Hamilton County Facilities

THP

Comm Center – BE Assessment (F041)

PM: Rycca Thacker / Ian Zellner, John Millar
03/06/26 – HC requested an assessment SOSS.
03/13/26 – THP provided an SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working on Assessment. Roof testing/thermal scans 4-6 weeks out from April request. Testing contingent on weather conditions.
06/16/26 – THP completed field survey and roof scans.
08/05/26 – THP published the final report.
08/27/26 – Put into Archibus. THP has full restoration and partial, agreed to enter full cost and in notes put reduced scope.

Comm Center – BE Assessment (F041) Read More »

Colerain – Animal Shelter – (F037)

PM: John Millar/Emily Phillips
01/30/26 – THP issued SOSS for review.
02/17/26 – Hamilton County approved the SOSS.
02/18/26 – THP completed preliminary field survey.
02/26/26 – THP working on repair documents.
03/25/26 – THP finalizing document review set for review with HC early April.
04/27/26 – THP published Owner review documents.
06/25/26 – THP working on Bid Documents.
08/26/26 – THP working on Bid Documents with included demo walkway.
09/22/26 – THP published DD documents.
09/24/26 – Project plans to publish bid documents 9/28/26.
10/13/26 – Prebid meeting occurred.
10/16/26 – Addendum No. 1 issued (prebid meeting minutes).
10/29/26 – Project update – Bids due 11/23/26.

Colerain – Animal Shelter – (F037) Read More »

CH – Stone Stair Assessment (F033)

PM: Rycca Thacker, John Millar
09/03/25 – County asked THP to review stair condition at Courthouse stairs.
10/03/25 – THP submitted SOSS.
10/17/25 – County approved SOSS.
12/11/25 – THP plans to walk the steps next Monday and provide a report by 12/15/2025.
01/28/26 – THP is currently reviewing existing conditions and discussing internally.
02/17/26 – THP issued a draft report.
02/23/26 – THP issued final report.
02/25/26 – THP updated Archibus project request.
03/26/26 – OK to Archive.

CH – Stone Stair Assessment (F033) Read More »

Crime Lab – Leak Investigation (F032)

PM: Rycca Thacker, John Millar
08/28/25 – County asked THP to review water infiltration at the coroner building.
09/05/25 – THP completed an initial site visit to investigate the conditions.
02/25/26 – THP had follow meetings and discussion with HC. THP published an email with summary of potential leak areas and an opinion /of probable costs.
04/03/26 – Based on THP recommendations, County directed THP to complete water tests of the suspect areas.
04/09/26 – THP and HC staff completed water testing at the louvers and screen wall. Testing found multiple leaks in the screen wall.
06/25/26 – Project Archived.

Crime Lab – Leak Investigation (F032) Read More »

CH – Parking Lot Repair (F029)

PM: Matt Butz, Paul Bellman
06/03/25 – County, Kleingers and THP had a meeting to discuss scope of asphalt repair work.
07/24/25 – County and THP met to discuss project phasing.
07/30/25 – THP published preliminary opinion of probable cost for the project.
08/08/25 – THP published SOSS.
08/18/25 – County had kick off meeting with Tumlin, Champlin, THP, and Kleingers.
08/20/25 – County approved SOSS.
08/28/25 – Kleingers scheduled to survey the parking lot.
09/08/25 – Kleingers survey received
09/22/25 – Kleingers, THP, HC reviewed Courtyard lot for RFI #03 regarding overlay vs milling.
11/05/25 – THP, HC, and Tumlin reviewed milling conditions and full depth repair options.
11/14/25 – Kleingers provided updated striping plan.
11/18/25 – THP reviewed new asphalt in courtyard during heavy rain. Puddling and improper slope was observed on east portion of lot.
01/28/26 – No updates – weather pending.
02/26/26 – No updates – weather pending.
03/24/26 – No updates – Status of ponding in Courtyard area?
04/30/26 – THP to review on site conditions.
05/28/26 – No updates. Work in adjacent areas ongoing.
06/25/26 – Sink hole and active line was discovered in Courtyard lot. THP, Davies, and HC discussed scoping, filling void, and providing cleanout per supplied detail. Tumlin to get CO cost to repair.
07/30/26 – No updates from THP. Have not heard from Tumlin on the CO costs to repair sink hole in Courtyard Lot.
09/23/26 – No updates.
10/29/26 – No updates. Punchlist coming and cleanout addressed soon.

CH – Parking Lot Repair (F029) Read More »

Alms & Doepke – City Knock Down (F028)

PM: Rycca Thacker, John Millar
05/06/25 – County approved SOSS.
05/23/25 – County and THP had a kick off meeting.
08/28/25 – THP anticipates sending bid documents to contractors on 8/29/25.
09/02/25 – THP issued bid documents to American Façade Restoration, Buckeye Concrete Restoration, Hardig Industrial Services, and ZSR Contracting and Restoration. Kestner was unresponsive.
09/09/25 – Site prebid meeting occurred.
09/17/25 – Bids were received from three contractors. American Façade Restoration was the low bidder.
09/19/25 – THP reviewed the proposal with American Façade Restoration.
09/22/25 – THP published the a recommendation for American Façade Restoration to complete the work for the County to review.
09/24/25 – County requested additional bidders from the Bold list be invited to bid the project.
09/25/25 – THP sent three additional requests out to BSBE and MBE firms.
10/03/25 – THP received one proposal from LRT that was $15,000 over the low bidder.
10/15/25 – County issued a PO for AFR to complete the work.
10/29/25 – AFR is working through background checks. AFR is proposing to complete the work 11/10 to 11/14. Work is weather dependent and second shift.
12/11/25- THP has completed the survey at the building and is working on providing a City report regarding the observation by next week.
01/18/26 – The report has been approved by HC and THP submitted the report to the city.
04/30/26 – OK to archive this project.

Alms & Doepke – City Knock Down (F028) Read More »

SPHQ – Fall Protection Upgrade (F026)

PM: Matt Butz, Paul Bellman

04/01/25 – County requested SOSS for Fall Protection upgrade to the existing roof.
04/24/25 – THP to publish SOSS for review.
05/21/25 – SOSS approved.
06/25/25 – THP requesting roofing plans to start layout.
07/30/25 – THP working on DD drawings and plan to send draft to HC late next week.
08/27/25 – THP finalizing DD drawings and plan to send to HC at the end of the week.
09/24/25 – THP working towards CD drawings. Need to schedule a review meeting with HC.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
11/19/25 – THP issued summary letter to HC recommending NR Lee Restoration.
12/11/25 – HC finalizing paperwork for Contract approval.
01/14/26 – HC issued fully approved Contract to HR Lee Restoration.
01/27/26 – Preconstruction Meeting held virtual.
01/28/26 – THP issued Preconstruction Meeting Minutes.
02/19/26 – Preconstruction Meeting held On-site.
02/20/26 – THP issued Preconstruction Meeting Minutes.
03/25/26 – HR Lee is scheduled to deliver telehandler forklift 3/26 or 3/27 and material on 3/31. Work scheduled to begin shortly after.
04/08/26 – THP and HC reviewed on site substantial completion by HR Lee.
04/20/26 – HR Lee submitted Change Order for requested additional railing at small roof. THP to review with HC.
05/26/26 – HC issued signed and approved CO for additional railing. HR Lee placed order and updated schedule requested. Closeout documents in progress.
06/25/26 – THP is scheduling a final walk-thru with all parties. Closeout documents in process.
07/14/26 – On site final walk.
08/21/26 – THP sent CO #2 for requested safety line and final punch items to HR Lee for signature. Signed CO#2 returned to HC.
09/22/26 – On site review of final punch list items. HR Lee to schedule remaining work by next week.
10/08/26 – HR Lee completed final punch list items and THP and HC reviewed and approved.
10/15/26 – HR Lee submitted final closeout docs.
10/29/26 – HR Lee submitted paint touch up procedures from manufacturer for warranty work and would like to schedule paint touch up of bases.

SPHQ – Fall Protection Upgrade (F026) Read More »

SPHQ – Parking Lot Repave (F025)

PM: John Nester, Paul Bellman

04/01/25 – County requested SOSS to repaving of the Patrol HQ Parking Lot.
04/02/25 – THP completed a preliminary walk of the site.
04/18/25 – THP coordinated consultant proposals from Kleingers and Terracon.
04/24/25 – THP to publish SOSS for review.
05/07/25 – SOSS approved.
05/19/25 – Design kick off meeting complete.
05/29/25 – Civil survey and underground detective work complete.
06/25/25 – Terracon scheduled for underground exploration. THP coordinating with HC.
07/16/25 – Terracon completed borings and sent Draft report.
08/15/25 – Terracon sent final boring report.
08/28/25 – Meeting scheduled with THP, Kleingers, and Terracon to review boring report to finalize plans. Told Rycca THP can have this out late September.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
12/11/25 – Project on hold till further notice.

SPHQ – Parking Lot Repave (F025) Read More »

800 – Façade Repair SD (F022)

PM: John Nester, John Millar
01/02/2 – Champlin reached out to THP to provide SD services for the new Animal Shelter.
02/25/25 – THP provided an SOSS for SD Services.
03/26/25 – Elevar pending approved PO. Truescan started scanning the building from the interior.
04/23/25 – Design team had internal kick off meeting. Project update – Scanning complete and THP working on base Revit model for the project.
05/28/25 – Elevar has site walk scheduled for 05/30 to review windows. THP completed initial surveys and plans to rappel 5/29 and 5/30.
06/26/25 – Elevar investigating window replacement vs restoration and window cleaning products.
07/31/25 – Window drawings are progressing and a set will be provided to THP for inclusion in the next checkset to HCFD.
06/30/25 – THP completed aerial platform surveys of the lower section of the building and interior surveys of the façade 6/30 to 7/3.
07/17/25 – Stone stabilization proposals received and AFR is the low bidder.
07/22/25 – THP sent 800 Broadway review set to County. Set included windows and fall protection.
07/30/25 – AFR installing supplemental anchors on north elevations. Anticipate being complete by 7/31/25.
07/30/25 – AFR completed installation of supplemental anchors and THP confirmed the work.
08/27/25 – THP published share file with SD review drawings. Drawing included stone, window, and safety package.
08/28/25 – Summary documents and initial estimate planned for week of September 2.
08/28/25 – Window SD set provided to THP 08/15.
09/25/25 – Elevar provided ROM estimate to THP.
10/30/25 – Review mtg with HCFD scheduled for 11/06.
10/23/25 – THP issued opinion of probable cost for all work.
10/30/25 – County review meeting scheduled for November 6th.
12/11/25 – Review mtg held with HCFD. Revised estimates and design schedule to be provided.
12/01/25 – Schematic Design meeting occurred. Scope, budget and next steps presented.
12/23/25 – HC requested an SOSS – DD through Bidding.
01/19/26 – THP published SD report for County project planning.
01/29/26 – THP/Elevar working on SOSS.
01/31/26 – THP and County working through project scope and design team services.
02/25/26 – THP published SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working through initial design phase planning.
05/27/26 – Design Kick off meeting completed.
06/08/26 – Project summary for security meeting published.
06/17/26 – Project placed on hold.
07/29/26 – THP published summary of conditions for use by the County.
09/24/26 – Project on hold.
10/25/26 – Project on hold

800 – Façade Repair SD (F022) Read More »

General Structural Services (F019)

PM: Rycca Thacker, John Millar/Paul Bellman
04/24/25 – THP completed an initial analysis of the Hillcrest storage shed truss/decking for review by the County. Preliminary findings for published via email.
07/30/25 – THP was requested to review Justice Center parking configuration and walked the site with John and Tony.
08/14/25 – THP published two Justice Center parking options for review by the County.
08/28/25 – THP attending monthly meetings, updating website and coordinating structural questions.
09/25/25 – THP attending monthly meetings, updating website and coordinating structural questions.
10/24/25 – THP submitted updated General Service SOSS.
10/29/25 – THP attending monthly meetings, updating website and coordinating structural questions.

General Structural Services (F019) Read More »

Colerain – Animal Shelter Wood Canopy (F020)

PM: John Nester, John Millar
10/21/24 – HC reached out to THP asking for repair of the Animal Shelter Wood Canopy.
10/31/24 – THP reviewed internal past documents and County email. THP to meet with County to discuss next steps.
12/11/24 – THP working on repair design.
12/16/24 – THP surveyed the site and met with County personnel. Shoring configuration was discussed and direction was given to install preliminary shoring.
12/17/24 – THP sent shoring detail for review.
12/19/24 – HC installed shoring and sent photos of sample shores. Shoring detailing was confirmed.

Colerain – Animal Shelter Wood Canopy (F020) Read More »

230 – Façade Repairs (F016)

PM: Matt Butz, Fateme Shahiyan

08/29/24 – County request THP rebid Alternate Façade repair package from SOSS F003. SOSS Hamilton County.
09/23/24 – THP published review drawing to County.
09/23/24 – County provided review comments to THP.
09/26/24 – Final bid to be released to purchasing with Advertise to bid scheduled for 9/30/24. Bid opening scheduled for 10/30/24.
10/16/24 – THP issued Addendum No. 1 – (prebid minutes and updated prevailing wages).
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received.
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received and BCR was the lowest bid.
11/05/24 – THP had a Bid Review with BCR
11/14/24 – THP sent the bid summery and recommendation letter for BCR to Hamilton County.
01/16/25 – Preconstruction meeting completed.
01/29/25 – Progress meeting completed.
01/30/25 – Project status – BCR has rigged and complete the first knock down survey of the north elevation. Work will progress north to west to south.
02/21/25 – Crew moved to the west elevation to do the knock down and have the spots ready to patch when temperature gets better in the next week.
02/24/25 – BCR send out Pay App No.1 for THP review and THP approved that.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/26/25 – BCR start installing the swing stage on roof for the north return wall of the building.
03/31/25 – BCR completed the work and sounded the north return wall. No major sports or damage.
04/04/25 – BCR submitted pay app No.2 and was approved by THP. BCR needs to provide the closeout documents.
05/27/25 – BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/10/25 – BCR has provided all closeout documents, which have been approved by THP. BCR is in the process of sending the notebooks and USB drive containing the documents to the County. Once that is completed, THP will send the signed final pay application to HC.
07/30/25 – Project status: All closeout documents approved. Waiting on project notebooks.
08/26/25 – BCR planning on complete the closeout documents and send it to the county by end of the next week along with the TPC project.
09/15/25 – BCR dropped off the closeouts documents to HC/Matt Butzz. However, the electronic documents, notarized warranties and 2 payrolls for the project were missing. BCR is planning to provide the documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.

230 – Façade Repairs (F016) Read More »

2025 Structural Estimates CIP Resubmittal (F010)

PM: John Nester, John Millar

06/11/24 – THP HC requested SOSS for project estimates broken down by New, Resubmittal and CIP Resubmittal.
06/25/24 – Champlin published draft project lead list.
07/15/24 – Thermal Tech published final edit.
08/28/24 – THP published SOSS.
08/29/24 – THP working on estimates.
09/26/24 – THP finalizing estimates.
12/11/24 – THP completed structural project estimates.

