12/15/18 – TEI spoke with CWW on adding new city water main and abandoning old main underground. This seems to be an acceptable solution for everyone.
12/31/18 – SOSS approved, ThermalTech can start design for replacement.
01/31/19 – ThermalTech has completed several field trips for this work and worked out replacement with the CWW for this job. THP will provide notes for sealing up the wall after piping is removed. We will try to have ready for ITB and bidding in early February. We will get prices now for Facilities to see about funding.
02/28/19 – Project updated with revised scope and sent to Bert. TEI met with GBBN and THP to discuss their role in the final TEI drawings and got some information about how the project will work. TEI to update drawings and cost estimate with final scope.
03/21/2019 – THP Finalized foundation repair detail and related specification sections and emailed to TTE for review.
03/27/19 – THP submitted drawing package to ThermalTech. TEI incorporated details into job and updated floor plans. Final review set going out this Friday.
04/24/19 – Prices submitted, project awaiting approval by County.
05/28/19 – Project on hold awaiting release by the County.
06/27/19 – Project on hold pending funding.
07/25/19 – Project on hold pending funding.
08/28/19 – Project on hold pending funding.
09/25/19 – Project on hold pending funding.
10/30/19 – Project on hold. Fire Pump Study working on peripheral items associated with this update.
12/11/19 – Project on hold.
01/24/20 – Project SOSS for Bidding & Const submitted to County for approval. Drawings are pretty much ready for bidding upon County approvals.
02/20/20 – SOSS and PO forthcoming after speaking with Facilities. TTE should prepare the bid document work in Feb/March.
03/23/20 – Final review drawings are nearly complete. TTC need to check over and send to Tony.
04/16/20 – Drawings will be sent to Tony Matre for final review by May 1. Spoke to Tom Frimming about pump requirements and new water main installation for this job; forwarded those comments to Tony for review.
05/27/20 – Final markups not included yet from TTC markups. I am thinking that I will pick up the final markups myself beyond this markup set but I do need to send Tony his final dwg set for his markups.
06/23/20 – Project on hold awaiting funding.
07/29/20 – Project on hold awaiting funding.
08/26/20 – City performed work in the alley this month for new sidewalks, curbs and concrete. TTC measure the depth of the city water line while the alley was demolished. The piping is 19″ below grade with the alley removed and potentially another 9″ below the landscaping in front of the 800 Broadway building.
09/18/20 – No updates this month.
10/28/20 – No updates this month. But we did refresh the drawings a little bit and try to improve the PID.
12/10/20 – Tom F called to say that SA Comunale ran the annual fire pump test last week and the building does not hold on one water main. TTC reached out to Daryl Meadows at the CFD about what the Fire Watch would include during the City Water shutdown and TEI will update the drawings accordingly. Also, however, TTC reached out to SA Comunale for the actual failure points. The low water cutoff means (i.e. if the pump can’t pump 125% of the flow, that doesn’t mean it can make 100% of the flow and that may be critical in the fire watch work over the weekend). The sensor turned the pump off before the pump reaches maximum by design.
01/25/21 – TTC sent latest drawings to Nester.
01/26/21 – TTC printed out final set, met with TAB to start final layout, planning on having review set to County on 2/5.
02/24/21 – Project going to bidding today with a prebid on March 12 and a bid opening of March 31.
03/22/21 – Addendum #1 issued last Monday. TTC has been coordinating with CFD on alternate methods to keep the fire pump running while the work is completed but no definite direction was agreed upon between CFD and ThermalTech so the fire watch will remain in the base bid and used for this project. Add 2 will increase the budget to $100,000. The final Addendum is due today.
04/29/21 – QCM was apparent low bidder on project. ThermalTech held a post bid summary with QCM and recommended them for this job. Base Bid and Alternate for Fire Tee accepted, contract in for review.
05/26/21 – Final contract sent to QCM. Site Safety, safety, and tax-exempt certificates have been shared. We are ready for a pre-const meeting with Facilities and QCM.
06/17/21 – Kickoff meeting with contractor on-site at 800 Broadway. Schedule, submittals, SOV, background checks all requested from QCM. TTE to submit plumbing drawings to city for permitting with QCM.
07/28/21 – Waiting on QCM background checks to clear so they can do the work in August.
08/06/21 – QCM preparing project site.
08/10/21 – Trench work underway and mostly done. Fire watch set for Saturday.
08/12/21 – Final connection work at CWW tee has issues. TEI on-site surveying the issues. New water line cannot be connected to existing water line with Duke electric duct bank in the way of our water line. Weekend cutover postponed to Aug 20. Hydro excavating is scheduled for Monday.
08/16/21 – Hydro excavation revealed more pipe, valve, and tee structure. QCM is not comfortable connecting any of the existing piping and suggest getting CWW involved to allow us to replace the valve and tee. TEI working with CWW on solution and approval.
08/22/21 – Working with CWW to resolve the new connection.
08/24/21 – Approvals received from CWW on replacing CWW valve and tee to extend out new water main into the building. QCM change orders received.
08/25/21 – QCM remobilizing for rest of 800 work. Valve and tee on order.
09/27/21 – CWW permitting discussions went well. CWW process requires fire calls. TEI to reach out to city to get the original 1992 fire protection calcs.
10/15/21 – TEI reached out to Dalmatian, Dalmatian fire companies for original calcs. Dalmatian reported they don’t have them. TTC asked a local fire protection to help with the calcs if we can’t find them, they will help.
10/22/21 – City came through with 800 permit drawings from 1992. They sent us over 1000 files and Coty found the fire calcs in the downloads. We are working on fixing the contrast so we can submit them for this job. This is good news.
10/28/21 – We are working with CWW and City permit office to submit a FA Calc plan to city and CWW for approval of changing the fire pump feed. We have the city permit documents and found the original calcs. We will get this out in a week.
11/23/21 – ThermalTech working with City and QCM for revised fire protection piping change for fire pumps. GCWW rejected the first permit application due to non-licensed plumber being selected in the application process.
11/30/21 – GCWW permit has been resubmitted to the water works. No update on city permit status yet.12/01/21 – Weekend work postponed for approved city and GCWW permit.
12/08/21 – TTC spoke with GCWW on permit and it is on hold until the city water main can be brought up to current standards. TTC emailed John and Rick and needs to set up a follow-up call with John about the feasibility of the GCWW request.
01/25/22- TTC needs to update the drawing for the GCWW review for the remote valve they want on the property line. TTC going to do his own cad for this work.
02/24/22 – Revised drawing is ready for review. Rick Seaver has left QCM, TTC will call and coordinate with Bryan Gilbert who is taking over for Rick.
03/31/22 – Drawings and study complete.
04/28/22 – No updates this month, try as I might.
05/25/22 – Met with the GCWWW last week on potential updates to give them what they want on this job. They will not accept either of the proposals that we gave them to modify the fire and domestic water feed. ThermalTech working on acceptable domestic water solutions that gives the county some savings for the cost needed to meet GCWW requirements.
06/25/22 – Created change order drawing for QCM to provide pricing on city water valve option.
07/22/22 – Change order received from Queen City and forwarded to the County for consideration.
08/19/22 – We are moving to close out the project. We are getting final prices from QCM for closeout. TTE working with Bryan on closeout documents.
09/22/22 – Keeping this open for QCM to do some selective valve replacements at 800. Coty working on the final list and cost for us.
10/26/22 – Project closeout documents received. TTC has final change order to review to close out.
12/15/22 – OK to close out.