Hamilton County Facilities

TTC

230 – Plumbing Upgrades

PM: Megan, Terry Cannon,
04/30/26 – Project opened on website. DEG started fieldwork and is working on bid CD documents. Need to check on SOSS approval.
05/27/26 – Need to request meeting with new building manager before proceeding. Meeting June 4 at 9am for design meeting with Jesse.
06/25/26 – First review set probably ready in July.
07/30/26 – Plumbing ready for review, electric will be ready soon then to County for Owner review.
08/26/26 – Review sets sent to County and limited comments received back. Floor plans updated. The project will be ready to bid soon.
09/15/26 – Prebid
09/18/26 – Addendum 1 issued.
09/22/26 – Addendum 2 issued.
09/24/26 – Bid due Friday.
09/25/26 – Bids received. Triton and QCM Mechanical submitted bids. DK and others did not bid the project.
10/22/26 – Facilities notified DEG that the bids are not awarded due to contract technicalities. TTC informed Triton in person.
10/27/26 – TTC & Rycca discussed how to rebid the job with a few small changes and make it suitable for award. DEG will update the bid documents adn send back out for a price refresh from the same vendors.

230 – Plumbing Upgrades Read More »

800 – Tower AHU Replacements

PM: Matt, Terry, Elevar
03/26/26 – Original SOSS rejected, need XBE on this job. DEG got proposal from Elevar last week and resubmitted on 3/25. Robert approved but need LOI for Elevar. DEG to provide and resend SOSS.
04/29/26 – More fieldwork completed last week with Tom and we have selected which units will be replaced. DEG working with Habegger on new unit selections and putting background drawings together. We will have a kickoff meeting in May with Elevar on electrical work for these units.
05/27/26 – Unit selections are made, we will be ready to meet with Elevar for electrical kickoff first week of June. No real surprises with new units other than they are all converted VVT to VAV units now. ALC controls kickoff meeting discovered that they cannot reuse any of the JCI VFD drives on this project.
06/25/26 – HVAC design progressing, Electrical kickoff meeting held with Elevar, more fieldwork next week. Owner planned end of July.
07/30/26 – Met with owner on design scope. Design continues, Owner review set still planned for end of July. Working on coordination with Emcor and Elevar on scope for VFD’s and electrical needs.
08/26/26 – Another field trip and final design concepts updated for several AHU.  We have meeting with Facilities Thursday afternoon to discuss budget, final scope, and asbestos abatement.  Then we are ready to bid.
09/15/26 – Project Issued for Bid. Bid opening scheduled for 11/12/26.
10/26/26 – Addendums issued bid opens on 11/12/26. Addendum 1 issued. No additional questions have been received as of 10/26.

800 – Tower AHU Replacements Read More »

525 – HVAC Retrocommissioning (No ITB)

PM: Rycca, Terry
Closeout Contact: Will Fisher wfisher@davieseg.com


02/24/26 – SOSS submitted for CX work.
03/25/26 – No updates.
04/29/26 – SOSS received last week. Internal kickoff meeting yesterday. Client kickoff meeting scheduled for Friday.
05/13/26 – DEG on site for initial fieldwork and discovery meeting.
05/20/26 – Internal meeting with Emcor & Habegger for RTU retro commissioning at 525. Commissioning is set for 5/28/ and 5/29 with Will Fisher, Emcor and Habegger.
06/25/26 – Bison currently repairing RTU-4, Triton currently upgrading economizers for RTU-2,3. Once complete CX will continue. Graphics updated to match other buildings.
07/30/26 – Bison repaired their units. Parts delayed on Triton units until 8/5. After economizers are programmed CX continues.
08/26/26 – Final parts came in yesterday and Triton is scheduled on site 8/27 to install missing parts for these units, then final commissioning will begin.
09/23/26 – DEG and Emcor met earlier this month and finalized the commissioning for this building and set final report to HC. Outstanding item are the exhaust fans in the main warehouse which are owner items to troubleshoot and repair.
10/26/26 – All work is complete the retro-commissioning is complete, final report sent to the County.

525 – HVAC Retrocommissioning (No ITB) Read More »

JC – Kitchen and Laundry Water Heater Upgrade

PM: Matt Butz, Terry Cannon
02/12/26 – DEG kicking project off and setting up fieldwork.
02/25/26 – We’ve confirmed the new heaters are the high temperature laundry and kitchen PK heaters. The SOSS is submitted and DEG is beginning preliminary engineering.
03/25/26 – SOSS submitted, project setup.
04/29/26 – Initial fieldwork started, drawing setup underway. Pat Bemmes will be assisting with this project.
05/27/26 – Drawings are setup, equipment submittals and cost have been requested from vendors.
06/25/26 – Project put on hold. Send final DEG invoice.

JC – Kitchen and Laundry Water Heater Upgrade Read More »

SPHQ – AHU-3 Replacement

PM: Matt Butz, Terry Cannon
02/12/26 – Kickoff meeting being scheduled with HamCo.
02/25/26 – The SOSS has been submitted. Barrett meet Ian on site and review existing conditions. This unit is only five years old, do we really want to replace it.
03/25/26 – Waiting on SOSS and kickoff meeting to determine final scope.
04/26/26 – Internal meeting on project progress. We will scheduled next meeting with Ian after 525 RECX gets underway.
05/27/26 – On hold wafting on direction from County on how to proceed. AHU already replaced five years ago.
06/25/26 – Project put on hold, send final DEG invoice.

SPHQ – AHU-3 Replacement Read More »

800 – HVAC Controls Upgrade (STS)

PM: Terry Cannon, Tony Matre
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com

 


08/19/25 – Kickoff discussion with Emcor.
11/18/25 – Emcor running low voltage at the building for new DDC network.
12/09/25 – Const Mtg and meeting minutes distributed.
01/08/26 – Const Mtg. Emcor making progress on equipment in the basement and on the first floor. They need help with access to some rooms that are under HCSO control.
01/20/26 – Const Mtg and new schedule released. Emcor gearing up for Chiller plant programming in March. Joe says they will take care of the 6th floor network cable. AM reports it is still not in the right place. The switches are in place and ready.
01/21/26 – Emcor shared missing submittals with DEG on VFD’s.
02/25/26 – Work continues as Emcor is planning on working on the chiller plant in March.
03/25/26 – Work continues, chiller plant programming in progress. Emcor ready to commission when building starts the chilled water plant for the season.
04/28/26 – Const progress meeting with Emcor held with DEG, Tom and Emcor. Small progress being made on new controls. Emcor asked to start boiler plant this week, it was decided to wait because of cold weekend temperatures. Tom had issues with chiller operation, Emcor found chiller in manual and released it. Emcor did some training with Tom to show him how to use new system but Graphics are not complete yet and the chiller plant is not fully programmed yet. Emcor to work on graphics, updated chiller programs and preparing for heating plant integration.
05/25/26 – Const Meeting held adn Emcor reported they started the boiler plant upgrades and they are making good progress. The communication infrastructure is in place for the future upgrades and the 800 Tower units can be added to it.
06/25/26 – Const meeting held last Tuesday, working out graphics updates and final controls work. Tom requested training.
07/30/26 – Project nearing completion, chiller sequences being updated.
08/26/26 – Project is complete and in commissioning. PCHWP-2 has an issues that DEG will be on site troubleshooting on Thursday.
09/23/26 – DEG met onsite to review chiller operations. DEG recommends to follow DK recommendation to replace thermal overloads on PCHWP-2. Tony said that Craig could perhaps replace these since they are less than $100. That is our recommendation as well. DEG updating the PID to new conditions after replacement of CH-2.

800 – HVAC Controls Upgrade (STS) Read More »

800 – Fire Pump Replacement

PM: Matt, Terry Cannon
Engineers: Coty Groeschen, Wesley O’Hara
08/27/25 – Prebid held today, bids are due in September. Owner furnished equipment includes fire pump, jockey pump, low suction controller and fire pump controller.
08/28/25 – Issued for Bid 8/13 and bids open 9/24.
09/24/25 – Bid Opening today at 11AM.
10/03/25 – Post bid meeting held with Alpha and they are recommended for the project. Base bid no alternates accepted.
12/12/25 – Jesse reported contracts close to being sent to contractor for signature.
01/25/26 – Contract should have went to BOCC on Jan 19, no updates. Sending Permit Drawings Tuesday 2/3. Electrical RFI received and in the process of being answered.
02/12/26 – DEG starting pre-construction work with Alpha and subs.
02/25/26 – Contracts are back. DEG coordinating with Duke and IBI on power installation requirements for the MI cable. Alpha EC vendor being weird about MI cable requirements and cost.
03/25/26 – Alpha arranging EC vendor for this job. DEG working on necessary CFD details before work begins.
04/22/26 – FDC testing complete and 800 passes inspection. DEG checking with Alpha on starting this project and getting permits to begin. A project schedule should be ready to share with the owner in a couple of weeks.
05/27/26 – SOV was approved today. We are ready to set up the Pre-Const meeting. DEG sent mechanical drawings for permitting to Alpha last week adn IBI drawings are already in for permitting.
06/25/26 – Kickoff meeting held with contractors. IBI permit approved, City permit under review. Electric change order under review. Schedule, SOV, Site safety documents received and under review.
07/30/26 – Had meeting with vendors on electric change order. Third meeting scheduled today at 1PM. Prices are coming down but not going away. Met with CFD and received their thoughts on allowing the high rise fire pump to provide temporary service for both low and hi rise, they are amendable provided we provide a letter stating it will work. Griffith sent us that letter.
08/26/26 – CO-1 sent and signed by DEG and Alpha, returned to County for approval. Planning on scheduled work to begin in October after Duke power is stable.
09/23/26 – 9/26 shutdown pushed back to Veterans Day. Alpha agreed to January 2027 startup without the project incurring any additional cost.
10/26/26 – JTL requested site visit to start working on the electrical portion of the job. DEG informed them to coordinate with Facilities on access adn that we wanted to be cc’ed on all visits so we can stop in and check progress.

800 – Fire Pump Replacement Read More »

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

230 – Summer Boiler Replacement

PM: Tony Matre, Terry Cannon
07/31/25 – SOSS approved. ThermalTech is conducting fieldwork to see if we can fit a boiler into the elevator and down to the in a size matching the KN boiler 2000 MBH. We did confirm that the boilers intended to be used on the Ameresco will not fit into the elevator, but they are 2500 MBH.
08/20/25- Final review drawings ready to review. TTC will send to County for review.
08/25/25 – Boiler selection is waffling, not sure where guys are going to fit a boiler in the elevator and down to the basement. We decided to have a base bid boiler and an Alternate boiler that matched future boilers.
09/24/25 – Review will be sent to Tony Matre for his review today.
10/29/25 – TTC preliminarily setup prebid meeting but did not get confirmation from bidders except one bidder (Triton) who showed up. TTC to reschedule.
11/14/25 – Prebid meeting with four vendors.
11/26/25 – Bids received, tabulated and sent to County. All bids were overbudget.
12/12/25 – TTC repackaged drawings and sent to DK for State Term pricing.
01/25/26 – County deciding if they want to award this project via State Term to Emcor and Debra Kuempel.  It does sound like it is going that way.
02/25/26 – No update on moving forward on this project yet.
03/25/26 – No update, still awaiting green light from County to move forward with state term work.
04/26/26 – DEG and Ameresco working on new boiler plant, this project can be archived.

230 – Summer Boiler Replacement Read More »

TPC – 7th Floor New Sink

PM: Megan, Terry Cannon
05/14/25 – Field trip to site with Rycca.
07/28/25 – Owner review set sent to County.
08/20/25 – Option 1 & 2 sent to owner for review with cost estimates.
08/28/25 – We received prices for SS pans and will update the cost estimate and send back with updates today.
09/24/25 – Project is also on 2026 Project Cost Estimates, we will use same numbers for the estimate.
10/29/25 – Project is updated in Archibus 26-ADM-0138-2485.
12/12/25 – TTC needs to revisit site with Rycca for new scope.
01/25/26 – Ryan and Sam to meeting with Rycca for kickoff meeting – waiting to here back about when this will be. We do need to draft an SOSS for this work and bid it out Small Project.
02/25/26 – Waiting to send SOSS, latest news was that this may be included in a bigger floor renovation?
03/25/26 – Questions out about final scope and expanded floor plan. Revised SOSS not submitted yet.
04/29/26 – Scope questions answered, DEG owes Champlin revised SOSS for final floor plan.
05/27/26 – Project On hold.
06/25/26 – Project on hold.

TPC – 7th Floor New Sink Read More »

All Buildings – Fire Damper Testing & Inspection

PM: Tony Matre, Terry Cannon
05/22/25 – Tony Matre asked for an SOSS to rebid this project in 2025.
06/25/25 – SOSS submitted.
07/30/25 – SOSS approved this month. Internal meeting conducted for kickoff to collect as-builts and setup new drawings.
08/28/25 – Drawings are nearing review status. Coty and Luke made good progress, but we have a lot of as-built items to incorporate from the last bid.
09/24/25 – We are updating the drawings for the new buildings including 525, EMA, and Mercy. Drawings should be ready for review in a couple of weeks for the whole bid package.
09/25/25 – 525 does not have any fire rated walls. CHA answered Coty about Dane.
10/30/25 – Still putting new buildings together.
12/12/25 – Original building drawings updated. New building drawings added, ready for TTC review. We noticed that several fire dampers missed in the Justice Center because of the spline ceiling are open and accessible. TTC worked with NKYHC to get a quote to update the fire dampers in the JC lobby now before the new ceilings go back in. NKYHC working with Triton to use their lift.
01/25/26 – Review sets sent to Tony Matre for distribution and review. After comments are received, we will setup the bid schedule for this project.
02/25/26 – No comments received yet, ttc checked in a couple of times.
03/25/26 – We are waiting on green light from Tony before bidding. Review sets are in for comments.
04/26/26 – Project on hold awaiting green light from Tony.
05/27/26 – DEG needs to add to buildings to the the bid and then we will start putting together the ITB.
06/25/26 – Finalized scope for new buildings, updated and found missing data from previous bid and addendums, final items being added to scope for bid package.
07/30/26 – Talked to Tony and we are removing 1701 and 111 from scope. We don’t have to wait for any additional comments from Facilities, TTC can package this up for bidding.
08/26/26 – Coty reviewed drawings this month and made changes but said he needs to clean up some items from the Coop work and he will get that done this month for my final review.
09/23/26 – Review project with Tony, putting 2026 budget together for Tony, but he also said to get the job out for bidding in October 2027.
10/26/26 – TTC will review drawings before Partner meeting.

All Buildings – Fire Damper Testing & Inspection Read More »

A&D – Water Heater Draft Study

PMs: Tony Matre, Terry Cannon

01/27/25 – Wireless space pressure sensors installed 1/24. Initial pressure readings indicate the water heater room is slightly negative (0-0.025 in WG) compared to both outside and the elevator machine room. The observed airflow showed consistent flow from the elevator machine room into the water heater room and from the water heater room to outside, suggesting the pressure would be elevator machine room > water heater room > outside. The observed draft on the water heater was a slight backdraft from the flue into the water heater room. The thermal camera was used to look for temperature gradients in the flue which could indicate a clog, but none were observed. ThermalTech is continuing to observe pressure readings and look for irregularities.
02/26/25 – Wireless equipment has been installed and we are monitoring the room. We have had one incident where the air seemed to be moving into the elevator room. TTC discussed with Glen cover all transfer openings and continuing to monitor for another 30 days.
03/13/25 – Covers were placed on the VAV duct and the transfer grill between the mechanical room and elevator to isolate the room from draft influences. Another test was conducted when there was little draft by opening the door to provide combustion air, but this did not fix the issue either.
03/25/25 – Draft still an issue. ThermalTech camera the flues and found them to be clear.
TTE brought in a Enervex for a third party review of the installation. They suggested extending the flues another 6ft each and thought the additional elbows added below the heaters might be a problem, they are running flue calcs for us to review.
04/23/25 – Project recommendations sent to Tony and Glenn and some additional conversation was had, but we have not been given direction to where to go next. We recommend new roof penetration and longer flue pipes to eliminate the issues.
05/28/25 – Project on hold.
06/25/25 – Waiting on County direction for next steps.
07/30/25 – Prices came back too high and too much scope. Barrett reached out to DK to realign cost and scope.
08/28/25 – Prices updated and given to Tony and Glen for next steps.
09/24/25 – Archived.

A&D – Water Heater Draft Study Read More »

JC – Condenser Pumps Replacement

PMs: Matt Butz, Terry Cannon
01/17/25 – SOSS Requested.
02/26/25 – SOSS received, TEI starting preliminary engineering.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project design has begun, we should have preliminary review ready in a couple of weeks, and then we can meet and talk particulars for this project.
05/28/25 – First round of internal reviews complete. We are picking up TTC markups, creating a construction cost estimate, and filling out electrical coordination sheet. We will have the mechanical drawing issued for owner review on 5/30.
06/25/25 – No comments back from anyone that I know of, should we move to bidding?
07/28/25 – We sent drawings back for comment and requested AIA documents for bidding. Ready to bid but ITB not requested until budget is set.
08/28/25 – Budget set at $200,000. Comments and AIA contracts forthcoming from Facilities for this project.
09/24/25 – Prebid held last Friday, it was well attended. Addendum 1 due out this week.
10/29/25 – Pre Award meeting held with Geiler today and they can be recommended for this project.
12/12/25 – In contract approval stage.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed. We have reviewed submittals already and are waiting on project kickoff to send them back to Geiler.
02/25/26 – Contract and PO are ready. DEG preparing for project kickoff. Pump submittals are approved.
03/25/26 – No kickoff meeting yet, submittals are approved, awaiting go ahead from County to move on this one.
04/29/26 – Kickoff meeting held early this month. Geiler commented that pumps were bid to be replaced when entire chilled water system was down. We are going to get everything in place and start this project in November 2026.
05/27/26 – DEG approved first pay application for $5500 and will send to County. Project on hold until November.
06/25/26 – Payapp received. Equipment in town, DEG to review at Geiler warehouse.
07/30/26 – Equipment approved, waiting on next Payapp from Geiler.
08/26/26 – Hold till November start.
09/23/26 – On hold until November, TTC approved and sent in Payapp 1, Payapp 2 already paid.
10/23/26 – Payapp 1 has cleared at Geiler.
10/26/26 – Pre-const meeting November 5. TTC removed the tentative tag on the meeting and update the invite.

JC – Condenser Pumps Replacement Read More »

800 – Low Rise AHU Replacements

PM: Matt Butz, Terry Cannon
01/17/25 – SOSS requested.
02/26/25 – TTC still needs to submit this SOSS, this is the last one on my list to submit.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project underway. We have completed our first field trip to the building. TEI running load calculations to verify sizing, setting up existing drawings and working on ventilation calculations. After we get the preliminary design complete, let’s meet and discuss project particulars.
05/28/25 – We held a kickoff meeting with the Facilities in the last month and made another round of field trips to the building for additional information. We are trying to prove HVAC AHU sizing from original job and collect factory information from original install of the low rise units to verify coil sizing, heating and cooling loads and whether or not air side economizers make economic sense during this replacement.
06/25/25 – ThermalTech doing additional fieldwork to lock down actual ductwork in the mechanical rooms. We should be ready for bidding next month.
07/31/25 – Project submitted for Owner Review. Project Manual didn’t make it through TTC review, will be sent later. Look for prebid third week of August.
08/26/25 – Prebid meeting Wednesday 8/27. TTE invited many.
09/24/25 – Addendum 1 previously released. Bid opening today at 11AM.
10/29/25 – Project on hold pending official bid award. TTC answered Nester email inquiry this morning about award status. TEI/DEG has not advised either bidder the project has been awarded yet.
12/12/25 – in contract approval stage. TTC notified contractors that Triton received the bid and Alpha did not.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed.
02/12/26 – Contracts are back. Pre-Const meeting being set up now.
02/25/26 – Triton has been awarded the project. We are scheduling the project kickoff meeting soon. We do need to discuss what are we going to do with AH-71 and it’s proximity to the parapet wall.
03/25/26 – Submittals coming in, no kickoff meeting scheduled yet.
04/26/26 – DEG working on change order request drawing to relocate AHU-L71 to farther away from parapet wall. Once complete we will get a price from Triton for the change.
05/27/26 – DEG sent revised AHU-L71 location to Triton for pricing to rotate away from parapet to get 10 foot clearance.
06/25/26 – Awaiting project kickoff. AHU-71 change order not received yet.
07/30/26 – Pre Construction meeting held with Triton. Working on submittals, sent permit drawings to Triton, working on getting project n place for January start so unit can be replaced over long County weekend.
08/26/26 – Reviewing submittals preparing for January start.
09/23/26 – Still on track for January start, no new submittals in September from Triton.
10/26/26 – Had meeting with Triton and Emcor on HVAC Controls. We are awaiting the resubmittal of the controls package to DEG for full review. The controls have not been approved for this project yet. AHU submittals including curbs are approved. We are verifying current lead time for equipment.

800 – Low Rise AHU Replacements Read More »

Records Center – Showers, Washers, Dryers

PM: John Nester, Terry Cannon

12/12/24 – Plumbing drawings for dog washing shower area submitted and construction began last Friday.
01/27/25 – Triton has secured permit and is currently installing the dog showers in the facility. The trench drain has been cut, they didn’t like the cover, we are working getting a grated cover instead.
01/28/25 – Field visit reviewed existing conditions. TTC will send some questions to Triton about the install as a follow-up. The trench drain cover has been replaced and is currently curing.
02/26/25 – Showers and trench drain installed. Washer and dryer work is underway as well.
02/27/25 – Ready to Archive. Move all washer and dryer time to new Records Center Animal Shelter.
03/25/25 – The showers, washers and dryers are installed and being used.
04/23/25 – Space is in use this phase can be archived. New work will be picked up on the Records Center Animal Shelter project.
05/28/25 – Archive this project.

Records Center – Showers, Washers, Dryers Read More »

Colerain – Animal Shelter Boiler Replacement

PM: Tony Matre, Terry Cannon

09/26/24 – After SD and pricing efforts, we have decided to bid this project via Small Project bid with one for one like boiler and no recirculation pump replacements in the Base Bid.
10/30/24 – Drawing are modified and ready for bidding. NKY will be but no word back from DK and Geiler on their willingness to give us a price for this work.
12/12/24 – No updates since last meeting. BW said to go ahead and get three prices for the boiler replacement but they are not moving on doing the work this year. One price received so far.
01/28/25 – No updates.
02/26/25 – No updates.
03/25/25 – No updates.
03/26/25 – Tony confirmed this project on hold. No work for TEI at this time.
04/23/25 – Project on hold.
05/28/25 – Archive until further notice.

Colerain – Animal Shelter Boiler Replacement Read More »

All Buildings – Fire Sprinkler Inspection & Testing 2025

PM: Tony Matre, Terry Cannon

09/26/24 – SOSS Requested.
10/30/24 – SOSS submitted. Preliminary project setup has begun. TTE needs to add three buildings to the bid this time around, 111, 525, 4210 Dane, Crime Lab and Coroners Office.
12/12/24 – Approved SOSS and PO not received yet.
01/28/25 – PO received. Preliminary specs assembled by Barrett. We need to scheduled fieldwork to confirm quantities. We heard the first deadline for draft review is end of February.
02/26/25 – Limited updates, we will be working on this one in March.
03/25/25 – No updates. We still plan on bidding this job by end of April.
04/23/25 – Fieldwork is completed. New buildings are added, old buildings are removed. Specs have been updated for 2025 Code references. The Project manual is ready for Tony Matre review.
05/28/25 – TTC compiling proposed bid cost to request the ITB number for this project. Trying to scheduled a two day prebid for this project. Bid will be in June.
06/25/25 – Prebid meetings scheduled for July 9,10.
07/21/25 – Addendum #1 sent to bidders.
08/28/25 – Bids opened and awardable. SA Comunale had only openable bid. Next steps by County.
09/24/25 – Contract being drafted. We answered some questions about the give year testing.
10/29/25 – Archive.

All Buildings – Fire Sprinkler Inspection & Testing 2025 Read More »

EMA – Tornado Siren Conditions Assessment (No ITB)

PM: Matt/Trades, Terry Cannon
Closeout: Terry Cannon, tcannon@davieseg.com


06/25/24 – Proposal from ANS sent to Bert Watts for review.
07/24/24 – Submitted for 2025 budget. County may know in Q4 about viability.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
01/17/25 – SOSS Requested.
02/26/25 – Kickoff meeting on hold while TEI researches additional technologies.
03/19/25 – Preliminary conditions meeting held with EMA on SOSS modifications. TTC submitted revised SOSS with additional scope same day.
04/23/25 – MCP sent a very high proposal in to assist on this project. TTC to follow up with Nester on next steps.
05/28/25 – TTE release PO to ANS for Siren Assessment, scheduling the first kickoff meeting June 30 or July 2, this request out to Mike D at ANS. ANS says they will need about 45 days to perform the onsite analysis. MCP quote came back very high, looking for other specialist contractors to assist with assessment.
06/25/25 – ANS cannot make the July 2 date, TTC to pick another date.
07/18/25 – Kickoff meeting held at 525 with ANS and EMA. Project set to kickoff August 4.
07/27/25 – Nick commented that third party vendor not required for future recommendations of system and we can concentrate on the siren conditions first.
07/30/25 – Additional scheduling taking place, project set to kickoff August 11 onsite at Siren #414. EMA, TEI, HCDF and ANS.
08/28/25 – ANS has made two deployments to the County so far. Zone 4 was completed the first week of August. Zone 5 was addressed this week. We are not sure how far ANS will get this week but shadowing ANS, each siren was about one hours to 90 minutes of work with travel. We have questions out for what constitutes a FAILED siren, especially in regard to test 3.1.4 on the Audit worksheet. The Siren Tracking sheet was created and updated and implemented by ThermalTech and put to use in the OneDrive. The OneDrive folder is available for use on this project. We are on schedule for targeted completion.
09/24/25 – Vendor meetings continue. Zone 6 is complete. 26 audits have been uploaded, no failures for this group. Several sirens were skipped for access and traffic control. Joe is in town for Zone 1&2 at this time.
10/29/25 – ANS has completed their initial visit to all sites in all zones. ANS returning November 3 for Traffic Control sites. The traffic control sites and daily order was released today to all team members. Friday November 7 is a backup day to pick up remaining sites. Facilities has followed behind ANS nicely fixing and putting UNSAT sirens back into service.
12/12/25 – Traffic Control and Access impeded sites have been visited. DEG checks with ANS every day for final audits. We have received 8 of the final 37. TTC must submit 25% Draft Report by Friday.
12/31/25 – Draft report sent to Hamilton County Facilities & EMA for review.
01/12/26 – Received final 17 Audit reports from ANS and incorporated them into the report.
01/15/26 – Reviewed report with EMA and tabulated all siren conditions from ANS and presented these numbers to EMA as well.
01/25/26 – Updated report being sent to the EMA this week for second around of reviews.
02/25/26 – Rev-5 sent to the EMA for comment. This version includes the Acoustic Model from ASC. No comments received from Rev-4 yet.
03/25/26 – No comments received yet.
04/16/26 – Met with the EMA on comments on the report. They are extensive comments. DEG will begin working through the changed.
04/27/26 – DEG continues working on report updates. We’ve gotten though some of the proposed cost changes, most of the editing is complete, inventory changes picked up and now TTC has to contact Federal Signal and get their information for the report.
05/21/26 – Met with EMA and Facilities and sent back next revision of report to EMA for approval and review.
06/25/26 – TTC checked back with Morgan on comments or progress, no update yet.
07/30/26 – No updates on markups to final report.
08/26/26 – No updates, saw Nick at Sharonville Life Safety event, he didn’t mention.
09/23/26 – No updates but we are starting two siren relocations with Ben, Keith, and Zach.
10/26/26 – Waiting on next review meeting with EMA. Project is in closeout.