2025 Structural Estimates CIP Resubmittal (F010) Read More »

CH – Facade Repairs/Roof Replacement (F005)

PM: Matt Butz, John Millar, Eryn Thamann
06/26/24 – THP provided SOSS to Elevar.
07/25/24 – County approved SOSS.
08/14/24 – THP and Elevar completed a kick off meeting and general walk of the roofs.
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
09/26/24 – Truscan came out two days ago and modeled the building. Elevar will share with the partners, over one billion points scanned, CH and surrounding areas. More fieldwork needed.
10/30/24 – Model shared with THP and SD continues.
12/09/24 – THP working with model and performing site work.
10/30/24 – Model shared with THP and SD continues.
12/11/24 – THP completed initial field work to confirm model accuracy. THP provided review comments and has begun working on model joints.
01/29/25 – THP has performed several facade tests but weather limited site work; surveying still ongoing to document stone/terra cotta joints. Roof plans are developed; THP/Elevar coordinating on roof edge details now.
02/25/25 – Deliverable schedule sent to MB. Work ongoing.
03/26/25 – Met with HCFD to review SD status drawings. THP has additional site investigation to perform but still look on track for May SD deliverable.
04/24/25 – Team is progressing with design. Elevar to get masonry contractor under contract to complete destructive investigation.
04/24/24 – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
05/28/25 – Decision on mason expected 05/29. Elevar to schedule work with HCFD.
06/26/25 – Mason under contract and patiently awaiting their onsite schedule. THP/Elevar meeting to coord. designs. Final SD set expected to HCFD end of July.
07/31/25 – Mason walk-thru 07/24 with THP/HCFD and scheduled onsite start for 08/04. Badging will start if crew will be inside but will determine at walk-thru. Deadline pushed back to accommodate mason.
08/28/25 – Waiting for final mason contractor to get badged to start investigative demo.
09/25/25 – Mason onsite in Sept and design team finalizing drawings based on findings.
10/30/25 – Final SD set provided to HCFD along with cost estimate. Review mtg schedule for 11/06 with HCFD/THP.
11/06/25 – THP and Elevar met with HC to review SD set. HC requested updates to OoPC and schedule.
11/21/25 – THP sent final OoPC to Elevar, with requested updates from HC.
12/01/25 – THP reviewed design schedule with Elevar and HC during 800 Broadway meeting.
12/11/25 – Final cost estimate and design schedule will be provided to HCFD this week.
01/29/26 – Elevar/THP working on SOSS.
02/23/26 – THP published fee proposal to Elevar for Phase II of design work.
03/26/26 – SOSS approval pending.
04/24/24 – THP update – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
04/30/26 – SOSS approved. Need to schedule kick-off meeting with team and HCFD.
05/28/26 – Design kickoff mtg occurred 05/27. Elevar to send pdf presentation to team for review with Court Admins. Team will provide design schedule very soon.
06/17/26 – Project placed on hold.
06/25/26 – On hold. Design kickoff minutes and presentation provided to HCFD.
07/30/26 – No update. Remains on hold.
08/14/26 – THP provided recommended critical repair scope and budget.
08/27/26 – Priority list provided by THP to HCFD. Could restart after November with very limited scope.
09/24/26 – Project on hold.
10/25/26 – Project on hold

CH – Facade Repairs/Roof Replacement (F005) Read More »

230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003)

PM: John Nester, Fateme Shahiyan

04/26/24 – THP provided SOSS Hamilton County.
05/09/24 – County approved SOSS.
05/24/24 – THP provided review documents.
05/28/24 – County provided comments to review documents.
05/31/24 – THP provided Economic inclusion work sheet.
06/04/24 – Economic inclusion package returned to THP.
06/07/24 – THP issued bid documents.
06/20/24 – Prebid meeting occurred.
06/21/24 – Addendum no. 1 issued.
06/26/24 – Bid opening scheduled for July 23, 2024.
07/23/24 – The County received one bid from BCR. Base Bid was 8% over the project opinion of probable cost.
07/24/24 – Department of Economic Inclusion noted the bid was responsive.
07/25/24 – THP and the County to review the bid.
08/15/24 – THP published bid summary letter, recommending BCR.
09/26/24 – Earlier, County sent contract to BCR for execution.
10/04/24 – Contract executed and published.
10/15/24 – Preconstruction meeting occurred.
10/21/24 – County published rooftop safety tie inspection report.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
11/08/24 – BCR published the SOV for review by THP.
11/19/24 – BCR published their schedule for the project
12/04/24 – BCR sent the Pay App No.1 to THP
12/10/24 – BCR Resubmit the Change order No.1
12/10/24 – BCR sent revised Pay App No.1 to THP and THP approved it.
12/10/24 – BCR completed about 30% of the work including sounding and opening up the lintel areas on the fifth floor and providing temporary flashing over the top of the ledge angle.
01/30/25 – Project status – BCR completing sounding, concrete and masonry repairs on West Elevation of Todd Portune Center. Remaining work is corner of south elevation of the TPC. Due to low temperatures crews moved to the 230 WHT building to complete knock down survey work. Crews will return after work at 230 WHT is complete.
02/24/25 – Project is still on hold and crew are still working on 230 WHT.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/25/25 – THP send the pay app No.4 from BCR, to HC for the final review.
04/23/25 – Project is completed and BCR needs to provide closeout documents.
05/27/25- BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/25/25 – HC requested Change Order #3 (CO#3) for the emergency concrete repair on the north elevation of the Portune Center. BCR has provided CO#3 to HC, and HC is currently working to get it approved. BCR is planning to send the supporting documentation, including the cost breakdown with any applicable markups, to THP and HC by the end of this week.
07/01/25 – Change order #3 approved.
07/14/25 – BCR started work.
07/24/25 – THP visited the site and reviewed the work. Field report published.
07/25/25 – BCR finished knock down work.
08/26/25- BCR provided the last pay app for the emergency repair to THP for review. BCR planning on complete the closeout documents and send it to the county by end of the next week.
09/15/25- BCR dropped off the closeout documents to HC/Matt Butz. The electronic documents, notarized warranties were missing. BCR planning to provide all documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.
02/26/26 – Ready to archive.

230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003) Read More »

JC – Skywalk Roof Replacement & Exterior Repairs (F002)

PM: Bert Watts, John Millar

02/01/24 – Hamilton County requested an SOSS for roof replacement of Skywalk bridges.
02/29/24 – THP reviewed roof approach with Contractor and roofing manufacturers. THP working on proposal.
03/14/24 – THP issued DD review set of roof replacement with the Skywalk Exterior façade repair.
03/28/24 – THP working on bid package.
04/25/24 – Project combined with F077. THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
07/19/24 – THP issued Bid Documents to the County and Arc.
07/22/24 – Bid Documents Released on Bid Sync.
07/25/24 – Prebid meeting scheduled for July 30th and Bids due September 12th.
07/30/24 – Prebid meeting completed.
08/29/24 – Addendum No. 1 to be published.
08/29/24 – Addendum No. 1 published.
09/09/24 – Addendum No. 2 published.
09/19/24 – The bids were received from Browning Chapman and Buckeye Construction and Restoration. Both bids were under budget and within 8% of each other.
09/25/24 – THP and Browning Chapman had bid review meeting. BC appears to have all major scope items covered, including site logistical needs. The group discussed extending the contract to include time this winter to allow for shop drawing and window fabrication. BC is reaching out to the subcontractors to determine feasibility and needs. THP to publish summary letter after BC determines the needs.
10/08/24 – THP published the bid summary letter recommending Browning Chapman based on the bid amount.
10/31/24 – Hamilton County working on the AIA contract.
12/11/24 – Contract before the BOC for execution.
12/11/24 – Contract before the BOC for execution.
12/17/24 – Contract approved and sent to BC.
01/30/24 – Project status – BC finalizing submittals and background checks. Preconstruction meeting scheduled for 2/18/25. Anticipated construction starting end of March.
02/17/25 – Browning Chapman sent submittals for THP’s review.
02/18/25 – Preconstruction meeting completed.
2/27/25 – Browning Chapman finalizing background checks, submittals and permitting. THP working on submittals.
3/11/25 – Progress Construction Meeting.
3/18/25 – Progress Construction Meeting.
3/24/25 – Browning Chapman mobilized.
3/25/25 – Progress Construction Meeting.
3/26/25 – THP finalizing revised submittals and reviewing pencil Pay App #1.
04/01/25 – Progress Construction Meeting.
04/08/25 – Progress Construction Meeting.
04/09/25 – Permit Issued.
04/15/25 – THP finalized all submittals.
04/15/25 – Progress Construction Meeting.
04/21/25 – Roofing demo and window removal on East Skywalk began.
04/22/25 – Progress Construction Meeting.
05/06/25 – Progress Construction Meeting. East Skywalk roofing.
05/13/25 – Progress Construction Meeting. East Skywalk roofing complete. Steel Installation. North Skywalk mobilization.
05/20/25 – Progress Construction Meeting. East Skywalk steel painting, window flashing, painting mock-up. North Skywalk stair scaffold and roofing on east portion.
05/27/25 – Progress Construction Meeting. East Skywalk window installation. North Skywalk roofing and window removal/temp. panels on east portion.
06/03/25 – Progress Construction Meeting. East Skywalk Window install complete. North Skywalk Roofing east half complete and window removal/angle install in progress.
06/10/25 – Progress Construction Meeting. East Skywalk Façade painting in progress and North Skywalk roofing west half in progress.
06/17/25 – Progress Construction Meeting. North Skywalk Roofing west half complete and window removal complete. North Skywalk window install in progress. Punchlist started.
06/24/25 – BC sent Pencil Pay App #4 for review. THP to return shortly.
07/15/25 – Progress Construction Meeting. North Skywalk Façade painting.
07/29/25 – THP issued punch lists for North Bridge roof work and East Bridge. North bridge roof work was completed.
07/29/25 – Progress Construction Meeting. North Skywalk Façade Painting complete. East Skywalk Punch Complete. EJ Work in progress. BC sent Pencil Pay App #5 for review. Final Punch scheduled for 8/14/25 @ 1pm.
08/15/25 – THP investigated reported leak condition on the east end of the north bridge.
08/18/25 – BC, THP, and County completed water test and confirm leak was from roof drain line in the cavity below the bridge slab at the east end of the bridge.
08/19/25 – BC and THP used a camera to scope the drain line and found two breaks in the drain line that corresponded to the leak location.
08/21/25 – BC, THP and County completed punch trip for north bridge.
08/28/25 – THP exploring different plumbing repair options and developing opinion of probable costs.
10/29/25 – BC to begin Roof Drain line repair on 11/03/2025. 2 week schedule.
11/06/25 – THP completed site visit to review completed drain line.
11/14/25 – THP reviewed hatch mockup. Proposed hatch too big for panel. Updated panel size ordered. Weather permitting panel work to start in December.
12/11/25 – BC is installing the access hatch in the panel at the shop. Painter is scheduled to paint the panel in the shop. Once complete, BC to schedule panel installation.
01/28/26 – THP is reviewing BC’s Closeout Documents and should be returned 01/30/26.
01/28/26 – BC is currently estimating repairs for Concrete truck damage to North Skywalk.
02/05/26 – THP returned all Closeout Documents with comments to BC for final submittals to HC.
02/25/26 – THP to reach out to Imbus regarding mental panels and bending 20′ lengths.
03/25/26 – North Skywalk leak – BC indicated they are in contact with Delaware glass.
03/25/26 – Concrete truck panel damage – BC reaching out to metal panel manufacturers to get custom panel pieces and working up pricing. BC would like to coordinate panel repairs with leak.
04/20/26 – BC sent proposal to THP for Metal Panel Repairs. THP to review proposal with HC and schedule the work.
04/28/26 – BC is working with Delaware Glass on the leak at the North Skywallk and is working on scheduling them next week. A lift is required and will need to be delivered.
05/11/26 – Lift Plan submitted for Metal Panel work and glass warranty work.
05/19/26 – BC submitted cost breakdown for skywalk repairs to HC.
06/25/26 – Delaware Glass has completed warranty work for leak in North Skywalk. BC has completed metal panel work at North Skywalk and has processed all requested closeout documents.
07/30/26 – Verify with County if project can be archived.
09/23/26 – THP completed a site visit on 9/16/26 to review paint peeling on exterior skywalk façade. Field report to follow shortly.
10/26/26 – BC scheduling a site visit with Painting Contractor to review paint Issue.
10/28/26 – HC received letter from City of Cincinnati Permit District Inspector regarding open inspections for the project. BC was notified.

JC – Skywalk Roof Replacement & Exterior Repairs (F002) Read More »

2020 – Slab and Masonry Repairs (F001)

PM: Rycca Thacker, Paul Bellman
02/01/24 – Hamilton County requested slab project be rebid based on previous project.
02/12/24 – THP published review documents to the County.
02/16/24 – Hamilton County provided review comments to the documents.
02/16/24 – THP published bid documents to Hamilton County.
02/20/24 – Hamilton County advertised project for bid.
02/27/24 – Prebid meeting occurred.
03/11/24 – Addendum 1 issued to Purchasing.
03/14/24 – Addendum 2 issued to Purchasing.
03/15/24 -Addendum 3 issued to Purchasing.
03/28/24 – Bids due date April 8, 2024.
04/12/24 – Reviewed Bid with Browning Chapman.
04/19/24 – THP issued Bid Summary Letter to Hamilton County.
05/02/24 – Hamiliton County issued Contract Documents to Browning Chapman.
05/10/24 – Browning Chapman returned signed documents.
05/30/24 – Hamilton County Board review on 06/06/24.
07/19/24 – Browning Chapman working on pricing estimates for floor finishes, submittals, and background checks.
07/23/24 – Hamilton County requested to schedule a kick-off meeting.
08/15/24 – Preconstruction meeting completed.
08/19/24 – THP issued meeting minutes.
08/28/24 – Browning Chapman issued revised flooring options estimates. Browning Chapman’s submittals approved. Project to be scheduled.
09/25/24 – Browning Chapman submitted new flooring proposal for polished concrete. Approved and BC will need to develop Change Order.
10/28/24 – THP returned submittals to Browning Chapman.
10/31/24 – Final Pre-Construction meeting scheduled for Friday 11/01/2024.
11/01/24 – Kick-off meeting.
11/04/24 – HC sent Notice to Proceed.
11/07/24 – Progress Construction meeting.
11/14/24 – Progress Construction meeting.
11/20/24 – Progress Construction meeting.
11/20/24 – THP Signed Pay App #1 and sent to HC.
11/27/24 – Progress Construction meeting.
12/05/24 – Progress Construction meeting.
12/10/24 – THP signed Change Order #1.
12/12/24 – Progress Construction meeting.
12/13/24 – THP Signed Pay App #2 and sent to HC.
01/09/25 – Progress Construction meeting.
01/16/25 – Progress Construction meeting.
01/23/25 – Progress Construction meeting.
01/23/25 – THP Signed Pay App #3 and sent to HC.
01/30/25 – Progress Construction meeting.
02/13/25 – Progress Construction meeting.
02/20/25 – Punchlist Walkthrough.
02/26/25 – Browning Chapman finalizing punch list items. Final walkthrough scheduled 03/06/25.
03/06/25 – Final Walkthrough and signoff of completed items.
03/07/25 – THP signed Pay App #4 and sent to HC.
03/26/25 – Email sent to Browning Chapman requesting Closeout documents. BC indicated Closeouts will be ready for review on 3/28/25.
04/11/25 – BC sent closeout documents to THP for review.
04/18/25 – THP sent reviewed closeout documents and comments back to BC.
04/22/25 – THP sent HC signed Pay App #5 – Final Retainage.
04/24/25 – BC sent HC Final Closeout Documents.
05/29/25 – Can THP archive project?
06/25/25 – Project Archived.

2020 – Slab and Masonry Repairs (F001) Read More »

Hillcrest – Birch Cottage Removal (F095)

PM: Bert Watts, Paul Bellman
09/28/23 – Hamilton County requested SOSS.
10/30/23 – THP provided SOSS for review.
11/20/23 – County approved SOSS.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/22/23 – THP issued 90% Drawing Owner Review set to Hamilton County.
02/16/24 – THP issued Bid Documents to Hamilton County.
02/20/24 – Hamilton County Purchasing advertised documents to bid.
03/04/24 – Pre-bid meeting held.
03/19/24 – Addendum 1 issued to Purchasing.
03/28/24 – Bid opening scheduled for April 10, 2024.
04/18/24 – THP scheduled Bid review with O’Rourke for 04/25/24.
05/16/24 – Hamilton County requested documents from O’Rourke.
05/30/24 – THP to follow up with requested documents (Schedule of Values, Schedule, Safety plan, general submittals) and schedule pre-construction meeting.
06/05/24 – THP emailed O’Rourke regarding submittals and Pre-construction Meeting.
06/25/24 – THP sent follow-up email to O’Rourke.
06/26/24 – Hamilton County received Asbestos Inspection – Notice of Compliance. O’Rourke to start sending submittals on plumbing material and valves in conjunction with other things.
07/16/24 – Pre-Construction meeting held.
07/17/24 – Pre-Construction meeting notes distributed to all parties. Mobilization scheduled for 7/29/24 (tentative).
07/29/24 – Mobilization and utility work started.
08/16/24 – Demolition complete.
08/23/24 – Final grading complete.
08/28/24 – Seeding and strawing postponed – hold retainage. THP to review pay-app.
09/12/24 – Hamilton County and THP – Final Site walk through.
09/19/24 – THP issued Field Report.
09/25/24 – THP issued closeout list to O’Rourke.
10/09/24 – O’Rourke issued Closeout Documents to THP.
11/27/24 – THP sent pencil copy of Closeout Documents to Hamilton County for approval.
12/10/24 – THP sent final Punch List to be signed and notification for payroll documentation.
12/11/24 – O’Rourke is sending Closeout Documents to Hamilton County.
12/13/25 – Closeout Documents sent to Hamilton County.
01/03/25 – Finalizing Final Pay Application for retainage.
02/26/25 – No updates on Certified Payroll from O’Rourke/Park’s Electric.

