10/27/20 – THP sent SOSS for moisture investigation.
12/10/20 – THP and TEI to follow up on water line testing.
01/28/21 – THP completed multiple water tests and has determined water sources. THP developing excavation proposal. Draft report partially completed.
02/23/21 – SOSS requested by Hamilton County.
03/23/21 – THP provided SOSS. Three posts migrated to this project.
04/22/21 – Excavation completed along the north elevation, along with subbasement excavation.
04/29/21 – THP finalizing draft report. Anticipated publish date 5/7/21.
05/27/21 – THP updating the report with the excavation information.
10/27/21 – Budget issued in September then final report with updated interior repair added issued on 10/27/21