EMA – Tornado Siren Conditions Assessment (No ITB) Read More »

2020 – Sewer Deduct Meter

PM: Tony Matre, Terry Cannon
05/28/24 – Cooling tower makeup water reviewed and approved by GCWW and should be on bill next billing cycle.
06/27/24 – Irrigation sewer deduct ready to review by County. It’s ready to send to GCWW.
07/24/24 – Second deduct meter sent to County for review. TTC followed up by email.
08/28/24 – Received Tony signatures on final paperwork, ready for submission to GCWW.
09/24/24 – Second application has been given to GCWW and MSD, they confirm they have it but it has not been reviewed or processed yet.
10/30/24 – Additional data requested and sent last week to MSD.
12/12/24 – MSD and GCWW have all the data they need, we are waiting on their approved and meter review. The first meter has been on the bills since June, and we are getting a deduct for it. Meter number S03787, so far, they have saved a little over $1,000 in sewer charges in the first few months with the meter online.
01/02/25 – We have the meter and the transmitter has been located. We are moving towards installation in the near future.
01/27/25 – HC has installed the meter and transmitter. ThermalTech is coordinating the final inspection with MSD.
02/26/25 – Meter has been installed and approved. We will check water bills to see when it shows up on the GCWW bill.
03/25/25 – Sewer deduct meter not on water bill yet.
04/23/25 – March water bill has both sewer deduct meters logged on the bill but the irrigation meter has no usage usage yet. This project is ready to archive.
05/28/25 – Archived.

2020 – Sewer Deduct Meter Read More »

2025 Project Cost Estimates

PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.

2025 Project Cost Estimates Read More »

RSC – City Water Main Extension

PM: Rycca, Terry Cannon
04/24/24 – Kleingers sent preliminary survey to County and ThermalTech for approval. Two items were tagged for review from the survey, the creek crossing and box culvert.
04/25/24 – SOSS approval going in front of the Board on May 2. BW needs all the TE paperwork by Monday for this work.
05/17/24 – Bert checked on status of submission to GCWW for water permit. TEI working on fire calculations for the load. We have the city water demand at 90 GPM.
05/28/24 – Colerain Township asked for the cost to extend the water line past the property. TEI and Kleingers will have to discuss additional cost.
05/29/24 – TEI to have preliminary application ready to discuss at Stated meeting this Thursday and completed by Friday.
06/26/24 – Preliminary application submitted this month. HC asked us to submit a SFHA permit too, which Kleingers is taking care of.
07/24/24 – Kleingers submitted both applications. TTE will check on progress with Doug.
08/28/24 – Update meeting scheduled for next week with County and City.
09/24/24 – Kleingers is currently working updating the drawings and its going well. It’s pretty straight forward except for the creek crossing, that might be tricky.
10/30/24 – Kleingers, ThermalTech and GCWW met onsite two weeks ago. TTE and Kleingers group sent out updates from meeting. The plan is agreed upon, Kleingers continue to design the routing and scope for new water line. GCWW says they will probably run a 12″ main in the street for current and future growth.
12/12/24 – Kleingers spoke with Bert this week and received the okay to proceed with the final construction drawings creating for the new water line.
01/28/25 – Kleingers sent an update to Bert. TTE sent review comments to Kleingers. Doug inquired if there was any progress on easement around bridge for new line.
02/26/25 – We had a progress meeting with GCWW, HamCo, Kleingers, adn ThermalTech and reviewed progress. TKG will follow up on easements and permitting. ThermalTech send load calcs to GCWW for use in their model.
02/27/25 – BW already made call on easements but believes the Engineer Office probably wants a Right of Way enlarge so the utilities can get back to maintain utility in the future. The routing of the line from the tap to down the road may change to meet GCWW needs for taps. TTC to check back with Doug on additional updates.
03/25/25 – Kleingers submitted an updated set of review drawings this week for review.
04/23/25 – Project in for review. Some emails are going around for coordination right now.
05/28/25 – Biweekly design meetings are now being held on Friday afternoons. ThermalTech hosting the meetings on Teams. Current work includes final approvals form GCWW, communication with Colerain Fire Dept about hydrant locations and finalizing HC Engineers Office comments. The Right of Way for the work around the bridge is in HC hands. Kleingers review drawings are up to date and distributed.
06/25/25 – Kleingers sent review drawings to the team yesterday. TTC to review and work on branch application. GCWW said the first shipment of piping will be delivered Friday.
07/11/25 – Design meeting to review County engineer comments
07/18/25 – Design meeting to review comments with GCWW. Kleingers to update and send new drawings for GCWW review to everyone.
07/30/25 – Next meeting is August 1 to comment on revised drawing sets and proposed budget. Bert sent easement requirements to Kleingers for their help with.
08/01/25 – Design Mtg #8 was held. The schedule was coordinated with the latest timeline. Kleingers will pick up latest markups and update the BOM on the dwgs for CWW. We are sending final review set to every for review the week of August 18. The easement work is underway.
08/04/25 – Kleingers sent latest drawings and materials list for final approvals.
08/22/25 – Final review project manual and drawings submitted to Bert Watts for approval. Budget and cost estimate finalized and coordinated with Bert. Comments sent to Kleingers by TTC for updates into final bid package. KEG working on easement with HCEO. Mylars sent to City for approval. New budget around $1.14M and we will publish at one million.
09/24/25 – Final review with City, GCWW and HamCo held on 9/12. We must wait until city/county agreement is signed and funds approved for bidding then TEI can publish the project.
10/29/25 – Kleingers has paid the OEPA bill and sent the City receipt. The project is nearly ready to bid but we await the City/County agreement to move forward with bidding. All the documents are ready to go minus final review and assembly.
12/12/25 – City/County agreement went to Board for Approval on 12/11, assuming that is approved bidding for RSC City Water Line will be in January.
01/21/26 – Received comments back from Bert Watts indicating that the City and County would have final comments back to DEG by Feb 6. Issuance pushed back to Feb 11 and bid date extended.
02/18/26 – Project Issued for Bid to County Purchasing.
02/25/26 – Prebid scheduled for March 4 on site. Bid opening schedule for April 1.
03/25/26 – The project is out for bid. Addendum 1 & Addendum 2 have been issued. Bids open April 1.
04/22/26 – Bids extended to April 22. Bids were opened and read. Four awardable bids.
04/24/26 – The low bidder has pulled his bid because they did not include the full paving requirements.
04/27/26 – The pre-award meeting is scheduled with the next low bidder QCM on Friday at 1:00 PM.
05/27/26 – QCM was recommended for the job. Their contract is in for review with the prosecutor office.
06/25/26 – Contract sent to QCM and signed. DEG met with QCM on SOV and schedule on 6/24. QCM to send SOV in for review and they are okay with schedule extension and August 1 start. They would like to have a pre-const ASAP.
07/30/26 – Early Pre Const and Pre Const meeting held, notes distributed. Next meeting August 4. QCM acquired ROW permit, survey complete, and had begun marking and cutting pavement.
08/26/26 – Const Mtg #1 & #2 held on site. QCM making progress to about 1200 LF of piping installed. FH 13 installed. 50 sticks of piping missing but we’ve tracked it down to a missing shipment. US Pipe working to provide missing lot to the project site for use. Payapp #1 received and approved.
09/23/26 – Payapp #2 approved and submitted. Next Const Mtg is next Tuesday at 8AM not 9AM. QCM working on CO cost for hydrant and culvert, we will have something by the end of the week. Things are going well.
10/19/26 – Project team met on site to review landslide condition at Station 4 where the water line goes down hill to creek. It was decided to bring Terracon out to review existing road conditions.
10/22/26 – Project team met Terracon on site to review existing conditions. Facilities, GCWW, Terracon, QCM, DEG and Kleingers discussed alternate routes and proposed solutions. GCWW is leaning toward keeping the line where design and shoring up the hillside and sharing that cost with HCEO. Facilities and HCEO has afternoon meeting to discuss next steps. Afternoon meeting reviewed original design and field conditions with HCEO, Facilities and DEG. Kleingers not at afternoon meeting. It was decided to do more investigation, look for previous soil boring and to reconvene with another HCEO and Facility meeting on 10/30/26 for updates.
10/26/26 – HCEO working on reviewing existing field conditions at and around original water line path so we can keep water line in original spot. Terracon submitted boring report to Facilities from 1970’s for this area. This report was shared with the project team. Follow up meeting on Friday.

RSC – City Water Main Extension Read More »

JFS – General Services

PM: Rycca Thacker, Terry Cannon

04/01/24 – JFS Category created to track JFS General Services work.
04/22/24 – 2024 SOSS submitted.
07/24/24 – SOSS not approved yet.
08/28/24 – No updates.
09/24/24 – No updates.
10/30/24 – No updates.
12/12/24 – ThermalTech working on draft issue in the penthouse with Glen on the Water Heaters.
01/28/25 – A&D draft troubleshooting is a JFS general services.
02/26/25 – OK to archive.

JFS – General Services Read More »

Barth Safety Prorgram

PM: Ted Graham, Mike Barth

03/28/24 –  Program started, poster created, training held, policies & procedures entered into the record for all to see 🙂


04/24/24 – Barth is still on the fritz, his doctor extended his convalescence another four weeks.  After that, they will probably just remove the foot and replace it with another hand so he can do three times as much work as he normally does.   One hand for CAD, one hand for the calculator one hand for a cell phone, his other foot will be used to kick the butt of all the coops at the office.


05/09/24 – Program membership has grown by 100%!  Welcome to the program Mr. Ted Graham!


06/18/24 –  Welcome to the program, Rycca!  This month’s safety topic is monitoring for Overexposure to UV Radiation.


07/24/24 – Hopefully no updates this month 🙂
08/28/24 – No updates to report.
09/24/24 – We have lost the tree, crying, grieving, and bemoaning has ensured.

Barth Safety Prorgram Read More »

A&D – First Floor Drinking Fountains

PM: Rycca Thacker, Terry Cannon
02/01/24 – Create project for single upgrade of core area drinking fountain.
02/23/24 – Met onsite to review existing conditions. Champlin putting SOSS together for TTE to use for SOSS to county for one EWC on first floor. Build out into Security space seemed doable.
03/19/24 – SOSS submitted for approval, full scope.
03/22/24 – Fees seemed high for single drinking fountain, second SOSS submitted with reduced scope.
04/24/24 – On hold waiting on direction from County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold. Ready to archive.

A&D – First Floor Drinking Fountains Read More »

A&D – Mother’s Room Upgrades

PM: Rycca Thacker, Terry Cannon
01/22/24 – Fieldwork rechecked, owner review set by Friday.
01/31/24 – Drawings sent to Rycca for review. We will assist with permitting through the City of Cincinnati and with install as needed by Trades.
02/23/24 – County reviewing drawings.
03/22/24 – Still on hold.
04/24/24 – On hold waiting on direction from the County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
12/31/24 – HC said to archive this project.

A&D – Mother’s Room Upgrades Read More »

JC – Underground Fuel Tank Replacement 2024

PM: Matt Butz, Terry Cannon
01/24/24 – Project created for tracking any 2024 updates.
02/23/24 – Drawings are created for this year’s bid.
03/22/24 – TTC to create new SOSS in the hopes this job bids again this year.
04/24/24 – TTC has not submitted the SOSS for this job yet. Not sure it needs one, ask on Thursday.
05/29/24 – One of the first steps is to engages Terracon to scan the parking lot around where the new underground tank will be located for anomalies.
06/26/24 – TTC will get Terracon scheduled for July hopefully.
07/24/24 – Terracon has been asked to update their proposal. No SOSS has been submitted for 2024 project yet.
08/28/24 – Revised proposal received today, TTC to review.
09/24/24 – Project will now be rolled up with Emergency Power updates and their next bid.
10/30/24 – Archived.

JC – Underground Fuel Tank Replacement 2024 Read More »

SPHQ – ALC Upgrade BAS Commissioning 2024

PM: John Nester, Terry Cannon

01/24/24 – Post created for tracking.
01/31/24 – Two punchlist sent to ALC for work on the current job. Training scheduled for Friday with Mike Bowman and Emcor.
02/02/24 – Training went well. Ian, Kendall, Curtis, Terry and Barrett attended. We made a few adjustments while reviewing.
03/22/24 – Project completed, just waiting on some summertime use before we close it out.
04/24/24 – Emcor onsite this week trying to get AHU-1, AHU-4 worked out for dual circuiting. AHU-1 VFD installed on 4/23. NKYHC replacing refrigerant and ambient.  Emcor wrapping up they Comm Center and starting the 250 WHT building next week.
05/29/24 – Controls work has been completed and VFD installed. We need to check back with Ian to see if its working better.
06/26/24 – DK currently working at 250, will check on progress.
07/24/24 – 250 WHT is almost complete. 486 next, then Comm Center. TTC checks the graphics and there is work to do before we say they are done.
08/28/24 – Working on final stages of 250 WHT.
09/24/24 – 250 WHT graphics are not complete, points are being programmed now. SPHQ appears that most upgrades are complete. Comm Center graphics are intact but no space temperatures are shown on floor plans, none of the mechanical equipment is shown on a site plan anywhere, found it in the Basement but there is no chiller shown on the plans. Public Works Garage has updated controls on the new work from the renovation has not been programmed and we have no feedback on space temperatures yet. The Records Center has no space temperatures on graphics.
10/30/24 – All buildings are complete except for Records Center according to Emcor. They are waiting on an outdoor enclosure for the outdoor RTU.
12/12/24 – TTC reviewed SPHQ and asked that Emcor put space temperatures on the floor plans with the thermal graphics maps like we did at SPHQ.
01/28/25 – Progress ongoing. All buildings are either done or partially complete. Price received for temps on floors and passed along to Tony for consideration.
02/26/25 – TTC reached out for an update from Mike and Steve yesterday.
02/27/25 – Emcor received final IP address for last building. Mike Bowman will be out to add the last building and then TTC to punchlist.
03/25/25 – ALC should be complete with all buildings. TTC will create a punchlist for each building in the next 30 days.
04/23/25 – TTC working on punchlist right now.
05/28/25 – Archived.

SPHQ – ALC Upgrade BAS Commissioning 2024 Read More »

JC – Fire Pump Replacement (085-24)

PM: Matt, Terry Cannon
Closeout: Haeli Johnson, hjohnson@tritonservicesinc.com, Dayna O’Brien, dobrien@davieseg.com

 


01/24/24 – Post created for tracking.
02/01/24 – TE to submit SOSS for this project.
02/23/24 – Coty will be working on this job.
03/22/24 – Initial fieldwork started this week. SOSS submitted. Electrical review scheduled for next week to ensure fire pump feeders meet current code. Life safety code updates may apply to this upgrade.
04/08/23 – Met with our electrical group this week to discuss the power feeders to the fire pump. We decided the best course of action that saves the County the most money is to let the Emergency Power project go first and update the MCC disconnects to isolate the fire pump disconnect in its tub so that it meets current code. Once that work is complete, we can bid out the replacement of the fire pump with out running into issues with the new NEC requirements for feeders in concrete or the fire pump being fed first before ancillary equipment.
04/24/24 – The preliminary drawings are ready for TTC review.
05/29/24 – TTC marked up drawings for owner review. TEI working with Fire Marshal on component required for replacement versus new NFPA code. This has to be bid this year even though it will be installed after the Emergency Gen update.
06/26/24 – Final drawings are ready for review, changes have been made from our field trip with Andy earlier this month. CFD not willing to provide pumper truck for weekend, we are checking on rental fire pumps and fire watch. SA believes a fire watch can be used.
07/24/24 – We were waiting on the JC Emergency project to be awarded so we could move forward with bidding our design out. The FPC will provide the fire watch as needed to make these piping changes and replace the pump vs using the CFD. I have not seen any CFD response in writing to our design request.
08/28/24 – Final internal review scheduled Friday.
09/24/24 – Project is out for bid. Prebid scheduled for Oct 8 at 9am. Bid Opening is Oct 30.
10/30/24 – Bids opened with four bids under budget, two of which were non-awardable due to a bond issue. TTE to interview KFI on Friday for compliance to bid specs.
12/12/24 – Triton was the low bidder via the base bid and Alternates accepted, we await the contract and PO to have the kickoff meeting.
01/30/25 – Contract going to commissioners tomorrow for approval.
02/26/25 – Contract is back, we are setting up Pre-Const meeting.
03/25/25 – Pre Const meeting was held and meeting notes distributed. Schedule, SOV, and equipment submittals have been requested.
04/23/25 – Construction Meetings started. Stamped permit drawings have been sent to Triton for submissions. Submittals have been requested. Other project startup documents have been requested.
05/28/25 – ThermalTech received written direction on suction valve controller which is not required on this replacement as long as we have the low suction cutoff report as a supervisory back to the FACP. We are approving the Fire Pump Controllers and rejecting the Fire Pump and Jockey pump due to under sizing and rotation issues.
06/25/25 – Equipment ordered and waiting on equipment delivery. The latest ship date is September 18, 2025.
07/30/25 – Pump submittals are finally approved. Bulletin #1 drawings sent for pricing to fix test header.
08/28/25 – Latest update is that the fire pump will arrive 9/19. Triton to coordinate replacement with Owner.
09/24/25 – Work being scheduled now including fire watch requirements.
10/29/25 – The fire pump has arrived. The test header was repaired by SA Comunale, now the wall and patching work needs to be completed. A new test ring needs to be installed on the outside FDC. Quality Fire has two people badged, checking on TJ Williams badged contractors. We need to iron out Fire Watch details with Triton.
12/12/25 – Triton and Quality ready to begin the project. Final fire watch details being negotiated. Inspection test header has been repaired, outdoor placard spacing is loose.
12/22/25 – Construction meeting held, we are working out details of shutdown, fire watch and submittal approvals.
01/12/26 – Const Mtg, finalizing shutdown details, fire watch, and schedule for work. Fire Watch must be provided by Triton for non-secure areas, DEG to issue drawings for scope. Electrical shutdown may require Courthouse to provide steam for Justice Center based on weather.
01/21/25 – Adding additional details and scope to the shutdown and next phase of work. USPA does not have background checks complete for fire watch yet. Electrical changes submitted to IBI. Feb 3 will be electrical emergency crossover and Feb 10 will be the primary crossover. Pump replacement scheduled for Feb 23.
02/25/26 – Emergency power is connected. Normal power has become a power struggle between Duke and IBI and DEG is working through those requirements and obstacles with both parties. the pump install will be coordinated after the power requirements are resolved.
03/25/26 – Normal & Emergency power are connected and ready to go. CFD required paperwork submitted & 3 of 4 FDC did not pass inspection. March 23rd replacement rescheduled until FDC are repaired. SA coming in on Friday to begin repairs and assessment.
04/29/26 – 3 of 4 of the FDC are repaired. The fourth FDC is currently under repair but SA is having trouble sourcing an access panel for the wall opening. TTC asked to open the wall now and repair the FDC which should only take a day, temporarily install a wall covering to keep the fire pump job moving along. The fire pump is currently scheduled to be replaced May 18-22.
05/18/26 – Replacement started on the fire pump today. Triton and DEG providing 24/7 fire watch.
05/19/26 – Repairs and fire watch continues.
05/20/26 – Repairs and fire watch continues. 99% of electrical and mechanical work is complete. Corporate equipment pre-inspected the fire pump installation and it passed. We are trying to move up final inspection to Thursday at 1:00PM.
05/21/26 – Replacement complete. Fire pump tested at 1:00PM with full water test, manual and automatic starts with City of Cincinnati and Cincinnati Fire Department in attendance. All system passed, the new fire pump was put online about 4:00PM and the fire watch was completed.
05/27/26 – DEG provided the punchlist for the project and will distribute later this week.
06/25/26 – Project in closeout.
07/30/26 – Working on latest change orders for this project. COR-1.
08/26/26 – Change Order #2 in the works? Working on other closeout documents.
09/23/26 – Change Order #2 COR #1 data all updated and sent in for approval to County.
10/26/26 – Final change order approved and signed the project is in closeout. TTC reached out to Triton to get all closeout documents by 10/31.

JC – Fire Pump Replacement (085-24) Read More »

CH – Vestibule Air Curtains 2023

PM: Jesse Estes, Terry Cannon
09/21/23 – Tony requested SOSS for this work. Replace all three he confirmed in a phone call with him.
09/27/23 – Working on SOSS today.
10/25/23 – Review set will be ready Friday for owner review.
12/06/23 – Bids received from DK and Triton. DK is the apparently low bidder. Tony suggested accepting only the Alternates to add heaters to the left and right vestibules. TTC will review the bids with DK and recommend the award for this project.
01/11/24 – DK submitted additional paperwork for this project per request.
02/23/24 – Contract under review.
03/22/24 – Contract under review.
04/24/24 – Contract in for final review.
05/28/24 – Stamped permit drawings sent to DK for permitting.
05/29/24 – Setup kickoff meeting with AJ, Tony, Tyler for starting this project.
06/23/24 – Pre Const meeting held, coredrill complete, team met on door swing issue this morning.
06/26/24 – DK reported that heater was deeper than the door swing and submitted an RFI for resolution.
06/28/24 – A top cap “box” solution was given to DK for pricing. This would move the heater up high enough for the door to open.
06/30/24 – IBI Issued the electrical permit. CIC2402080
07/08/24 – TTE requested factory review of the proposed box solution for the heater depth issue.
07/09/24 -The factory reported that we did not have enough clearance for proper airflow and TTC discovered the maintenance access was blocked by the proposed design.
07/10/24 – A revised solution was sent to the County for comment that moves the heater on top of the panel.
07/24/24 – TTC checked back on the revised design and it was accepted by Tony Matre, TTC forwarded to DK for review. Tyler inquired about still using the box solution.
08/28/24 – Left and Right heaters are installed. Reviewed and approved by TTE and Facilities. DK engaged for change order revision on the center heater in the middle vestibule with the exact same unit the left and right has. DK agreed CO#1 using the allowance monies to pay for the additional heater. Paperwork signed and sent to AJ this week.
09/23/24 – The left and the right heaters are installed, painted, and electrified. The center heater was ordered via change order and should ship 10/2. Once the third heater is installed the electric and controls will be finished for all three heaters.
10/30/24 – All three heaters are installed. Two of them have power and final paint. AJ trying to get electrician on site to power up the final heater. AJ lining up Joe Bulach for DDC integration after third heater is ready.
01/02/25 – Controls are installed, all heaters should be working, punchlist sent, contractor has been asked to start closeout on this project. The heaters are discharging about 110F.
01/27/25 – Still waiting on final closeout documents from contractor.
02/26/25 – Closeout Documents almost complete., they are coming in.
03/25/25 – Closeout documents received and final pay apps being processed.
04/02/25 – Jesse Submitted final pay app today.
04/23/25 – Project can be archived.

CH – Vestibule Air Curtains 2023 Read More »

2024 Project Cost Estimates

PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.

2024 Project Cost Estimates Read More »

CH – Backflow Preventer Replacement

PM: Jesse Estes, Terry Cannon
04/18/23 – Request for SOSS to replace BFP at CH
05/05/23 – SOSS submitted.
06/21/23 – Fieldwork scheduled.
06/29/23 – We decided to bid this job Small Project given our previous experience with the JC BFP. Project submitted for final review to John.
07/26/23 – Final drawings being prepared, we will add two shutoff valves ahead of the BFP when they are replaced. We should be able to get this bid out within the next month.
08/29/23 – Project is ready for XBE. TTC to prepare for bidding.
09/27/23 – We are putting together front end documents together for this bid now.
10/25/23 – Addendum 1 ready to go out today. Bids are due 10/31.
12/06/23 – Bids received and vetted by ThermalTech. DK was the apparent low bidder and was recommend for award. Contract and PO approval stage.
01/17/24 – Additional paperwork requested by John Nester for this project.
01/24/24 – TTC contacted Bill Roach again for bid documents.
01/31/24 – Nothing received yet.
02/23/24 – Waiting on contract documents from DK.
03/22/24 – Contract under review.
04/24/24 – Contract signed by DK, County waiting on insurance from DK. Submittals were received and sent back for updates. The revised submittals were received today and sent back to the County and put back in the queue for TTE review.
05/28/24 – PO and Contract ready, setup kickoff meeting with DK and County.
06/26/24 – Pre Const held last week. DK has equipment in stock. We need to decide on a couple of valve questions before DK gets started.
07/01/24 – Pre Const meeting minutes distributed to the group. the BFP are in town and the work can be scheduled with HamCo on their schedule. No payapps or SOV has been received or approved yet.
08/28/24 – DK waiting on one more background check to clear and then they will schedule the work.
09/24/24 – Last DK worker did not make it through background checks. DK preparing to do the job with three workers. Bill setting up new schedule.
10/30/24 – Bill ready to do work in November, December time frame with three plumbers over two weekends. He will pick the weekend and give us a scheduled soon.
12/12/24 – The West BFP Replaced last week plus the two isolation valve above the city water booster pump. A small leak was discovered in the West BFP. GCWW does not know where the main city water shutoff is on the east side of the Courthouse so they are doing more fieldwork this week. DK will be after the holidays to do the next BFP. We received work from the city water inspector that the BFP clearances from the floor are acceptable.
01/28/25 – GCWW still searching for east side shutoff valve for east BFP. We are getting conflicting data about the exact location of the existing valve. Regardless it appears as thought GCWW would like to replace this valve when found. One valve found in the street apparently has bad packing, this valve would also be replaced. We will continue to coordinate and get updates from DK and keep the County up to date.
02/26/25 – Still waiting on GCWW to located and fix East Side main shutoff.
03/25/25 – HamCo provided updated from GCWW about locating and find the East shutoff valve for the building. As soon as that is located we will proceed with the next phase.
04/23/25 – GCWWW has scheduled multiple visits to fix or replace the Courthouse isolation valve for the East side of the building. As of this meeting, it is not complete. DK is checking in weekly with GCWW for updates. The DK change order has been submitted for the spool piece leak repair.
05/28/25 – DK meeting GCWW on site Friday to verify the new shutoff valve is holding. Then they will scheduled BFP replacement with County including the new spool piece.
06/01/25 – Will spoke with Justin at DK and have the following update to our never-ending waterworks saga. The isolation valve in the street has been replaced by GCWW. They haven’t patched the road yet so there’s no access to the valve without a backhoe to remove the road plate. DK will wait until the road is patched before performing work(expecting sometime this week or next week for that to take place). At the earliest, DK may replace the backflow preventer next Friday. They’ll be in touch to schedule the work.
06/25/25 – Second BFP replaced last Friday. Spool piece replaced at the same time. Everything seems to be working correctly.
07/28/25 – Both backflow preventers are replaced. TTE needs to do a final punchlist and verify final invoices before closeout.
08/26/25 – Punchlist complete and sent to Debra for signature and updates.
09/24/25 – Checking in with DK weekly for closeout and approvals.
10/29/25 – No closeout paperwork or additional communications from DK have been received. We reached back out for an update. Billy was out 10/6-10/10.
12/12/25 – Ready to Archive. Final documents being delivery to Jesse on 12/13.