Hillcrest – Birch Cottage Removal (F095) Read More »

THP 2024 General Services (F093)

PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
02/29/24 – Record Center roof was noted to be leaking in a number of locations. Roof is under warranty. THP documented the conditions and met with the manufacturer and contractor. Manufacturer’s warranty department has approved a repair approach. Contractor is pricing.
02/29/24 – 800 Broadway tile in NE stair tower had cracking at the first floor level. THP coordinated contractor stabilization, removal and repair. Repair is complete. THP to provide a summary report.
04/25/24 – THP no update.
06/27/24 – Record center roof repair started today and is planned for the next 2-3 weeks. THP scheduled to be on site Friday to review progress.
07/12/24 – Tremco completed warranty repairs and submitted reports for review.

THP 2024 General Services (F093) Read More »

JC – Façade Monitoring 2023 (F087)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 11th.
10/03/23 – Field survey of façade started.
10/11/23 – Rappel of façade completed.
10/26/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
07/25/24 – THP completed assessment and report. No work needed. Final City report due 07/01/27 – Ready to Archive.

JC – Façade Monitoring 2023 (F087) Read More »

2020 – City Façade Monitoring 2023 (F086)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/06/23 – Rappelling of façades completed.
09/28/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update
08/29/24 – No repairs needed final report due next June.

2020 – City Façade Monitoring 2023 (F086) Read More »

800 – Annual Façade Monitoring 2023 (F085)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 10th.
10/10/23 – Rappelling survey of Tower completed.
10/17/23 – East wing loose debris survey started.
10/19/23 – East wing loose debris survey completed.
10/26/23 – THP working on summary report updated.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/26/24 – Monitoring updated report submitted.
06/27/24 – Budget submitted to County.
08/29/24 – THP scheduling façade knock down survey and inspection for 2024.
09/26/24 – THP to review knock down approach with larger repair package.
10/31/24 – Ready to archive.
12/10/24 – THP closing out the project.

800 – Annual Façade Monitoring 2023 (F085) Read More »

A&D – Annual Facade Monitoring 2023 (F084)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/06/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 3rd.
10/03/23 – THP completed rappelling and façade monitoring survey.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
08/29/24 – THP working on repair package for City repairs.
12/10/24 – THP closing out the project.

A&D – Annual Facade Monitoring 2023 (F084) Read More »

CH – Annual Façade Monitoring 2023 (F083)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
05/16/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of courtyard façade scheduled for October 3rd.
10/03/23 – Rappelling canceled due to additional rappelling needed at A&D building. THP to reschedule.
02/29/24 – Rappelling scheduled for March 20th and March 21st (weather pending).
03/20/24 – Rappelling completed in the courtyard, but cancelled for the exterior of the building due to high winds.
03/28/24 – THP to reschedule rappelling for mid April.
04/25/24 – THP to reschedule final rappelling in mid May.
05/30/24 – THP plans to schedule rappel end of June.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
9/26/24 – THP to reach out to the City and determine placing repair package on hold for larger project.
12/10/24 – THP closing out the project.

CH – Annual Façade Monitoring 2023 (F083) Read More »

Records Center – Winton Road Asphalt Repairs & Accessibility Stall Improvement Project (F082)

PM: John Nester, Paul Bellman
04/06/23 – Hamilton County requested SOSS.
04/06/23 – THP, Kleingers, and HC – Site Visit – Review Scope
04/25/23 – Received Kleingers proposal.
05/09/23 – Received Terracon’s proposal.
05/23/23 – THP submitted SOSS to County for Review.
07/12/23 – Hamilton County approved S0SS.
08/21/23 – Terracon on site to mark boring locations.
08/23/23 – OUPs to mark utilities prior to boring.
08/24/23 – Terracon on site for drilling of test bore locations.
09/12/23 – Hamilton County communicated to THP the flipping of Base Bid and Alternate work.
09/18/23 – THP received parking options from Kleingers. Need to review with Hamilton County.
09/26/23 – THP scheduled on site meeting with Kleingers and Hamilton County. Meeting cancelled – Reschedule Teams Mtg.
10/09/23 – THP and County had meeting to review budget and scope of work. Scope of work adjusted to available funds.
10/10/23 – County Issued AIA forms for bid documents.
10/20/23 – Kleingers sent THP review bid drawings and technical specifications.
10/20/23 – THP issued review bid documents – project manual, drawings, and XBE opinion of probable costs.
10/26/23 – Issue of bid documents anticipated for October 31, 2023.
10/30/23- Documents advertised to bid.
11/08/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 issued.
12/07/23 – Bid opening scheduled for 12/13/23.
12/13/23 – Bid opening. (3) bids received and under review.
02/23/24 – Hamilton County sent THP Contract Document A101 for review.
02/29/24 – KT Holden low responsive bid. Hamilton County sent AIA contract to KT Holden for review and execution.
03/25/24 – KT Holden returned signed contract to Hamilton County.
03/22/24 – Approved Contract issued to KT Holden by Hamilton County.
05/14/24 – Preconstruction meeting held on site.
05/16/24 – Hamilton County issued notice to proceed to KT Holden.
05/17/24 – Preconstruction meeting minutes issued.
05/20/24 – KT Holden submitted Schedule of Values and submittals.
05/22/24 – KT Holden submitted for permit.
05/28/24 – Kleingers returned submittals. THP to review and return.
05/21/24 – KT Holden picked up approved permit.
06/25/24 – THP returned submittals to KT Holden. Revised submittals returned to THP and sent to Kleingers.
06/25/24 – KT Holden indicated work is scheduled for August.
07/18/24 – THP emailed KT Holden for schedule update.
07/24/24 – KT Holden Scheduled for mobilization on 8/05/24.
08/23/24 – Kleingers conducted a site visit. Utilities and sawcuts were marked.
08/28/24 – KT Holden on site and started construction.
09/03/24 – KT Holden working on asphalt removal and subgrade work.
09/11/24 – KT Holden asphalt work begins.
09/12/24 – KT Holden concrete work begins.
09/25/24 – Hamilton County, THP, and Kleinger met for final site walk through. THP issued Field Report and Punch list.
09/25/24 – KT Holden submitted Pay App #1 and #2 for review.
10/07/24 – THP returned Pay App #1 and #2 to Hamilton County.
10/31/24 – THP will send Closeout requirements to KT Holden.
11/27/24 – Building Inspection passed and Inspector will close permit in system.
12/11/24 – THP Reviewing Closeout documents and submit pencil copy to County for review prior to printing.
01/24/25 – KT Holden sent Closeout documents to Hamilton County – Confirmation received. Final Pay Application needs to be submitted.
02/04/25 – THP sent Hamilton County Final Pay Application #4.
02/27/25 – THP to archive project.

Records Center – Winton Road Asphalt Repairs & Accessibility Stall Improvement Project (F082) Read More »

Hillcrest Birch Cottage Removal Assessment (F078)

PM: Bert Watts, Paul Bellman
– Hamilton County requested SOSS.
04/26/23 – Pinnacle Enviromental to provide proposal.
05/01/23 – THP submitted SOSS to County for review.
05/10/23 – County approved SOSS.
05/22/23 – THP sent Pinnacle Contract for signature.
07/07/23 – THP received signed Contract from Pinnacle.
07/18/23 – THP forwarded Pinnacle contacts for background checks.
08/21/23 – Pinnacle Environmental on site for NESHAP Hazardous Material Inspection.
09/27/23 – THP Requested proposals from ThermalTech and Pinnacle. Provide SOSS to Hamilton County.
10/19/23 – THP received Pinnacle Pre-Demolition NESHAP report.
10/20/23 – THP published Pinnacle report to the County.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/18/24 – THP reached out to Chris Belcher with Pinnacle for final report.
01/31/24 – THP reached out again to Chris Belcher with Pinnacle for Ffnal report.

Hillcrest Birch Cottage Removal Assessment (F078) Read More »

TPC – Rail and Gate Project (F073)

PM: John Nester, Matt Rigdon
08/26/22 – Hamilton County requested SOSS.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County met to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
08/31/23 – THP to send review of the new lapeyre stair at TPC which is to be included in the WHT Railing package.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/23/23 – ZSR Contracting and Restoration was awarded the project at the end of November. Email received from Hamilton County that the contracts are still being processed. Lead time for materials to be 5-6 weeks once contract is received.
2/28/24 – No updates from THP.
3/26/24 – THP received SOV and Project Schedule. Pre-construction meeting to be set closer to delivery time of prefab stair. Prefab stair expected to be delivered first week of May.
04/24/24 – Preconstruction meeting completed.
05/23/24 – THP received revised shop drawings for stair at Portune Center.
09/26/24 – First Progress meeting held on 09/23/24. ZSR to mobilize this week and begin demolition of existing stair at TPC.
12/03/24 – ZSR has addressed outstanding items at the new staircase. THP to begin close out procedures with ZSR.
01/29/25 – Closing out – beginning phase. Doug (ZSR) sent everything over to their office manager last week and he is getting AIA docs together. Doug is hoping to have everything to me this week to review.
3/26/25 – Finalizing Closeout documents. Should be ready to forward to HC soon.
04/24/25 – THP dropped off final closeout documents.
04/24/25 – Archive project.

TPC – Rail and Gate Project (F073) Read More »

JC – Skywalk Exterior Repairs (F077)

PM: Matt Butz, Paul Bellman/John Millar
12/30/22 – Hamilton County requested SOSS.
02/23/23 – THP Submitted SOSS.
03/22/23 – Hamilton County approved SOSS.
04/27/23 – Design work scheduled to begin 6/1/23 and the project being bid 9/1/23.
07/21/23 – THP needs to schedule a kick-off meeting with the County.
08/21/23 – Kick-off meeting held with Hamilton County and THP.
09/26/23 – THP met with Hamilton County to review site logistics. Preparing Bid Docs for 10/09/2023.
10/04/23 – THP published bid document project manual for final review by the County Facilities.
10/05/23 – THP published bid document drawing for final review by County Facilities.
10/06/23 – County provided comments to the documents.
10/06/23 – THP published final bid documents to Purchasing, Facilities, and Arc.
10/11/23 – Skywalk project advertised to bid.
10/18/23 – Prebid Meeting occurred.
10/23/23 – Addendum No. 1 Issued.
10/26/23 – Bid opening scheduled for 11/15/23.
10/31/23 – Bid questions received by County and forwarded to THP.
11/01/23- Addendum No. 2 issued by THP. Bid opening changed to November 20, 2023.
11/09/23 – Addendum No. 3 issued by THP.
11/20/23 – Bid opening occurred. Browning Chapman and Buckeye Construction submitted bids. One bid was below the advertised budget and the second bid was under the 20% threshold. Purchasing sent bids sent to economic inclusion department for review.
12/07/23 – Bids under review.
12/15/23 – Bids found to be unresponsive.
02/01/24 – THP requested to repackage project for rebid in 2024.
02/29/24 – THP working on DD set.
02/29/24 – THP to issue updated Bid Documents to Hamilton County for Owner review.
03/14/24 – THP issued DD review set with combined roofing project.
03/21/24 – HC Board of Commissioners approved budget for Façade project.
03/21/24 – THP met with Hamilton County to review project DD documents. Based on timing and bid procedure, County requested project bid in early June.
03/28/24 – THP working on documents.
04/25/24 – THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
06/26/24 – THP working on documents and targeting a bid set for July.
07/17/24 – Project is combined with FOO2 – Justice Center Skywalk Roof Replacement.

JC – Skywalk Exterior Repairs (F077) Read More »

THP 2023 General Services (F069)

11/09/22 – Hamilton County requested SOSS.
11/21/22 – THP provide SOSS for review.
12/12/22 – Hamilton County approved SOSS.
12/29/30 – THP coordinated Courthouse stone knock downs and surveyed southeast corner of the building.
12/30/22 – THP supported Champlin with 2020 Auburn flooring repairs.
01/06/23 – THP and AFR completed knock down work at Courthouse.
01/26/23 – THP updated project status work and attended monthly mtg.
02/23/23 – THP updated project status work and attended monthly mtg.
03/14/23 – THP attend WBE/MBE training meeting for Partners.
03/30/23 – During March, THP hired and coordinated special inspection work for 800 Broadway concrete pour.
04/26/23 – Railing redesign work for 800 Broadway work concrete platform and bulletin was completed.

THP 2023 General Services (F069) Read More »

230 – Guard Rail – Safety Gate (F068)

PM: John Nester, Matt Rigdon
09/02/22 – Hamilton County requested SOSS.
09/29/22 – THP and Hamilton County walked the sites.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County meeting to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to send review set of revision drawings that account for existing ductwork interferences. THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
07/17/23 Requested to combine the two safety gate projects for WHT & TPC Buildings into one drawing set. Requested by HamCo to separate Railing at WHT as individual project.
07/26/23 – Documents being finalized and to send July 31.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/31/24 – No updates from THP.
2/23/24 – County sent AIA contracts to ZSR for review and execution.

230 – Guard Rail – Safety Gate (F068) Read More »

525 – Warehouse Doors and Ramp (F072)

PM: Rycca Thacker, Paul Bellman
12/07/22 – THP submitted SOSS to Hamilton County.
01/08/23 – THP spoke with City and have verbal confirmation a new curb cut is allowed.
01/10/23 – THP proposed initial layout to Hamilton County.
01/19/23 – THP and Thermal Tech met Hamilton County and EMA personnel onsite to review site layout and get field measurements.
02/10/23 – THP sent owner review documents to Hamilton County.
02/21/23 – Owner has approved the warehouse improvements. Hamilton County getting funding put in place.
02/24/23 – THP and Kleingers meeting with Hamilton County and EMA personnel to measure vehicles for final ramp layout and design.
03/16/23 – THP sent bid documents to Hamilton County Purchasing Department.
03/20/23 – Bid Documents released by Hamilton County Purchasing Department.
03/29/23 – Prebid meeting completed.
03/30/23 – Project opening scheduled for 4/13/23.
04/13/23 – Bid opening occurred with John P. Tumlin & Sons being the apparent low bidder and under budget.
04/21/23 – THP published a bid summary letter, recommending the County proceed with Tumlin.
05/21/23 – Permit drawings created and sent last week.
04/21/2023 – THP published a bid summary letter, recommending the County proceed with John P. Tumlin & Sons.
05/15/23 – HC sent contract to John P. Tumlin & Sons and requested their insurance certificates.
05/31/23 – HC waiting on Board of Commissioners for contract approval.
05/31/23 – John P. Tumlin & Sons working on schedule of values, schedule, site specific safety plan, material submittals, background checks, etc.
06/29/23 – THP receiving submittals from John P. Tumlin & Sons.
07/12/23 – HC notified THP that the construction contract will be presented to the Commissioners at their public meeting on 07/27/23.
07/27/23 – TTE returned the PTAC submittals again (second time) for changes.
07/28/23 – HC sent approved contract, PO, and Notice to Proceed to THP and Tumlin.
08/22/23 – Pre-Construction meeting set for Wednesday, August 30.
08/30/23 – Pre-construction meeting with THP, Hamilton County, Tumlin, ThermalTech Engineering, and Kleingers.
09/27/23 – Tumlin submitted construction schedule. Tentative date for mobilization set for October 2.
10/02/23 – Tumlin mobilized to site to begin construction.
10/25/23 – Interior overhead doors installed, masonry repaired at office, PTAC installed in office, interior slab on grade has been removed and replaced, interior man door has been installed, steel framing and masonry work at exterior door openings has started. Gas line has been relocated and additional gas line repairs have been approved via change order.
11/27/23 – Steel framing and masonry work for exterior openings has been completed. Both exterior overhead doors have been installed. Electric work and painting continuing inside. All mechanical/gas line repairs associated with this project have been completed. Exterior ramp (grading, forming, rebar/mesh, etc.) has been started. Concrete ramp pour scheduled for the week of 11/27/23.
12/06/23 – Electric work continuing inside. First two concrete ramp pours completed on 11/30/23 and 12/06/23.
01/02/24 – Last concrete pour for ramp completed.
01/24/24 – THP, ThermalTech, Hamilton County, and Forest Park met onsite to walk through and discuss required life safety items to get temporary certificate of occupancy for Phase 1. Team to address issues.
01/26/24 – Punchlist Walk Through with Bert Watts. Sent list to Tumlin.
01/30/24 – Additional Overhead Doors in back of warehouse started to get installed.
02/26/24 – THP, ThermalTech, and Champlin met onsite to review the vehicle layout. Champlin and ThermalTech to update Life Safety drawings and Electrical drawings, respectively, for in place vehicle layout with egress, emergency and exit lighting, etc to address issues that were discussed with Forest Park Building Department and Fire Department.
04/18/24 – THP received updated electrical drawings with emergency/exit lighting from ThermalTech. Request for change order pricing and updated drawings sent to Tumlin for installation.
04/24/24 – THP waiting to receive change order pricing from Tumlin. Installation of emergency/exit lighting required to close out phase 1 and building permit.
05/10/24 – Change Order for Emergency/Exit Lighting approved.
05/14/24 – Fully executed Change Order sent to all parties.
05/21/24 – Emergency/Exit Lighting submittal received. Waiting on review from ThermalTech to send approval. Installation to follow after submittal approval.
06/26/24 – ThermalTech reviewed Lighting submittal – Approved as Noted.
08/29/24 – Safety electrical items being installed.
09/26/24 – Pay Application #7 received for review.
10/11/24 – THP returned Pay Application #7 to Hamilton County.
10/31/24 – Closeout Process needs to be initiated.
12/11/24 – Closeout Process needs to be initiated.
01/23/25 – Closeout Process initiated with Tumlin.
02/26/25 – Closeout Process in progress by Tumlin.
03/26/25 – THP to follow-up with Tumlin on Closeout.
04/08/25 – THP sent Tumlin email on Closeout documents.
04/22/25 – Tumlin responded to email and indicated another request was sent out to subcontractors for closeout documents.
05/16/25 – Fire Alarm testing caused a short in the new fire alarm control panel. A fire watch was required for this weekend and was provided by a third party firm. TTE helped HamCo on first session until fire watch company arrived.
05/20/25 – Cin-Day installed the new FACP and replaced one address module, tested the existing system and found it to be working with no Trouble. We still need to work out warranty requirements.
05/19/25 – THP received close-out documents from Tumlin.
05/28/25 – THP started review of close-out documents.
06/25/25 – THP to return comments on close-out documents to Tumlin.
07/30/25 – THP reviewed close-out documents and sent Tumlin final comments/documents.
08/27/25 – Tumlin is sending final closeout documents to Hamilton County.
02/20/26 – Preconstruction Meeting held for Generator Plug-In Relocation.
02/23/26 – THP issued Preconstruction Meeting Minutes.
03/11/26 – On-site meeting held to review logistics of panel relocation.
03/24/26 – THP verified panel had been removed from the existing Blue Ash location. Status of permit drawings, IBI Inspection, closeout?
04/28/26 – Tumlin is working on final PW info for HC for Closeout Documents.
05/27/26 – County said do not archive until we get all closeout documents.
06/25/26 – Tumlin submitted requested Closeout Documents.
07/30/26 – Need IBI Inspection report for Closeout Documentation for Plug-in Electrical relocation. Davies to submit.
08/20/26 – THP sent project Meeting Minutes to HC.
08/27/26 – Rycca believes they have paid out this project.

