09/24/20 THP submitted SOSS for inspection of building facade.
11/30/20 -THP received SOSS and PO for work.
12/10/20 – THP survey and assessment to occur spring 2021, purpose is to assess the façade after the winter freeze / thaw cycles.
01/28/21 – Delayed to Spring.
04/29/21 – THP staff passed background check. Rappelling and aerial platform work scheduled for week of 5/3/21. Thunderstorms and rain, may shift field work to later in May.
05/04/21 – THP and AFR completed aerial platform survey of the base. Loose mortar and limestone debris was removed.
05/13/21 – THP rappelled the tower.
05/14/21 – THP rappelled the tower.
05/27/21 – THP working on the report.