CH – Backflow Preventer Replacement Read More »

JC – Plumbing Study

PM: John Nester, Terry Cannon
02/23/23 – All fieldwork is complete. TTE writing report now and creating cost estimates.
03/29/23 – Report is complete and in for final review with TTC.
04/25/23 – Report sent back as not complete, need pricing and scope updates.
05/21/23 – Phasing drawings completed. Cost estimated updated, final report updated for review. It shoudl be ready by Thursday meeting.
06/28/23 – New version ready to send in for review. This version has the cost estimate, sanitary repairs and drawings included.
07/26/23 – Report is done and priced up. Need to give Facilities the report, drawings and appendices on a thumb drive.
08/29/23 – Coty updated the report this week and cost in the 2024 adn the report were reconciled to some extent. TTC needs to spend time finalizing this work.
09/27/23 – Report is complete, cost estimate is done. I hope to send to JN before the meeting.
10/25/23 – Report is complete, still owe John a final copy.
12/06/23 – OMG I can’t believe this has not been sent to John yet. I HAVE to get this by end of year.

JC – Plumbing Study Read More »

CH – Courtroom 380 Restroom Study

PM: John Nester, Terry Cannon
02/14/23 – Met with John on site to explore options for installing this restroom, Coty, Terry, Sam.
02/23/23 – Champlin to prepare concept drawings, and then we will estimate two options and cost for the job.
03/29/23 – Estimate, dwgs and cost sent to County for consideration.
03/30/23 – OK to archive, HCDF is self-performing the work by swapping the judges chamber and jury room.

CH – Courtroom 380 Restroom Study Read More »

P&D Plumbing Study

PM: John Nester, Terry Cannon
02/23/23 – Fieldwork completed this week. Report is underway.
03/29/23 – Report is complete and in for final review with TTC.
04/25/23 – Being reviewed now and should be sent to JN before Thursday.
05/21/23 – Final Report should be sent in by Thursday meeting.
06/28/23 – Final Report delivered in hard copy to John.

P&D Plumbing Study Read More »

250 WHT – Plumbing Study

PM: John Nester, Terry Cannon
02/23/23 – Fieldwork complete. Report has been started. No dissimilar metals were found.
03/15/23 – Additional fieldwork conducted to confirm missing piping.
03/29/23 – Report is being updated.
04/25/23 – Being reviewed now and should be sent to JN before Thursday.
05/21/23 – Final Report sent this evening including final drawings.
06/28/23 – Final Report delivered in hard copy.

250 WHT – Plumbing Study Read More »

TPC – Data Center Decommissioning (9th Floor)

PM: John Nester Butz, Terry Cannon
09/19/22 – Submitted SOSS.
09/23/22 – SOSS approved.
10/26/22 – Drawing created for rebid.
12/15/22 – Champlin has head start on this job, ThermalTech planning on having this ready for review in January 2023.
01/24/23 – Ready to re-kickoff this job and get this out to bid early in 2023.
02/16/23 – Sent Review set to Matt, got ITB, estimate and dates all set. Issue 2/27, prebid 3/8, Bid Opening 4/3.
03/27/23 – Addendum 1 is issued.
03/29/23 – No additional questions received, bid opening Monday, April 3. TTC confirmed two bidders are planning on bidding.
04/25/23 – Bids were opened and Alpha is the apparent low bidder on this job. We have had an online post-bid meeting with Alpha and we followed up with a review of the proposed SOV for the project which was sent back with comments to Alpha. A follow-up phone call with Alpha discussed discrepancies between the budget and bid prices. A final recommendation is being made to he County.
05/21/23 – Pre-Award minutes shared with the team. Contract in approval stages.
06/28/23 – Contracts approved, we are seeting up the Pre-Const Mtg second week of July.
07/26/23 – Pre-Const meeting scheduled for August 18.
08/29/30 – Holding for startup.
09/27/23 – Holding for Startup, should I tell Alpha March 2024 or stick with January 2024.
10/25/23 – Talked to new Alpha PM and will setup meeting to discuss schedule and background check requirements with him. Brandon Winsted.
12/06/23 – Alpha in holding pattern awaiting kickoff of project on our schedule.
01/09/24 – Coordination Meeting #2 held between City and County. PO has been issued by the County to the City for the new fiber line. CAGIS ready to move servers by the end of January. Next meeting to have CLEAR in attendance.
01/30/24 – Coordination Meeting #3 held between City and County. City ready to execute PO to Thayer for fiber run between buildings. TE issued an updated drawing showing the fiber to terminated in CH 2nd Floor in Rack #17. City stated a new Integration Router will be installed in the new County server room in Rack #17 to reduce downtime of the cutover for the Integration router. We need to find a router for the Heroin task force when we demo the 9th floor. 9th Floor demo scheduled for April/May. Next meeting in four weeks.
02/23/24 – Updated Alpha on project progress. Assumed start date May 2024.
03/22/24 – Met with Alpha last week in the room. Pre Const Mtg mid April to be scheduled.
04/24/24 – TTC advised Alpha that our demolition start date will probably be June/July timeframe and that the service elevator will probably be worked on in May, June and July this year. CMSNet is currently getting a quote to move the database server out of the 9th floor over to the CH Server Room.
05/28/24 – Contacted Alpha and pushed back start date to August 2024.
06/26/24 – Admin CH fiber is installed, ttc to get photos today of server room progress. Another City/County meeting was held on Tuesday, ttc sent minutes out for review. July 21 6am is tentative date for Integration router relocation to Admin basement.
07/24/24 – Project walk through scheduled with Alpha for starting to mark existing equipment and demo.
08/20/24 – TTE contact Risk Mgmt and the final server was moved out of the 9th floor room.
08/19/24 – Alpha Construction started in the room. This week they removed ceiling pads and inspected the area. Asbestos contractor coming next week.
08/26/24 – Asbestos contractor began working in the space this week. An exhaust duct was routed across the 9th floor to the nearest window for ventilation. The Ante Room is under remediation now. The main room will be started next week. The floor demo to begin the third week of September.
09/24/24 – Building permit was submitted on 9/18. Fire permit was submitted on 9/18. 2024P08366 but permit is not ready for issuance yet. asbestos remediation has been completed in the ante room and server room, all clear has been issued. Demolition for the raised floor and ceiling is underway. Alpha asked about the status of the E-Waste products in the space and several pieces of equipment are still powered up. County coming on Thursday to remove products.
10/30/24 – Demolition nearly complete in the space. Alpha submitted COR for interior Liebert demo. Fire protection permit is approved and Preferred will be onsite next week to start their work. As soon as the wet
fire system is pulled into room, Alpha will start remaining demo and asbestos remediation.
12/12/24 – Fire protection is complete and the Halon tanks are removed from the building. Asbestos abatement is ongoing at this time and supposed to be done by the end of this week.
12/31/24 – Alpha sent and email outlining the delays in completion due to Testing agency staffing issues and told us completion will not be until early 2025. Testing actually completed their work today and Alpha will be back on Friday to wrap up their work. This job will be ready to punchlist next week Jan 6 – Jan 10. TTC advised all team members.
01/15/25 – Punchlist visit by ThermalTech and Champlin, Jesse and John G were in attendance.
01/28/25 – Punchlist distributed to contractor.
02/26/25 – Project is complete, punchlist has been issued and completed, now Alpha Const is working on back punchlist options. Alpha said they would have closeout documents sent to use by Friday.
03/25/25 – Alpha working on closeout documents for this project including finalizing punchlist, final payapp, and sending closeout documents.
04/21/25 – Punchlist #2 has been submitted to the contractor for completion which includes repairs to two broken windows on the 9th floor and additional electric items.
05/28/25 – Everything completed on second punchlist except windows which are coming in in two weeks.
06/25/25 – Alpha replacing broken windows Thursday to complete punchlist.
07/30/25 – All work is complete including the windows, waiting on owner approval for window repairs.
08/26/25 – All work is complete and approved. TTC will drop off closeout documents on Thursday.
08/28/25 – Closeout documents turned over to County this morning.
09/24/25 – Archived.

TPC – Data Center Decommissioning (9th Floor) Read More »

230 – Sewage Ejector Replacement

PM: John Nester, Terry Cannon

03/31/22 – County reaches out for SOSS for this job.
04/02/22 – ThermalTech reached out to Derek Koogler to get a submittal and quote for the job.
05/24/22 – ThermalTech on site for fieldwork.
05/27/22 – First set of plans created for job.
06/02/22 – Markups complete, given back to TTC.
07/20/22 – Markups returned to TTC again.
07/26/22 – TTC returned dwgs with additional markups. New lid information requested, use the same style as A&D.
08/05/22 – Page created and back-filled with project data. Progress drawing sent to County. We need preferred floor drains for replacement from John or Ernie.
08/22/22 – Met with John and Ernie on site and finalized scope. One new
08/24/22 – Final markups sent in for Cad. Bid in September, maybe August.
09/22/22 – Bid opened, DK apparent low bidder. Pre-Award meeting scheduled for next Tuesday. We have the budget to take all the Alternates on this job.
10/26/22 – Waiting on final contract and PO to begin work.
12/15/22 – Submittals returned for correction, new submittals should be here any day. Pre const meeting was held with Debra and everything went well.
01/24/23 – Pushing the manufacture hard to update submittals with the correct voltage. Other than that the submittal looks great.
02/20/23 – New submittals were returned FAC so the equipment should be on order this week. We still need external disconnects and transducer submittals. DK getting new delivery schedule.
03/29/23 – Pumps are ordered, assembled scheduled to be complete by the end of April. Tigerflow ship date not confirmed.
04/25/23 – Weekly check-ins with the vendor and contractor has not gotten us a firm date when the package will ship from Tigerpaw.
05/12/23 – Schedule of Values submitted, reviewed, and returned for changes.
06/28/23 – Schedule of value resubmitted for approval. Equipment scheduled to arrive at Tigerflow second or third week of July.
07/26/23 – Pump package will be here in August. Pre-Const meeting will be scheduled in August.
08/07/23 – Pre Construction Mtg #2 was held with Debra and the County. Meeting minutes will be distributed later this month. DK supposed to start in August.
09/27/23 – DK will send Dirk to do this job after they wrap up PBS Ice Machines which will be complete by the end of MNF week (this week). They should be mobilizing in next two weeks. I will check on paperwork again.
10/23/23 – Met Dirk onsite for project kickoff. Mobilization and tools today. DK started disassembly of sewage ejector system. Water filled sump about noon from fire pump test, but was pumped out before DK left for the day.
10/24/23 – Work continued on pump replacement no more water issues.
10/25/23 – Pumps are installed and operating. DK jet cleaning floor drains but finding clogs. Floor was hand scanned before saw cutting. DK used jack hammer to install new floor drain near blow down tank. New line and floor drain installed, concrete poured back into placed. We will meet on Friday for punchlist. Corporate equipment coming Friday for startup.
12/06/23 – Work is complete. Punchlist was issued. Backpunch and training completed. The system is up and running. DK to label each pump in field. DK to provide all closeout paperwork for this job.
01/31/24 – Project is complete. Discuss contractor and allowance with John Nester before accepting final payapps ($5k vs $12k).
02/23/24 – Review closeout documents with John.
03/22/24 – Ready to Archive this job but DK has not provided all closeout documents yet.
06/01/24 – Working with DK on closeout.
09/01/24 – Working with DK on closeout.
12/01/24 – Working with DK on closeout.
01/25/25 – Received Consent of Surety for final closeout today, sent that and final payapp to Hamilton County for closeout and processing.

230 – Sewage Ejector Replacement Read More »

2023 Project Cost Estimates

PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive

2023 Project Cost Estimates Read More »

EMA Sirens PM Schedules

PM: Nester, Cannon
05/26/22 – SOSS has been submitted for this work.
06/30/22 – No updates.
07/27/22 – PM will be entered in 2023.
04/25/23 – No updates this month.
05/21/23 – No Updates.
06/28/23 – Met with guys on starting the PM’s. They found equipment but have questions on existing PM’s for them.
07/26/23 – Will start on these after we get Ameresco PM squared away.
08/29/23 – County has started performing PM’s on the sires. the SOSS was approved in June, we can use new siren PM worksheet to enter the PM’s.
09/27/23 – Kicked off working internally on collecting equipment ID’s. Need to get an update from the guys.
10/25/23 – No updates this week.
12/06/23 – Siren locations reviewed. PM written and submitted for TTC approval. There are about 10 sires in the Archibus Module that do not match where we had Sirens place. This probably not a big deal as long as HamCo electricians know where the sirens are. I pulled my people off of verifying every single address, there were too many small discrepancies with the final address names. We will continue with the PM assignment after my review.
01/31/24 – Siren worksheet submitted and reviewed by County. Discussion with John indicated we can look at PM previously entered and massage the start dates to Ben’s latest request.
02/23/24 – Review PM already entered in Archibus, reset schedule to match EMA zoning.
03/22/24 – New SOSS written for repairs, the PM work is good to go.

EMA Sirens PM Schedules Read More »

264 – HVAC & Electric Conditions Assessment

PM: John Nester, Terry Cannon
04/28/22 – SOSS received and approved.
05/25/22 – It’s on the radar but not started yet.
06/30/22 – No updates.
07/27/22 – We visited the building for our first field trip. We’ve researched HVAC solutions for the space and will probably recommend splitting the existing HVAC unit into two systems one for the first floor and one of the second floor, adding a thermostat for better control, modifying basement ductwork to create two zones and adding one condensing unit for split system control.
08/24/22 – No significant progress this month.
09/25/22 – Draft reports should be done in early October.
10/26/22 – Electric reporting has been started, mechanical items are not so much. Soon…soon.
11/30/22 – Final report was turned over for final review and use. A few edits were made and the final report was resent to County amid several email blunders by TTC.
01/25/23 – No updates.
02/23/23 – Ready to Archive

264 – HVAC & Electric Conditions Assessment Read More »

JC – Underground Fuel Tank Replacement

PM: Matt Butz, Terry Cannon
04/26/22 – SOSS has been received. TTE met with County on kickoff meeting earlier this month. We met with the Fire Marshal and discussed scope of replacement, FM requested double containment piping on both the FOS/FOR piping. TTE on site with Duke to get into the vault and verify pipe routing and type. FOS/R is all double wall contained so we should meet code and fire marshal request for this project. THP not required on this project yet.
05/25/22 – CAD drawings and backgrounds are mostly updated, we are working on specifications and awaiting TTC markups for next step.
06/30/22 – CAD markups are back to designers. This job should be out for bidding by end of July.
07/27/22 – Review drawings are ready. We will submit them for review next week.
08/24/22 – Final markups in for updating. Bid in September.
09/25/22 – JN has provided contracts, TTC putting together bid documents. The project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – No bids were submitted after extending the bid for local contractors. The job was repackaged as a Rebid and a new prebid was held last week. The local contractor still is not comfortable bidding the work, we have an Alternate design to send out for Addendum today for consideration. Job set to bid on 12/21/22.
01/24/23 – No bids submitted on rebid either. We will try to roll this scope into the Emergency Generator upgrades.
02/23/23 – Project combined with JC Emer Gen project in 2023. Archive this report.

JC – Underground Fuel Tank Replacement Read More »

JC – Germicidal Unit Upgrade

PM: John Nester, Terry Cannon
04/27/22 – SOSS received and approved. TEI to schedule project kickoff.
05/25/22 – Field trip for design kickoff on June 2, 10:30am.
06/02/22 – Design Mtg #1 complete. TEI to research options for whole system UV versus wall mount units.
06/30/22 – Schematic design ideas sent to several manufacturers and pricing has started coming back. We are compiling the study results now. I like the whole unit option.
07/27/22 – Review drawings are ready. We will submit HVAC drawings next week.
08/24/22 – UV design in existing ductwork at AC-D5 being drafted now. TTC did additional fieldwork earlier this month. Bid in September.
09/25/22 – JN has provided contracts, TTC is putting together bid documents. Project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – Bid was opened, Debra was the apparent low bidder. Pre-award meeting went well and DK was recommended for the job. Contracts and insurance are getting finalized prior to starting work.
01/24/23 – Contracts and PO are in place. We are ready to have the preconst meeting. The first submittal is ready to be reviewed.
02/21/23 – Checked in with DK and they told me they need their submittal back for this job so we reviewed and sent that back this week.
03/10/23 – Equipment ordered and confirmed with the right voltage. Shipping date to be confirmed.
03/30/23 – Permit drawings have been sent to Debra for permitting.
04/25/23 – No update on permit approval yet on city website. TTC checking with DK.
04/26/23 – Parts on in town and at DK office. Permit will be applied for this week. DK ready to start working. Time to have a Pre Const meeting.
05/21/23 – Debra permitting the project now and waiting for badged employee to be available to work on this project.
06/28/23 – TTE sent back permitting responses. Ball is in DK court to get city permit then IBI permit. Dave is trying to get Installation Manual from vendor to submit to the city.
07/26/23 – Permitting not in place yet. Need to check on DK progress. “No detailed information available for the approval of Contractor Registration (This approval is reviewed upon the completion of all other required approvals)”
08/29/23 – Checked with DK a week ago and they had no update. The permit not approved, still in contractor registration phase.
09/27/23 – Talked to Dave at length about this project and its a resource issue for DK. He has not resolved the permit issue yet which he admits they need to get done. DK is currently trying to fix the JC boiler flue before winter and as soon as they are done with that, they will start the this project. DK will get a guy on the Permit this week. I believe they also need EC help for this job and I think that is one of the holdups to get started. All the equipment is in and approved.
10/25/23 – John contact DK this month and demanded a start to this project. Dave Gleason to get people started on this job and coordinate with Andy on access.
12/06/23 – Permit it approved. County reached out earlier this week and asked for an update on progress. TTE reached out to DK several times but also no updates from them at this time. I am thinking we ask Dave for a new project manager for this job so we get someone with more time to help.
01/31/24 – Multiple check ins with Dave Gleason and even Andy, not sure if electricians have started demo, but that is what was supposed to have happened.
02/23/24 – Met DK last week on lighting installation locations. DK has lights installed, need to have electric installed next and start demo.
03/22/24 – Mechanical work is done, need update from DK on electrical demo of existing UV and power for new UV lights.
04/24/24 – DK Electrical has visited the site to start to sort out the electrical scope. John told them to coordinate with the HCSO and Andy for schedule and to be onsite. DK report the new UV lights are powered up, TTE cannot confirm that yet.
05/28/24 – Met with DK today and discussed schedule and first demo of existing units. Sheriff will move inmates around one pod at a time while the units are demolished.
06/26/24 – We had a const meeting earlier this month, one cell will be used first to see how demo goes and Sheriff will move detainees to another cell while DK removes and patches one cell. AJ reported today that he believes the last unit was demolished yesterday and DK should be wrapping up demo very soon.
07/24/24 – Work is complete according to AJ, TTE waiting to punchlist this job.
08/28/24 – Punchlist to be performed 8/29 at 2pm.
09/24/24 – DK onsite patching up existing units, masonry, paint, and patch work on the punchlist. I talked to them today and they will be back down this week and next to wrap this job up.
10/30/24 – TTE checking on final punchlist progress.
12/12/24 – Dave Gleason says that we will have all the closeout paperwork by this Friday.
01/28/25 – Closeout paperwork received. We are working on the closeout process.
02/26/25 – We have received about half of the closeout documents for this project. See new Closeout page.
03/25/25 – Final closeout pages received, we are proceeding to full closeout.
04/23/25 – Project ready to archive.

JC – Germicidal Unit Upgrade Read More »

CH – HVAC Control System Replacement (081-22)

PM: Matt Butz, Terry Cannon, Will Fisher
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com