525 – Warehouse Doors and Ramp (F072) Read More »

250 WHT – Façade Repairs and Window Replacement (F067)

PM: Matt Butz, Paul Bellman
09/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
09/30/22 – THP published SOSS. (8 years ahead of schedule).
03/27/23 – THP Revit Model in progress.
04/25/23 – Revit Model 95% complete.
05/23/23 – No updates from THP.
07/20/23 – Hamilton County on site meeting with THP to review scoping.
08/23/23 – County placed project on hold.
09/27/23 – THP to provide Hamilton County with status drawings the first week of October.
10/23/23 – THP provided review documents (drawings and project manual), plus economic inclusion opinion of probable costs.
01/31/24 – No updates from THP.
02/29/24 – No updates. On hold.
03/27/24 – On hold.
04/25/24 – On hold.
05/30/24 – No updates. On hold.
06/26/24 – No updates. On hold.
07/24/24 – No updates. On hold.
08/29/24 – No updates. On hold.
09/26/24 – No updates. On hold.
10/31/24 – No updates. On hold.
12/11/24 – No updates. On hold.
12/12/24 – Champlin to check on const 2B vs 5B and maybe we submit an engineering change to modify it to 5B.

250 WHT – Façade Repairs and Window Replacement (F067) Read More »

CH – Critical Façade Repairs (F064)

08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
10/20/22 – Hamilton County approved the SOSS.
01/26/23 – THP developing design documents.
02/23/23 – THP is continuing to develop design documents. We have partially surveyed the façade for specific damage, and are developing repair/stabilization details. THP will return this week to finish survey.
03/23/23 – THP is developing design documents and plans to have owner review set ready by week of 3/27. We have some remaining survey work from within the courtyard to complete
04/27/23 – THP plans to issue bid review documents May 2nd.
04/27/23 – THP plans to issue bid review documents.
07/13/23 – THP published updated bid review documents to the County.
08/10/23 – THP published bid documents. Bid documents included new XBE program requirements.
08/22/23 – Prebid meeting occurred.
08/23/23 – Addendum No. 1 issued.
08/30/23 – Addendum No 2 issued.
09/07/23 – Bid opening occurred. One bidder over budget. Bid rejected.
09/13/23 – THP issued a bid summary email.

CH – Critical Façade Repairs (F064) Read More »

A&D – Façade and Foundation Repair (F063)

PM: Rycca Thacker, John Millar
08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP anticipates publishing the SOSS 10/4/22. Working with Tru Scan and Thermal Tech.
10/17/22 – THP published SOSS.
01/25/23 – Model created, design ready to start.
02/23/23 – Civil surveys and field surveys in process. Surveys include roof and site work.
04/27/23 – Project updates: Civil survey complete, fall arrest SD complete, and field survey of attic completed. THP coordinating with potential contractors and geotechnical testing company to develop foundation repair package.
07/27/23 – THP anticipates issuing an complete SD set on 8/3/23.
09/28/23 – THP working on SD documents.
10/26/23 – THP scheduled to publish review set October 31.
12/06/23 – THP issued review set.
01/31/24 – THP needs to schedule review meeting with Hamilton County.
02/07/24 – THP met with County to review design development documents.
02/28/24 – THP working on bid documents.
03/28/24 – THP working on bid package.
04/25/24 – THP working on bid package.
05/30/24 – THP working on bid package. Bert said he wants to get it packaged to the point to where it can be bid ready, even if it is shelved.
06/27/24 – Rycca said to go ahead and bid out safety repairs from report.
07/25/24 – THP working on safety package for City Repairs.
08/29/24 – Safety package anticipated for issued 9/4/24.
09/26/24 – Safety review package anticipated for issued 10/09/4/24.
12/10/24 – THP closing out project.
01/24/25 – THP submitted closeout DD package.
02/26/24 – THP published City Façade repair letter.

A&D – Façade and Foundation Repair (F063) Read More »

800 – Sub Basement Storage Floor Repair (F058)

12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
03/08/22 – THP completed an initial site visit for scope of work.
03/25/22 – THP submitted a SOSS for review by the County.
04/13/22 – SOSS approved.
06/30/22 – THP working on staff background check. Plan to start mid June.
07/27/22 – THP visited site and needs to get a fire rating from the floor which would require a concrete solution. Looking at potential solutions now.
08/19/22 – THP issued review drawings for County review.
08/25/22 – THP working on option pricing for proposed design and removal of the fill.
09/21/22 – THP issued review Bid Set to John Nester for comments.
09/24/22 – THP issued Bid Set drawings and project manual to the county. Scheduled Pre-bid conference for 10/5/22, last day for questions 10/11/22, last day for answers 10/13/22, and a bid opening date for 10/19/22.
10/19/22 – Bid opening for the project. Four bids received all below or within the project published budget. SSRG the apparent low bidder.
10/26/22 – THP conducted bid review phone call with SSRG.
01/03/23 – SSRG sent Workers Comp. Insurance & CGL Insurance to HC
01/06/23 – HC Signed contract and PO
01/09/23 – HC Approved contract and PO and sent it to SSRG
01/13/23 – THP sent sealed conformance documents to HC and SSRG
01/17/23 – SSRG sent preliminary SOV and Schedule
01/18/23 – HC and THP sent comments back for revisions to SOV and Schedule due to long lead times for railings and the background checks.
01/24/23 – SSRG begun background check process
01/24/23 – SSRG sent submittals for steel rebar, steel railing, and anchorage.
02/27/23 – SSRG asked about the removal of existing piping that is in the way of the slab formwork.
03/01/23 – THP visited the site and, along with verification from the county, noted that the pipe was an abandoned fuel line and that it is acceptable to move/remove pipe as necessary for form work. SSRG will do so with no additional cost.
03/01/23 – SSRG noted they need to use permanent forms instead of digging pea gravel trenches for formwork. THP noted this as acceptable.
03/02/23 – Terracon was contracted to be the special inspector for this project for steel reinforcement and concrete.
03/06/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. It was requested by the county to draft a pump plan for the concrete pour day to notify parking inhabitants before the pour date. This was supplied that same day.
03/06/23 – Fuel tanks were noted to be buried under the pea gravel. This was deemed to not affect our design since the slab is designed to be structural.
03/06/23 – Concrete mix design was sent to Terracon for reference
03/06/23 – THP supplied SSRG with design loads for permit.
03/07/23 – Special inspections were scheduled
03/09/23 – Stamped special inspection form was sent to SSRG for permit.
03/13/23 – Progress meeting 1 meeting notes were distributed to the team.
03/13/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. Steel inspection and concrete pour scheduled for 03/13 and 03/14 respectively.
03/13/23 – Steel inspection was performed by Terracon, and steel reinforcement was reviewed by THP for consistency with design drawings. No comments were noted.
03/14/23 – Concrete pour was performed. THP on site from 7:45 AM until about 12:00 PM. Concrete pumping, finishing, and the site cleanup was observed by THP as required.
03/16/23 – Terracon sent reinforcing steel observations report.
03/17/23 – THP sent an elevation for SSRG & steel fabricator use for guardrail modifications.
03/17/23 – SSRG sent pricing for stairway move and rebuilding, and excess pea gravel removal.
03/17/23 – Progress meeting 2 meeting notes were distributed to the team.
03/17/23 – Field Report 02 for concrete pour was distributed to the team.
03/21/23 – SSRG sent Pay App #2 for approval.
04/21/23 – Bulletin No. 1 issued for review by the County.
04/25/23 – Bulletin No. 1 issued for pricing.
05/25/23 – Project summary. SSRG provided pricing for Bulletin No. 1 and Hamilton County declined the modifications. SSRG scheduling the final railing install. April pay application placed on hold, because work is for railing and closeout.
05/30/2023 – SSRG sent May Pay App for review
06/01/2023 – SSRG installed the guardrail per original drawings after Bulletin 01 option was rejected by County.
06/08/23 – THP sent the approved May Pay App to the County
06/12/23 – THP sent email to SSRG outlining the documents required for project closeout.
06/15/23 – THP performed a final punch visit, accompanied by John Nester.
06/15/23 – THP sent the final punch report to SSRG.
07/07/23 – SSRG completed punch list items on site.
07/12/23 – THP reviewed, approved, and sent previously-held April Pay App to County.
07/24/23 – THP reviewed SSRG’s completed punch list work and sent out a field report indicating these items were complete.
07/24/23 – THP compiled and sent As-Built drawings to SSRG for closeout documents. Waiting for SSRG to send closeout docs.
07/26/23 – THP published as-built drawings and completed punch list field report.
08/15/23 – THP contacted SSRG regarding an update to the progress of their closeout documents.
08/18/23 – THP received closeout binder electronic documents from SSRG. Documents included are: General 1 year warranty, As-built drawings (provided by THP), and THP’s Field Report 001. SSRG indicated they are still awaiting their front ends team to compile and send forms G706, G706a, G707, and the affidavits. THP reviewing.
09/26/23 – THP delivered approved project binders to the County.
09/26/23 – THP forwarded approved final pay application to the County.

800 – Sub Basement Storage Floor Repair (F058) Read More »

Comm Center – Asphalt Resurfacing (F056)

PM: Matt Butz, John Millar/Matt Rigdon
12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/25/22 – THP and County met to discuss scope.
04/04/22 – THP submitted a SOSS for review by the County.
04/25/22 – County approved SOSS.
06/10/22 – THP issued design development documents.
06/21/22 – THP received contractor opinion of probable cost. Within project budget.
06/22/22 – County published AIA forms for final bid documents.
06/30/22 – THP documents ready for bid. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot
07/21/22 – THP issued Addendum #1.
08/03/22 – Bid opening scheduled.
08/03/22 – No bids received at opening. THP contacted over 12 contractors during the bid period. Contractors noted extremely busy for 2022.
08/25/22 – Project documents updated and work rescheduled for spring of 2023. New bidding period advertise 8/26/30, prebid 9/6/22 and bids due 9/13/22.
08/26/22 – THP issued “For Bidding” submittal with new schedule for 2023.
09/06/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot.
09/14/22 – Bids are due.
09/14/22 – Bids from Rack7, Prus and JK Meurer were received. All base bid within budget. Rack7 was the apparent low bidder.
09/21/22 – THP and Rack7 completed an initial bid review meeting. Rack7 did not include unit cost work in the base bid and has withdrawn from the bid.
09/28/22 – THP and Prus will complete an initial bid review meeting.
09/29/22 – THP and Prus completed an initial bid review meeting. Prus did not include unit cost work in the base bid and has withdrawn from the bid
10/05/22 – THP and JK Muerer completed an initial bid review meeting.
10/11/22 – THP issued a Bid Summary Letter recommending JK Meurer for the contract.
11/21/22 – J.K. Meurer was approved contract and corresponding PO. Kick-Off meeting sometime after the first of the year. Anticipate work after Winter/start of Spring.
01/04/23 – HC sent CO 001.
01/05/23 – THP signed and returned CO 001.
01/06/23 – J.K. Meurer signed and returned CO 001.
01/10/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
01/26/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
02/23/23 – Background checks to begin this month. Anticipating Preconstruction Meeting for March 15, 2023.
03/15/23 – Preconstruction Meeting
03/23/23 – Anticipating work schedule is May 1st-22nd. The following still needs to be submitted by J.K. Meurer: SOV, emergency contacts, and official schedule. No submittals have been submitted; Anticipating Mix Design Submittal.
04/25/23 – No updates for April. Work to start on May 1st (weather pending). Anticipating on-site visit with J.K. Meurer and Hamilton County on May 2nd (weather pending).
05/01/23 – J.K. Meurer provided mix design submittals. Asphalt resurfacing work began at Visitor Lot.
05/02/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to ADA space to allow for access aisle to be at west side rather than east side of parking space.
05/05/23 – J.K. Meurer completed work at Visitor Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
05/08/23 – J.K. Meurer began work at Secured Lot.
05/09/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to the berm at the loading dock ramp.
05/15/23 – J.K. Meurer completed work at Secured Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
07/26/23 – Bulletin being prepared and to be sent for review July 31.
08/09/23 – THP met with Ian to review drive repair needs.
09/26/23 – County request gate repair as part of drive work. Motor details sent to THP.
09/28/23 – THP forward JK Meurer quote for drive and gates.
10/06/23 – County approved quote for drive and gate. THP notified JK Meurer to proceed.
10/11/23 – JK Meurer proposed full slab replacement. THP provided slab requirements for the new ramp. JK Meurer provided updated proposal.
10/17/23 – Project budgetary numbers sent to County for review. JK Meurer proposal using cash allowance funds. Work is below total project budget.
10/17/23 – County sent draft Change Order No. 2 for authorization of new drive and gate motor.
10/25/23 – County published executed Change Order No. 2.
10/26/23 – JK Meurer schedule to begin drive work the middle of November.
11/03/23 – Drive repair work rescheduled to accommodate interior renovation project.
12/04/23 – Demolition of the ramp started.
12/06/23 – Lower section of ramp subgrade and steel prepared. Bottom half of ramp poured and concrete tested. THP inspected steel and Terracon tested concrete.
12/07/23 – Upper section of ramp schedule for completion.
01/15/23 – Concrete replacement at ramp was completed mid-December. Email received from contractor that installation of new gate operator is expected to be installed at the end of January.
01/30/23 – Gate contractor notified THP that the operator is now expected for production on 01-31-24. Production is backed up for LiftMaster and the ship date keeps changing. Installation is TBD in February.
0002/28/24 – Gate contractor is to notify THP and County once the vendor is contacted. Delivery has been delayed for approximately two months.
03/13/24 – Gate operator was delivered and installed on site. Overhead Door did not put the operator in service due to the condition of the gate.
03/18/24 – THP, HamCo Facility Manager, and Overhead Door met on site to review condition of inoperable gate.
03/27/24 – THP received quote from Mills Fence Co to replace existing gate. HamCo has approved. CO to be made up next week.
04/25/24 – JK Meurer planning on complete repair to top of drive on 4/26/24.
05/1/24 – JK Meurer and subcontractor has revised their project close out documents and sent to County. Project is closed. No more updates.
05/18/24 – JK Meurer to revise their pay app 2.
05/23/24 – Mills Fence Co checked gate to ensure it is working. JK Meurer and THP to start the project close out process.
09/26/24 – Awaiting final Change Order deduct from Hamilton County and Mills Fence lien waiver for close out documents.
12/11/24 – THP to review close out documents following updated close out procedures.
01/29/25 – Closing out – last phase. All documents are in and reviewed by THP. (3) As-built Hard Copies, (1) copy of final pay app & AIA docs, (3) copies in notebooks of O&M, and (1) USB flash drive. Will hand in at Thursday’s meeting.
02/24/25 – Final pay application approved.
02/25/25 – Final pay application prevailing wage documentation sent to County.

