January
12/01/20 – Drawings submitted to IBI for Plan review.
12/10/20 – IBI and permitting in place. County can start work.
12/17/20 – Epi teardown 1/5-1/6 install 1/7-1/8. IT/PHEP teardown 1/5-1/6. Install 1/7-1/8. HPE teardown 1/11- install 1/12-1/13
01/25/21 – Electrical punch list completed.
01/28/21 – Holstegge coming out Monday to pick up some items and Trades are filling out the rest of the work. Carpet guys are coming out soon.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

250 WHT – HC Public Health Dept. EPI & IT/PHEP Interior Renovations Read More »

2020 – Floor Patching

06/09/20 – Site visit to see existing conditions. SOSS submitted. Waiting for authorization to proceed.
09/08/20 – Received authorization to proceed. CA to schedule site visit
10/29/20 – Site visit to confirm existing conditions. Broadloom carpet made it difficult to confirm extent of cracks. Bid package in process with reasonable assumption for scope of work.
12/9/20 – SD Drawings and Estimate uploaded into Archibus.
01/21/21 – Structural Allowance added to cost estimate.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

05/27/21 – No Update

06/25/21 – No Update

07/13/21 – SOSS submitted to County

08/26/21 – No Update

10/27/21 – Bid set sent to County for approval. Ready to bid.

11/10/21 – Pre-bid held on site. flooring replacement scope added to be alternate #1, #2 and #3.

11/19/21 – Bids came in. Triton was the low bid. Waiting for contract now.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

05/26/22 – No Update.

06/30/22 – Kickoff meeting held. Notice to proceed issued. Submittals received and returned.

07/28/22 – No Update.

08/25/22 – Kickoff meeting held. subcontractor to provide schedule.

09/29/22 – Ready to begin project when materials arrive

10/27/22 – Construction began.

12/15/22 – Construction ongoing. should be complete by end of next week.

01/26/23 – Punchlist conducted last week. Corrections to be fixed in the near future.

03/30/23 – Damaged doors discovered from flooring repair. Triton to correct.

04/27/23 – Triton to remove and replace wood veneer on doors.

05/25/23 – Doors have been refinished. They need a final sealant coat and will be installed next week.

06/29/23 – Doors installed. Closeouts received.

07/27/23 – Closeouts need final approval.

08/31/23 – Final pay app sent to county and closeouts approved. Waiting on Triton to provide hard copies.

2020 – Floor Patching Read More »

A&D – JFS Furniture Renovation 2020 SD

06/22/20 – Kick-off meeting. Attended by Mike and Christy from Champlin, John from THP, Mike and Terry from ThermalTech, Susan and Megan from IPM, Rycca, Bert, and JFS executive team from County.
07/09/20 – THP provided a proposal to Champlin for structural support.
08/21/20 – SOSS submitted. Waiting for authorization to proceed.
09/23/20 – SOSS Approved. Kick-off meeting attended by Christy
10/29/20 – programming received from Michael Patton. Typical cubicles were revised and sent to Rycca. Ready to present to JFS.
12/10/20 – Regular design meetings in place.
01/26/21 – TEI and IPM worked out details on walls around the fintube radiators along the outer walls.
01/27/21 – Weekly meetings on Fridays. Final programming meeting scheduled 2/5.
02/25/21 – Weekly meetings still ongoing. planning to start on the 1st and 5th floors.
03/25/21 – Ongoing weekly floor-by-floor presentations of space planning to Michael Patton.
04/29/21 – Ongoing weekly meetings. Field verification walk thru scheduled 5/3/21
05/07/21 – Final Coordination meeting with JFS
05/20/21 – Sent final misc. questions to Michael Patton.
05/21/21 – Received 4th and 5th Floor comments and revisions from JFS
06/03/21 – Field verification to determine signage scope.
06/24/21 – Rough draft of SD Set sent to Rycca for review.
06/25/21 – TEI owes Champlin a SOSS for the plumbing work. Gender-neutral question is out there too.
07/28/21 – Archibus #2106 is updated with MEFP cost and sketches for this project including plumbing updates for bad flow conditions.
07/29/21 – SD documents submitted to Rycca for JFS review. The next step will be a design review with TEI on final design decisions. THP will need to review the new layout from the load study perspective.

08/26/21 – Final Review meeting with County, Thermaltech and Champlin.