02/19/22 – ThermalTech submitted SOSS for the project.
03/04/22 – Met with Emcor on Ameresco pricing and scope exercise.
03/09/22 – Met with SBS on new technology and ALC interfacing capabilities
03/10/22 – TEI has created all the background drawings and base specifications for the project in the new CSI format.
03/11/22 – SOSS received and work begins. TTC setting up kickoff meeting on this project.
03/15/22 – Met with Honeywell onsite today and reviewed scope of Chiller controls and scope of this project in more detail. Two new corporate guys met us onsite and review past history and what they plan going forward.
03/22/22 – TTE met and review the action item list for bidding this out in 2022. We need to get background checks complete, BDS coming down tomorrow for BGC, Fisher has his badge, Constable BGC is complete and needs his badge. We’ve agreed to meet with Honeywell and JCI as the additional manufacturer’s for this project. We also want some time to sit with the con
03/23/22 – Started specs in new CSI format. Set up meeting with Honeywell for April 8 and JCI for April 11. We are trying to meet with Barth to review acceptable communication paths in the CH. We will schedule fieldwork soon.
03/31/22 – Meeting updated with JCI for 4/7. The badge process is started for 3 guys.
04/15/22 – Final controls meeting with vendors held this day. All said they can bid this job and meet the requirements.
04/28/22 – Project design schedules distributed. Fieldwork and design in April, May, June, July. Bidding in August, September. Award and contracts are October, November. Fieldwork started last Tuesday with Bracken and Matt. Basement, sub-basement, and roof equipment was verified.
05/25/22 – ThermalTech has been on the building finalizing equipment locations and needs for the last month. Our review drawings for all the equipment including VAV boxes will be out the County on June 3. We are also developing airflow diagrams for the control sequences based on our findings and Honeywell existing information. We are on schedule to bid in August.
06/30/22 – This month we finished up equipment takeoffs and sent them back to the County for review. Comments came back in a day and we have scheduled another field trip to check out additional equipment. JN asked for us to check our equipment against the archibus database, however, I cannot see the equipment database in archibus yet. Ask HC for help at meeting.
07/27/22 – A full equipment set of drawings was submitted to the County for review. TEI scheduling another field trip for final equipment information next week. We want to be on site with Randy so we can finalize sequences on standalone equipment and missing equipment in the sequences.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 & 2 issued. Bid was extended to Nov 15. At least one more addendum before bid opening.
12/15/22 – Bids were opened on schedule and the apparent low bidder is Debra Kuempel. A full pre award meeting was held and the recommendation sent to the County for Base Bid and several Alternates for this job that were still under the published estimate. Project is moving forward, Emcor called for an update yesterday.
12/20/22 – County sent the contract to Emcor for signature.
01/24/23 – Contract was sent, not sure if the PO is back yet. Ready for kickoff.
01/30/23 – John checked back with Steve on contract status.
02/23/23 – Project is in front of the board for approval. DK putting together their project team and was instructed to run all communications through the County PM.
03/29/23 – All contracts are in place and we are ready to have pre-const kickoff meeting. TTC to schedule and reach out to ZH commissioning for their background checks.
04/25/23 – The Pre-Const meeting was help and Emcor was introduced to the project team. After the meeting, we walked one AHU and DK spent time on site surveying the existing building and equipment. We are in submittal and background check phases.
05/21/23 – It Meeting was help this month. DK putting together proposed network locations for our review. The County is working on ordering 7 network switches for the new Control VLAN inside the Courthouse.
06/28/23 – DK continues to work on background checks. Initial network switch location rejected, looking for new locations. TTC & MCB to suggest locations, then will give to DK to review, we may need additional network switches.
07/26/23 – Emcor still working on getting staff background checked for this job. Net network locations reviewed and sent to County for their review. We may potentially meet and go over them at Partner Meeting on Thursday. TTC invited IT and Telecom.
08/16/23 – Met with DK and have new prices for the fiber backbone change order. Steve Yockey sent them to TTC who will review and send to County.
09/27/23 – We are very close to finalizing the change order for the fiber infrastructure for this job. TTE will create a final room location drawing for DK after we receive comments from Jack, Steve and the County. Any issues with what is on the our change order markups for VE options? Controls Submittals have arrived for TTE review.
10/25/23 – Background and LEAD checks underway. DK working with JN. Network location finalized with County and Debra and Change Order #1 for network infrastructure sent to DK for signatures, we are accepting the Value Engineering proposal for this work. Controls submittals returned to DK Revise and Resubmit. We’ve incorporated ZH commissioning comments, WF, BDS and TTC comments into specifications. DK and TTE have coordination meeting on Thursday to review in details to ensure resubmittal is correct.
11/03/23 – Bi-Weekly Construction meetings begin. Emcor working on schedule. TE working on submittal review. Team working on network infrastructure. Jack can’t make Friday meetings until 2024.
11/17/24 – Const Meeting. Working on Background Checks and LEAD checks. Emcor low voltage working on cable runs.
12/01/23 – Const Meeting. Start working on deficiency report format, LEADS checks, low voltage routes.
12/15/23 – Const Meeting. Continue with Submittals work, background check and low voltage routes.
12/20/23 – Submittals returned for equipment and sequences. We still have a couple of outstanding items.
01/05/24 – Const Meeting. Work continues and is making progress.
01/19/24 – Const Meeting #6. Emcor and DK working on after hours progress, TE working on missing piece of equipment and getting ZH in Leads checks program.
01/26/24 – Deficiency List and Honeywell Scope meeting in Room 608.
02/23/24 – Const Mtgs continue. DK running new fiber continues. Deficiency list is begin worked and updated. Honeywell contacted for their portions. Emcor pricing up actuator replacements from deficiency report. Submittals are being updated, penthouse controls are being updated.
03/22/24 – Biweekly meetings continue. This month Honeywell got the chiller plant online, the secondary chilled water pumps VFD’s are online and working, Bacnet has been added to three of the four chillers. DK submitted change orders for four pneumatic upgrades to four units. TTE reached out to Honeywell for pricing on these same four units plus their deficiency list items. Emcor has many of the fibers ran to the server room, they need to repair the walls where they brought items into the room and finishing punching down the cabling. The DDC server is installed in the Rack.
04/24/24 – Next Const Mtg tomorrow is this Friday. Will is out this week and Bracken will cover the meeting. Emcor is being pushed to provide a best guess schedule. AH-52 has been submitted. TTE is reviewing sequences for the new equipment, we will have a design meeting with Emcor to go over sequences and make sure they can do what we have asked for in the Project Manual.
04/25/24 – Biweekly meetings continue. The fiber and CAT6 installation is scheduled to be finished by April 30th. The new network and front end are scheduled to be online during May and equipment changeover to the new controls system shall begin immediately afterwards. Emcor will begin with changing smaller equipment in the basement that is less disruptive to everyday operations. Emcor is beginning to work on replacing the approved pneumatic valve actuators that were deficient.
05/28/24 – Biweekly meetings continue. Low voltage wiring will be completed in the next 2 weeks, only the fourth floor remains incomplete. The new ALC controls database will be uploaded to the old server by Emcor this week. The database will then be transferred over to the new server once HAMCO brings the new server online. Emcor will be starting the first equipment change overs next week, once the database is uploaded. Emcor will begin with the smaller equipment in the basement that is less disruptive to everyday operations. CO#3 has been approved to add AHU-52 to the scope of the project, changing that unit to ALC controls. Emcor and ThermalTech have reviewed the controls sequences and are working to finalize the sequences.
06/24/24 – Biweekly meetings continue. Low voltage wiring on the fourth floor will be completed this week and the new network switch will be installed. Emcor has uploaded the new ALC controls database to the new server. Emcor has begun bringing materials to the site and are planning to begin work in the next 2 weeks to change over equipment in the basement. ThermalTech, Emcor, and ZH are working to finalize the controls sequences based on the latest comments provided by ThermalTech.
07/22/24 – Biweekly meetings continue. Emcor has begun to change over equipment in the basement to ALC controls. Emcors graphics department has begun work on the graphics for the front end. CO-01 is nearing completion, ThermalTech will be creating a punchlist to close out the work. Emcor and ZH Commissioning are coordinating to commission the equipment that’s been changed over. ThermalTech is coordinating a controls sequence meeting with ZH and Emcor. ThermalTech is also coordinating a deficiency list review meeting to close/address any open deficiency list items.
07/24/24 – Met with Dale and Ben today on sequences, they should be finalized before end of next week. Met with ZH commissioning today and ALC not ready with graphics for them to star CX, so we are pushing them back a week.
08/26/24 – Biweekly meetings continue. Emcor continues to change over equipment in the sub-basement and basement to ALC controls. Emcor has changed over the south central VAV’s on the first floor, further work on the first and second floor will begin in the next 2 weeks. Emcor continues to develop the graphics, expecting to complete them by the end of August. A preliminary BAS training took place this month to get Tyler Laws and his team familiar with the new system; another training will be scheduled once the graphics are complete. Commissioning by ZH Commissioning will take place once the graphics are completed. Controls sequences have been finalized by ThermalTech and Emcor, the sequence submittal is expected to be submitted by Emcor within August. Work for CO-01 is almost complete, Emcor will provide a punchlist and ThermalTech will verify it. The deficiency list is nearing completion, with a few items being addressed by HAMCO and a few items still to be investigated by Emcor.
09/23/24 – Biweekly meetings continue. Emcor continues to change over equipment in the basement and first floor to ALC controls and has begun work on the second floor. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session will take place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning has begun starting with the basement equipment. The fiber and CAT6 installation is nearly complete; Emcor has turned over a punchlist that ThermalTech has started to review. The deficiency list is nearing completion with a few items being addressed by HamCo and some items requiring Honeywell assistance.
10/28/24 – Biweekly meetings continue. Emcor continues to change over equipment on the second and third floors to ALC controls. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session has taken place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning is ongoing and currently focused on the basement equipment. The fiber and CAT6 installation are complete. Once the record network submittal drawings are received, ThermalTech and HAMCO will review and walk down the punch list items. The deficiency list is nearing completion with the last few items being addressed by HAMCO once the steam system is turned on for the winter.
10/29/24 – ThermalTech scheduling change order review meeting with HamCo. We need to work out some scope issues on the drawings vs reality of what is in the space.
12/12/24 – Emcor is mostly complete with the basement and moving up through the building to floors 1 thru 4 as well. They are onsite every day and working towards the April deadline. ZH commissioning has started creating an CX list that Emcor will have to help correct the CX issues as we move forward and complete the work. VPN seems to be working.
12/23/24 – Biweekly meetings continue. Emcor has completed all changeovers on the second floor and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement, basement, and first floor. Emcor has a few small items to update in the BAS per HAMCO preference. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. The fiber and CAT6 installation are complete. Record network drawings have been received from Emcor. ThermalTech and HAMCO will review and walk down any network related punch list items. The deficiency list will be checked again in January, no deficiencies have been checked on in December. Change order #2 work for AHU-21, AHU-22, OAHU-1, and AHU-B2 has begun. All of the AHU’s mentioned previously have new valves installed per CO#2, only the damper work remains to be completed.
01/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls; these floors should be completed in January. Emcor will begin the sixth floor in early February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. Most equipment in the basement that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The few remaining items on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for AHU-21, AHU-22, OAHU-1, and AHU-B2 should be completed in January, closing out CO#2 work. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
02/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, and fourth floor. Emcor continues to change over equipment on the fifth and sixth floors to ALC controls. The fifth floor should be completed in February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover will begin in February. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The one remaining item on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going and should be completed in February, closing out CO#2 work. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
03/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to change over equipment on the sixth floor as well as wrapping up the equipment in the basement and beginning on the chilled water system and large AHU’s. AHU-82 is the first large AHU that has been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover is on-going. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 85) have been changed over. March will focus on the large systems in the courthouse, the chilled water system and the remaining large AHU’s.
04/23/25 – Work is progressing with about about 84% of the project complete. Emcor has asked for a two month extension for completion. ZH is following behind Emcor and catching up on commissioning. The County has some decent request for front end modifications that Emcor needs to work through. The large AHU’s are being converted now. The Chilled Water plant is current under integration and Emcor has been asked to provide a boiler plant integration cost outside of the scope of this project (see TTC & AKM).
04/28/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the sixth floor, seventh floor, and the chilled water system. All large AHU’s (AHU-68, 75, 82,85) have been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement (Pending deficiency item repairs). Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning will be next. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. A schedule extension change order is in progress. May will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the few remaining items and the chilled water system. The following are the remaining items to be changed to ALC controls for the project: Chilled water system, AHU-B, AHU-B16, EF-71, and misc. (4) condensing units. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Change order #4 is closed. Change order #5 has been signed, extending the schedule to June 13 and adding in the changeover of FCU-8 and AHU-B to full ALC controls. June will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/28/25 – Emcor did not submit a payapp for January. Payapps 12, 13 and 14 are wrong. We are working on corrections. We received corrected copies of 13 & 14 today but 12 is still wrong.
06/23/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for the chilled water system and (4) misc. condensing units, which are on-going. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HamCo and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Emcor is back checking all of their work, currently expecting to be done and ready for ThermalTech to punchlist on August 1. Basement, first, and second floors are largely complete and functioning correctly. HamCo is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. July will focus on checking all equipment and resolving any commissioning deficiencies identified by ZH Commissioning to prepare for August 1 punchlist.
07/25/25 – Const Mtg held with HamCo, TTE, and Emcor. ZH not present.
07/28/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for (4) misc. condensing units in the basement, which are on-going. The chilled water plant is now changed over and running in automatic mode. Emcor is focusing the majority of their time back-checking the commissioning items found by ZH and resolving any issues with the large AHU’s (85R has some pressure sensor issues being worked on). All change order work is completed. CO#6 is being drafted to give credit to HAMCO for systems that have been removed from scope and to extend the schedule. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is completed. State contract work is on-going for misc. repairs. Commissioning by ZH is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network (CO#1) related punch list items. Emcor is back checking all of their work, revised date for ThermalTech to begin punchlist is now August 15. Basement, first, and second floors are largely complete and functioning correctly. HAMCO is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. County wants to make sure that DK is doing the t-stat touch up plates. Make sure the County knows when.
08/25/25 – The project has entered the punchlist phase. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing the majority of their time backchecking the commissioning items found by ZH and resolving any issues with the large AHU’s. All change order work is completed. CO#6 is being drafted to give credit to HamCo for systems that have been removed from scope and to extend the schedule. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HC and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Punchlist walk with ThermalTech and HC is scheduled for early September.
08/26/25 – We are having a hard time narrowing down the graphics for the generators in the Courthouse. EGEN is the emergency generator in the basement. GEN-1 is the standby generator on the platform.
09/22/25 – The project is in the punchlist phase. Punchlist was developed during a one-day site walk with HAMCO and ThermalTech. Draft punchlist was supplied to Emcor, punchlist will be submitted to Emcor as final once ZH’s commissioning is completed. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing on completing items on the punchlist or checking the commissioning items found by ZH and resolving any issues. All change order work is completed. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is nearing completion. All equipment (except for heating equipment) has been commissioned. ZH has commissioned the chilled water plant. ZH is coordinating with HamCo and Emcor to resolve any issues found. The Punchlist has been issued, and we are ready to enter the closeout documents phase.
10/29/25 – The second training session was held earlier this month with the operators. I think it started our rough but was better received by the end of Training. More use will make the end user more comfortable with the new product. The Project punchlist still being completed. ZH Commissioning has a few days left to complete their work on the deficiency list for this project. We found that the free cooling HTX was not on the graphics yet, DK fixed yesterday and the heating plant is not working correctly yet, DK to assist Tyler in making this right.
12/12/25 – Functional testing deficiencies list meeting held today to review progress from Dec 3-5. Some items complete, many are not. DK needs to devote resources and technician to site to complete the CX work. DEG will have to setup owner internal review meeting later this week to review our outstanding resolution items. TTC pushing for 02/28/26 drop dead date for all the outstanding work, requested basic progress scheduled for DK too address final items.
12/22/25 – Punchlist completion is on-going. Site visits in December discovered that there are numerous open items on the resolution tracking form to be resolved. Resolution tracking form items are planned to be resolved by the end of February. HAMCO has given a PO to Emcor to replace HX-1 and HX-3 steam valves to DDC on state contract terms. Weekly meetings have been scheduled to check on the progress of the resolution tracking form items.
12/23/25 – HTX-4 Meeting scheduled for Jan 7 with County, DK and Davies.
01/25/26 – Emcor and DK making good progress, we are hopeful that this project will complete by the end of February. Ethan making good progress knocking out all final items and coordinating with HamCo and ZH Commissioning. VPN access requested for Will Fisher, Anthony said they will send him application. Smell and temperature on sixth floor better but not gone all the way that I know of. Weekly meeting continue with DEG, Emcor, DK and Facilities.
02/25/26 – Weekly Const meetings continue. Emcor has completed the TE punchlist and ZH resolution tracker except for the chiller plant which they are working on this and next week. The HTX will be taken apart and tested in March or April. TTC reached out to Emcor for a full PW download directory as requested.
03/25/26 – Emcor working on Chiller and Cooling tower plant controls. Emcor commissioning ready to start as soon as chillers are started. DEG and ZH met on commissioning deficiencies. DEG issued Punchlist #2, ZH working on revised resolution tracker worksheet. We are scheduled to inspect the HTX next month.
04/20/26 – Emcor, DEG and ZH reported for final commissioning and worked through the final punchlist and functional testing markups this week.
04/28/26 – Checked in with Tyler and everything seems to be working well.
04/29/26 – Tyler reported this morning at the cooling tower overflowed with water this morning and the penthouse was flooded. Investigation showed that some equipment was commanded off and a second condenser water pump started causing the overflow condition. DEG asked Emcor for an additional logic step to prevent this from happening in the future. Emcor also asked that equipment be release to operated in automatic mode so this does not happen.
05/27/26 – All punchlist and resolution tracker work is reported as complete. DEG requested closeout documents from Emcor for project closeout.
06/25/26 – Project in closeout.
07/30/26 – Working on closeout documents. Emcor collecting OM’s and paperwork. We check back every Friday.
08/26/26 – Almost all closeout documents received including releases. We are working on full closeout.
09/23/26 – After months of work, coordination, and emailing Emcor, we have the final closeout documents and TTC will hand delivery to Ted and Mat ton 9/24. We have requested final payapp for processing.
10/26/26 – Project is in Closeout.

CH – HVAC Control System Replacement (081-22) Read More »

Comm Center – Cell Tower AC Replacements

PM: Rycca Thacker, Terry Cannon
10/20/21 – SOSS approved.
10/21/21 – Draft project manual distributed for review.
10/28/21 – Project prebid tomorrow 10/29. 12 sites. One base bid Blue Ash, 11 alternates.
11/08/21 – Bid received by TEI.  JCI and DK bid the work and Trane declined to submit a bid.  Bids were tabulated and sent to County for award.
12/13/21 –  This month we worked on getting the contract in place with Debra Kuempel for the Bid Bid and seven Alternates.  We continue to work on paperwork and contract.  Terry talked to Kerry last Friday about the intent of the specifications and verified with DK that the bids include all the labor and materials for the work.  Kerry preparing to write a non-AIA contract for use on this project and warned that an STD contract ADA contract protects the county less than a full ADA contract.
01/25/22 – Contract in signing stages at DK
02/24/22 – Still in contract stages, goes to BOCC this Wednesday and PO after that.
03/31/22 – PreConst next week.
04/28/22 – Pre-const meeting was held. Debra is preparing to start the work and call Scott. Submittals have been sent in for the Marvair unit, DK working on the Indian Hill split system.
05/25/22 – DK is scheduling kickoff meeting and fieldwork with Comm Center. I check in a couple of times with Dave. We also reached out to Mobilcom on alarm monitoring and set up a field meeting with DK and Comm Center to all visit a site to see how the alarms are connected to the AC units so we order them correctly. Submittals are still in my inbox pending this field finding.
06/30/22 – All submittals returned and approved. Equipment is on order DK starting at Indian Hill, however the installed equipment is different than planned, DK taking care of it. Payapps should start this month.
07/27/22 – DK started the Indian Hill site this month and is trying to get three Marvair units for the other sites this summer.
08/24/22 – Indian Hill #1 is complete, #2 is being done this week. Payapp #1 submitted with corrections for payment.
09/25/22 – Payapp #1 submitted, Rycca working with DK on some PW issues. No update on the Marvair units for delivery date, checked in with Dave 2 or 3 times.
10/26/22 – Equipment scheduled to arrive Nov 16.
12/15/22 – About 6 sites are complete and Debra is working on the additional sites daily. They hope to be done by the end of the year if the weather holds up.
01/24/23 – All sites are done and DK has billed for all the material. Scott says as soon as he gets time, he will coordinate a punchlist visit for us.
02/17/23 – Scott, Rycca, Terry performed an punchlist at three sites. TTC to prepare punchlist for DK to use on this project. TTC spoke to Dave about some issues we found in the first few locations and DK will take care of them.
03/29/23 – Closeout documents are under review for this project. Final payapps have also arrived. TTE making three binders for closeout.
04/25/23 – Punchlist sent to DK, O&M printed and will be delivered this week to Rycca. DK to check Eden Park for status.
05/21/23 – Working on closeout and punchlist with DK. Eden Park site was checked for issues.
06/28/23 – Punchlist complete, DK working on closeout documents.
07/26/23 – Signed punchlist sent to County for approval. Final payapps sent in for processing. Ready to archive.

Comm Center – Cell Tower AC Replacements Read More »

A&D – Plumbing Modifications

PM: Rycca Thacker, Terry Cannon
10/28/21 – TTC provided update on low flow plumbing issues at the A&D Building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called Underground Detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
12/13/21 – TTC in contact with RC Frey & Associates to order the part for testing purposes.  A new SOSS was created for this part of th Study.  Once I get the part in town, i can coordinate with Danny on the installation needs of this part of the test.
01/25/22 – TTC needs to coordinate and pick this part up or have it ordered by County.
02/24/22 – TTC has to get this done this week. I will talk to Danny about getting this ordered.
03/31/22 – TTC stopped at Ferguson earlier this week and the part is special order, order into “inside sales” and as soon as they confirm, we will put on order through TTS.
04/28/22 – TP-4 is here and TTC picked it up and will drop it off today at the meeting. The next step is to coordinate with Danny and Steve on installation.
05/25/22 – Plumbing fixes relocated to the Furniture design job. I spoke to Danny about piping changes inside the chase when we open it open. I plan to discuss at Friday Champlin meeting on a Furniture project. I have also searched out what may be an even easier fix with a new Zurn product but I don’t have the specifics quite yet.
06/30/22 – Need to schedule 5E wall opening with County. Ask at the meeting.
07/27/22 – I was able to get into the chase with three existing chases on the 6th floor and found what I needed for plumbing design.
08/24/22 – Setting up a field trip with Danny, hopefully on Friday at 8:30 am to go over installation.
09/22/22 – Found the flush timers online and there is some discussion to try the flush timers first instead of installing the trap primers first.
09/29/22 – TTC to provide equipment selection to Danny to purchase and install.
10/26/22 – Working out final order details with GenieFlush from California. We should be able to order the equipment by Friday.
12/15/22 – Parts are in, TTC needs to meet with Danny to install and test.
01/24/23 – Two auto flushers were installed two weeks ago and set to two hours intervals. WE will monitor and keep track of clogging.
02/21/23 – One flusher is on 4E and one is on 5E. The fifth floor is working just fine, the fourth floor has a sticky flush rod, TTC to reach out to the vendor for a replacement part.
03/29/23 – We reached out to the vendor for a replacement part and he would like pictures of the bad module.
04/26/23 – No updates.
05/21/23 – No updates.
06/28/23 – Archive.

A&D – Plumbing Modifications Read More »

A&D – Sewage Ejector Pumps

PM: Terry Cannon, Tony Matre

10/28/21 – Sewage ejectors not working correctly. Tony called for replacement work on them. Prebid set for today 2pm today.
11/30/21 – Bids received, QCM apparent low bidder. Pre Award meeting held virtually and QCM recommend for work.
12/14/21 – Tony getting PO for work to QCM for job. TTC to setup a pre const meeting late Dec 2021.
01/18/22 – Pre Const Mtg with QCM. Equipment approved and on order. The meeting went well, Drew and his foreman looked the job over. We are shooting for a Feb or March start date.
02/24/22 – No update on equipment delivery yet. QCM talking to Corporate Equipment every day to finalize a delivery date.
03/31/22 – Changed to submersible pumps, approved new submittals, created new dwgs and sent to vendor, should be installed mid-April.
04/18/22 – New pumps were installed and completed. MC and EC are done, and controls are coming to hook up the alarm points.
04/28/22 – The system is working well, pump #2 is going out on overload. EC dispatched to look at on Wednesday, they called Streamkey to look at the issue on Thursday. ALC controls are not hooked up yet, need additional wiring for the interface.
05/25/22 – Project complete and punchlist distributed to QCM. Emcor ALC waiting on badged low voltage electrician to run their alarm wiring before we close out. I sent all closeout docs to QCM. The system is working well.
06/30/22 – Just waiting on controls to finish DDC work, closeout documents from QCM.
07/27/22 – Controls work is complete. TEI requested O&M and Closeout documents from QCM.
08/24/22 – Project complete, we’ve requested closeout documents.
08/26/22 – All closeout and final payaps received. Project ready to closeout.

A&D – Sewage Ejector Pumps Read More »

CH – Gas Booster Pumps

PM Tony Matre, Terry Cannon
10/28/21 – Project is issued for bidding. Bids received and are awardable. Queen City Mechanical (QCM) is the apparent low bid. TEI conducts the pre-award meeting and provides recommendations to award. AKM indicates that he has PO and the project is moving forward.
12/13/21 – Bids received.  QCM is the apparent low bidder.  Post bid interview went well.  TTC setting up pre const meeting and reviewing submittals for the job.  Trying to coordinate electric with CH shutdown for the Server room which is the MCC in the boiler room where the booster is also fed from.
01/25/22 – Gas pumps are on order. Electrical permit drawings sent to QCM for permitting last Friday. We are trying to get the transfer switch in place during the CH Server shutdown.
02/24/22 – No major updates yet, QCM says the delivery date has been pushed back to April 2022.
03/31/22 – Electric submittals are reviewed, EE permit next. Booster will be here late April or mid-May.
04/28/22 – Stoermer stated the gas booster will be here mid-May to June now. The electrical submittals are returned with limited comments. IBI permit drawings were sent to QCM. They will schedule the work as soon as the equipment this in town.
05/25/22 – QCM and Stoermer have updated the equipment delivery date to be mid to late June. When the equipment gets here, the project will be started.
06/30/22 – Equipment not here, waiting on an update from Stoermer. Gas booster delivery delayed until end of July.
07/27/22 – Gas Booster pump delayed to mid-August. TEI reached out for an updated delivery date.
08/24/22 – Gas booster delayed until the end of August. All other facets of the job are read to go.
09/22/22 – Gas booster delayed until the end of September per Stoermer.
09/28/22 – Gas booster is here. Pad being poured this week, booster will be mounted next week then piping can begin.
10/26/22 – QCM submitted RFI for new piping arrangement with pump rotated 90 degrees to provide clearance around new disconnect in basement.
12/15/22 – Work is complete. First testing was not successful, we are waiting for a warm afternoon day to verify rotation of the new booster before we try again. QCM bringing extra fuses down to replace blow fuse during testing.
01/10/23 – Field rotation was verified and the gas booster started up with factory support. The backup gas booster is ready to go. There is a question about secondary gas pipe heat sensor.
01/24/23 – No closeout paperwork has been received yet on this job.
02/23/23 – No closeout paperwork has been received yet on this job. TTC checked back with QCM as certified PW keep coming in.
03/29/23 – Reached back you to QCM for all closeout documents.
04/26/23 – Closeout documents received.
05/21/23 – Closeout documents reviewed and approved. TTE processing final pay application.
06/28/23 – Final closeout documents delivered to County with Final Payapp. Ready to Archive.

CH – Gas Booster Pumps Read More »

TPC – Air Compressor Upgrade

PM: Terry Cannon, John Nester
07/29/21 – Remaining air compressor items after Ameresco work is complete. Is there any way to convert the final remaining devices to electronic? TTC to check on smoke purge control with fire alarm
08/26/21 – Met with Ameresco on scoping remaining pneumatic devices 3 times in the last two weeks. FA testing at Admin on Thursday night to verify existing sequences but the latest thought is that we will have to keep a pneumatic air compressor at the building. We will put a small project bid together for that work and get that out for bid ASAP.
10/19/21 – Final bids were submitted. ThermalTech created a bid tab and sent to the County.
10/22/21 – Talked to Bert about updated bid tabulation and waiting for final approval to move forward.
12/13/21 – Spoke to all vendors about the job and to be ready to start this job as soon as the Admin Fire Alarm.  We are set to begin this project and can schedule a kickoff with the county as soon as convenient.
01/25/22- Construction Work is scheduled to begin late February or early March. We are asking for submittals now.
02/24/22 – Submittals are in, will start right after Fire Alarm.
03/31/22 – Admin FA testing happening now, this project will be started after the FA is approved in April.
04/28/22 – Final FA test was completed and final meeting is coming up soon. TTC to send controls submittals back to Emcor ASAP. JCI submittal not received yet. This project is ready to get going in earnest.
05/25/22 – TTC needs to finish submittals and get Emcor scheduled for the next phase, will move this up to the front burner.
06/30/22 – Submittals are partially reviewed. TTC will setup kickoff meeting with Brian & Katie first week of July.
07/27/22 – The Pre-Const meeting was help with DK and a project schedule was submitted for work to begin in August through October. TEI starting to schedule contractors and vendors for a November final test.
08/09/22- Const Mtg #2 held with contractors. Things are going well DK is on schedule. We addressed several questions after the meeting on the walk through. TTE to work on FA final inspection schedule at end of job. EF-1,3,4,6, SF-8 complete.
08/23/22 – Const Mtg #3 and things are going even better. No major questions. EF-6,10,7, SF-1 Penthouse UH complete. Programming being updated as equipment is brought online. Graphics and controls look good.
09/22/22 – Const Mtgs continue, the job is about half done. DK is on schedule and continues converting pneumatic devices in the building. We have decided to submit a permit for this work and have it tested wit the city one final time. November 10 & 12.
10/26/22 – The project is complete from the DK scope. Pretesting went well and after some programming updates by Emcor during pretesting, the system is probably ready to test with the City. We spoke to Ameresco trying to use their existing permit to retest the system but that permit is closed. We will need to submit a new permit to the city.
12/15/22 – Work is complete, functional testing is complete, all systems are online and ready to go. AC has been turned off. TTC to issues cleanup punchlist to Debra. Project ready to start closeout.
01/24/23 – Work is complete and we talked to DK about cleaning up the rest of the job. AHU-1E is experiencing some issues probably note related to this job but also some issue that are related to this job. Two pneumatic dampers were found that need to be upgraded, but these dampers are already scheduled for demo in the Auto Title project so we instructed DK to lock them open and we have turned off the Air Compressor. Closeout documents started on this job.
02/21/23 – Project is complete, no closeout documents yet.
04/26/23 – Closeout documents requested.
06/28/23 – TTC will check with Steve on closeout documents.

TPC – Air Compressor Upgrade Read More »

Crime Lab – PM Schedules

06/25/21 – ThermalTech has been working on project over the last few weeks. New equipment was added to the worksheet, TTC to review final list.
07/29/21 – Susan contacted me about completion and I suggested that we could get these done by August 13. She reviewed our test work in DEV and had some questions. Ryan and Nathan will help me complete this work.
08/12/21 – Discussed progress with Susan and committed to a 8/31 completion for 9/1 PM’s. TE has updated Coroner’s Equipment list to check one more time before completion. We are verifying no duplicates exist.
08/25/21 – TTC sent in final list for equipment creation with 3 or 4 questions. Talked to Susan, Steve and Bert about process to finish. I received codes and values back from Facilities to use on our equipment creation list.
10/01/21 – Final equipment list sent to County for upload to Archibus.
10/08/21 – Needed to add asset column for equipment list and warranty item needs to be added.
10/19/21 – Revised worksheet and equipment list sent back to County. I still have to create warranty information for equipment when we enter the PM’s.
12/01/21 – Crime Lab PM’s entered minus a couple of extraneous electrical PM that TTC is checking the needs on.
12/13/21 –  Electrical PM not needed for exit signs, security gate, or power conditioner.  Steve checked in on warranty items and TTC reported that TTE can enter these manually, I just need a review on how to enter the warranty items.  We are meeting this week on how to do this work.
01/22/22 – All equipment and warranties are entered and up to date.
05/25/22 – Ready to Archive.