Comm Center – Asphalt Resurfacing (F056) Read More »

230 – City Façade Assessment (F054)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/27/22 – THP Completed a majority of the rappelling survey of the façade.
04/28/22 – Final rappels anticipated first week of June and report to be published in June.
06/30/22 – City Report due 7/1/23. THP to combine final rappel with Portune Center and complete in August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.

230 – City Façade Assessment (F054) Read More »

TPC – Center Beam Repair (F053)

PM: Matt Butz, Matt Rigdon
12/14/21 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/24/22 – THP submitted a SOSS for review by the County.
03/11/22 – SOSS approved.
03/25/22 – THP completed a survey of the beam repair area.
04/28/22 – THP is developing documents.
05/17/22 – THP published review documents.
05/27/22 – County published review comments to DD documents.
06/30/22 – THP – Issue with Concrete repair around building electrical feeds determined. Repair needs in electrical feed area minor and can wait until electrical area needs service and come off line. THP documents ready. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Portune Center Lobby.
07/21/22 – THP issued Addendum #1.
07/22/22 – THP issued Addendum #2.
08/03/22 – Bids are due.
08/03/22 – Bids from LRT, Buckeye and ZSR were received. All base bid within budget.
08/18/22 – THP and LRT completed an initial bid review meeting.
08/22/22 – THP issued a follow up sketch for field clarification.
08/24/22 – LRT reviewed sketch and bid, and provided an updated price to their bid.
09/01/22 – Site visit and developed a design change to accommodate existing MEP.
09/16/22 – THP issued new “For Bidding” submittal with design change.
09/27/22 – THP hosted pre-bid meeting at HC Portune Center Lobby. Bids are due 10/7/22.
10/06/22 – THP issued Addendum #1 with new Bid Opening Date for October 13.
10/13/22 – Bids are due.
10/13/22 – Bids from ZSR, LRT, Buckeye, and SSRG were received.
10/14/22 – THP and ZSR completed an initial bid review meeting. THP sent a follow up letter to the County recommending they proceed with ZSR for the based bid and all four alternates.
12/12/22 – ZSR was approved contract and corresponding PO. ZSR has signed and returned COI. Kick-Off meeting sometime after the first of the year. Anticipate work in February 2023 depending on background checks.
01/12/23 – ZSR has begun submittal process.
01/18/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
01/26/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
02/14/23 – Preconstruction Meeting
02/23/23 – All submittals are in. Anticipating work to start February 27.
03/23/23 – Drilled holes for rebar on 3/20/23. Permit completed by end of this week. Anticipating deck supporting steel to be installed week of 3/27. Special inspections to be completed following the steel installation.
04/20/23 – On-site visit with Hamilton County to observe completed work. No comments on work from Hamilton County. THP to send close out report.
07/26/23 – Bulletin being prepared and to be sent July 31.
09/28/23 – THP forwarded pricing from ZSR for the beam repair. County coordinating possible repair of beam with electricians.
10/19/23 – County moving forward with electrical and beam repair. County requested ZSR beam repair proposal to develop an AIA Change Order.
10/26/23 – County developing AIA Change order for ZSR.
01/12/24 – Change order for additional beam repair cancelled due to electrical conflicts.
01/31/24 – Project is in the process of closing out. Awaiting final close out docs.
02/28/24 – THP received project close out documents and is reviewing.
03/14/24 – THP received revised project close out documents and is reviewing.
04/25/24 – THP approved draft closeout package. ZSR to send hard copies and USB drive.
05/01/24 – ZSR revised their project close out documents and sent to County. Project is closed. No more updates.
08/29/24 – All final work closeout documents completed. Waiting on final pay application.
12/09/24 – THP reached out to Terracon to provide special inspector stamp for close out to Permit. Terracon to provide this week.
01/29/25 – THP Closedout Procedure – January 3 – City of Cincinnati is currently closing out the permit (Jeffery Hinkle).
03/26/25 – Project Archived.

TPC – Center Beam Repair (F053) Read More »

TPC – City Façade Assessment (F052)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/28/22- Rappelling anticipated first week of June. Report to be published in June.
6/30/22 – City Report due 7/1/2023. THP completed review of new cellular towers. THP to schedule rappelling late July. Report to be complete by end of August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.

TPC – City Façade Assessment (F052) Read More »

CH – Annual Façade Monitoring (F051)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/27/22 – THP Completed rappelling survey of the façade.
04/28/22 – Report to be published in June.
06/29/22 – THP issued reports and City form.
06/30/22 – THP Scheduled to submit form to City.
08/25/22 – Project complete.

CH – Annual Façade Monitoring (F051) Read More »

800 – Annual Façade Monitoring 2022 (F050)

PM: Bert Watts, John Millar
12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/07/22 – THP Submitted SOSS for review by the County.
04/21/22 – County Approved the SOSS.
04/27/22 – THP Completed rappelling survey of the façade.
04/28/22 – Base survey anticipated end of May and report in June.
06/30/22 – City report due 7/1/2023. THP plans to issue draft report for review 7/8/22.
08/25/22 – THP working on findings presentation.
09/28/23 – THP completed new cost data with project estimates. THP working on final presentation.
02/29/24 – THP no update.
03/27/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.

800 – Annual Façade Monitoring 2022 (F050) Read More »

A&D – Annual Façade Monitoring (F049)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/12/22 – County Approved the SOSS.
04/14/22 – THP Completed rappelling survey of the façade.
06/29/22 – THP issued reports and City form.
06/30/22 – THP Scheduled to submit form to City.
08/25/22 – Project complete.
10/27/22 – Ready to Archive.

A&D – Annual Façade Monitoring (F049) Read More »

CH – Rooftop Patio Renovation (F042)

PM: , John Millar
10/07/21 – Hamilton County requested SOSS to repair the roof of one of the old “Bear Dens”.
10/14/21 – Hamilton County and design partners met to review design needs.
10/28/21 – THP Submitted a SOSS for review.
05/26/22 – Save the Tree.
04/27/23 – Save the Tree.

04/25/24 – FOOORRRRRRRRKKKK!!

06/27/24 – DUUUUUUCCCCCKKKKK!!
09/26/24 – The tree has unfortunately left this world and we are saddened by its departure.

CH – Rooftop Patio Renovation (F042) Read More »

Hillcrest – Birch Cottage Storm Damage Investigation (F033)

06/23/21 – During storm tree fell on Birch Cottage at Hillcrest causing significant roof damage.
06/25/21 – THP provided SOSS to investigate storm damage.
07/01/21 – County approved SOSS.
07/06/21 – THP visited the site and confirmed initial damage. Cottage unoccupied.
08/16/21 – THP published opinion of probable cost to rebuild cottage or demolish it. OPC included support cost from Champlin Architecture and Thermal Tech Engineering.
10/20/21 – THP issued final report.

Hillcrest – Birch Cottage Storm Damage Investigation (F033) Read More »

Hillcrest – Birch Cottage Storm Damage Repair (F044)

PM: Bert Watts, John Millar

11/03/21 – Hamilton County requested SOSS to repair Birch Cottage.
12/01/21 – THP, Champlin and Thermal Tech met at Birch Cottage to review scope.
01/27/22 – THP submitted SD proposal. Bert has updated on scope of work on the work for the project for coverage of the damage.
04/22/22 – County reached out to Champlin to restructure the approach with Champlin leading the full effort. Champlin requested an updated proposal.
04/26/22 – THP send an updated proposal to Champlin.
01/25/23 – SOSS requested for Birch Cottage demolition.
02/23/23 – THP following up with contractors for environmental study prior to demo for spoils remediation.

Hillcrest – Birch Cottage Storm Damage Repair (F044) Read More »

2020 – Roof Replacement (F034) and Davit Upgrade (F027)

PM: Rycca Thacker, John Millar
07/29/21 – THP Submitted SOSS to County.
08/23/21 – SOSS approved.
02/2321 – THP completed roof cuts and assessments. THP scheduling masonry survey for repairs, anticipated week of 2/28.
03/07/22 – Week of March 7th, THP Surveyed interior for masonry distress and slab settlement.
03/24/22 – THP and County reviewed field findings from THP survey.
04/27/22 – THP developing DD documents.
06/30/22 – THP developing DD documents. Plan to bid mid August.
07/28/22 – THP proposed design schedule update DD issue 8/30/22 and CD issue 9/15/22
10/27/22 – THP to publish 90% drawings 10/28/22.
01/10/23 – County provide review comments.
01/26/23 – THP anticipates CD documents issued 2/3/23.
02/23/23 – Finalizing documents. Plan to issue bid documents week of 2/26.
03/24/23 – Bid documents anticipated the week of 4/3/23.
05/31/23 – Documents advertised for bid.
06/07/23 – Prebid mtg occurred.
06/16/23 – Addendum No. 1 issued.
06/27/23 – Bid opening occurred. Two submitted bids received with low bid 16% above advertised budget. THP to review with County next steps.
08/31/23 – June bids rejected. County requested roof and masonry project be separated and bid this fall. THP published review documents 8/31/23.
10/06/23 – Roof Repair project approved for KEE system. AIA documents issued to THP. Slab and Masonry Repair project approved. AIA documents issued to THP.
10/0923 – County comments to the review documents published to THP.
10/09/23 – Inclusion goals published.
10/12/23 – Review Bid Documents published for both the Roof and Slab Lifting Projects.
10/13/23 – Final Bid documents published for both the Roof ITB 116-23 and the Slab Lifting and Masonry Repairs ITB 117-23 projects.
10/16/23 – Roof and Slab projects advertised for bid.
10/25/23 – Prebid meeting occurred for both projects.
10/26/23 – Bid opening scheduled for November 30, 2023.
11/09/23 – Slab and Masonry Repairs Addendum No. 1 issued.
11/13/23 – Roof Repairs Addendum No. 1 issued.
11/14/23 – Slab and Masonry Repairs Addendum No. 2 issued.
11/17/23 – Roof Repairs Addendum No. 2 issued.
11/20/23 – Roof Repairs Addendum No. 3 issued.
11/30/23 – Slab and Masonry Repairs Bid opening. No submissions.
11/30/23 – Roof Repairs Bid opening. Five contractors submitted bids with a range of $1,761,452 to $2,103,895. One bid was below advertised bid amount and the remaining bidders were within 10%. Bids sent to the economic inclusion department for review.
12/23/23 – Kelly Brothers Roofing found responsive and THP notified to review the bid.
01/08/24 – THP and Kelly Brother’s reviewed the bids.
01/15/24 – THP published bid summary recommending Hamilton County contract with Kelly Brothers for the roof project.
02/06/24 – Hamilton County sent AIA contract to Kelly Brothers Roofing.
03/02/24 – Kelly Brothers returned contracts to Hamilton County.
03/25/24 – THP published conform and permit drawings to Kelly Brothers and Hamilton County. Drawings updated with 2024 code review and requirements.
03/27/24 – Project contract goes before the board on April 4th for final approval.
04/11/24 – Executed contract sent to KBR.
04/29/24 – Preconstruction meeting completed.
05/30/24 – Project update – THP processing submittals and shop drawings.
05/31/24 – Initial scaffolding installation for roof access to start.
04/29/24 – Preconstruction meeting occurred.
05/31/24 – Project mobilization occurred.
06/27/24 – Contractor working on Roof D, E, and F. Existing roofing removed, repairs started and installation of the complete system started on roof D south end. Roof work on hold until July 1.
07/25/24 – KBR working on Roof D installing system south to north. Temporary scaffolding stair tower at roof F extended to roof D. Temporary stair tower and bridge installed to Roof C.
08/16/24 – THP published Bulletin No. 1.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
09/12/24 – THP published walk mat layout review drawing.
09/16/25 – THP sent SOSS for additional services for Roof Safety Design.
09/19/24 – KBR completed main installation on roof D and E and working on detailing on both. Preparation for Roof F has started.
09/19/24 – THP published roof safety review drawings.
09/24/24 – THP published roof safety review drawings, Rev. 1.
09/25/24 – Hamilton County, CMI and THP had a MS Teams meeting to review the roof safety drawings and proposed approaches.
09/26/24 – KBR completed main installation of Roof F.
10/25/24 – THP released initial safety package for pricing by KBR. THP working on platform design to finalize complete package.
10/31/24 – KBR completed Roof D,E, &F including initial punch work. Roof A,B, & C and punch trip review complete. All lightning protection work scheduled to start early November.
10/30/24- KBR completed the work on lower roofs A,B and C and THP completed the initial punch review with KBR and HC for these roofs. THP needs to review the final fibertite’s punch review for the final confirmation.
11/06/24- HP approved pay App No.4 from KBR and send it to HC for the final review
11/07/24- THP send out the Bulletin No.2 to KBR for Pricing.
11/15/24- THP had a visit to KBR’s warehouse to confirm the walk mat materials purchased by KBR.
12/03/24- KBR send the Pricing for Bulletin No.2 to THP for review.
12/05/24- THP requested the breakdown of cost and resubmitting the CO No.2 from KBR.
12/09/24- HP approved pay App No.5 from KBR and send it to HC for the final review.
12/10/24- KBR sent the breakdown of costs for CO#1 for THP’s review.
12/11/24 – THP forwarded breakdown of cost and backup review to Hamilton County.
12/18/24 – County and THP approved KBR pricing. Final change order to be coordinated with safety upgrade work.
01/29/25 – County sent KBR AIA Change Order No. 2 for signature.
01/30/25 – Project status – Roof installed. Change order No. 2 waiting for execution and weather to install new safety platforms, RTU removal, and roof reconfiguration.
02/04/25 – Change Order No. 2 executed.
03/06/25 – Lightning protection work is complete, KBR is still waiting on the certification letter from Maxwell.
03/21/25 – THP reviewed the shop drawings for the platform and sent it back with comments to KBR. KBR Believed it should be roughly 7-8 weeks from getting them on-site for install.
03/26/25 – THP/LJB’s proposal for roof in progress.
04/24/25 – LJB provided updated proposal on 4/17/25. THP sent final proposal to County for review.
05/21/25- KBR confirmed that fabrication for the ladder and platforms is completed and they are at their site ready for deliver and install. KBR are getting themselves put on the schedule and will follow up with THP once they have a date.
06/18/25 – KBR will begin roof work on 07/07, including installation of ladders, platforms, and fall arrest systems on the ladders. Remaining work includes installing walk mats, replacing drain rings and cages on all roofs, and capping abandoned curbs on Roof C. KBR anticipates completing the Change Order #2 (CO#2) work within approximately two weeks from the start date.
06/24/25 – KBR submitted the lightning protection certification for THP’s review.
07/11/25- KBR completed 90% of the CO#2 works including installing walk mat on roofs, platform installation on both roof C and E, installing drain ring & strainers and caping abounded curb.
07/30/25 – KBR will provide CO#3 and CO#4 for remaining work including safety railing on roof D and E, Hatch guard, stair tower rental and all the work regarding removing old davits and installing new fall protection system. (the fall protection system work will be based on LJB design)

