800 6th Fl Courtroom Renovations

Project Lead: GBBN

08/12/13 – Kick-off Meeting with Bert Watts and ThermalTech.

08/16/13- TEI submits break down of scope, reimbursable expenses and hours to GBBN,

08/17/13- County requests new SOSS based on lowered scope. Bert Watts confirms no scope of work involved on 12th Floor. Moving by Owner.

08/19/13- GBBN submits SOSS to Bert Watts.

08/19/13 – County requests break downs for consultant scope and hours for the SOSS to GBBN. ThermalTech is working on the CT strategy and will talk to the HVC chemical treatment contractor.

05/21/14 – GBBN requests full recycling tracking information beyond the paper only sent 5/24/14. Request also made for total waste disposal records from building to determine percentage of waste that is recycled.

05/27/14 – Bert Watts sends Sustainable Purchasing Tracking information to GBBN.

05/29/14 – GBBN receives word from USGBC that the review of the LEED EB+OM application has been received.

06/10/14 – GBBN receives word from USGBC that the review of the LEED EB+OM application is commencing.

07/09/14 – USGBC sends initial review comments to GBBN for review.

07/28/14 – All involved partners attend team meeting to discuss approach for returning responses to the review comments back to USGBC.

09/09/14 – Bert Watts requests estimate for this project to be authored and billed to General Services Contract.

01/28/16 – Project ready to archive.