Crime Lab – PM Schedules Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

P&D – Restroom Renovation

PM: John Nester, Terry Cannon
04/21/21 – Nester requested SOSS for small restroom renovation, emailed next day.
05/26/21 – Kickoff meeting scheduled Friday at 2:00 pm on site.
06/11/21 – Sent preliminary layout with new fixtures located.
06/18/21 – Sent owner review set to John & Greg for review.
06/21/21 – Answered budget questions & Small Project bidding questions via email.
06/25/21 – Use as many BOLD participants as we can.
04/28/21 – Prebid held last week. Addendum #1 issued this week. Addendum #2 will be issued Friday with some cost savings ideas included. Bids are due August 5.
08/16/21 – Bids received and tabulated and sent to County for approval.
08/20/21 – Post Bid review with DK went well. County, TEI and DK working through contract documents.
09/30/21 – PO and Contract approved, all paperwork sent to DK for processing, and project information requested.
10/28/21 – Paperwork received from DK. PO and Contract are in place and the project is ready to go.
12/08/21 – Pre-const mtg scheduled on site but rescheduled to next week for availability.
12/13/21 – Pre-Const mtg schedule for Wednesday.  Submittals are returned.  Permit drawings will be hand delivery to DK at meeting.
01/21/22 – Tumlin has measured for toilet partitions and Debra is updating the project schedule. Permits are ready for this job. DK arranging for temporary toilets. We just need to get started.
02/24/22 – DK almost done. Rough-in work complete and passed plumbing inspection. Walls are being reconstructed, partitions installed and fixture to be hung next.
03/31/22 – Tumlin performing change order work for extending toilet partitions this week. DK performing punchlist work this week. Change Order 1 approved.
04/28/22 – The project is complete. Punchlist was distributed and completed including change order work. Some minor touchup may still need to be done. We can start closing out this project.
05/25/22 – Working on closeout with DK at this time. No additional paperwork has been received yet. Bill says they are close.
06/17/22 – Spoke to Bill & Donna at DK. They are working on getting closeout documents.
07/27/22 – Most of the closeout documents have arrived. I think JN reached out for a PW document.
08/24/22 – Reached to DK for more closeout docs. PW received so far.
09/25/22 – All closeout documents received. Project ready to close out.

P&D – Restroom Renovation Read More »

CH – Chiller & Boiler Room Control Updates

PM: Terry Cannon, Tony Matre
04/23/21 – Tony requested an SOSS for a chiller study on controls and operations.
05/26/21 – Discussed scope with Tony Matre today and he wants better control of the system and better maintenance.
06/25/21 – Based on recent conversations with everyone about upcoming projects, I have not submitted a separate SOSS for this work yet.
07/28/21 – SOSS approved. The study will begin next week.
08/18/21- TTC discussed similar scope with Ameresco and their findings on the Courthouse Chillers
08/24/21 – TTC met with Honeywell and discussed chiller, cooling tower, free cooling controls and programming and learned a lot about what has been changed in the last few years. Honeywell can meet with ThermalTech and the County late September given Randy current scheduled. TTC will advise Matt and Tony on this schedule.
09/27/21 – Reached out to Ameresco and discussed previous jobs with Garyne and Brad and get download on what they’ve done.
10/27/21 – Contacted Randy for pricing on recommissioning project and scope.
10/28/21 – Emailed and called Randy today for pricing for recommissioning today. Randy called back today and promised to give us his recommissioning cost by Nov 4, TTC to turn over to Matt and Tony immediately afterward.
12/13/21 – TTC scheduled the Chiller Recommissioning work with Randy and County for 12/27 at 9:00am on site.
12/30/21 – TTE collected and sent sequences to Honeywell for use on this project. Cc’ed the County.
01/22/22 – Honeywell working on new sequences and project schedule. TTC to check on VFD repairs.
02/24/22 – Honeywell started the fieldwork and deficiency report work last week and was down at the Courthouse collecting data.
03/31/22 – met Randy and corporate on-site. Getting deficiency report for next steps.
04/28/22 – Honeywell turned over all the existing points list and we have gone through it. We have not seen the due diligence report yet but Randy is working on it. I have stayed in touch with Randy weekly on this job. CH-3 will not be here unit August for installation. Comm is Bacent MSTP on the existing chillers.
05/25/22 – Randy is working up a new controller that will handle the sequences we need for this job and getting pricing, all hopefully, within his budget. And help promises to send an deficiency report to me via email.
06/30/22 – As soon as Randy is done with the Server Room, he will start the Chiller Room work.
07/27/22 – Randy is onsite now working on controls, he may get to some of the Chiller Room controls this week.
08/03/22 – Trane Chiller #3 ships 9/18/22, Tony wants chiller controls completed before then.
08/18/22 – Met with Dave Johnson on CH Boiler Room Controls today. We discussed his scope and schedule for integrating the boiler plant into two control scenarios. 1) Courthosue controls which will be minimal boiler operation and 2) CH & JC and what does that look like? Dave will update his controller for two scendarios and we will work in the HTX-5 operation with the Summer Reheat operation.
08/24/22 – Reached out to Randy for Chiller update and reminded him this work to be done before 9/18.
09/22/22 – Randy back on 9/21 but he spent that time on CH Server Room job. He is coming back next week.
08/24/22 – Randy will be back on 8/31 with a new controller board and continue to work on CH updates. He owes us a quote for a new controller to get the chiller RECX done before 9/19.
10/26/22 – Randy has made some progress. Honeywell will be back Monday. NO updates form TPC on CH boiler controls.
12/15/22 – Vendors have been contacted multiple times to complete this work but I have not gotten them on site to do this work yet. I will have to try harder this month.
01/24/23 – Randy promised he will be down to do the CH Controls work on Friday. Dave Johnson does not call me back.
02/21/23 – Honeywell on-site twice last month but the new controller is not installed yet. Met with DJ and he is working on new controls programming.
03/29/23 – Honeywell Randy to install new controller this week. Dave Johnson working with TTC.
03/30/23 – Randy confirmed this morning is installed and controls completed.
04/26/23 – Honeywell coming back May 5 to finish programming on the chiller plant.
05/21/23 – Checked in wtih Honeywell last week, no updates yet.
06/28/23 – Chiller and Cooling Tower controls are in place. Next step Boiler Controls.
07/26/23 – ThermalTech will check programming on Thursday when on the building BAS system. DJ having open heart surgery, his work may have to wait.
08/29/23 – Chiller controls in place. Boiler controls awaiting DJ recovery.
09/27/23 – No updates on this yet, will check in with DJ in October.
10/25/23 – TTC contacted DJ on health condition to see if he is ready to return to work yet, no answer yet.
12/06/23 – Chiller Controls are in. Dave Johnson said that he will call me back with a day to come down and do the boiler reprogramming so he is feeling better and back in business. We will get this on the schedule and get it done very soon. TTE reviewed the plan for having a Courthouse Mode and a Justice Center mode. DJ has to program some of this ahead of time.
01/31/24 – Randy Waddell to be onsite by this date for CH Chiller Controls. Trane sent all data he need for Chiller integration. Dave Johnson not answering phone calls about boiler controls.
02/23/24 – Randy Waddell was onsite this month installed controller for chillers. New wires ran to VFD, but no power is on new VFD’s yet. MCC update coming soon.
03/22/24 – Honeywell was onsite two days last week and pulled their controls back to the front end. four VFD’s powered up with controls. The Carrier chilled is not hooked up yet.
04/24/24 – Honeywell says they are done but the Carrier chiller is not hooked up to DDC nor can we see the KW on it. TTE to reach out to Don Webber. Randy Waddell has to come back to the building to work on Bacnet points, add the generator to the systems and the deficiency report items. Dave Johnson has suggested May 18 and 19th for his weekend work at the CH.
05/28/24 – Chiller work is complete, all chillers are on graphics.
06/26/24 – Honeywell has completed their work and the systems appear to be working. Dave Johnson is being scheduled for July.
07/24/24 – Chillers are complete and working well. Boilers are scheduled August 24,25th with Dave Johnson.
08/10/24 – Met Dave Johnson and Tyler Laws on site and reprogrammed the boilers. We got most of the reprogramming done on Saturday but we will have to come back on Sunday.
08/11/24 – Met Dave Johnson on site Sunday to wrap up the boiler programming updates. The boiler room was flooded due to the boilers being off and some of the recirculation pumps being off. Later we discovered a room upstairs flooded too, note to self turn off all pumps when the boilers are off. Programming complete with two operator settable modes and three working modes. (1) Courthouse, (2) JC Low Load March-November, and (3) JC High Load Dec-Feb.
09/24/24 – Dave J contacted multiple times this month for Summer Boiler troubleshooting and Modbus map for boiler controls to ALC to no affect.
10/30/24 – Dave Johnson coming back in November to finish up but boilers are running okay so far.
12/12/24 – Dave Johnson has not returned yet and I have not gotten a new commitment date from him.
01/28/25 – Talked to Dave last weekend and he is going to send some availability for February to finished the Summer Boiler work.
02/27/25 – Original proposal cancelled by Auditor. TPC sent new proposal for recommissioning and troubleshooting services. New proposal rejected due to wording. Tony requested new proposal.
03/25/25 – New proposal sent last week with updated language and 2025 rates including additional troubleshooting for the summer boiler. TPC also included sole source letter.
04/23/25 – PO sent to Dave Johnson for troubleshooting work and summer boiler integration.
05/28/25 – TTC trying to get summer boiler date from Dave Johnson. No luck on confirmed date of work yet.
06/25/25 – No commitment from Dave Johnson on summer boiler startup.
07/30/25 – No updates from Dave Johnson, spoke to Tony about Emcor proposal to take over boiler controls.
08/26/25 – Helped Tony get BBC in the vendor database, now we can schedule David through BBC.
09/24/25 – Sole source letter on BBC letterhead received. TTC requested schedule dates to troubleshoot summer boiler.
10/29/25 – Repeated attempt to schedule Dave Johnson back down for summer boiler startup were unsuccessful.
12/12/25 – No updates from Dave on performing the summer boiler work. Just Archive and put this job out of its misery.

CH – Chiller & Boiler Room Control Updates Read More »

800 – Plumbing Study

PM: John Nester, Terry Cannon
03/25/21 – SOSS submitted.
04/21/21 – SOSS approved. Terry, Coty, Ryan will work on this project.
04/29/21 – Contract sent to QCM for signature. Check on progress. Okay to do fieldwork during city water main shutdown.
05/26/21 – ThermalTech secured the services of Mike the plumber from Triton (same guy that installed the work at the CH) for the plumbing survey at 800 for one daytime and two nighttime visits). We will probably do this work in June.
06/09/21 – Met with County, walked the building, started reviewing existing installation.
06/25/21 – Updated drawings since 6/9 meeting, almost ready for field work.
07/27/21 – Day 1 Night Fieldwork with Terry, Coty, Danny, Triton, Tom. Basement, First, Second, 14,15,16 floors were completed.
07/28/21 – Day 2 Night fieldwork with team complete for the rest of the building. We have to return to finish the basement, access the drug testing labs and some judge’s private RR. Very little galvanized piping found. The building appears to be in good shape for plumbing piping materials.
08/26/21 – Existing drawings slightly updated from fieldwork. We will be on this in earnest the second week of September. There is limited scope to change based on what we found in the field. Our basement fieldwork will coincide with the city water main work on QCM Saturday.
09/30/21 – Drawings are complete and ready to TTC review. Study report started, TTC going to let Coty have a shot at it first and then will edit for final submission.
10/28/21 – Working on Fire Department design this month and did not make a lot of progress on wrapping this up yet. We could send drawings in for review.
12/13/21 – Project completion pushed to the end of December for this work.  TTC coordinating with Coty on putting the final touches on this work.  The laminated CH placards drawings were emailed to the County.
01/22/22 – Drawings are being completed now.
02/22/22 – Plumbing schematic ready for review, floor plans mostly completed and on final review and editing.
03/31/22 – Final Draft report complete, TTC will send today.
04/28/22 – Plumbing report and recommendations were sent to the County. Design SOSS requested.
05/25/22 – Design SOSS is almost ready. It’s a simple one but I need to finalize it and get it to John. We did meet with QCM this week and tell them we’d like their help.
06/30/22 – TEI has a field trip setup next Tuesday at 800 to final water shutdown plans and finalize valve locations.
07/27/22 – TEI performed additional fieldwork and found more valves and useful locations for valves. We’ve schedule another field trip to wrap up final details next week.
08/24/22 – Two additional field trips were held this month for finalizing changes. Updated drawings and revised report will be ready 8/30.
09/22/22 – Coty has prices back from QCM, they are revising and sending back for final scope on Monday. Some more valves were fixed during the last walk through.
10/26/22 – New pricing submitted by QCM. They called twice wondering which way we are going to go with the change order. I told Drew, we are probably just doing a material purchase and a fire detector restock.
10/27/22 – JN sent change order to TTC for review.
12/15/22 – Change order awarded to QCM. Drawings are updated for final scope, limited rework in the building is necessary. OK to close and archive this project.

800 – Plumbing Study Read More »

JC – HVEC-1 Replacement

PM: John Nester, Terry Cannon

03/25/21 – SOSS Approved
04/29/21 – The first draft of drawings are ready for review. TTC to send to JN.
05/26/21 – TTC initial review is finally complete and back in for changes. We will get a review set to the County by Friday, June 18 that includes both mechanical and electrical.
06/18/21 – Review set sent to County. The basic design is complete. TTE reached out to JCI for a controls budget number for the project.
06/21/21 – JCI provided existing sequences that were missed from our as-built drawings. We confirmed the existing unit has steam heat, city water cooling and a VFD that is linked to the washer control. We are are proposing upgrading the controls to monitor the dryers, running the VFD at three speeds, insulating the lint collection plenum and reducing the required outdoor air for better space control.
06/24/21 – County sent AIA contracts for inclusion in the bid manual. 90 Days completion time.
07/26/21 – New equipment submittal received from Trane with budget pricing. $18k for new unit. TTC working out new control sequence with JCI and finalizing pricing for bidding. Target bid issuance in next two weeks.
08/23/21 – Mechanical drawings and equipment selections are complete. Drawings sent to JCI for final controls sequences for the job. Electrical needs VFD information to relocate VFD to EF wall for reuse in new scheme.
08/26/21 – Project will be ready for bidding 9/1.
09/25/21 – Addendum 1 issued.
09/27/21 – Addendum 2 issued.
09/28/21 – Prebid went well, many bidders attended.
10/07/21 – Bid opening complete. two bidders, Debra & Blau. DK apparent low bidder.
10/28/21 – Pre-Award meeting with Debra went well, recommended for this job. project pending contract for the contractor.
12/13/21 – Project contract and PO are being finalized by the County.  DK has sent submittals that TEI has reviewed.  We are awaiting the project paperwork to be in place to return submittals and hold pre-const meeting.
01/22/22 – Submittals returned to DK and project schedule requested.
02/24/22 – update forthcoming from DK.
03/31/22 – Control submittals are in, TEI to review.
04/28/22 – Checked with DK and Trane, Unit will be here in June. Control submittals are returned and ready. DK to verify delivery date so we can setup the next const mtg.
05/25/22 – Dave and I both have reached out to Trane to get an updated delivery on this unit but we cannot get it out of them yet. As soon as we have that, we can set the schedule.
06/14/22 – Trane delayed the delivery until 8/17/22. We will schedule the pre-const meeting closer to this delivery.
07/27/22 – Checked in on delivery date – no confirmation from Trane yet.
08/24/22 – DK mobilizing for unit replacement work. We don’t have an isolation valve where we need one to work on this unit without drawing the entire north building so we will do hot taps and run new 2″ piping to the HVAC unit. The existing unit can remain on and cool during the demolition work doing it this way.
09/22/22 – HVEC-1 is demolished. New piping and hot taps are done. The new unit is being installed now. Some spacing issue is going to make changing the filter tricky.
10/26/22 – Everything installed with the unit, piping under pressure test, only electric and controls are left to complete.
12/15/22 – Per Debra all work is complete except for the controls work, waiting on JCI to finish. Ready for punchlist.
01/24/23 – I have been working with JCI to get their subs background check approved so they can finish the control work on the unit. The MEP work is complete. It’s down to controls. I can punchlist this job.
02/2/23 – JCI has background checks complete, working on final controls programming, rest of work is complete.
04/17/23 – Electrical and Controls vendors on site this month to startup up the unit. After some back and forth we finally have power and controls. the unit is ready for a punchlist.
04/26/23 – The unit was making noise yesterday. ThermalTech and DK on site to get this resolved. The blower motor was realigned by noon and put back online.
05/21/23 – Unit is up and running JCI made additional control changes last week. First stage cooling and fan where scheduled on anytime the space was in operation. 2nd and 3rd stages tied to the dryers. TTE needs to commission and punchlist this project.
06/28/23 – After checking on the unit three times this month, I can confirm it is providing cold air to the laundry room measure air at less than 65F this week. I still need to do the final punchlist. JCI technician has left JCI, trying to find who our new engineer is.
07/26/23 – Punchlist scheduled 7/26 at 1pm.
07/27/26 – Punchlist distributed to project team.
08/29/23 – Request closeout documents from DK again. I am holding final payapp.
09/27/23 – DK says they are working on closeout documents but we do not have them yet. We are also working on JCI controls punchlist with JCI but they have not confirmed who is out new technician. I asked DK to find out who is finishing this job for JCI and reached out to Dustin Stewart, our new sales engineer.
10/25/23 – JCI working on new technician for closeout and controls punchlist but no one has been assigned yet. County sent approved list through TTE to JCI today. Working on closeout with Debra Kuempel. Unit seemed to do fine this summer, it was definitely better in the room with the new unit running.
12/06/23 – TTC has been talking to DK and JCI about assigning a new technician for our work. But as of yet, no avail. TTC called Dustin Stewart and Greg Platt to get this moving!
01/24/24 – Motor bearing bad on unit. DK removed motor and took it out for rebuild at A-1. They will reinstall the motor ASAP.
01/30/24 – Closeout documents received from DK. JCI cancels punchlist visit due to family emergency. TE rescheduled to next Tuesday.
02/23/24 – Met JCI onsite this month and it went well.
03/22/24 – Project is ready for closeout.

JC – HVEC-1 Replacement Read More »

JC – Drinking Fountain Replacements

PM: John Nester, Terry Cannon
03/25/21 – SOSS approved.
04/23/21 – Acorn and StreamKey suggested moving the airtrol valve inside. After discussion with Facilities, this doesn’t seem like a solution. About 30 drinking fountains need a close connection. We are working on better solutions.
04/29/21 – The first draft of the drawings are ready for review.
05/26/21 – StreamKey reaching out to Acorn to send a revised mock-up for the close quarter’s actuation valve for us to test before we bid out this work. 32 drinking fountains required this type of actuator. We rejected the interior drinking fountain installation.
06/15/21 – Worked with StreamKey this week to iron out final samples of the AirTrol retrofit kit. Acord will manufacturer one item and send it to the County for testing. It will ship to StreamKey who will deliver it to County for testing.
07/28/21 – Drawings and Specs sent to HamCo for final review. Project will be Issued for Bidding on 8/2/21.
08/18/21 – Addendum 1 issued.
08/25/21 – Bids were opened today and we received several good bids within reason of each other. They are all significantly under the published estimate.
08/28/21 – Triton was the apparent low bid. TEI vets the bid and sends a recommendation to HCFD to proceed with Triton. Pre-construction meeting and kickoff meeting conducted.
12/02/21 – Onsite kickoff & coordination meeting with Facilities and JC held with Triton.  The material is onsite and Mike Adams will be our lead plumber from Triton.  We meet with John, Andy, and Danny for previous plumbing work and kickoff.
01/24/22 – All work complete and TTE to start punchlist.
01/25/22 – North Building Punchlist complete. TTE to send to Triton for rework. Relocate controllers mounted on the duct, provide tubing management.
02/24/22 – Triton says all punchlist is complete in the North building and almost done with the South building.
03/31/22 – Punchlist completed in North building, same work was proactively done in South building. TEI coming down to punchlist the South building in April.
04/26/22 – South building punchlist is complete. TTC to distribute. All drinking fountains are working expect one does not drain and one does not have a drain pipe any longer. All base bid work looks good.
05/25/22 – Punchlist distributed to Triton. County fixed a couple of owner-related items. Requested pricing from Triton on helping with Lobby sinks but prices seemed a little high. We have some money left in the PO from the allowance. I will request closeout documents from Triton next, the project is complete and working well.
06/30/22 – The project is done, closeout documents are here. Waiting on final payapp from Triton.
07/27/22 – Closeout documents are being finalized. O&M manuals are at the Courthouse awaiting final paperwork.
08/22/22 – Taking project to closeout, requesting additional equipment from Triton.

JC – Drinking Fountain Replacements Read More »