HC Juvenile Justice Center Davit Upgrade (F027):
THP PM: Rycca Thacker, John Millar
03/27/25 – County identified a number of safety concerns with roof operations. THP and the County had follow up meetings.
04/17/25 – THP received proposal from LJB for design of the safety davit system.
04/18/25 – THP published SOSS for County review.
05/07/25 – SOSS approved.
05/29/25 – THP coordinating design with LJB. Initial design discussions/meetings complete and formal SD to be submitted mid-June.
06/23/25 – LJB sent the preliminary drawings for the fall arrest system upgrade to THP. The design will be discussed with HC on 06/26. If there are no major changes, the final design is expected to be completed by the end of July.
07/11/25 – LJB sent the 90% drawings set and it was approved by THP and HC. LJB planning to provide the final design by August first.
08/22/25 – KBR completed remaining work on the ladder at roof F.
08/27/25- THP requested an updated cost estimate from KBR for CO#4 with a labor and material breakdown on the few Items including ( Safety Railing Roof D and Roof E, Hatch Guard, Flash New Davits and New Fall Protection) per county’s request and deducting the Terrecon cost from the list since that will be through THP.
08/27/25 – LJB send final review documents to THP. THP to review then forward to the team.
09/10/25- Terracon conducted a site survey to inspect the platform and ladder on roofs. They have noted that (2) attachments bolts on the top of the ladder at Roof E were loose. THP has reached out to KBR regarding this matter, and they are planning to have the steel crew back on site to complete the work.
09/19/25- LJB adjusted few items in their drawings per THP request and THP has sent the final drawings to KBR and HC for their review. KBR is waiting on CO#4 approval to start the rest of the work.
09/26/25 – County requested a breakdown of CO #4 work to be completed with railing material costs provided by the County.
10/09/25 – KBR provided updated pricing for CO #4 with the County providing the railings.
10/10/25 – THP reviewed pricing and noted one item to update.
10/16/25 – KBR provided an updated CO #4 breakdown pricing.
10/16/25 – THP approved pricing.
10/20/25 – County sent fully executed CO #4 to all parties.
10/26/25 – County received pricing for railings for CO #4 work with KBR. THP to review once cut sheets and product information is provided.
12/10/25 – KBR had the crane on site for delivering the roof railing on Friday 12/5 and were planning to complete the work the week of 12/8 weather depending. The work will include the installation of the railing at the roof edge on roof D and E and railing around the hatch at roof D.
01/08/26 – The railing installation on both roof has been completed and installed safety railing at roof hatch needs to be replaced. KBR and LJB will begin the installation of the new fall arrest system at the beginning of march and all remaining work and miscellaneous items will be completed at that time. THP will schedule a meeting before starting the work on March to go over all items with KBR and LJB.
02/23/26: KBR has installed the new railing around the roof hatch and planning to start the work on March 2nd with LJB for installation new fall arrest system. The Crane will be on site on 03/2/26 and contractors are estimating the work will be completed by end of the March.
03/18/26: THP has reviewed the new design layout with LJB, KBR and HC and approved the layout for Roof E, and then the partial section of roof D on 3/20. The rest will be reviewed by THP on the first week of April.
04/30/26: Project summary – LJB and KBR have installed 95% of the fall arrest system. At roof D an assembly needed to be adjusted and fall arrest for the ladder system has a back ordered component. Contractor anticipates finishing end of May.
09/24/26 – Work reported to be complete. THP and KBR coordinating final punch review by Fibertite and Terracon.
10/07/26 – THP completed formal punch trip with KBR. Missing gates noted.
10/29/26 – KBR ordered gates.

2020 – Roof Replacement (F034) and Davit Upgrade (F027) Read More »

JFS – General Services

PM: Bert Watts, John Millar
06/10/21 – County requested a general structural service proposal.
06/11/21 – THP sent SOSS.
07/12/21 – County approved SOSS for TEI, THP, and CHA.
10/28/21 – TTC provided an update on low flow plumbing issues at the A&D building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called an underground detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
04/28/22 – Loading dock upgrades and striping and loading sign.

JFS – General Services Read More »

JC – Loading Dock Upgrade

PM: John Nester, John Millar,
07/29/21 – Creating SOSS.
08/03/21 – SOSS submitted to Hamilton County for review.
08/09/21 – Hamilton County accepted SOSS.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering) to review project and begin putting bidding documents together.
9/16/21 – THP sends project manual and drawings to Hamilton County for review. THP revises bidding documents based on County review and sends bidding documents to Triton, KFI, and Schrudde-Zimmerman.
9/22/21 – KFI notifies THP they will not be bidding on the project. THP sends bidding documents to Diversified Facility Solutions and Leo Brielmaier.
9/27/21 – THP holds pre-bid meeting at HC Justice Center. Triton and Leo Brielmaier are the only contractors to attend.
10/5/21 – THP issues addendum No. 1
10/11/21 – Bid due date. THP receives only one bid from Triton.
10/14/21 – THP calls Triton to discuss/review bid.
10/15/21 – THP sends Hamilton County bid review/award recommendation letter for Triton.
11/15/21 – Signed contract and PO issued. Triton to have contractors receive background checks as needed and start submittal process. Pre-construction meeting and NTP to follow in near future.
2/23/22 – Waiting for lead time on new loading dock. Will schedule Pre-Con meeting with Hamilton County and Triton when we have updated lead time/schedule.
3/16/22 – Triton informs Hamilton County and THP that the loading dock lift supplier has received the new lift.
3/14/22 and 3/30/22 – Hamilton County and THP has reached out to Thermal Tech for review of the submittal and to see if an electrical permit is necessary for this project. No response from Thermal Tech.
3/30/22 – Need to confirm with John Nester, Hamilton County the time frame for the project and schedule a pre-construction meeting.
4/20/22 – Triton submitted site specific safety plan.
4/27/22 – Thermal Tech reviewing electrical permit needs of the lift.
6/30/22 – Thermal Tech reviewed the electrical connection and no permit is needed. Contractor working on background checks.
5/26/22 – Thermal Tech reviewed submittal and confirmed a new electrical permit is not required.
06/10/22 – Finalizing and confirming background checks have been performed for necessary crew members for Triton and Sub-Contractors.
07/26/22 – Pre-Construction Meeting has been scheduled for August 2.
08/02/22 – Pre-Construction Meeting at Justice Center with Hamilton County, Sheriffs Department, Thermal Tech, and Triton.
08/10/22 – Field site visit with Triton and sub-contractors.
08/25/22 – Work is scheduled to be performed overnight. Expected to be completed in 1-night.
08/25/22 – New loading dock lift was installed on 08/25/22.
08/26/22 – THP and John Nester visited the site. THP sent field report to Triton for punch list items.
08/30/22 – Issue with loading dock motor. Motor has seized up/burned up. Triton to coordinate with Equipment Depot to get new motor and fix the issue.
09/15/22 – Repairs to the loading dock lift are completed and it is up and running.
09/19/22 – Sheriffs Department informed THP and John Nester that a sizable gap exists between the loading dock edge and the platform edge. THP notified Triton and Triton is working on getting Equipment Depot back on site to review the issue and complete the punch list items.
09/30/22 – The sizable gap between the loading dock edge and the platform edge has been corrected and the other punch list items have been completed.
10/13/22 – Triton, Hamilton County, and THP met onsite to review the loading dock lift and completion of punch list items. Equipment Depot to complete paint touch ups on a final follow up visit.
10/21/22 – Triton working on finalized pay app and all required documents for project closeout.
12/07/22 – Required close out paperwork and final pay app submitted to Hamilton County.

JC – Loading Dock Upgrade Read More »

Animal Shelter – Roof Replacement

05/21/21 – Hamilton County requested SOSS for the roof replacement of two roofs with alternates.
06/03/21 – THP provided SOSS for roof replacement project.
06/15/21 – County approved SOSS.
08/02/21 – THP visited site to survey and document existing conditions.
08/16/21 – THP issued Opinion of Probable Costs to Hamilton County for project budget approval.
08/20/21 – THP issued progress drawings and project manual for Owner Review.
08/25/21 – THP visited site to review condition of exposed decking in office and verify conditions at Entry canopy.
09/01/21 – THP received and reviewed AIA contract documents for project manual.
09/02/21 – THP met Hamilton County at site to review drawings and confirm scope of work items and Alternates.
09/03/21 – THP finalized and issued documents for bid.
09/09/21 – THP received and replied to substitution request email from roofing supplier and updated specifications.
09/14/21 – THP led pre-bid meeting at Animal Shelter.
09/15/21 – THP developed pre-bid meeting notes and issued Addendum 01.
10/05/21 – Bid opening. Received bids from Ace Exteriors, Wm. Kramer & Son, and Imbus Roofing.
10/06/21 – THP had conversations with Ace Exteriors to qualify bid, discuss pricing for canopy replacement, and request references and manufacturer’s certifications.
10/08/21 – THP finalized letter to Hamilton County summarizing bid process and recommending award to Ace Exteriors, including Base Bid and Alternate 1 scopes of work.
10/08/21 – THP responded to email from Hamilton County summarizing reasons bids received for canopy exceeded original estimates.
10/18/21 – THP received and began review of roofing products received from contractor as substitutions due to material availability.
10/20/21 – THP had conversation with Contractor and emailed Hamilton County about status of registering Ace Exteriors as a vendor.
10/21/21 – THP received from Contractor and forwarded to Hamilton County completed Substitutions form missing from bid proposal.
10/28/21 – THP issued revised title sheet with wind load information for Office/Admin. and Cat House roofs and requested Contractor review with manufacturer the potential implications on warranty and adhesive requirements.
11/05/21 – THP had conversation with Hamilton County to discuss material substitutions proposed by Ace Exterior due to material availability and schedule issues.
11/05/21 – THP had conversations with Wm. Kramer & Son about material availability and confirmed they would not be able to provide the specified roof insulation and cover board by spring 2022.
11/05/21 – THP emailed Hamilton County recommendations to proceed with the project using the substitute materials proposed by Ace Exteriors.
11/10/21 – Hamilton County emailed contract to Ace Exteriors.
11/23/21 – Ace Exteriors emailed Hamilton County the signed contract, worker compensation certificate, and a project-specific certificate of liability insurance.
12/23/21 – Hamilton County emailed the signed contract and PO to Ace Exteriors and requested development of required preconstruction documents.
01/28/22 – THP emailed Contractor about status of materials order, development of required pre-construction documents, completion date, and additional details to be developed.
02/01/22 – THP emailed Contractor draft of revised roof plan and details showing contract scope and new details at interface between project scope and canopies to remain.
02/04/22 – THP finalized and issued revised documents for Permit and Construction.
02/10/22 – THP reviewed and returned product submittals for roofing materials.
03/08/22 – THP received and reviewed Contractor’s pricing and lead time information for aluminum v. galvanized edge metals.
03/10/22 – THP had conversation with County about approval of proposed metal substitution due to increased costs and lead time issues, and re-reviewed submittals for roof specialties.
04/05/22 – Preconstruction meeting.
04/12/22 – THP issued minutes from preconstruction meeting.
04/12/22 – THP reviewed submittals and requested revised insulation layout.
04/13/22 – THP had conversation with Contractor about discrepancy in slope of tapered insulation between documents and submitted revised insulation layout, and retuned submittal with exceptions noted.
04/13/22 – THP had conversation with Contractor about installation issues and additional cost of taller fascia that would be required with 1/4″ slope tapered insulation v. 1/8″ slope indicated in documents. Contractor to request updated/revised tapered layout to reflect the 1/8″ slope.
04/19/22 – THP received, reviewed, and returned re-revised insulation layout submittal.
04/22/22 – THP had conversations with Contractor and Hamilton County to discuss delayed start date due to weather and insulation slope issue, and emailed team about rescheduling first progress meeting.
05/02/22 – THP met project team at site for progress meeting and site visit to document progress.
05/02/22 – THP emailed Contractor a link to a shared folder containing original construction drawings.
05/02/22 – THP developed and issued minutes from progress meeting #1.
05/03/22 – THP issued field report 01 from 5/2 site visit.
05/03/22 – THP reviewed pencil copy of Contractor’s first application for payment and replied with comments.
05/03/22 – THP reviewed and approved notarized copy of Contractor’s first application for payment and forwarded to Hamilton County.
05/12/22 – THP met Contractor on site to review and document progress.
05/15/22 – THP issued field report 02 from 5/12 site visit.
05/16/22 – THP met project team at site for progress meeting and site visit to document progress.
05/20/22 – THP developed and issued minutes from progress meeting #2.
05/20/22 – THP issued field report 03 from 5/16 site visit.
05/24/22 – THP visited site to review and documented completed installation of EPDM.
05/26/22 – THP issued field report 04 from 5/24 site visit.
06/01/22 – THP reviewed Ace fascia and coping profiles submittals.
06/29/22 – Progress meeting and site visit scheduled to review installed drains and progress of edge metal installation.
07/22/022 – THP visited site to do final inspection of completed work and identify punchlist items.
07/25/22 – THP published field report and punch list for roof work from 7/22/22 visit.
08/09/22 – THP emailed Contactor about status of completing punchlist items.
08/09/22 – THP developed Change Order #1 for unused Cash Allowance and Unit Price credit and forwarded to Contractor for signature.
09/21/22 – Contractor emailed team about status of completing punchlist.
09/26/22 – THP emailed Contractor about acceptance of remaining two punchlist items, status of second application for payment, closeout documents, and approval of Change Order #1.
10/28/22 – THP visited site to confirm completion of punchlist items, and emailed Contractor about the status of closeout documents, approval of Change Order #1, and the application for payment #2 for substantial completion.
11/09/22 – THP replied to email from Contractor rejecting request for additional use of Cash Allowance.
11/18/22 – Contractor provided preliminary closeout documents for THP’s review.
11/21/22 – Change Order #1, a credit for unused Unit Price Repairs and Cash Allowance, was signed by Contractor and Hamilton County.
12/01/22 – THP reviewed Contractor’s preliminary closeout documents and replied with revisions to be made and additional documents to be provided.
12/07/22 – Contractor provided revised closeout documents for THP’s review.
12/12/22 – THP reviewed revised closeout documents and emailed Contractor to proceed with providing hard copies, including notarized legal documents and the project binder.
01/03/23 – THP reviewed Contractor’s hard copies of closeout documents and project binder and requested revised as-built drawings using permit set as basis for markups.
01/04/23 – THP received revised as-built drawings, emailed Hamilton County a link to a shared folder containing digital copies of all closeout documents, approved Contractor’s second and final application for payment, and delivered project binder.
02/23/23 – OK to Archive.

Animal Shelter – Roof Replacement Read More »

CH – Boiler Rm Carrier Fan Platforms (F029)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
03/25/21 – SOSS will be combined with the 230 work.
04/01/21 – SOSS approved.
04/19/21 – THP completed field work.
04/27/21 – THP sent SD drawings with draft platform options.
04/29/21 – THP and County to schedule review meeting.
05/11/21 – THP and County met to review SD plan.
05/21/21 – THP DD review drawings and OPC published.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/12/22 – THP submitted permit response letter and supplemental documentation to the City for Building Permit Application. Waiting for response from City.
1/25/22 – Building permit application for the Hamilton County Courthouse has been approved. Hamilton County suggests another pre-construction meeting with Hamilton County, THP, and Triton to go over schedule/details before starting work on the boiler room platform. Schedule pre-construction meeting as soon as possible.
2/10/22 – THP, Hamilton County, and Triton had another Pre-Con meeting at Courthouse to go over schedule.
2/16/22 – Triton mobilized to Courthouse to begin site layout and scanning existing boiler room floor.
2/21/22 – Triton to begin sawcutting existing floor for new footers.
3/15/22 – Existing slab sawcut for (4) new column foundations. Other two column foundations will be anchored to existing concrete.
3/18/22 – Terracon onsite to inspect existing soil conditions. To achieve the necessary bearing capacity for the new footings, Terracon recommended to excavate another 6”-8” of material, add a little water, and then tamp the soil for compaction.
3/19/22 – Platform steel delivered to Courthouse Boiler Room.
3/30/22 – Triton starts to pour concrete for (4) new column foundations. Terracon was onsite for special inspections (soil, rebar, concrete). Other two columns will be anchored to existing concrete. Platform installation, steel erection to follow.
4/26/22 – Courthouse platform installation is complete. Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections.
5/25/22 – Courthouse platform installation is complete. THP and Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.
12/07/22 – Required close out paperwork and final pay app submitted to Hamilton County.
01/19/22 – THP requested CAD files from Hamilton County to update Master Files.

