800 First Floor Staff Relocation

Project Lead: GBBN

08/09/15 – County requested GBBN attend a kick-off Meeting at 800 Broadway on Tuesday, August 11th at 2:00 pm.

08/11/15 – Kick-off Meeting held at 1st floor north Office Suite area. Scope drawings prepared by Facilities is distributed to GBBN. Photos taken of north and south side areas and existing systems furniture.

08/12/15 – GBBN notifies Facilities of the existing electrical code implications of disassembling and reassembling the existing workstation cubicles per TEI and IPM’s input.

08/25/15 – Facilities notifies GBBN of the two Archibus Pop-up Project Request numbers for the estimating input.

08/26/15 – GBBN completes both estimates in Archibus and reports to Facilities they are completed.