CH – Server Room Construction

PM: Matt Butz, Terry Cannon

01/06/21 – Foundation submittals arrived and was approved by THP.
01/26/21 – Graybach is ramping up the start of the project again shooting for a 2/15 restart date. The schedule is being updated for this start date. We will start sending out weekly updates on background checks and project updates this week. More steel submittals have been submitted and returned and we are currently finalizing and coordinating efforts with all the sub-contracts on status of equipment approvals from last year. A couple of RFI have been submitted, answered and returned for the GC.
02/02/21 – Change Order #2 arrived. Very large change order, TEI requested additional backup to this change order before taking it to the County. On 2/10reached out to Graybach for additional information and further breakdown on Subs costs for this CO.
02/03/21 – Updated LEADS list arrives, only one Graybach employee aprp2/10 – Permits approved for Building and HVAC work. Paid for and picked up by Graybach. Skip Zimmer is our inspector for this job.
02/06/21 – Three sets of questions/suggestions have been sent in on the steel submittals have been sent it and THP has been reviewing and answering. Everything has been approved except for the weight of the hatch. The county asked that the hatch weight 50 lbs or less and the submittal has them at 92 lbs, we continue to work with Graybach and their sub for an acceptable weight. As of 2/17 we do not have the final solution and they believe there is a cost impact to that solution when we make the change.
02/10/21 – Graybach making headway on badging. One superintendent, Nick Neyer, approved. He will be ready to go on March 1. Several other people have been. Graybach requested we setup Pre Const Mtg #2. Send me good days this week for that meeting please. Barth and I can do Tuesday afternoon, Wednesday morning, Friday all day.
02/16/21 – Concrete mix submittal arrived and uploaded to Procore.
02/17/21 – Rebar submittals returned. Fall arrest submittal submitted, uploaded to Procore on 2/22.
02/19/21 – Safety guide submitted arrived, forwarded on 2/22.
02/22/21 – Background check update worksheet attached.
02/24/21 – Pre Const Mtg held. Graybach furnished SOV and Project Schedule for final review. TTC to distribute meeting notes and changes order to the county. Graybach scheduled to start on March 8 with demo and complete the job in July 2022.
03/09/21 – Const Mtg #1 held. Graybach started its own Procore site for this project. Room 263 scope discussed and reviewed with Graybach. Ceiling heights were discussed in regards to the HVAC and Fire devices.
03/16/21 – Const Mtg #2 held. Parking lot spacing and usage discussed. RFI submitted to Procore site. Hallway door options discussed, project schedule closer to final, change order #2 and #4 were discussed and submitted for consideration.
03/23/21 – Const Mtg #3 held. Project schedule submitted, follow-up afterwords targetted dates for site work and eventual server room work. TTE reviewing material change order cost from 2021 means. Geiler, Graybach, County, ThermalTech to have a conference call on upcharge for Liebert units. TTE working on Rack options for the job to discuss with CMS and Facilities. Data cable and server racks to be purchased by owner, fiber provided by DK, HC telecom providing data and phone in Room 263.
04/29/21 – Weekly Const mtgs underway. Room 263 progressing, studs are up, rough-in inspection is complete, HVAC and electrical work is started. In the Courtyard the concreate has been poured and THP has checked on progress. Terracon has been on site for special inspections. The grade beams and column bases are in place and getting wet today. Additional meetings for finalizing racks, discussing change orders and coordinating with CMSNet.
05/27/21 – Room #263 work continues for mid-June move in date. GBBN punchlist 5/28, TEI punchlist 6/4.
05/28/21 – GBBN punchlist distributed to contractors. Spencer’s last day on the project.
06/04/21 – ThermalTech punchlist visit complete and distributed.
06/08/21 – Met on Platform questions and generator placement.
06/09/21 – Met Kohler on-site for generator placement questions and code requirements.
06/17/21 – Prosecutor moves into Room #263.
06/22/21 – Met with Fire Marshal on generator placement, code questions and CFD requirements. ThermalTech summarizes meeting notes for CFD, following up on additional research for generator needs.
06/24/21 – Created bollards drawings, sent to Graybach for pricing.
06/25/21 – Discussed resolving the CFD and BPS issues on the generator and platform placement work and needs. Steering committee meeting when very well. FM-200 safety characteristics passed along to committee. If the generator fits on the existing platform and can be five feet from the wall, that is preferred. Add bollards around the platform okay, adding paint for fire proofing on structure okay too, THP to get more info for TEI.
07/06/21 – Const Mtg. Progess continues. We are working on change order items and starting server room demo.
07/13/22 – Const Mtg. Server room demolition continues. Questions from GC, controls and fire protection.
07/20/21 – Const Mtg move to 7/22.
07/22/21 – Full Const Mtg with all subs. We are working on plumbing pan, fire protection coordination, mechanical layout, window removals, schedule, demo and HVAC controls. Server room demo well underway. Work in CMS spaces making good progress and new walls and wall openings are looking good. Follow up meeting with County on reclaiming the HVAC shaft into an electrical room was held. COR sent to Graybach for pricing.
07/28/21 – No const mtg this week. CFD emails resent and permit drawings were sent directly to fire department per their request.
08/24/21 – Weekly Const Mtgs continue. First floor mechanical and fire work continue. Coredrills plans for this week. Patching continues and painting to start next week. The schedule is becoming clearer for Server Room work but we need a decision on the generator placement. Pipe support RFI submitted for comment.
08/25/21 – CFD returned our calls and emails and agreed to our proposals on the emergency generator so we can move forward with moving the generator 5ft away from the building in all directions, no bollards, no painting and fuel oil system is okay.
08/26/21 – Material change order cost submitted for approval.
09/07/21 – Const Mtg. Generator placement and structural changes discussed.
09/14/21 – Const Mtg.
09/21/21 – Const Mtg.
09/28/21 – Const Mtg. Sprinkler piping relocation requested.
10/05/21 – Const Mtg. Condensing units set on platform.
10/12/21 – Const Mtg. Battery charging question.
10/19/21 – Const Mtg. Condensing Unit placement, disconnect locations discussion.
10/26/21 – Const Mtg. Condensing unit orientation, disconnect location picked, generator steel rework finalized. Fuel oil routing discussed. RFIs for electrical (Clean agent panel power and Fiber optic cable selection ) responded to in Procor. Projected date to set the Egen on platform is 11-11.
11/02/21 – Const mtg discussed project updates, fire protection changes for hot aisle design and generator controls meeting.  Working with CDW on Rack order.
11/09/21 – Const Mtg. JCI submitted revised hot aisle fire protection drawing.  TEI approved.  Fiber rating and telecomm wiring discussed.  Generator lift scheduled for 11/11.  DK to complete steel modifications prior to setting the generator.
11/11/21 – Const Mtg. Generator lift schedule in Courtyard.  TEI on-site and logged with pictures and video.  The generator was set without incidence.
11/16/21 – Const Mtg. Discussed next stages of work including CO for armored cable, server rack selections, fiber cable requirements, fuel oil excavation and generator control.
11/23/21 – Const Mtg. Graybach working on updating change orders from the previous PM.  TTC and Reid meeting on CO status. Final fuel oil line coordination discussed.  We confirmed the racks would arrive unassembled to the job site.
11/30/21 – Const Mtg. COR 21, 22 sent in by Graybach this week.
12/04/21 – Fuel oil excavation begins in Courtyard, Geiler working weekends and late nights.  Geiler hit several underground conditions while digging the trench for the fuel oil pipe but in the end the line is in adn it was pressure tested adn held for days.  Geiler backfill adn cover the pipe.  Plates cover the trench.
12/07/21 – Const Mtg.  Fuel Oil line pipe is underground Reviewed Generator controls sequences.  Fuel Oil valves provided by TEI to Geiler for official submittal from WC Storey.  Blacktop and sealing later this week.  Under platform to be turned over to DK next week.
12/09/21 – Several options for temporary boiler power submitted to county for approval by MCB.  TTC and Matt review and comment.  TTC working with Ameresco and feasibility to use new JC steam boilers ahead by Jan 17 to carry the load temporarily.
12/12/21 – TTC working with Bert and Matt on potentially changing the number of server racks purchased and sending out surveys to departments that are interesting in coming over to the new server room.  TTC latest density calculations show that we have plenty of spare capacity even if we reduce the number of server racks in the server room to 22 total racks instead of 24.  Physically this appears to fit better in the space with the latest equipment layout.  TTC to follow up with CDWG.
01/25/22 – Flooring work mostly complete. Generator controls and sequences worked out with Buckeye, testing of the generator tanks can begin. Final piping and fuel oil ties can be scheduled. Electrical outage and temporary power plan in place for Feb 5, 12. Geiler will be back for Gen exhaust and venting work. 9 server racks have arrived and are at the DK warehouse. The CH Server Survey has been sent for distribution.
02/24/22 – Met Fire Marshal on site and got approval for generator and fuel oil installation from CFD. Generator tanks have been tested and passed, exhaust and venting work completed, cable trays are being installed in the room now. Electric work continues, power outages complete, temporary connections made, Server Racks on on site, floor waxing tentatively scheduled for early March, and Server survey came back from CMS yesterday.
03/31/22 – All racks are in the room. Power being pulled to room this weekend. HP was onsite and assembled half the units. HAC coming soon, RFI for new duct size opened. Rack Survey being converted to rack loading. CMS gets 6 or 7 racks in the layout. Equipment startup next week.
04/28/22 – Final electric shutdown is scheduled for this weekend. HPE was onsite to verify missing parts this week and will be back on Thursday and Friday to install accessories. Missing parts are on order (I think). Door access control and security cameras hookup was resolved and email sent. DK to test fuel oil pump system and start coordinating Al Harden field visit for final testing with Buckeye and TEI.
05/25/22 – The contractors are almost complete. Graybach has performed their punchlist review and uploaded to Procore for ThermalTech review. HPE has not given us an update on the warranty replacement parts yet so we are field changing some stuff to make this work out for us when the parts arrive. The Clean Agent system is live and all water removed from the room. Door access and security cameras are on. The facilities switch is programmed with Honeywell IP addresses, we need to get a Cat6 cable pulled from 2 to 5 for Honeywell to communicate. Randy will be back June 6 week to finish up. Liebert startup is being scheduled. Internal fuel oil pump testing next Tuesday with TEI then we will schedule Al Harden for final. Final department survey due from TTC to County. Rack switches were not included in our budget. We should setup a design meeting with CMS about final configuration details in the next couple of weeks. TTC to help provide update at next steering committee meeting.
06/14/22 – Telecomm meeting about fiber interconnects was held with Mitch.
06/17/22 – TTC replaced the warranty items on the server racks and got them to a place where they all work and the HAC is contained.
06/20/22 – The Generator Load Bank testing was completed today. The second fire alarm test was conducted with unsatisfactory results. TEI trying to get contractors to rectify issues and troubleshoot the system. The remaining fuel oil pump started leaking today and was shutdown but testing continued.
06/23/22 – Bert asked about the condenser coil cleaner and protecting the refgrigerant lines.
06/29/22 – A change order meeting was held with the county today to review the cost submitted with change order COR4 for the job. The contractors provide cost and hour backup for their change order COR-4. We reviewed with County.
06/30/22 – Graybach punchlist items are starting to be completed. TEI needs to issue its punchlist this week.
07/27/22 – This month the Facility Switch was installed and Honeywell setup communication was started. The fiber connections are in. The HAC are finished. The fuel oil containment pipe is installed but no terminated. The final generator test is being scheduled for early August. IBI permit for modified grounding is approved and was paid for on 7/26. JCI submitted revised change order for fire alarm devices in the Server Room, DK and Graybach to fully submit.
07/29/22 – IBI Grounding permit was approved today. Information sent to contractors.
08/11/22 – Generator Testing passed city inspection. We still need to connect fuel oil drain line to county detection system.
08/22/22 – We have been working on final change order cost all week adn finalized remaining change orders with Graybach. Sent to County for review.
08/23/22 – Attended change order meeting with Graybach and DK and resolved final change orders with contractors. Worked on finalizing and inspection schedule to wrap this project up with the city and contractors and turn over to the city.
08/26/22 – All inspections to be complete by 9/15/22. Schedule backup testing for the generator.
09/10/22 – Final electric testing scheduled. Kirk key operation tested. All test passed.
09/21/22 – Fire Alarm pretest scheduled with JCI & Dk. Discrepancies found and rectified.
09/22/22 – Fire Alarm and General Const final fire alarm test scheduled in the evening. Final inspections passed.
09/23/22 – Final change orders being collected. Next payapp reviewed.
09/25/22 – CRAC training scheduled for 10/6 with County & ThermalTech.
09/10/22 – Final electric testings for backup power sources. Test passed.
09/20/22 – Final Fire Alarm & General Const inspection. Inspection passed.
09/29/22 – TTC to check on parking lot spaces, coordinate with Tony, Rycca, Matt.
10/26/22 – Clean agent training complete, electric training complete, signs arrived, final cleanup instruction issued to Graybach. Closeout documents coming in for final approval. Floor condition needs to be addressed by Graybach for dents and paint on floor. CMSnet ready for access.
12/15/22 – Graybach says floor tiles are replaced, clean and wax scheduled for this Saturday, coordinating with Jesse on access. Met with Planning & Development, requested data from Facilities on server counts, met with CMS and Telecom on core switching and interconnection. Reviewing and approving closeout documents from Procore.
01/24/23 – Telecomm finishing their work for communications. TTC really needs to get the rest of the departments ready to start migrating to the server room by reaching out to each of the departments. I have been in contact with HP a multitude of times and been passed to two new sales reps trying to find the keys. Birdscreen in production. Labels need to be made.
02/22/23 – Closeout documents are approved, Graybach working on hard copies. Meeting on 2/27/23 for RCIC cutover.
03/30/23 – Signage on switches complete, birdscreen to meet DK on site, O&M one hard copy complete we need two more hard copies for the county, backup generator is below critical high alarm after last weekend work, firmware patch delayed for two weeks for generator comms, surveys sent out to tenants, core switch coming next week, RCIC meeting mid-April with CMS and CAGIS.
04/26/23 – Currently working on telecom communications, decommissioning the Admin 9th floor, repathing the fiber connections, survey final room tenants, applying firmware patch to generator and some controls checking on Honeywell system. We’ve met with CMS, Telecom, CAGIS and City this month several times.
05/21/23 – Several department meetings coming up next two weeks. Most departments have returned our calls and we have space for them in the server room. We are working on getting the fiber cable ran from CH to Admin right now so we can close out.
06/28/23 – This month we finalized meetings with the end users for spaces and confirmed nobody has too much equipment for the Rack they’ve been assigned. We’ve also had several meetings with Debra Kuempel on providing this fiber line but they are not doing the work nor are they giving us a cost to do the work. Our next step is to solicit a price from another vendor for this work. Both CMSnet and Telecom have communications up and running in the server and are ready to start testing communications in the room. Next month we potentially can have equipment in the room full time.
07/26/23 – Fiber meeting wtih DK scheduled for this Friday. Prices came in from Glenwood. We are working with City on their fiber prices.
08/29/23 – City prices coming Friday. Working with P&D, DDS and Risk Mgmt for move-in timelines. CMSnet is in the space and using the system. The second Liebert has been started, the temperatures have been turned down some.
09/27/23 – Risk Mgmt released to move in on their schedule. P&D scheduled to move in October 5. Met with Chris yesterday and measured his equipment and confirmed it all fits in the Rack we’ve designated for P&D. Scheduled a meeting with the Treasurer for Oct 6 for a walk through with them in the server room. All equipment appears to be running and operating properly.
10/25/23 – Room is ready for occupancy. The Emergency Power Off button was accidentally engaged this month. The room was restarted and ThermalTech created as step by step guide for a cold system restart. An alarm Lexan cover was installed by TTE to prevent another accidental EPO. Keys assemblies were removed and given to Acme to match locks and keys, no final word back form Acme yet. HPE can source new locks for about $3500 for 12 (6 front, 6 rear) locks, TTE would install these if accepted but we are hoping Acme can rekey them for cheaper. Jack Wilson at Acme is our contact. Mickey Halls at HPE is leaving the company and we have a new contact to finish the order if we go that route.
12/06/23 – Email to DK and Graybach today about the scope reduction letter. No final acceptance from DK has been forthcoming. We have shared everything the city gave me with Graybach and emailed them an update. HPE has provided the Sole Source letter for the keys. We are in the process of getting a PO for the new keys. Met with City CAGIS this week and showed them the server room specifics and access.
01/31/24 – This month P&D has moved into the server room. HCSO has moved into the Server Room and the final key order was placed and is scheduled to arrive on 3/4/24. The remote temperature sensor is not working for TE.
02/23/24 – Closeout documents updated and turned over to Matt on two USB’s.
03/22/24 – New CMSnet locks are installed on CMS racks. Keys left for CMS and marked for each rack. The new locks are individual to each rack. CAGIS is currently moving over to the server room this evening. Matt and Terry were on site while the movers were onsite. As of 11pm Telecom got communication pathways all setup. Switches are installed, servers are installed, i know telecom can ping the equipment. Just waiting for CAGIS to come back online now.
04/24/24 – Project is complete. Closeout documents are submitted. Ready to Archive.

CH – Server Room Construction Read More »

JC – Pneumatic Delivery System

09/03/20 – SOSS and scope of work discussed for this project.
09/22/20 – Initial fieldwork.
09/23/20 – Pulled drawings from the Archive and scanned them for use on this job.
10/27/20 – Talked to Colombo and got a quote for system replacement, shared cost with county.
12/15/20 – Very preliminary cost and options sent to county and sheriff for review.
12/30/20 – Email summary sent to county and sheriff, repair options and replacement options discussed. TTC reached back out to Colombo for additional pricing on 12/31.
01/26/21 – Recommissioning cost never came back from Colombo, TTC woefully behind on final report to Bert. All work to be bid through this estimate, don’t use trades labor on this job.
02/24/21 – TTC needs to send final report with costs. Not done yet.
03/01/21 – ThermalTech sent Draft Report with costs to the County for review. The recommendation is to bid out the repair of the existing system replacing major equipment but all existing tubes can remain. Colombo sent in additional information for pricing today. TTC reached out with request for full replacement cost.
03/25/21 – Report complete and with the County, Facilities and Sheriff discussing next steps.
04/29/21 – Awaiting next steps.
05/24/21 – Colombo sent an email stating that the replacement carrier they had manufactured is ready for testing. I put us down for one at $350 when they are ready for public purchase.
05/27/21 – County reported the Sheriff has some movement on this project, TBD
06/25/21 – No updates from TTE this month.
07/28/21 – No updates.
08/26/21 – No updates.

10/28/21 – No updates. OK to archive.

JC – Pneumatic Delivery System Read More »

SPHQ – Furnace 1, 2, 3 Replacements

PM – John Nester, Terry Cannon
12/10/20 – SOSS submitted.
12/28/20 – SOSS approved.
01/11/21 – Fieldwork. ThermalTech & Ian.
01/25/21 – Verified furnace units new and old. Talked to Jackson about historical work at SPHQ and what “3” furnace replacement meant back then. He confirmed what we found on site last week. F-3 in the main SPHQ is new circa 2019. F-17 and F-18 are in the Academy and were installed in 2015, 2016. F-19 is in the Fitness area and was installed in 2004. Thse units may a newer condenser. TTE to verify this.
01/26/21 – Reached out to Ian to setup second field trip for TTE to take off HVAC for CAFM drawings and get information on the Property Barn unit so it can be replaced as part of this project.
02/24/21 – Fieldwork and CAD complete on existing Fitness center. Loads complete on all spaces. TTC to review work.
03/25/21 – HVAC design complete, TTC needs to review and share with the County.
04/29/21 – Marked up changes, awaiting CAD changes and TTC will send to JN for review.
05/26/21 – Talked to Ian and agreed that we need to do more fieldwork on the Property Barn before putting anything on paper for that Alternate. Base Bid and Alternates marked up and turned in for edits. I am waiting to get the electrical on board until the HVAC is complete. I am shooting to have this bid out this summer.
06/11/21 – We met on site and discussed basic scope and alternates with Ian and John. It was decided to demo the non-working Reznor unit and replace the three ceiling hung Reznor units on the back wall. Investigate expanding the ductwork in the property barn for additional comfort control as an alternate.
06/25/21 – MEP drawing mostly ready for county review except for the Alternate on the property barn. The Reznor units are obsolete but we found very similar replacement from our local rep. A cost and new venting was provided for our use in the Alternate design.
07/28/21 – Revised design into CAD for final markups. This will go out for bidding in August.
08/26/21 – TTC getting help to finish this project in the next couple fo weeks.
10/28/21 – Project released for bidding. Addendum #1 was issued on 10/27/21. Bids opening 11/08/21.
12/13/21 – Bids were received and Northern KY was the apparent low bidder.  A pre-award meeting was conducted by TTE and NKYHC was recommended for the work  The PO and Contract were approved in late November.  Submittals were sent to TTE and returned on Sunday 12/12 by TTC.  A pre const meeting is scheduled for 12/22 with the County and contractor.
01/25/22 – Revised scheduled sent to County from NKHC for work in February.
02/24/22 – Work is coming along nicely. New furnace is in, two new unit heaters are installed, RTU is on grade.
03/31/22 – Property Barn thermostat replaced and reprogrammed. Temperature swings still happening overnight but we think the unit heater is off. Ian to check for us.
04/28/22 – New thermostat seems to be working fine. Tony asked about heat in garage because door is being replaced and I told him all new units are installed and working. the old Reznor above the bathrooms is defunct and not being replaced. F-3 is complete and working.
05/25/22 – All work complete on the original scope. IBI permitting getting updated by Rick and Holstegge Electric. We are looking at change order work now with Ian and Rick.
06/30/22 – Electric rework is complete. Rick submitted revised change order for new Condensing Units and is fixing a bad fan on one now.
07/26/22 – Change Order #1 was approved and signed for the replacement of two condensing units. We solicited a change order bid for the full ALC control package which came in and was forwarded to the County for review.
08/09/22 – Sent Change Order #2 request to NKYHC for pricing.
08/23/22 – Checked back on CO progress for the condensing units and the reheat pricing. Controls pricing is already here.
09/22/22 – Submittals received from NKYHC. Payapps received and process for payment. Change Order for the condensing units and coils approved. Hot water reheat change order is but not officially approved yet. County working on PO increase for rest of work. Emcor provided reduced prices for remaining control work.
09/29/22 – Meeting on Monday to review change order work at SPHQ.
10/26/22 – Change Order 3 drawing ready for pricing. TTC coordinate with Rick. Permit drawings almost ready to give to rick for permitting on this job. We updated the floor plan to include the additional RHC locations and upsized the piping for the new work.
12/15/22 – Condensers are installed and ready. The initial refrigerant charge is on the new units. We have a controller question on on of the air handlers but both are wired up and running. Additional change orders are out for pricing. Emcor conversion of existing JCI field components came through this week.
01/24/23 – We have been working all week on getting the change order in placed and the submittal for the hot water coils approved. We are working on Rev-3 versions now. All change order #1 work is complete and inspections are approved.
02/22/23 – Revised RHC drawings sent to Rick and CAI for coil sizing and prices with new temperatures and CFM’s. Base bid and change order 1 work is complete.
03/30/23 – Working on repricing the CO#2 and CO#3 cost with Emcor and NKYHC. CO3 came in at $51,000 but ALC offered a $9000 credit for combined work.
04/17/23 – Controls submittals have been received. NM reviewed the RHC, TTC to do the rest.
04/26/23 – Change Order #3 approved for rest of RHC conversion and controls upgrades for the DDC system at SPHQ. The first batch of RHC are here. Check on start time with Rick.
05/21/23 – RHC are in. Piping is complete for all 15 RHC coils to valves . 7 valves are installed. TTE ready to punchlist first phase.
06/28/23 – Punchlist completed and sent to NKYHC. Requested update from Emcor on ALC progress. New compressors need controls update.
07/26/23 – Emcor upgrading controls, this work should be done in August.
08/23/23 – The project is nearly complete, only a couple of controllers are left.
09/27/23 – All work for this project is complete including HVAC, Electrical and Controls. However there are operational issues we are still addressing which include 1) HW pump did not appear to be pumping enough water, contacted vendor reset control sequence. 2) new condensing units did not have the right controller for dual circuit operation, but this is not fixed but led to question in #3. 3) one of the AHU has a VFD on it and NKYHC reset the speed of this fan in the summer for full load but now that it’s fall, they had to reset to fan to a slower speed. We are working on this to fix it for all seasons because it’s too cold in some areas. NKY working on final punchlist items.
10/25/23 – NKYHC is complete and finalizing punchlist. Emcor is complete but controls have not been commissioned. Boiler is going out on high limit. NKYHC has been working on reprogramming the unit with help from Lochinvar. We are meeting Friday to work out control issues with the pumps, boiler and new reheat coils. So far new the boiler had to be reprogrammed because ALC landed new controls on the boiler, a jumper had to be changed on one Admin VAV box, water had to be added to the HHW system. We will find out more on Friday.
12/06/23 – Project is complete and in final punchlist phases. We need to spend some time commissioning with Emcor to get the sequences worked out with them.
01/09/24 – This week we worked on AHU-2 gas heating furnace not working correctly. After several trips and replacements, the furnace is working but may not be working well all the time, the rollout switch was replaced with a non-automatic reset switch, creating more nuisance work for Ian. When the first floor heater is working the building work a lot better. The first floor boiler was not sized for full heating of the entire building, it is sized for heating on the second floor and some reheat on the first floor only. We must have the gas furnace working on the AHU-2 to heat the building in the winter.
01/31/24 – This project is complete and the final programming work moved to SPHQ BAS Recommissioning project.
02/23/24 – Closeout documents sent to NKYHC for use on closeout docs.
03/22/24 – Closeout documents AIA forms sent to County, we need the rest of the closeout paperwork, requested from Lisa today.
04/24/24 – NKYHC doing warranty work on AHU-1 and AHU-4 as part of this project. Emcor commissioning the dual circuit control for the new units. Closeout paperwork submitted to John Nester with a thumb drive. This project is ready to Archive.
05/28/24 – O&M manuals updated and complete, this project ready to archive.

SPHQ – Furnace 1, 2, 3 Replacements Read More »

CH – AHU-B4 Replacement

PM: Terry Cannon, John Nester
12/10/20 – SOSS submitted for approval.
12/28/20 – SOSS approved.
01/26/21 – Kickoff meeting scheduled for 2/2/21 at 9:00am with Jesse.
02/24/21 – Project setup and work underway. TTC and TAB to meet next week on Alternate work.
03/25/21 – HVAC design pretty much complete, TTC needs to review and share with the County for comment.
04/29/21 – Still need TTC review and then to JN for comments.
05/26/21 – Reviewed and back in for editing. Our plan is to have the mechanical and electrical sets in for County review by June 18, 2021.
06/18/21 – Review drawings submitted to owner for final review.
06/24/21 – AIA contracts sent to TTE for bidding purposes and calendar days set at 120 for this job.
07/21/21 – Ready for ITB request. TTC to create project manual and get ready for bidding next week. This project will be bid in August.
08/26/21 – Project will be finalized after JC HVEC goes out for bid.
10/28/21 – Project issued for bids and DeBra Kuempel is apparent low bid. Expectation is to award Base bid, plus Alternates #1 and #2. HCFD to confirm. TEI will schedule pre-award meeting week of 11/1.
12/13/21 – Bids were received and DK was the apparent low bidder.  TTE conducted a pre-award interview with DK and recommended them for the Work.  Contract and PO were submitted for approval and we await their return.  Submittals have been sent to TTE for approval.  The Trane unit submitted has an extra coil access panel that makes the unit longer.  we are going to approve this unit as it provides better maintenance of the unit and doesn’t affect access around the unit.  A pre-const mtg will be scheduled soon.
01/25/22 – Submittal returned for equipment order. Project is ready to begin.
02/24/22 – Controls discussion with Honeywell.
04/28/22 – Const Mtg next Tuesday for full kickoff and construction start.
05/25/22 – Const Mtg was held. DK putting together the final schedule but we don’t have good dates from Honeywell yet. For now, we are scheduling the AHU replacement over the weekend of 6/25. Controls submittal was received, marked up, and sent back to Honeywell but some statements in the sequences didn’t match actual conditions, waiting on revised control sequences.
06/30/22 – Shutdown is scheduled for 6/7,8,9 with County and DK. CH VAV box replacement scheduled the 7/12 at 8am for next phase.
07/27/22 – AH B-4 is up and running. Controls are being upgraded this week and next. Debra scheduled to begin Alternate Work the weekend of August 6.
08/16/22 – DK has made coredrill for new hot water reheat piping and made hot taps for connection to HTX-5 system. VAV boxes are being installed and Honeywell will be right behind them for control work.
08/17/22 – One set of hot taps not on an active line, TTE to investigate. TTC met with County and determined that this was correct, we showed one set of lines coming off the HTX-2 header. We will update the drawings and coordinate with DK on getting both lines fed from HTX-5.
09/22/22 – The unit is installed and working. The programming is not complete yet. The county is working on providing a new data drop near the B-4 unit for Honeywell to finish their programming. TTC met with Ameresco on the solar water heating components because we need the solar water heating to reheat for B-4 courtrooms.
10/26/22 – Honeywell programming and adding three extra VAV boxes on Monday, then the job will be done and ready to punchlist.
12/15/22 – All mechanical and electrical work is complete, and the unit is running. Honeywell scheduled last Friday to make their final programming changes have not gotten confirmation on if that work is complete.
01/24/23 – Honeywell was down last Friday to complete controls on this unit. The labor is complete.
02/22/23 – Honeywell worked on the controls two times and is currently troubleshooting an IT compatibility issues.
03/30/23 – Balance report sent to TTE for review. JN asked for updated PM’s.
04/26/23 – Unit is complete and in use. TTC requested training from Honeywell on new system. It is ready for punchlist.
05/21/23 – Work is complete, TTE ready to punchlist.
06/28/23 – Unit seems to be running well but I need to see the Courtrooms and check unit from front end.
07/26/23 – Punchlist scheduled for 7/27.
07/27/23 – Punchlist distributed to team members.
08/23/23 – No updates on closeout, DK checked earlier this month.
09/27/23 – Still not closed out, nor has DK confirmed punchlist work. We will check in with Dave again.
10/25/23 – DK contacted Randy for closeout documents yesterday. No payments sent until final closeout is completed.
12/06/23 – Trying to get DK to closed this job out. Need documents from contractor.
01/18/24 – The CHW line froze across the driveway. DK dispatched to fix the line and and added insulation and heat tape for future protection. Heat tape not hooked up but ready.
01/30/24 – DK has submitted the closeout documents for this project.
02/23/24 – TTE needs to get final closeout from Honeywell for this job.
03/22/24 – B-4 not on the Bacnet yet but running manually remotely.
04/24/24 – Can’t close out this project unit Honeywell gets the unit back on the front end and under Bacnet control.
04/25/24 – Give this work to Emcor and have them integrate B4 early in the HVAC Controls job. TTC to coordinate between the contractors.
05/28/24 – B-4 is back on graphics. Final closeout documents requested from DK. Some received, but we need the rest.
06/26/24 – Not completely closed out yet. TTC waiting on final documents from DK.
07/24/24 – Closeout documents still not received. TTE reached out to DK and Honeywell for final documents earlier this week.
08/28/24 – We have the G706 and G706A now. We are waiting on the Surety and Affidavits. TTE agreed to create the books, thumb drive and As-Builts.
09/24/24 – Project Closeouts paperwork received. TTC to markup final drawing for As-Built then this job can be closed. TTE has dedicated one person for closeout to help with getting these wrapped up. OK to add closeout time to SOSS.
10/31/24 – All closeout documents received except for as-built drawing that has to be updated by TEI now without the heat tape across the hallways.
12/12/24 – Everything submitted for closeout.
01/28/25 – Project ready to archive.