CH – Boiler Rm Carrier Fan Platforms (F029) Read More »

CH – Boiler Room Exhaust Fan Platforms (F024)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
04/01/21 – SOSS approved.
04/19/21 – THP completed field work.
04/27/21 – THP sent SD drawings with draft platform options.
04/29/21 – THP and County to schedule review meeting.
05/11/21 – THP and County met to review SD plan.
05/21/21 – THP DD review drawings and OPC published.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/12/22 – THP submitted permit response letter and supplemental documentation to the City for Building Permit Application. Waiting for response from City.
1/25/22 – Building permit application for the Hamilton County Courthouse has been approved. Hamilton County suggests another pre-construction meeting with Hamilton County, THP, and Triton to go over schedule/details before starting work on the boiler room platform. Schedule pre-construction meeting as soon as possible.
2/10/22 – THP, Hamilton County, and Triton had another Pre-Con meeting at Courthouse to go over schedule.
2/16/22 – Triton mobilized to Courthouse to begin site layout and scanning existing boiler room floor.
2/21/22 – Triton to begin sawcutting existing floor for new footers.
3/15/22 – Existing slab sawcut for (4) new column foundations. Other two column foundations will be anchored to existing concrete.
3/18/22 – Terracon onsite to inspect existing soil conditions. To achieve the necessary bearing capacity for the new footings, Terracon recommended to excavate another 6”-8” of material, add a little water, and then tamp the soil for compaction.
3/19/22 – Platform steel delivered to Courthouse Boiler Room.
3/30/22 – Triton starts to pour concrete for (4) new column foundations. Terracon was onsite for special inspections (soil, rebar, concrete). Other two columns will be anchored to existing concrete. Platform installation, steel erection to follow.
4/26/22 – Courthouse platform installation is complete. Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections.
5/25/22 – Courthouse platform installation is complete. THP and Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

CH – Boiler Room Exhaust Fan Platforms (F024) Read More »

230 – Cooling Tower Safety Maintenance Stairway (F025)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS. OK to combine bids as long as the bids can be separated or itemized.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
05/27/21 – Project update County located existing drawings which included a previous THP design. THP plans to issue review drawings by June 2.
06/25/21 – THP to send review set next week to County.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse Boiler Room Platform project. Schedule and start date TBD. Most likely March/April time frame.
2/21/22 – Triton to mobilize to site to field measure site conditions.
2/23/22 – Waiting to hear back from City on the Permit Application.
3/2/22 – Permit application has been approved. Approved drawings and approved project manual has been sent to all parties involved.
4/25/22 – Triton submitted crane lifting plan. Hamilton County asked for additional information be provided for County review. Plan is still to crane material to roof on Saturday, May 7th. Roof stairs installation to begin following week.
5/10/22 – Stair posts installed by Neiheisel and roofing repairs performed by Tremco this week before crane lifting the rest of the material onto the roof.
5/14/22 – Remaining stair material crane lifted onto roof and installed onto posts.
5/16/22 – Neiheisel performed final stair installation and detailing. WHT roof stairs installation completed this week.
5/25/22 – THP and Triton to coordinate final cleanup and paint touch up before the final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

230 – Cooling Tower Safety Maintenance Stairway (F025) Read More »

THP General Structural Service (F021)

PM: Bert Watts, John Millar
11/17/20 – THP submitted SOSS.
11/17/20 – County approved SOSS.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.
05/10/21 – THP published draft flag pole footing sketch to Champlin for review.
05/21/21 – THP published final flag pole footing sketch.
05/27/21 – THP review proposed RTU replacement at 800 Broadway. Planned replacement next week.

THP General Structural Service (F021) Read More »

800 – Critical Façade Survey

09/24/20 THP submitted SOSS for inspection of building facade.
11/30/20 -THP received SOSS and PO for work.
12/10/20 – THP survey and assessment to occur spring 2021, purpose is to assess the façade after the winter freeze / thaw cycles.
01/28/21 – Delayed to Spring.
04/29/21 – THP staff passed background check. Rappelling and aerial platform work scheduled for week of 5/3/21. Thunderstorms and rain, may shift field work to later in May.
05/04/21 – THP and AFR completed aerial platform survey of the base. Loose mortar and limestone debris was removed.
05/13/21 – THP rappelled the tower.
05/14/21 – THP rappelled the tower.
05/27/21 – THP working on the report.

800 – Critical Façade Survey Read More »

A&D – Moisture Investigation

10/27/20 – THP sent SOSS for moisture investigation.
12/10/20 – THP and TEI to follow up on water line testing.
01/28/21 – THP completed multiple water tests and has determined water sources. THP developing excavation proposal. Draft report partially completed.
02/23/21 – SOSS requested by Hamilton County.
03/23/21 – THP provided SOSS. Three posts migrated to this project.
04/22/21 – Excavation completed along the north elevation, along with subbasement excavation.
04/29/21 – THP finalizing draft report. Anticipated publish date 5/7/21.
05/27/21 – THP updating the report with the excavation information.
10/27/21 – Budget issued in September then final report with updated interior repair added issued on 10/27/21

A&D – Moisture Investigation Read More »

2020 Roof Access Assessment (F018)

06/16/20 – Requested a SOSS for an Assessment of Facilities roof access (tie off and OSHA safety).
06/18/20 – County publish list of buildings to be included in the assessment.
06/25/20 – THP contacted LJB to provide anchor consulting support. THP plans to visit and catalog the roofs conditions next week for the SOSS.
07/14/20 – THP, LJB, and County surveyed downtown building roof to understand general conditions and needs of the County
07/28/20 – THP & LJB had a final scope meeting.
07/30/20 – LJB plans to provide a proposal to THP on 7/31. THP plans to submit final proposal early August.
08/11/20 – THP submitted SOSS to the County.
08/26/20 – Project placed on hold.
11/30/20 – THP received SOSS and PO for project.
01/13/21 – THP and LJB under contract for project.
01/15/21 – THP, LJB, and Hamilton County had kick off meeting.
01/28/21 – THP and LJB staff applied for background checks and waiting on approval.
02/25/21 – THP and LJB staff background checks approved. THP started field work on 02/24/21 – THP and LJB field work will continue until March 5th tentatively.
03/25/21 – THP and LJB completed initial site visits.
03/31/21 – LJB sent draft roof assessment report to County for review.
04/05/21 – County, THP and LJB met to review draft report.
04/29/21 – THP and LJB finalizing report based on comments from the meeting.
05/24/21 – LJB uploaded Draft report. THP reviewing cost and presentation.
07/16/21 – THP sent review drawing of report to LJB.
07/22/21 – THP and LJB reviewed comments. Overall minor updates to drawings.
08/26/21 – LJB working on final report.
09/16/21 – THP and LJB presented final documents to the County.

2020 Roof Access Assessment (F018) Read More »

CH – Skywalk Bridge Assessment (F013)

02/20/20 – Hamilton County requested SOSS to address City Bridge Report.
03/16/20 – THP and Hamilton County met to discuss scope of work.
04/21/20 – THP published SOSS with contractor support to assess the two bridges and attach loose metal panel.
06/25/20 – Project is approved. BC will get paperwork over to THP this week.
07/06/20 – THP proposed an inspection plan for mid-July. Bridges were noted to be still wrapped in signage that is planned to be removed this summer. Inspection placed on hold until sign is removed. Inspection tentatively planned for fall of 2020.
10/23/20 – Wrap removed and THP cleared to complete the work.
10/28/20 – THP scheduled to complete work November 3.
11/06/20 – Skywalk bridge ground survey completed.
11/07/20 – Skywalk aerial platform survey completed.
12/10/20 – THP draft report in progress, anticipated completion Friday December 18th.
01/13/20 – THP received previous roof replacement information from Tremco.
01/28/21 – THP updating report and plans to send by 1/29/21.

CH – Skywalk Bridge Assessment (F013) Read More »

DDS – Franks Center Roof Restoration

01/07/20 – Hamilton County requested SOSS for roof restoration project.
01/13/20 – Meeting setup up, but cancel by County.
02/11/20 – THP and County walked the site for a SOSS.
02/18/20 – THP issued SOSS to County for review.
04/15/20 – County review documents issued.
04/21/20 – THP received summary WTI moisture analysis reports.
04/24/20 – Bid documents issued.
04/29/20 – Alternate No. 1 issued.
05/13/20 – Alternate No. 2 issued.
05/20/20 – Bids received and Imbus Roofing is the apparent low bidder.
05/28/20 – THP issued a bid summary letter and draft contract to the County.
06/15/20 – Contract have been processed.
07/07/20 – County issued PO.
07/30/20 – Roof work anticipated to start mid-August.
09/21/20 – Gravel removal started.
10/2/20 – Gravel removal completed. THP and Imbus located 400 S.F. of unit cost repair items.
10/7/20 – Unit cost roof repair items being complete.
10/15/20 – Located (2) poor areas of roof installation at RTUs. Imbus to provided a follow up repair of the installation.
10/29/20 – Project update: 40% of surfacing installed and 90% of unit cost repair completed.
11/17/20 – Bulletin No.1 issued for pricing.
11/25/20 – Imbus submitted pricing for bulletin No. 1.
12/01/20 – Bulletin No. 1 pricing approved via email. Change order being processed.
12/04/20 – Change Order No. 1 issued for processing.
12/10/20 – THP received Change Order No. 1 from Imbus. THP forwarded to the County for final execution.
12/10/20 – Project update: 95% of project base bid work complete.
01/12/21 – Project punch list completed. A few small items noted.
01/18/21 – Imbus submitted January pay application (minus retention). THP processed it and sent to Hamilton County.
01/18/21 – Imbus submitted draft project manual.
01/22/21 – Imbus reported all punch list work completed. THP and Tremco to verify final installation.
03/04/21 – Final closeout documents sent to the County. All closeout documentation approved. THP to deliver hard copies to DDS and Facilities.

DDS – Franks Center Roof Restoration Read More »

2020 – City Façade Assessment

08/22/19 – THP provided SOSS.
08/28/19 – County approved SOSS.
09/26/19 – THP schedule to complete work in October.
10/18/19 – THP visited site to perform visual inspection of façade from grade and from roofs.
10/25/19 – THP visited site to rappel façade and perform close-up inspection.
10/30/19 – THP finalized draft of façade review report for Owner’s review.
12/12/19 – THP met AFR at site to confirm façade repair locations.
12/13/19 – THP met AFR at site to confirm completion of façade repairs and document locations.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs.
02/27/19 – Refer to F117 for status.

2020 – City Façade Assessment Read More »

A&D – Movable Wall (F005)

07/01/19 – Hamilton County requested to review and design a movable wall.
07/12/19 – THP provided an SOSS.
07/23/19 – County approved SOSS.
08/29/19 – THP completed initial design. THP to meet with County to review approach and design needs.
02/27/20 – Wall manufacturer went out of business, so project on hold.
06/25/20 – Facilities will touch base with JFS on the viability of this project.

A&D – Movable Wall (F005) Read More »

A&D – Façade Coating Survey

06/10/19 – Hamilton County requested SOSS to survey masonry coated area and remove loose debris.
06/12/19 – THP met with American Façade Restoration to discuss contractor scope and to get a proposal.
06/19/19 – THP submitted an SOSS for design services and AFR proposal to complete the work.
08/29/19 – Work scheduled to start after F117 complete.
10/31/19 – See F117 for project status.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.
02/27/30 – Refer to F117 for project status.

A&D – Façade Coating Survey Read More »

Records Center – Façade and Roof Repairs

05/16/19 – County requested SOSS for façade and roof repair package.
06/19/19 – THP submitted an SOS for design services.
06/27/19 – Verbally approved. Need to final bids and contract by November.
07/03/19 – SOSS Approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
08/29/19 – DD docs to be issued September 13th.
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/19/19.
11/06/19 – Addendum no.1 issued
11/04/19 – Addendume no. 2 issued.
11/21/19 – Three bids were received. Imbus was the apparent low bidder.
11/21/19 – THP discussed the bid with Imbus and issued a bid summary letter recommending Imbus complete the work alternates no1 and no3 for $353,130.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
03/03/20 – THP issued conform set.
03/04/20 – Preconstruction Meeting occurred. Construction to occur once weather allows.
04/16/20 – Imbus mobilized job site.
04/19/20 – Roofing submittals processed.
04/20/20 – Imbus began roof repairs.
05/04/20 – Pay application No.1 processed.
05/12/20 – Lintel submittal processed.
05/27/20 – Pay application No. 2 processed.
06/15/20 – THP issued updated canopy anchor requirements.
06/17/20 – Imbus subcontractor finished installing the canopy.
06/25/20 – Roof work completed. Team plans to meet and punch the roof 6/26/20.
06/26/20 – Punch list review meeting completed. Two minor items noted.
07/08/20 – Warranties submitted.
07/24/20 – Final pay application submitted.
07/27/20 – Changer order No. 1 approved.
07/30/20 – Punch list work complete. THP processing closeout paper work.
12/09/20 – Final project manual submitted.
12/10/20 – THP plans to drop off project manual and final pay request 12/11/20.
01/28/20 – THP dropped of project manual and final pay application mid December.
02/25/21 – Project can be closed.

Records Center – Façade and Roof Repairs Read More »

Burlington – Building Roof Replacement (F002)

04/10/19 – Engineering office requested a roof replacement project.
04/16/19 – THP visited the site to develop a SOSS.
06/24/19 – THP submitted an SOSS for design services.
07/11/19 – SOSS approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
09/26/19 – Meeting with Burlington Engineer 9/27/19
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/13/19.
11/13/19 – Three bids were received on 11/13/19. Wm. Kramer and Sons was the apparent low bidder.
11/22/19 – THP discussed the bid with Kramer and issued a bid summary letter recommending Kramer complete the work alternates no1 and no2 for $73,764.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/26/20 – County issued executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting early March once formal PO is issued. Work requested to start mid-April. Kramer confirmed start date is good.
03/03/12 – Conform documents issued.
03/12/20 – Preconstruction Meeting completed.
03/19/20 – Submittals processed.
03/31/20 – Kramer mobilized.
04/29/20 – Pencil copy of Pay Application No.1 returned for corrections.
05/04/20 – Kramer last day on site.
06/16/20 – Roof installation condition meeting completed.
06/25/20 – Roof needs final top coat installation and punch list completed.
07/20/20 – Punch list review meeting completed.
07/30/20 – Punch list work complete. THP processing closeout paperwork.
11/13/20 – Final project closeout manual submitted and sent County Engineer
11/18/20 – Final pay application approved and processed.

Burlington – Building Roof Replacement (F002) Read More »

230 – 2019 Façade Critical Façade Repairs

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/29/19 – Work scheduled to start after F117 complete.
09/16/19 – Work scheduled to start after F117 complete.
10/31/19- See F117 for project status.
01/30/20 – See F117 for project status. Construction work complete. Final closeout paper work in progress.
02/27/20 – Refer to F117 for project status.

230 – 2019 Façade Critical Façade Repairs Read More »

CAB – 2019 Critical Façade Repairs (F118)

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/29/19 – Work scheduled to start after F117 complete.
09/16/19 – Work scheduled to start after F117 complete.
10/31/19- See F117 for project status.
01/07/20 – THP finalized and emailed letters to city about completion of façade repairs.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.
02/27/20 – Refer to F117 for project status.
09/22/20 – THP emailed City of Cincinnati to ask about status of closing out façade inspection case for 2020 Auburn and 230 E. 9th St.
09/30/20 – THP visited site to document completed TPC letter installation, and issued field report 26.
10/06/20 – THP sent follow-up email and had conversation with contact at City of Cincinnati about open inspection cases at 2020 Auburn and 230 E. 9th.
10/22/20 – THP received, reviewed, and approved AFR’s 10th application for payment reflecting completion of all work. AFR to submit remaining closeout documents before submitting final application for payment for retainage.
11/06/2020 – THP reviewed AFR’s closeout binders, identified and requested missing information.
11/10/2020 – THP finalized closeout binders, reviewed and approved final application for payment, and delivered to Hamilton County.