09/15/21 – Champlin provided County with updated estimate.

10/12/21 – Champlin provided County with a breakdown of door types being replaced for review.

10/28/21 – Project is complete. Ready to Archive.

 

 

A&D – JFS Furniture Renovation 2020 SD Read More »

NFPA 80 Inspection

11/19/19 – SOSS approved for Downtown Fire Rated Door Inspection RFP
11/19/19 – SOSS approved for Auxiliary Buildings Fire-rated Door Inventory
12/18/19 – Champlin sent Fire Rated Door Inspection Bid Documents draft to County
12/31/19 – Champlin began inventory at 250 Taft
01/03/20 – Champlin visited Juvenile Center
01/06/20 – Champlin completes rest of field visits
01/15/20 – Champlin received instructions from Tony Matre to combine both projects into one.
01/21/20 – Champlin receives access to archives for existing drawings of Auxiliary buildings
02/07/20 – Champlin expected to send bid documents to County
02/14/20 – Kru and Sam met with Bert, Tony, Jessica, and Rycca to discuss scope of work to be included in documents. Champlin is waiting for service agreement draft from Bert.
11/20/20 – CA reached out to DHPace in Columbus for a unit price per door. No response after initial call. Reached out again last week and still no response. Looking for new contact to advise.
02/25/21 – No update.

03/25/21 – Preparing Bid package

04/29/21 – Bid package ready for review.

05/27/21 – No Update

06/25/21 – No Update

07/29/21 – No Update

08/26/21 – No Update

10/26/21 – Final bid set completed. Submitted to purchasing.

03/31/22 – Plans marking 0ut doors to be provided to county

04/28/22 – Plans sent to county. TPC Door schedule from GBBN incorrect (Appears to have been entirely copied from Taft Center). Champlin can provide review of TPC if directed.

05/26/22 – Champlin to review TPC friday or monday depending on availability.

08/25/22 – Champlin reviewed reports and door count discrepancy. A&D doors need further discussion.

NFPA 80 Inspection Read More »

230 – Probate Court Security Upgrade

10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
05/20/20 – Meeting at Taft center to discuss scope. Attended by Sam and Mike from Champlin, Rycca, Jessica, and Bryan from County and Scott from the Taft center.
06/03/20 – additional site visit to verify existing conditions
06/03/20 – Meeting at Taft Center to choose product. Attended by Sam, Mike, and Jose from Champlin. Rycca and Bryan from County and Scott from the Taft Center.
07/02/20 – Draft of ITB sent to County for approval
07/27/20 – final copy of ITB and Plans approved. Prebid meeting set for 08/03/20 at 10 am
08/20/20 – Bids received and apparent low is James Hunt Construction.
09/03/20 – Contract signed by Hunt
09/14/20 – Submittal returned to Hunt
10/29/20 – Construction planned for the weekend of 11/21. Punchlist to be scheduled monday 11/23.
11/21/20 – Project ran into complications. New date of install is the weekend of 12/19-20. Punchlist to follow.
12/26/20 – Installation 12/26-12/27 Champlin performed punchlist 12/27
01/18/21 – Additional punchlist issued.
01/23/21 – Glass and 1 dented post cover replaced. sometime this week 2nd post cover to be replaced.
02/24/21 – Back punch by Sam Hofmann, Danny Rusconi, Rycca Thacker and Scott Weikel. Final touch up items to be completed 2/25 at 4pm
02/25/21 – All punch items completed
03/25/21 – Project essentially complete. Final payment sent. The project can be archived.

230 – Probate Court Security Upgrade Read More »

250 WHT – First Floor Painting

10/16/19 – County made request for get pricing to bid out painting 250 William Howard Taft – first floor only.
10/25/19 – Champlin was at site for field verification.
12/5/19 – Cost Estimate and SD drawings sent to County
12/10/19 – Cost Estimate Revised
01/9/20 – SOSS submitted to county
01/22/20 – Approved SOSS and PO received by Champlin
01/30/20 – Waiting to receive bid schedule approval and list of approved vendors before sending RFP to potential bidders
02/21/20 – bid documents sent to County for approval
03/11/21 – Documents revisions sent to Champlin
03/18/20 – Bid documents sent to county
04/02/20 – Project put on hold due to Covid-19
06/25/20 – County reported that most of this work was completed in house.

250 WHT – First Floor Painting Read More »