CH – AHU-B4 Replacement Read More »

JC – Capacity & Recovery REBID

PM: Matt Butz, Terry Cannon
08/27/20 – BOCC agenda has these items on the agenda today. Rebid 9/3, Prebid 9/10, and Opened on 9/24.
09/24/20 – Five bids came in for this job. We are setting up the post-bid interview with the apparent low bidder. The bids did come in under budget and we are hopeful we can award the project.
09/28/20 – Post bid reviews are complete. The meetings went well and additional follow-up questions were answered and researched. Recommendation sent to County by partners.
10/19/20 – City in receipt of permit drawings and examination fees for initial submit from GBBN and ThermalTech.
10/23/20 – Permit accepted by the City and uploaded to their online upload portal. This does not mean the permit is approved, it has just been successfully uploaded for review.
12/10/20 – Triton started submitted paperwork on this job and the safety plan was approved today. The project is progressing forward with early-stage work by the contractor, design team, and owner.
01/05/21 – Team working on permitting & submittals.
01/20/21 – Pre-Const Mtg held at site with Sheriff, Facilities, and Triton. GBBN distributed meeting notes afterward on 1/22.
01/21/21 – GBBN sends a gig letter from City on permit approval.
01/22/21 – ThermalTech and GBBN work on additional permitting requests by the City.
01/25/21 – City says submission is acceptable but we have to take out a third permit for the Courthouse work. TTE tells GBBN that an HVAC permit is not required for that work.
02/05/21 – Plans reviews say approved and “en route”.
02/24/21 – Project submittals underway. GBBN working on permitting approvals. No devices can be supported by the new security ceilings. Jails suggested that we change the shower doors in lieu of a new shower curtain instead of shower door. Filling out a change order for Phase 4 on this job, could save $20k. IBI will be submitted after the building permits are ready.
02/26/21 – GBBN and TEI working with Josh at Triton on security ceiling submittals. We are coordinated access panel locations and attachment methods for in-ceiling devices.
03/01/21 – Permits are approved and ready for pickup on this project. Your permit applications have been APPROVED and are ready for issuance. The permit numbers are 2020P09115, 2020P09116, 2021P01219.
03/04/21 – IBI to require that their Plan review/permitting shall follow the lead from the building department. TEI to submit for (3) plan reviews to get (3) permits associated with the building permits.
03/04/21 – TEI reviewing Camera submittals from Glenwood. Sent the following in email to Glenwood and cc’ed Triton and GBBN. As a follow up to the voice mail that I left for you at your office the other day, I am trying to review/approve the submittals for the security cameras on the Justice Center Capacity and Recovery Project. On the Bill of Materials, the Camera Model Number indicated is a Vicon V804D-W312MIR, however, the cut sheet included is for a V802D-W312MIR Camera. There are resolution differences between these two cameras, so I was wanting to confirm which Camera that you are actually intending to provide.
03/25/21 – Submittals and permitting were worked on this week. TTC has controls submittals to review, talked to JCI yesterday about status. GBBN, Jails, Triton working on keying issues, Const Mtgs to hopefully start early April. GBBN setting up coordination meeting with Sheriff, Facilities, Triton and GBBN to discuss door hardware items.
04/29/21 – Pre Const and Const Mtg #1 held. Equipment has long lead times, limited demo and mobilization has begun. Triton coordinating with CH and JC on Jax area work and beginning const process. Triton to issue Const Mtg from yesterday. A schedule has been issued. All MEP submittals have been reviewed and return. Most GC submittals have been reviewed and returned. Spencer and Josh working on JAILS submittals. Design team to update completion date with Triton for this job as original completion date was July 2021.
05/26/21 – Additional construction meetings were held and demo work is underway in the JAX area. Payapp #1 pencil copy was submitted by Triton and change order work included VAV Access Panels and table top painting.
05/27/21 – Review project handoff with Spencer including change order work for tabletops and HVAC access panels.
06/25/21 – Bi-Weekly const mtgs are being held. Demo is the South building is underway. JAX area is under construction. Medical records move is forthcoming. The schedule not finalized yet due to door delivery unknowns. Lighting installation questions came in this week and Barth instructed Glenwood to install them per the drawings as lay-in fixutres.
07/28/21 – Weekly construction meetings continue. We are having a hard time getting a project schedule from Triton on this job. Triton to provide one very soon. Demo continues but we are getting to the point where new work needs to begin to keep phasing n place. TEI confirmed with Clay Bryngelson of Triton that the schedule was sent to HCFD (Matt and Rycca) for approval and then will issue to all parties.
08/19/21 – Const Mtg held, RFI #4 submitted on shower location. The preliminary schedule is distributed. State officials were down checking on progress.
08/26/21 – Clay and Scott are doing the project management on the JC Recovery project and things are moving along better than before. Plumbing submittal for Drinking fountain submitted and returned. P, we iping specialties submitted and returned. RFI #4 was answered by GBBN. Work continues in the South building. Jax is nearing completion. Exhaust fans can stay in JAX area as is.
10/28/21 – Construction continues with meetings the first and third Thursdays of the month. Core drill issues and location have been coordinated with THP, Triton and TEI. Walls for showers, toilets, and pipe chases evaluated and coordinated. GBBN and THP coordinate the core drill locations. Currently working in SE pod and building walls. Waiting for asbestos abatement team approval. coordinated core drill locations in the SW last week.
11/18/21 – Const mtgs continued every other week with the Sheriff.  Today we discussed progress in the SE pod and coordinate Medical, Jax, and OB/Gyn changes.  Schedule was briefly discussed. Core drill summary discussed and needs to be done.  Jails products need to get on order, current wait time is 14-16 weeks.
12/09/21 – Schedule mtg with Triton.  We discussed updating the schedule to match the July 1 deadline.  Clay provided a revised schedule with July 1 deadline that we review at the meeting.  This is the drop dead date with the County and State for this work.  THP, GBBN and Triton to meet on Friday to review cores.
12/10/21 – Met on site and picked new locations for core drills for SW pad.  We will meet all THP requirements for coreing the floor in this location.  3/4 core drills are moved to make this work.
12/13/21 –  TTC releases field report with notes and questions from the fieldwork.
01/25/22 – Project meeting this week went well. Plumbing and fixtures are being installed and pipe in SE and SW pods. NE and NW demo is underway. Abatement scheduled for this week. The handwashing sink for the OBGYN sketch was sent by TTE to Triton for piping up new location and we will be using the bathroom sink for the main room.
02/24/22 – Triton making progress in the South building. North building core drills are complete. North demo is almost complete. Window RFI submitted and answered for piping. We have a meeting with Triton this afternoon on project issues. We’re meeting to discuss the project specifics this afternoon.
03/31/22 – Southeast and Southwest pods are progressing ahead of NE and NW. The plumbing equipment is installed, electrical coming along, and ceilings coming in next week. NE and NW demo underway, medical wall not out yet. HVAC and controls are started. Window tint was approved last week.
04/25/22 – THP anticipates reviewing core locations for the northeast area the week of May 2nd.
04/28/22 – NE pod verbally approved for rotation of plumbing fixture. COR #8 and #9 submitted by Triton for consideration. Ceiling is being installed in the South building. Medical and medical wall scheduled for demo and move in May. This will allow core drill and final coordination for NW pod in early May.
5/16/22 – THP, Thermal Tech, Triton, and GBBN met onsite to discuss core hole locations for the NW pod. See GBBN’s field report for summary and pictures of core hole locations and discussion. Also, a couple items in the NorthEast pod were discussed: lintel bearing at 4” masonry wall and existing structural bolts through existing column.
05/25/22 – Weekly meetings continue for coordination with Triton on project progress. Significant progress was made in the North building during the past month. Final core drills are complete in the NE pod. NW pod ADA changes were finalizing with Triton, GBBN to issued Bulletin 2A to capture these changes worked out with Triton and County. We need to revisit scheduled completion for this work with Triton at next core meeting.
05/25/22 – THP working on answers for the lintel bearing at 4” masonry wall and the existing bolts through the existing column.
06/30/22 – The South building pod work is making progress. The ceiling grid is installed. The above ceiling inspection did not pass because the latest IBI drawings were not on site. Triton looking to update this. The North building work is progressing as well. Once the masons are done in the NW pod they will move to the NE and relocate the wall. The door installation was moved ahead of the window and windows cuts.
07/27/22 – Progress continues in all four pods. Clay has moved on and Jason is taking over PM duties. We need to update the Core meetings since Clay moved on. Jason emailed an updated schedule for the window cuts and we are working on final details on the order. ThermalTech scanned the pods this month and turned over the scan files to Matt on a thumb drive for their use.
08/04/22 – Window cutting delayed per Triton. “Bad news from Donaly as well this afternoon after they looked at their files on who were badged. One of the people they had badged is no longer with the company so they only have 1 person badged and cannot do the work next week since they only have 1 person. Please notify the Sheriff team that we are on hold until we get them thru the badging process. We will hold off on scaffolding until the work is ready to be completed. I will also notify the rest of my team, including scaffolding. Sorry for the delay in this portion of work. We will work to reschedule as soon as they are badged.”
08/18/22 – Const Mtg. Triton updated us on project progress to date. Scaffoldign arriving next Monday and Tuesday. Triton to coordinate delivery with Sheriff and Facilities. Two hallway door frames are set into place for masons to start blocking in. Triton to coordinate shutdowns with secure access to space during demo & new work. All plumbing inspections are complete and approved. Relocated WC/LAV set into place on relocated wall. Ceilign work is ongoing, all grid is in, working on tiles. We confirmed there is not ceiling on the observation deck on this job. Change order to fix flooring will be approved but Triton has to improve coordination and phasing so it doesn’t get messed up a second time.
08/22/22 – Washer & Dryer and Caulk submittals came in and were sent back for revisions.
09/01/22 – Good meeting with Triton, they are ramping up work to meet deadlines. Jails coming back next week to keep working on ceilings and doors.
09/08/22 – Core meeting, more coordination with Triton and pushing for completion. Washer & Dryer approved with credit for last two years of warranty from Triton. Windows openings are in the side of the building, Triton and Neiheisel are fabricating the weeps and sill plates for modified design.
09/15/22 – Const Mtg at JC, work continues. Floor grinding is starting second shift and Jails is onsite finalizing all work.
09/24/22 – Core meeting. Big discussion on cabinetry and casework. Triton submitted a laminated multi-use cabinet until the SS arrives. This led to a discussion about who is providing the other cabinets in the Observation Shack. After some research, it was determined the Sheriff is providing the cabinets that Triton is not per Alt 2 adn Triton still needs to provide the Multi-Use cabinet. RFI-28 returned on Sunday to Triton.
10/26/22 – Two secure hallway doors complete, two more hallway doors almost done, concrete polishing complete, observation platform almost done, beds are on site, tables at Jails, ceiling mostly installed, HVAC is complete, fire protection is complete, plumbing and plumbing accessories complete. RFI submitted on Deal Tray, RFI submitted on Observation glass. Exterior Windows are the hang up at this time, Jails is not or will not get them installed. Duct cleaning, tunnel repair and first floor finish will be last.
12/15/22 – Work continues on this project on a daily basis. South pod has been punched. TTC to finish his and send all three by end of week. Final windows for North building to arrive 12/28, Jails says they have 4 to 5 days of work left after the windows are installed. Deal trays, sills, jamb covers and door pulls are final details we are working out. Shower heads needs to be repositioned to keep water in the shower basins.
01/24/23 – Punchlsit were completed on 1/19 for MEP and 1/20 for GC. All punchlist sent to Triton. The windows are installed, the deal trays are installed, the bunk walls are done with painting happening now. The scaffolding was removed last week. Teh first floor epoxy was the wrong color. We are down to a new set of “opportunities” to get coordinated with Triton, including cameras, air balance, epoxy floors, sills and jambs. Change Order #8 was approved, signed by TTE and sent to Triton.
02/22/23 – Triton finished all four pods and acquired TCO for all four pods this week. Back punchlist were distributed to Triton for final work. No weld certificate is needed, TTE to tell Triton.
03/30/23 – Working with Triton on matrix issues and a potential change order for reworking the bandwidth associated therewith. Commissioners scheduled to walk the site tomorrow. Terry, Matt, Mike will attend.
03/23/23 – No updates from THP.
03/31/23 – The walk through was canceled. TTC working on Special Inspections with City after speaking to inspector yesterday. Scheduled for 4/14/23 all day with Terracon.
04/10/23 – Door and all hardware is installed in South pod. Triton is working to schedule the painter down to the jobsite to complete the painting of the door. Replacement shower curtains are installed in all pods. Attic stock has all been moved downstairs and placed by the cages as requested by Andy. All Jail Product crates have been removed from the loading dock area.
04/14/23 – Teracon onsite for weld inspections. Public walk through today with Commissioners and City and state dignitaries.
04/17/23 – Pneumatic actuator replaced in SE pod, Triton sent video showing it was working.
04/26/23 – Scheduling building cleaning with Triton and project closeout documents have been sent in for approvals.
05/21/23 – Project is complete and Substantial Completion sent. Window washing starts this week.
06/28/23 – Project cleaning is complete. Closeout documents have been received. Triton has billed for all but retainage. Issues with Jails have been worked out.
07/26/23 – Triton met us on site two weeks ago. As of today, they have not met their cleaner on site to fix the wall streaks. All As-Buit drawings sent in for this job.
08/28/23 – Triton sent request for second camera model for O&M manuals, and cleanign of the outdoor wall.
09/27/23 – Third party cleaning company was onsite today and recleaned the outside of the building with an 80ft crane and pressure washing with chemicals. Final pictures look good. Triton shared final condition today about 4pm. Triton ordered new part for leak on 3rd floor.
10/25/23 – Waiting on Phase 5 approval from State of Ohio. Outside of building is cleaned and third-party cleaning company worked out. Retainage payment signed and sent by GBBN, hold until county satisficed with State Review process.
01/31/24 – Project closed out and all paperwork submitted. Waiting on final certified payroll before we close this job out.
02/23/24 – Closeout complete and drawings submitted.
02/29/24 – Ready to archive.
03/22/24 – TTE requested updated closeout documents and all AIA closeout forms from Triton.
04/25/24 – Triton stopped over to look at floor tile cracks. Tommy believe the sub-floor came loose in only one pod. They will remove and repair under warranty. Champlin to assit ThermalTech in updating CAFM drawings.
05/28/24 – Project ready to archive.

JC – Capacity & Recovery REBID Read More »

Covid HVAC Study

07/21/20 – First field trips for the Covid HVAC study scheduled.
08/12/20 – First draft of the report submitted for review.
08/21/20 – First draft of the report resubmitted and comments returned.
08/20/20 – Started integrating the Portable HEPA filtration units into the report and finding truly equal manufacturers, lead times, and cost.
08/21/20 – Final Study Report submitted to County with floor plans.
08/23/20 – BW asked to break out the building improvements and send to Tony for each building manager. Send directly to Tony Matre.
08/27/20 – Reports were well received with the County. Phase 2 for HEPA placements and safety PM coming up next.
09/14/20 – Sent building reports to Tony Matre and final information to Prosecutor Office. Answered some additional questions for the prosecutor this week and followed up on some additional articles emailed to me.
06/26/20 – Sent touchless water review to County for review of Ameresco proposal.
10/01/20 – Bid questions sent to bidders who submitted bids on the Portable HEPA Units.
10/05/20 – PO was release to the vendor for the purchase of Portable HEPA units.
10/06/20 – ThermalTech released building Recommendations to Tony Matre for Bldg Mgr use.
10/09/20 – Created cross reference guide for filter replacements from Tony
10/13/20 – County asked for SOSS for PM creation for the HEPA filtration units.
10/28/20 – Safety consultant has submitted a price to TTC to update our SOSS for the PM work on this project.
12/04/20 – Talked to Bert and Joe this past week about delivery of the HEPA units. The UV lights are on a delayed delivery schedule. We are seeing how this affects equipment.
12/30/20 – Working on excel format for equipment PM.
01/15/21 – TTC talks to Tim Schuh about setting up unit PM for this job.
01/21/21 – HEPA units are arriving disassembled. Joe sends serial numbers to TTE.
01/26/21 – TTC sends email response to RWL request for BOMA review.
02/19/21 – TTC commissioned Comm Center Unit to final CFM and moved closer to the plug. Gave county option for the longer plug if needed.
02/24/21 – TTC and RAJ commissioned 230 East 9th & 2020 HEPA units. One HEPA at 2020 has been sent back to the factory for repairs. We will be visiting the other sites in the next two weeks.
02/25/21 – BW asked for TTC email to be rolled up into a memo, general update and usage, add Charlie safety to PM, add Komisky report as an appendix to the memo.
03/25/21 – All buildings CX fieldwork is complete. Several units have had additional issues and CAI has visited the buildings to troubleshoot. Two have to be fixed by the factory, one was reprogrammed in the field and that data shared with building managers for future troubleshooting. TEI starting on the final CX summary report.
04/29/21 – Bert revised the worksheet and request ThermalTech to get all final serials numbers for the remaining units. TTC dispatched Ryan to collect the information.
05/26/21 – This month we retrieved the rest of the serial numbers on the HEPA units, filled out, and sent in the equipment worksheet for Archibus. We assisted with some problem units at 2020 and TPC and we visited the Law Library and provided a recommendation on units in the Law Library.
06/25/21 – Final worksheets were sent to the County on Admin 6th floor waiting and BOCC meeting room and 2020 Multipurpose Rooms. Teh final equipment list including missing serial numbers is in.
07/28/21 – DEV PM entered for County review and comments were sent back this week. We are ready to move to actual PM for these entries. LOTO safety procedures can be uploaded as a PDF with the PM to be performed.
08/25/21 – TTC visited 800 Broadway 6th floor today and took field measurements. Created worksheets and sent out floor plan to facilities. HEPA units not required in this space per the existing HVAC serving this area.
10/28/21 – TTC submits recommendations for the Ohio Means Jobs building. All PMs were uploaded to Archibus on 10/5/21.
10/28/21 – Portable HEPA units PM are uploaded and ready for November 1. Tony found better filter pricing for these units.
11/09/21 – Covid report sent to Rycca for A&D 2nd, 4th, and 5th-floor lobbies. None of these spaces required additional Portable HEPA at this time.
01/22/22 – The lower level study for OMJ is complete and we did add one Portable HEPA in this space.
07/27/22 – No updates to the Covid study this month.
02/22/23 – Met with Rycca and Glen on A&D conference room Covid needs. Backed existing unit down to 100 to 200 cfm each per new calculation worksheet.
04/26/23 – No updates but in May the emergency mandate may expire and we will address the use of the Portable HEPA during that time.
05/21/23 – Units were removed from operation this week in some buildings.
06/28/23 – Update Ralph et al. on Covid updates from his email. No changes necessary.

Covid HVAC Study Read More »

Fire Alarm & Sprinkler Testing

07/29/20 – SOSS received for these projects. TTE already about 75% done updating the specifications. We have updated three buildings with new Fire Alarm inventories (A&D, Courthouse).
08/26/20 – TTC to finalize testing manuals this week for Tony review.
09/18/20 – Finalized all documents this week, went over project specifics and update the manuals. Got two new ITB and issued for bidding today. Prebid 9/29 and Bid Opening 10/14.
10/06/20 – Addendum 1 issued. Bid extended to 10/28.
10/08/20 – Addendum 2 issued.
10/23/20 – Addendum 3 Issued. Bid extended to 11/04.
10/28/20 – Questions Due.
10/29/20 – Addendum 4 issued.
12/04/20 – TTC reviewed final contracts several times prior to signature by the contractor. TTC participated in research on the bid documents and called the vendor for a post-bid interview prior to recommending this work. At this time the project is set to be awarded to SA Comunale for both Fire Alarm and Fire Suppression.
12/30/20 – Project to be Archived.
07/28/21 – Rebid complete and final documents turned over to Tony.

Fire Alarm & Sprinkler Testing Read More »

Archibus

11/30/19 – Worked with County to add IGS accounts for gas accounts.06/24/20 – Lots of work on Archibus this month. We’ve trained Sharon and Ryan to help with bill entry. Added the missing constellation bills to 264, 1033, 2611 accounts from the CCAO change. Fixed a myriad of IGS issues from missing accounts and bills. Reconciled the JC account from a missing gas bill in Nov 2019. Fixed 250 WHT from estimated electric bills that showed up in May 2020 for March and April 2020. Provided the regular monthly reports for Bert and Tim.
12/27/19 – Finalized bills and updated monthly reports.
01/31/20 – Finalized bills and updated monthly reports. CH gas has some issues.
02/28/20 – Finalized bills and updated monthly reports.
03/31/20 – TTC working more on Monthly reports and Archibus due to Covid. final reports sent to Bert late.
04/30/20 – TTC continues to work on Archibus with Bracken due to Covid. Final reports were missing data, ttc updated and re-sent reports to bw.
05/27/20 – TTC working on Archibus approval all month. TTC and BDS working on CH gas issues for Dec 2019 and Feb 2020, data and bills need to be updated.
06/24/20 – Archibus was updated this month. We spent time getting up to speed on the new updates, we spent a good deal of time manually creating header blocks for the Bert monthly reports due the Archibus update and we trained some additional people in Archibus usage. A&D and 250 WHT have Covid related billing issues and Comm Center was found to get missing IGS gas bills entered.
07/29/20 – The DOC addin is not online yet so we updated headers manually this month. The A&D was finally reconciled so we will need to input June bill and then unarchive April and May so we can fix these bills. The good news is that the County is getting money back. Courthouse IGS and Duke IT rate bills are goofy but we will figure them out.
08/26/20 – All estimated bills are corrected. Tim contacted TEI about adding the SPCA to the Archibus list of buildings.
09/18/20 – TTE owes county SOSS for SPCA, Courthouse EDI bill messed up again. AD building was estimated.
10/28/20 – Archibus is up to date. 222 Water estimated, 230 water is estimated, Courthouse Water is estimated, JC water is estimated, 800 gas estimated, 2611 Water missing, 2611, 2377, 264 IGS gas August missing. Bert monthly reports are ready for review.
12/10/20 – Archibus reports are being sent out on a monthly basis as usual. The Courthouse gas is being switched to the FT account and should start coming in on the regular IGS bills. several water and gas accounts are estimated presumably because of Covid. This month’s bills are caught up in the queue, several water bills are estimated.
12/28/20 – Monthly Reports sent to Bert.
01/26/21 – Monthly Reports are ready minus the IGS bills for November.
02/24/21 – CH gas bills not right end of 2020, working on EDI tax roll ups, approving regular bills.
03/25/21 – Most EDI bills missing this month. IGS and Duke gas bills are a mess, overbilled in November 2020, TTE to download Animal Shelter bills from Myduke and then enter them as part of last year SOSS.
04/29/21 – 2021 SOSS approved. ThermalTech entered all Animal Shelter bills through February. We are catching up on monthly bills.
05/26/21 – All bills for the last two months and Monthly Reports resolved except the Courthouse gas bill from October.
06/25/21 – This month has had a lot of Archibus activity. The EDI process has been in testing, TTE working on $15,000 utility credit from Duke and IGS finally resolved and the Crime Lab bills were added, checked, and approved in Archibus.
07/28/21 – Meeting with County went well. ThermalTech ready to start entering Water and IGS bills.
08/25/21 – Archibus Water and IGS bills entered and uploaded by ThermalTech this month. TEI uploaded all-electric and gas bills for all accounts this month too. Monthly reports already complete.
09/30/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report emails.
10/29/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report sent late by TTC.
11/30/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report sent by TTC.
01/22/22 – We have been working on the EDI integration with Duke this month and now have weekly meetings on the new EDI process. 29 bills are missing from December at this time and we are having a hard time getting them reimported from Duke. Duke sent a new text file to BRG for import, I don’t know if that is going to work. TEI stands ready to enter them manually if the import does not work.
02/25/22 – Lots of work on EDI bills in new format, fixing and entering new bills.
03/31/22 – meeting with Duke and County bi-weekly for new EDI process. Attended EDI training with County.
04/28/22 – New EDI bills are coming in and they are wrong; too many line items, usage is doubled and we can not access the Duke Portal. This was relayed to the Duke EDI team this morning during out bi-weekly meeting.
05/25/22 – Several Archibus and EDI meetings trying to resolve new billing issues. it’s better but not fixed. TEI manually updating all bills that come in at this time.
07/27/22 – We are still working with Duke trying to EDI billing resolved with BRG and Duke EDI and currently we are still entering most bills manually. After they are approved we are updating almost all lines, and we are entering water bills directly.
10/26/22 – Archibus bills updated as much as possible and Duke billing issues sent to Duke and IGS, big meeting next Monday.
02/22/23 – Archibus being updated monthly and TEI is fixing almost all EDI inputs from Duke.
03/30/23 – Working on final EDI resolution for double counting usages, fixing CH gas and electric bills, Record Center. Working with BRG to fix EDI input adn stop queueing issues. Dane and 111 will not work for EDI.
04/26/23 – BRG updated the macro for importing usage from EDI and the double usage has been eliminated. We have as a group decide not to import the EDI data from small accounts that have combined gas and electric. ThermalTech will enter these directly.
05/21/23 – Many problems still exist in Archibus from Duke bills or EDI entries from Duke but we are down to handling them on 3 or 4 projects. CH, 5035, 250 and Animal Shelter.
06/28/23 – Most problems have been worked out with the module. EDI billing is starting to smooth out. BRG requested to fix new billing lines last month. Combination electric and gas accounts will have to entered manually.
07/26/23 – Met with BRG and County this month to discuss Archibus updates and new version rollup.
10/25/23 – SPHQ and 5035 gas bills reconciled and records unarchived for approval. TTC approved modifying 18 months of SPHQ bills back to April 2022. 5035 corrected bill not as easy to approve, TTC sent question to Duke about rebill estimates. David Hiser is processing a billing records check for us.
01/31/24 – Archibus updates continue to be made on billing and modules. We are still waiting on final updated gas bills for IGS for 2023.
06/26/24 – Some bills still have issues but we are 99% back on track with Duke billings.
07/24/24- No major reported issues this month in billing.
09/24/24 – Duke EDI issues resolved, several bills have late charges and under billed, we continue to roll with the punches.
01/28/25 – Billing errors are begin reconciled with Duke and Dynegy and IGS. Monthly reports are being sent on schedule with specific data.
05/28/25 – Bill entry continues and errors are reducing, I dare say we are almost back to normal. Except JC reported no gas usage in April, Duke and IGS have been contacted.
06/25/25 – Bill entry continues and we are working out problems with EDI. The JC has an errant gas meter reading.
07/30/25 – Bill review going well. Dynegy and Duke have an issue on a bill and Hillcrest has an gas cost recovery issue.
08/26/25 – Dynegy cost misses being worked on with Duke and Dynegy. Duke received approval to recovery missing Gas Recovery cost for a large part of 2025. TTE tracking and predicting cost recovery for HamCo.
09/24/25 – JN asked to update the Siren procedures to start in March 2026.
10/29/25 – Siren PM was rescheduled to March.
12/12/25 – 111 Archibus entered in DEV and ready for review. DEG working on 1701.
01/25/26 – 111 submitted for review on Jan 26. 1701 will be started once 111 feedback is returned and worked on until complete. New access to past PM procedures will help greatly in crafting the new PM’s.
02/18/26 – 111 submitted. 1701 submitted for review and we met twice on conforming the 1701 PM’s into County standard format. Vogt working on updating the worksheet template for this and future project.
02/20/26 – Duke has agreed to separate and create new accounts for 111, 525, 1701 locations. This will eliminate the EDI issues with BRG. We are not sure when this will happen.
02/25/26 – Commodity usage getting double in 2026 again just like 2025, probably a BRG fix.
03/25/26 – DEG & BRG working on Archibus billing issues with Duke. 111, 525, and 1701 bills have been separated into electric and gas bills. We are working on organizing and getting into EDI the data and processed through BRG.
04/29/26 – We are working on March bills now for reports. Hillcrest access was granted this month and Duke fixed access to the newly separated bills for 111, 525, and 1701. Those should be entered soon. We will verify.
05/27/26 – Working on revised 1701 PM list with Robert and Tim. All other reports submitted on scheduled. Good month for billings.
06/25/26 – DEG to update1701 PM import, working with Tim on fixing bad data import. DEG to verify more equipment in field, need more time at building and with BMS to get additional data.
08/26/26 – 1701 Import template sent to County for final review. Working on Hillcrest export for Hillcrest start of work.
10/26/26 – 1701 has been finalized with edits and tweaks along the way. It should be final, final, final, final now.