CAB – 2019 Critical Façade Repairs (F118) Read More »

800 – 2019 Façade Stabilization (F117)

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/01/19 – THP met with Owner and Contractor for preconstruction meeting and issued meeting notes.
08/12/19 – THP reviewed and returned submittals received 8/7/19 from Contractor.
08/14/19 – THP reviewed and returned revised submittals from Contractor.
08/19/19 – THP met with Owner and Contractor for first progress meeting and issued meeting notes.
08/20/19 – THP met with Darnell at 800 Broadway to review additional façade issues to be reviewed for repair.
08/22/19 – THP met Contractor at 800 Broadway to review and document completed stone patch preparation progress and stone patch mockups.
08/23/19 – THP issued field report 1.
08/23/19 – THP had telephone conversations with Owner and Contractor to discuss status of mortar joint tuckpointing quantities relative to unit cost allowance amounts.
08/26/19 – THP met with Owner and Contractor for weekly progress meeting and issued meeting notes.
08/26/19 – THP reviewed pencil copy of Contractor’s first application for payment.
08/28/19 – THP visited 800 Broadway to meet Contractor, review progress, and do close-up inspection of south elevation in the area of the façade near the office where leaks have been an ongoing issue.
08/29/19 – THP directed Contractor to install two additional stone patch samples at 800 Broadway west elevation.
08/29/19 – THP reviewed and approved Contractor’s first application for payment.
08/30/19 – THP delivered application for Payment to HC.
08/30/19 – THP visited 800 Broadway to observe and document additional stone patch samples.
09/03/19 – THP issued field reports 2 & 3 from 8/28 & 8/30 site visits.
09/06/19 – THP visited 800 Broadway to meet Contractor and review progress.
09/09/19 – THP developed Change Order 1.
09/09/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/09/19 – THP met Contactor and American Scaffolding at 800 Broadway to review access for pricing repairs at southwest corner of tower.
09/09/19 – Change Order #1 for survey of A&D façade was approved and signed by Owner and Contractor.
09/09/19 – THP issued field report 4 from 9/6 site visit.
09/10/19 – THP issued notes from 9/9 progress meeting.
09/16/19 – THP developed Change Orders 2 & 3.
09/16/19 – THP met Owner and Contractor at CAB for progress meeting.
09/16/19 – Change Orders #2 for Justice Center façade repairs and #3 for 800 Broadway tower spall repair were approved and signed by Owner and Contractor.
09/17/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and identify additional repair areas.
09/18/19 – THP issued notes from 9/16 progress meeting.
09/20/19 – THP reviewed pencil copy of Contractor’s second application for payment and had conversation with Owner about use of unit cost allowances to cover additional façade repairs requested by HC at CAB.
09/20/19 – THP issued field report 5 from 9/16 site visit.
09/23/19 – THP met Owner and Contractor at CAB for progress meeting and issued meeting notes.
09/23/19 – THP reviewed and approved Contractor’s second application for payment.
09/23/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and document conditions at terra cotta excavation.
09/24/19 – THP issued field report 6 from 9/23 site visit.
09/28/19 – THP visited site at 800 Broadway to document progress of limestone removal at west elevation.
09/30/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/30/19 – THP visited site at 800 Broadway to document conditions of masonry backup wall at west elevation.
10/01/19 – THP issued notes from 9/30 progress meeting.
10/02/19 – THP met Contractor at THP to review conditions of backup wall at 800 Broadway and discuss details for installation of wall ties.
10/02/19 – THP had telephone conversation with Owner to discuss recommendation to demolish and rebuild a portion of the backup wall at the west elevation at 800 Broadway.
10/02/19 – THP issued field report 7 from 9/30 site visit.
10/02/19 – THP developed letter outlining effect of additional work at backup wall on overall schedule at 800 Broadway.
10/07/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/07/19 – THP issued notes from progress meeting.
10/07/19 – THP developed Cash Allowance Usage 1 and emailed to Owner and Contractor for review and approval.
10/07/19 – THP visited site at 800 Broadway to review and document progress of backup wall modifications at 800 Broadway.
10/08/19 – THP issued field report 8 from 10/7 site visit.
10/14/19 – THP met Owner and Contractor at WH Taft Center for progress meeting.
10/15/19 – THP issued notes from 10/14 progress meeting.
10/16/19 – THP met Contractor at WH Taft Center to review and document progress, then visited 800 Broadway and CAB to document completed work.
10/19/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/20/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/21/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/21/19 – THP issued field report 9 from 10/16 site visit.
10/21/19 – THP issued notes from progress meeting.
10/25/19 – THP reviewed and approved Contractor’s third application for payment.
10/25/19 – THP issued field report 10 from 10/19 & 10/20 site visits.
10/28/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/29/19 – THP met Contractor at CAB to document progress of GFRC installation, then visited 800 Broadway and WH Taft Center to document completed work.
10/29/19 – THP issued noted from 10/28 progress meeting.
12/31/19 – THP reviewed and approved AFR’s fifth application for payment.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/07/20 – THP delivered AFR’s fifth application for payment to BW.
01/07/20 – THP finalized and emailed letters to city about completion of façade repairs at CAB, 800 Broadway, and WHT Center.
01/13/20 – THP reviewed AFR closeout documents and discussed requirements with BW and AFR.
01/21/20 – THP developed and issued change order #5 for trench drain repairs at 250 WHT.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs at Justice Center and 2020 Auburn Ave.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/24/20 – THP received and reviewed AFR’s revised closeout documents and forwarded to BW for approval.
01/28/20 – THP reviewed and approved AFR’s sixth application for payment.
01/30/20 – THP delivered AFR’s sixth application for payment to BW.
02/04/20 – THP received Champlain Architecture drawing for CAB signage change and forwarded to AFR for change order proposal.
02/10/20 – THP received and reviewed change order proposal from AFR for CAB signage change, and forwarded to BW for review and approval.
02/12/20 – THP developed AIA G701 Change Order #6 for 250 WHT plumbing repairs and emailed to AFR for review and signature.
02/18/20 – Change Order #6 signed by AFR and BW.
02/20/20 – THP visited site at 250 WHT to observe and document progress of trench drain replacement at Bellevue Ave. entrance.
02/21/20 – THP developed AIA G701 Change Order #7 for CAB signage change and emailed to AFR for review and signature.
02/24/20 – Change Order #6 signed by AFR.
04/06/20 – THP visited 250 WHT to observe and document prep of south trench drain prior to concrete pour.
04/09/20 – THP issued Field Report #24 documenting 250 WHT trench drain repairs.
04/22/20 – THP visited Todd A. Portune Center, Alms & Doepke, and 250 WHT to document repairs.
04/24/20 – THP issued Field Report #25 documenting completion of repairs at Alms & Doepke and 250 WHT, and completion of coating at removed CAB letters.
04/28/20 – THP reviewed pencil copy of AFR’s 9th application for payment, and replied with markups about revisions for line items related to change order #8.
04/28/20 – THP had conversation with BW about signage company’s request for payment on new signage letters.
04/29/20 – THP requested and received photographs of letters in storage at signage subcontractor’s warehouse.
04/30/20 – THP signed AFR’s 9th application for payment and forwarded to BW.
06/25/20 – 2020 Auburn, and 230 E 9th/WH Taft Center are still waiting for final approval of completed façade repairs by city.
06/25/20 – Justice Center is closed as of 3/27/20. A&D sill repairs and 250 WHT trench drains are complete. CAB signage removed and repairs are complete, but the installation of the new Todd B. Portune Center for County Government letters has been put on hold.
07/30/20 – Portune letters still on hold.

800 – 2019 Façade Stabilization (F117) Read More »

THP – General Structural Services

PM: Bert Watts, John Millar
11/06/18 – Hamilton County requested SOSS.
11/15/18 – THP provided SOSS.
11/19/18 – Hamilton County executed the SOSS.
03/28/19 – THP completed internal review of Master Agreement. THP will forward to County by 3/29/19.
— New Contract —
04/08/19 – Hamilton County requested SOSS.
04/10/19 – THP provided an SOSS for review.
04/22/19 – THP provide updated SOSS with new F series number.
04/24/19 – THP SOSS approved.
05/10/19 – A small piece of Terra Cotta fell from the Alms and Doepke Building. THP coordinated contractor support to remove the remaining loose pieces of terra cotta. THP to follow up with a summary report.
06/07/19 – THP issued a draft Terra Cotta report for review.
06/10/19 – THP issued final A&D Terra Cotta report.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/20/19 – 250 WHT Trench Drain work order for cleanout and review planned. THP to review concrete conditions.
12/4/19 – 250 WHT Trench Drain – THP reviewed initial conditions and is reviewing with the City options.
12/10/19 – 250 WHT Trench Drain – Trench drain partially collapsed and is closed. THP and American Façade Restoration reviewed the conditions. AFR placed plates over the main drive lane.
12/11/19 – 250 WHT Trench Drain – THP issued a repair for pricing. AFR hopes to provide a price on 12/13/19.
02/13/20 – County requested THP review corroding steel at the Burlington Garage facility.
02/20/20 – County requested an SOSS for Courthouse bridge issues noted in City bridge inspection report.
02/26/20 – THP completed an initial visit to Courthouse bridge.
02/21/20 – THP and County reviewed field conditions at Burlington Garage. THP to generate an SOSS.
02/27/30 – For 250 WHT Trench Drain work refer to F117 for project status.
06/09/20 – THP met with Champlin at Juvenile Justice Center to review flooring field conditions. No visible structural deterioration or distress, but much of the structure is covered (flooring & fire proofing). THP to review approach with Champlin.
10/29/20 – THP has sent multiple email request to City to try to close out City Facade Inspections for 2020 Auburn and 230 East Ninth.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.

THP – General Structural Services Read More »

250 WHT – Trench Drain Investigation (F115)

09/20/18 – County requested a SOSS to investigate the south trench drain and provide recommendations to repair.
03/21/19 – THP visited the site. THP to review conditions with County.
03/21/19 – THP visited the site. THP to review conditions with County.
04/05/19 – THP completed a follow up to visit the Trench drain.
04/25/19 – Follow meeting with Bert work on hold.
09/26/19 – Project ready to archive.

250 WHT – Trench Drain Investigation (F115) Read More »

Records Center – Building Envelope Assessment (F112)

05/01/18 – THP visited site to document conditions at rusted area of metal decking for purposes of developing SOSS.
05/15/18 – County requested Tremco be included with the assessment, because roof is a Tremco system.
05/31/18 – THP and Tremco have worked out an approach. THP to published SOSS for the County’s review.
06/21/18 – County approved SOSS for the project.
08/26/18 – THP sent consultant contract to Tremco for review.
09/25/18 – THP and Tremco finalized subconsultant agreement.
09/27/18 – THP to schedule field work with County.
10/25/18 – THP looking to start work week of November 5, 2018.
11/07/2018 – THP visited site to survey facades, roof, interior of metal deck, and coordinate with Tremco during test cuts.
11/15/18 – Tremco provided draft report.
11/29/18 – THP developing report.
01/17/19 – THP received final report.
01/30/19 – THP completed internal draft report. Final report expected to be submitted on 2/7/19.
02/07/19 – THP submitted final report.

Records Center – Building Envelope Assessment (F112) Read More »

CH – Critical Façade Repairs (F103)

12/28/17 – THP publish SOSS to Hamilton County as requested.
03/16/18 – Hamilton County approved SOSS.
04/26/18 – THP provided owner review documents to the County.
05/24/18 – Revised Owner review documents sent to County.
05/25/18 – County provided comments.
05/29/18 – Documents issued to purchasing for review.
05/30/18 – Purchasing provided comments to the review documents. Project issued ITB 044-18.
06/1/18 – Issued bid documents to County and ARC for publication.
06/5/18 – Documents available to bidders
06/11/18 – Prebid meeting occurred at Courthouse.
06/12/18 – Addendum No.1 and No.2 issued.
06/26/18 – Bid opening occurred with four contractors submitting proposals. Two of the four bids under published estimate. American Façade Restoration is the apparent low bidder.
06/27/18 – THP had phone conversation with AFR to review their bid.
07/02/18 – THP provided a bid summary letter and draft AIA contract for review by the County.
07/05/18 – County published updated AIA contract and documents for review by AFR.
7/25/18 – County published executed AIA contract.
08/21/18 – Background checks approved and submittals in process.
08/30/18 – Preconstruction meeting scheduled for 9/1/18.
09/1/18 – Preconstruction meeting completed.
09/26/18 – American Scaffolding erected swing stage equipment for courtyard repairs.
10/12/18 – Change Order #01 Executed. During the dentil repairs it was discovered the cornice steel supports were heavily corroded. Change order #1 provide new support detail, that is integrated into the dentil repair.
10/25/18 – AFR working on courtyard dentil repairs.
11/16/18 – Change Order #02 Executed. Work to address loose stone, concrete, masonry materials observed during city façade assessments.
11/29/18 – AFR completed Courthouse base bid repairs. Roughly 60% of knock down survey and stone stabliziation work complete. Work scheduled to be completed December 8th (weather permitting).
12/07/18 – AFR completed all knock down work for Change order #02
12/31/18 – AFR completed final window repair for Change order #02.
01/17/19 – THP submitted the certified AFR pay application to the County.
01/18/19 – AFR submitted close out documentation to THP for review.
03/21/19 – THP forwarded final close out documents to the County.
04/25/19 – Project complete

CH – Critical Façade Repairs (F103) Read More »

A&D – Critical Façade Repairs (F104)

12/28/17 – THP publish SOSS to Hamilton County as requested.
02/15/18 – Hamilton County approved SOSS.
02/20/18 – THP published review documents.
03/09/18 – THP published bid documents.
03/15/18 – Prebid meeting completed.
03/29/18 – Bids received. American Façade Restoration the apparent low bidder.
04/3/18 – THP sent a letter of recommendation after a phone interview with AFR.
04/4/18 – THP sent draft AIA County / AFR contract to the County for review.
04/26/18 – County prosecutor reviewing the contract.
06/06/18 – Hamilton County and AFR under contract.
06/28/18 – AFR reported they plan to start work mid to late July. Work should take about two weeks.
7/23/18 – Preconstruction meeting completed.
7/26/18 – Anticipated start of construction will be 8/6/18 with work expected to be completed 8/31/18.
08/30/18 – AFR actively working on North, South and West elevations. Concrete and stone patching repairs 90% complete. South Elevation pilaster repair 50% complete.
9/5/18 – AFR substantial completion reached. THP reviewed work and generated a punchlist.
9/11/18 – AFR completed punchlist work.
9/27/18 – AFR working on closeout documentation.
10/25/18 – Project complete and closeout documentation complete.

A&D – Critical Façade Repairs (F104) Read More »

800 – City Facade Assessment (F105)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
03/06/2018 – THP completed ground survey of façade.
03/29/2018 – THP to schedule rappelling survey early April.
04/26/18 – THP schedule rappel the facade.
05/21/18 – THP completed draft of Cincinnati façade ordinance report and published.
5/31/18 – County reviewing report.
6/26/18 – THP submitted drafts of the Envelope Assessment Report and City Report
07/26/18 – THP finalized and published Cincinnati façade ordinance report. Signature by Ralph Linne’s required before THP submits report to City of Cincinnati Buildings & Inspections.
08/24/18 – THP received letter from City of Cincinnati acknowledging the submitted report.

800 – City Facade Assessment (F105) Read More »

CAB – Building Envelope Assessment (F106)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
03/29/18 – Field work to start first week of April.
4/13/18 – THP completed rappelling surveys.
4/23/18 – THP completed survey work from the ground and roof.
4/26/18 – THP compiling data for report.
5/31/18 – THP finalizing draft report for review by the County.
6/26/18 – THP submitted drafts of the Envelope Assessment Report and City Report.
07/26/18 – THP finalized and published Cincinnati façade ordinance report. Signature by Ralph Linne’s required before THP submits report to City of Cincinnati Buildings & Inspections.
08/24/18 THP received letter from City of Cincinnati acknowledging the submitted report.

CAB – Building Envelope Assessment (F106) Read More »

230 – City Façade Assessment (F107)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
04/19/18 – Completed visual survey from grade.
04/20/18 – Rappelled all four elevations.
04/26/18 – Report under development.
05/21/18 – THP completed draft of Cincinnati façade ordinance report.
05/22/18 – THP developed Opinion of Probable Cost for recommended repairs specific to Cincinnati façade ordinance review.
05/24/18 – THP finalized Cincinnati façade ordinance review report and application form.
5/31/18 – County provided verbal comments. THP reviewing comments.
7/26/18 – CORRECTION, comment on 5/31/18 for 800 Broadway assessment. Report approved as submitted.

230 – City Façade Assessment (F107) Read More »

JC – Building Envelope Assessment (F109)

01/22/18 – Hamilton County requested an SOSS
01/25/18 – THP provided SOSS as requested by Hamilton County.
02/15/18 – THP approved SOSS.
04/26/18 – THP scheduled field work to begin the first week of May including rappelling. Work is weather dependent.
05/02/18 – THP completed site rappelling surveys.
05/11/18 – THP completed site ground survey.
05/31/18 – THP working on reports.
06/28/18 – THP working on reports. THP verbally noted the façade did not have any safety issues that would impact a City of Cincinnati building façade inspection report.
01/31/19 – THP working on report. County draft report anticipated February 15 and final report completed February 28.
05/29/19 – THP completed internal City Draft of report and Façade section. Roofing assessment to be complete the first week of June.
06/05/19 – THP completed roof assessment.
06/06/19 – THP completed roof assessment.
06/27/19 – THP issued City Facade Application report to County for review.
02/27/20 – THP published the report to the County.
07/30/20 – Discussed at Partner meeting. Leave open for now.

JC – Building Envelope Assessment (F109) Read More »

Scroll to Top