Archibus Read More »

TPC – Community Development Relocation

ThermalTech Led, IPM sub
02/26/20 – TEI Authors SOSS for a new project to relocate Community Development from 10th floor to 8th floor of TPC.
03/26/20 – TEI receives signed SOSS and PO. HCFD working with IPM to program space and then IPM to send the layout to TEI for electrical design.
04/30/20 – TEI and JP visit project site to look at power/telecom existing conditions.
05/27/20 – Project release pending COVID-19 restrictions.
06/23/20 – Project release pending COVID-19 restrictions.
07/29/20 – No updates this month.
08/26/20 – No updates this month.
09/18/20 – No updates this month.
10/28/20 – No updates this month.
12/10/20 – No updates this month.
12/30/20 – TTC archiving this project for 2020.

TPC – Community Development Relocation Read More »

250 WHT – Booster Pump Replacement

01/22/20 – TEI fieldwork visit and researching equipment options.
01/30/20 – SOSS submitted and original fieldwork completed.
02/24/20 – SOSS submitted awaiting approvals.
03/23/20 – Project ready for review. TTC will send to county for review. New booster pump is 100% redundant but new pumps are 5HP. Barth confirmed conduit and feeders still sized properly for new loads.
04/16/20 – Bids received from Peck, Geiler, Triton and Debra. TEI tabulated and sent to the County for decision.
04/28/20 – TTC released bid tab to bidders. Did not tell bidders who the winning bidder is.
04/30/20 – PO in for approval with County, looking at weekend work for this job.
05/27/20 – Project in for approval with the County for weekend work with PHB as the apparent low bidder.
06/24/20 – PHB sent the submittals in on the project. ThermalTech reviewed and sent back to the vendor including limited comments from the County. PHB working on background checks with BC who is helping get them onsite to the work ASAP. Unfortunately, the lead time on the pump package is 5 weeks at this time because we missed the “on shelf” package they had waiting for us. The hope is to get this installed ASAP.
07/24/20 – PHB has scheduled the pump replacement on August 8 with the backup date of August 9. They have not however received their PO and Contract yet. TEI check with Facilities and it is in place and Tony will send it. PHB will install the pumps and get them working on the weekend BAS interface and local alarms will be picked up the next week by Peck.
08/26/20 – Peck performed the work over the 8/8 weekend. The new booster pump is working and online. TEI issued Punchlist for the project to PHB with remaining work items. Payapp #1 was submitted and approved. Final payapp was submitted but held for closeout documents.
09/16/20 – TTE on-site performing Records Drawing check. Some piping needs to be changed on Record Drawing and CAFM drawing.
09/18/20 – OM’s delivered. Punchlist work complete. TTE to approve the final invoice and send in the final paperwork. Project ready to archive.
10/28/20 – TTC checked in with PHB to ensure all payments have been made and project can be closed.

250 WHT – Booster Pump Replacement Read More »

CH – Plumbing Repairs

08/08/19 – TTE sends SOSS to County as F-119.
10/05/19 – Bert inquires about deadline for bidding documents for this job. TTC sent review set and believes TTE can be done 10/31 with this work.
10/29/19 – Jessica send email about status of project and will be the PM moving forward on this work.
10/30/19 – Coty is onsite during afternoon finalizing access panel locations for bidding.
12/11/19 – Bids were sent out to Triton, Geiler and Debra and came back with two bids and a no bid. ThermalTech discussed the project with Triton, the apparent low bidder who seems to have everything covered. Bid tab and Bids forwarded to County for approval.
01/24/20 – Triton has submitted bid documents to the County and contract and PO paperwork is being drafted.
01/30/20 – Triton sent back signed contracts to County.
02/20/20 – Pre-Const Mtg held with Triton. Meeting notes sent on Monday, need to get Emergency Contact list sent to Jessica. Triton ready to mobilize on Monday afternoon to see the job. Background checks need to be complete before they can come on site.
03/23/20 – Triton has a couple of people with background checks and has been down on the initial field trip. Actual project start may be delayed.
04/29/20 – Triton was supposed to be on site last Monday, TTC to follow up with Brian Day on update.
05/08/20 – Project schedule adjusted for personnel availability, looking towards end of May for work.
05/26/20 – Triton and the County set the additional isolation valve work for Friday May 29,2020. Triton to arrive on our about 3pm and work in the evening for the new access panel and valving. TTC plans to be onsite for questions and answers.
05/29/20 – Met Triton onsite for the work and ran into several issues. (1) the hot water valve was not close enough the access panel to meet the dwg requirements. (2) the cold water valve location was not acceptable given the marble façade that would have to be removed to install it’s access panel. We worked on other acceptable locations with Triton and BC while on site. We all decide that given these two issues, we would call off the shutdown and drain tonight and regroup with a new plan later.
06/12/20 – Triton and BC selected a new location on the second floor for the CW valve, they sent info to TEI for consideration.
06/19/20 – Went to the building twice this week to research new locations for the hot water valve. We didn’t take the Triton suggestion for the second floor but we did find a location on the basement floor where an existing valve is already installed. TEI sent emails and photos to the county for discussion and decisions.
06/22/20 – BW sent an email for an update and TEI followed up with Triton and the County on possible new location. TEI and Triton to meet onsite to discuss. County to decide about two valves in series or remove the gate valve.
06/24/20 – Talked to Triton today about getting a change order for this work and they are reporting they’ve spent $5000 in investigation extras on this job. We are coordinating our next visit down there to finalize this job.
07/17/20 – The new City Water valve was installed on 7/17. The first 4″ valve leaked and Triton had to secure a second valve at a supply house in town. That was installed and the work was complete about 11:30 pm. TTE arrived about noon to survey the piping and prove out the hot water line before Triton arrived for work. After 3 or 4 hours of additional confirming of the water lines using temperatures and more measuring the hot water and hot water recirculation lines were again confirmed to be where we thought they were from the previous fieldwork. After the building shutdown however we found the hot water was still pressurized after the main shutdown. Further investigation showed that the hot water recirc was backfeed the hot water main creating a second path through the PK water heaters (somehow bypassing the check valve, mostly likely stuck open). It as proven in the field that to shut the hot water down to the floors both the DHW and DHWR should be turn off. Ancillary to this work we found the PK heaters powered down, so we closed the valves serving the PK heaters too. We found the PK DHWR pump burned up so we powered that down as well. The new pump installed on the AO Smith heaters will serve as the new DHWR pump. When the water turn back on we tested the new CW isolation valve for the upper floors. Half of the floors were off and some were still running. After some additional field investigation, we found another valve that serve one back of public restrooms in the northeast corner of the courthouse. This valve must be shutoff in conjunction with the new valve to isolate the upper floors from lower floors. In the end there are two hot water and two water valves to shutdown the CH upper floor water systems.
07/28/20 – Triton sent a drafted letter confirming the piping found behind the walls in the 3rd and 4th-floor restrooms was indeed brass not galvanized. A change order request was sent to replace the quarter-turn valve found in the NE corner with a chain operated ball valve.
08/26/20 – Change Order #1 was processed for a deduct to the project. TTC and Bryan going to meet on new valve location tomorrow and we are working on the final schedule to wrap up this project work on the 6th and 7th floors.
09/18/20 – Triton on-site tonight finishing up the project. Jax area completed about 6:30 pm. Basement valve installed by 8:30 pm. Triton had to use one 2.5″ coupling and one 2″ cap from the plumber shop to complete the job. Water back on and everything working – no leaks.
10/28/20 – Work is complete, punchlist is distributed, another payapp was approved. We are waiting on insulation and chain operators to wrap this project up.
11/02/20 – County confirms punchlist is complete, insulation installed and chain operators installed. TEI asked Triton to close the project out ASAP.
12/10/20 – Project is completed. Final paperwork is coming in from Triton for closeout.
12/29/20 – Closeout documents from Triton came in today. TTC will review and begin closeout.

CH – Plumbing Repairs Read More »

800 – Fire Pump Study

10/19/19 – SOSS received and ThermalTech onsite for fire pump testing. We witnessed the fire pump test by SA Comunale and they stated that the fire pumps passed with both city water mains open.
10/30/19 – Terry and Cai met to review the model and report. So far the model is working and matching existing conditions. Cai did a great job interpolating the existing pressure drops from the field data we collected. It is our initial view that both city water mains need to be open for the fire pumps because of the large pressure drop across the BFP’s. WE have to get the mfgr data to confirm this. We also are setting up additional testing with CDFP for more field test.
12/12/19 – No new updates this month.
01/24/20 – This project can be archived in lieu of the City Water Main replacement which has been submitted for Bidding & Construction.

800 – Fire Pump Study Read More »

Animal Shelter – Due Diligence Study

10/28/19 – Champlin, THP, and ThermalTech meet on site at the Hamilton County SPCA for a building tour. We toured the facility to see existing conditions and meet with representatives from the ASPCA and SPCA to discuss requirements for animal shelters. TTE has the existing drawings for scanning.
12/11/19 – The teams revisited the project site last Friday, THP on Monday. We are creating the estimates and report scope this week in advance of turning over the final report and estimates.
12/12/19 – The team discussed what to put in the report for Bert and in current population and code population. This report is supposed to discuss if the County should renovate this space for the new code requirements for canine’s. The county is not actually responsible for the cat population. #1-Renovation Cost, #2-expand to code population needs, #3-New Renovation Cost? We are to send all summaries to Kru at Champlin. BW said he really needs this next week. BOCC terminated SCPA agreement this year and are now looking for keep SCPA services. Provide draft by 12/19 to County.
12/20/19 – All partners have submitted cost and write-ups to the County. The County is working with CA on new building cost estimates and any updates that might be associated with square foot cost. The Renovation/Upgrade of existing facility cost seemed to be within expected ranges.
12/13/19 – THP reviewed budget for reduced repair scope project and discussed with CA.
12/16/19 – THP had conference call with project team to discuss repair scope.
12/18/19 – THP finalized draft of building envelope assessment report and emailed to project team for review.
12/19/19 – THP finalized building envelope assessment report and issued to CA.
01/27/20 – All information submitted to the County in December, will check on any additional updates at this months meeting.
02/20/20 – No updates this month.
03/23/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
07/29/20 – Emailed Tony all the scanned drawings we have of the building.
08/26/20 – This project picked up a little bit this month in answering some building questions and discussing adding it to Archibus.
09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – OK to Archive.

Animal Shelter – Due Diligence Study Read More »

JC – Water Heater Replacement

07/11/19 – ThermalTech sends SOSS to County.
08/21/19 – County Issues SOSS and PO to ThermalTech for Work.
10/21/19 – Project Issued for Bid.
10/28/19 – Prebid is held for project.
12/12/19 – Project is in for contract and approval. County reported contract is with the vendor awaiting signature.
01/17/20 – Pre Const Mtg was held and project notes distributed. Submittals and schedules requested.
02/24/20 – Geiler started putting submittals together but we have not seen the schedule or SOV yet for this project. TTC to check in with Geiler on Schedule. The Water Heater submittals look great.
03/23/20 – Permit drawings sent to Geiler for permitting. Geiler says deliveries are running slow due to governments shutdown, getting updated delivery for this project.
04/27/20 – TTC working with StreamKey on new PK-4 heater because a discrepancy was found between the size that the original engineer had for this HTX and what the factory gave us last year when checked. The steam control pieces can be return for closer equipment. TTC to discuss with Tony.
05/25/20 – Due to a HTX failure on PK-2 the new PK heater was installed in place of PK-2 this month and is up and running (so PK-1 was installed in the PK-2 position). Which is okay because they are the same heaters. The mall gasket leak on PK-1 that can now be fixed at the County’s leisure. The new steam control valve for PK-4 is in stock and will be getting replaced shortly by Geiler. The PK-4 shell is already installed but not operational at this time PK-5 must continue to cover the load. The steam control valve upgrade for PK-7 is complete.
06/23/20 – Geiler finished the insulation last week on the final unit. All system seem to be up and running well. When the buiding reopens to TEI, we can do a final Punchlist. Reports from the bldg staff are good.
07/29/20- Approved all but final of Geiler payapps for this work. TTE awaits access to the building for the punchlist work.
08/26/20 – Punchlist for heaters needs to be distributed. TTC using Coty Groeschen field trip for writing the JC Water Heater Punchlist. I will try to get this out this week.
09/18/20 – Project is complete, ready to archive.

JC – Water Heater Replacement Read More »

JC – Cooling Tower Refurbishment

07/11/19 – ThermalTech Issued SOSS-F-113.
08/21/19 – County issued SOSS and PO to ThermalTech.
10/21/19 – Project Issued for Bidding.
10/28/19 – Prebid held for project.
10/30/19 – TEI working on Addendum 1 questions.
12/12/19 – Project is in for contract and approval. County reports the contract is with the vendor.
01/21/20 – Pre Const held with Andy, TTC and Triton.
01/28/20 – Pre Const meeting notes distributed. CO costing approved by TTC to Marley.
01/29/20 – Triton sent in SOV, project schedule and submittals.
02/24/20 – Triton really pushing for background checks, Tony to check on Monday and let us know. Triton needs to get started very soon to have any chance of getting done even by April 15.
03/24/20 – Triton emailed today that the project has been put on hold for this spring and summer and it will be done in October 2020 due to the government shutdown and delivery orders.
04/27/20 – Material has arrived at Triton. Pictures were sent to ThermalTech for approval for payment of stored materials. Covid-19 has this project on hold for the time being.
05/27/20 – No additional updates this month due to Covid.
06/23/20 – TEI updated the submittals and sent to Triton for the job. Block fill is in the Triton yard and awaiting installation in November 2020. There were a couple of items on the submittal review that Triton will check on with the mfgr. Brent Ernsthausen and Clay are our new PM on this job.
07/29/20 – Triton and Brent back on job, TTE caught up on prep work for these towers with Brent for fall work.
08/26/20 – Discussed paying Triton payapps based on equipment stored in their yard. TTC sent photos along with approved payapp.
09/18/20 – Allowance Usage #1 email out and signed by TTE and Triton, we are awaiting final approval by County.
10/28/20 – Pre Const meeting moved to 11/4/20 1:00 pm.
12/10/20 – CT#2 demo is complete. Crane is scheduled on 12/19 with a street closure anticipated. Triton keeping us up to date with email updates from Clay. The project is proceeding along nicely.
12/28/20 – Verbal approval on extra work for cooling tower C-3 replacements was given. Triton continuing work on the towers and order for new galvanized pans was placed with Stoermer.
01/26/21 – Triton continues to grind out the towers and prepare them for rebuild awaiting the parts from Stoermer for rework on the towers.
02/24/21 – Triton stopped for the cold but now back underway. Tower completion should not be an issue.
02/26/21 – Sealing was completed yesterday. With sealing completed, this has allowed us to install the nozzles and piping back into the towers. We are scheduling the alignment for the gearbox. We will begin the fill next week and should be completed next week as well. We will do the clean off of the roof the following week.
03/25/21 – Triton wrapping up final CT work with the hopes the towers will be ready to fill next week. They are working on the gearbox connections this week.
04/29/21 – Triton complete with all work. ThermalTech issued a punchlist to Triton for this project. There is a low water level alarm reporting back to JCI that is in alarm.
05/26-21 – Allowance #1 & #2 out to Tony for signature for the allowance usages related to the interior pans and repairs. There is a small amount that has to be paid as a change order to the job for extra work on the four pans repair, this will now include the level water floats that monitor the basin water levels. Triton has completed and returned the punchlist for this job minus these final items. Triton will purchase and install the floats in the next few weeks.
06/25/21 – New water level valves installed. Triton fixing final leak on CT. Closeout paperwork started. We need Tony to approve and sign allowances and change order #1.
07/28/21 – Project Complete.

JC – Cooling Tower Refurbishment Read More »

Comm Center – Temp Trailer Due Diligence

05/21/19 – TEI to study feasibility of adding a temporary trailer behind the building for additional office space.
07/25/19 – TTC to submit an SOSS for this work.
08/28/19 – No updates this month.
09/24/19 – No updates this month.
10/30/19 – No updates this month.
01/24/20 – No updates this month but officials are started to ask about starting this study.
02/24/20 – No updates this month.
03/24/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
06/25/20 – Archive for now, if the project comes back we will bring it back.

Comm Center – Temp Trailer Due Diligence Read More »

Burlington – HVAC Upgrade

09/14/18 – ThermalTech contacted to provide HVAC study at Burlington Garage.
09/20/18 – ThermalTech has Monnit sensors on site for space and humidity monitoring.
10/05/18 – ThermalTech issues final study of space conditions with recommendations for better space and humidity controls.
11/01/18 – ThermalTech issues Small Project Manual for bidding to local contractors for HVAC work.
11/26/18 – ThermalTech issues Bid Results to County.
12/03/18 – Engineer’s Office issues PO to winning bidder for the project.
01/16/19 – SOV approved for NKYHA and the work should begin shortly.
04/03/19 – Project punchlist issued to contractor for Work.
04/25/19 – Review work with County and NKYHA, final changes and adjustments underway.
05/29/19 – ThermalTech created Temperature Trend worksheet and emailed to Tony and Mike.
06/03/19 – ThermalTech issues weekly summary showing temperature and humidity’s are within limits; confirms that installed equipment appears to be operating correctly. TEI has not been on site to witness the workings of the dehumidifiers and RAWAL valves since the 4/25 field visit.
06/26/19 – ThermalTech issued temperature and humidity trends for the building. Everything looks great and all systems are go. We will continue to monitor until July 31.
07/25/19 – ThermalTech adding Monnit sensors for additional trending. Spaces look okay but discharge temperatures and unit temperatures not matching up.
08/28/19 – NKYHA added refrigerant to the Admin unit and TEI pulled out the Monnit sensors after several weeks of good data. Everything appears to be work okay. Humidistats were set to 65% so the units could do the majority of the dehumidification. When the separate dehumidifiers operate they discharge 100F air into the space as part of the dehumidification cycle making it harder for the split systems to maintain space temperature.
09/12/19 – Mark called to say NKYHA sent a payapp in with no signature. I told Mark to forward it to me for payment, but Rick sent it to me and it was wrong.
09/24/19 – Ready to Archive this project. Rick owes the County one more payapp because I rejected his last payapp because it had the wrong amount on it.

Burlington – HVAC Upgrade Read More »

CH – CMSnet AD Migration

PM: Terry Cannon, Bert Watts
03/08/19 – TEI met with CMSnet for a scoping meeting on the AD Migration Project and submitted an SOSS for the project.
03/20/19 – SOSS approved by County.
04/15/19 – Coordinating design meeting times with CMSnet.
05/15/19 – Attended CMSnet quarterly PM meeting and kicked off project with departments.
05/20/19 – Sent Purchasing a review set of documents and front end with dates which they approved in general. Need to finalize bidding schedule with CMSnet.
05/21/19 – Met with Conexio after 5/15 and discussed scope, schedule and work required for bid.
05/22/19 – Found two additional Novell to AD migration experts, invited them into ThermalTech to discuss means and methods of project.
05/23/19 – Internal meeting at ThermalTech to convert this job to a perform.
05/24/19 – ThermalTech forwarded review meeting books to Stephanie because Shannon is out.
05/28/19 – ThermalTech rewrote the specs as performance specs after meeting with CMSnet. TEI setup meeting to meet with specialist on Monday June 3.
06/20/19 – Met with specialist earlier this month and asked for some bidding data from them. Did not receive anything back. Circled back and checked with them again today.
06/27/19 – As of today nothing back from any third party vendors in the way of helping the bid but companies are interested in bidding the work. TTC will have final review specs next week for CMS review.
07/24/19 – Final RFP sent to Purchasing and CMSNet for approval.
07/25/19 – CMSNet sent back comments this morning. TTE will pick these up with the hopes of releasing this document on 7/31 as scheduled.
08/28/19 – CMSNet review book sent back with new dates and schedule. We are awaiting new comments from the department heads and approval of the new bidding schedule form CMSNet.
09/03/19 – Received email and comments back from CMSnet on the RFP document.
09/24/19 – Made comments and submitted back to CMSnet for approval.
09/25/19 – Talked to Shannon Supe to setup a meeting for final schedule on Friday for bidding out this project.
10/04/19 – Project Issued for Bidding. Bid Opening scheduled for Nov 7, 2019.
10/24/19 – Add01 Issued.
10/30/19 – Add02 Issued.
12/12/19 – One bid was received and eventually rejected by the County. We have submitted a small SOSS to cover the time to solicit State Term of GSA type contracts for mid January 2020.
01/24/19 – ThermalTech making final edits for rebidding through STS currently, will send to Shannon for final review this week.
02/20/20 – Met at CMSNet PM Mgr meeting and discussed final review of revised GSA STS bidding. Ready to bid after final remarks are picked up on bid documents.
03/23/20 – Final review document sent to CMS, checked back 2 or 3 times for final comments.
04/29/20 – Final review document sent to CMS, checked back 2 or 3 times for final comments.
05/25/20 – Talked to CMSNet this month and the releasing of this proposal is on hold pending funding for the project. ThermalTech is holding the project manual for bidding for the time being.
06/23/20 – CMS contacted TEI today for a refresh of this job. We sent a review set back to CMS and contacted the vendors about bidding the work. There is still interest in this job so this is good news.
07/29/20 – TTE followed up with CMSnet several times this month for progress update. We await the comments and dates on our final package submission.
08/26/20 – TTC checked back with CMSNet for updates.
09/18/20 – TTE wrapped up final markups on specs and will send for bidding next week.
10/28/20 – Bid packets sent out through ThermalTech for GSA pricing only. ThermalTech is managing the bid for the County. Three vendors are interested in giving us a price for this work. CMSnet currently reviewing the packet for current submitted questions. There was a misunderstanding on the timing of the bid which ThermalTech and CMS are working out currently. Addendum sent to extend the bid to the end of November and installation in mid to late 2021.
12/10/20 – We extended bid out to after the first of the year. No other updates.
01/26/21 – TTE suspended bid with vendors, contacted CMS and said that we are ready when they are ready. Until then on hold.
03/25/21 – No updates.
04/29/21 – No updates.
05/26/21 – No updates.
06/25/21 – No updates.
07/21/21 – Shannon said the contract is at Prosecutor for review, just waiting on feedback.
08/25/21 – No updates.
10/28/21 – No updates.
12/03/21 – No updates.
01/22/22 – No updates.
02/22/22 – No updates.
07/27/22 – Shannon emailed this month. We will work with Jeff Roy to update this bid packet for bidding. CMS may run the bid this time.
09/22/22 – Ready to Archive.

CH – CMSnet AD Migration Read More »

800 – City Water Main Replacement

12/15/18 – TEI spoke with CWW on adding new city water main and abandoning old main underground. This seems to be an acceptable solution for everyone.
12/31/18 – SOSS approved, ThermalTech can start design for replacement.
01/31/19 – ThermalTech has completed several field trips for this work and worked out replacement with the CWW for this job. THP will provide notes for sealing up the wall after piping is removed. We will try to have ready for ITB and bidding in early February. We will get prices now for Facilities to see about funding.
02/28/19 – Project updated with revised scope and sent to Bert. TEI met with GBBN and THP to discuss their role in the final TEI drawings and got some information about how the project will work. TEI to update drawings and cost estimate with final scope.
03/21/2019 – THP Finalized foundation repair detail and related specification sections and emailed to TTE for review.
03/27/19 – THP submitted drawing package to ThermalTech. TEI incorporated details into job and updated floor plans. Final review set going out this Friday.
04/24/19 – Prices submitted, project awaiting approval by County.
05/28/19 – Project on hold awaiting release by the County.
06/27/19 – Project on hold pending funding.
07/25/19 – Project on hold pending funding.
08/28/19 – Project on hold pending funding.
09/25/19 – Project on hold pending funding.
10/30/19 – Project on hold. Fire Pump Study working on peripheral items associated with this update.
12/11/19 – Project on hold.
01/24/20 – Project SOSS for Bidding & Const submitted to County for approval. Drawings are pretty much ready for bidding upon County approvals.
02/20/20 – SOSS and PO forthcoming after speaking with Facilities. TTE should prepare the bid document work in Feb/March.
03/23/20 – Final review drawings are nearly complete. TTC need to check over and send to Tony.
04/16/20 – Drawings will be sent to Tony Matre for final review by May 1. Spoke to Tom Frimming about pump requirements and new water main installation for this job; forwarded those comments to Tony for review.
05/27/20 – Final markups not included yet from TTC markups. I am thinking that I will pick up the final markups myself beyond this markup set but I do need to send Tony his final dwg set for his markups.
06/23/20 – Project on hold awaiting funding.
07/29/20 – Project on hold awaiting funding.
08/26/20 – City performed work in the alley this month for new sidewalks, curbs and concrete. TTC measure the depth of the city water line while the alley was demolished. The piping is 19″ below grade with the alley removed and potentially another 9″ below the landscaping in front of the 800 Broadway building.
09/18/20 – No updates this month.
10/28/20 – No updates this month. But we did refresh the drawings a little bit and try to improve the PID.
12/10/20 – Tom F called to say that SA Comunale ran the annual fire pump test last week and the building does not hold on one water main. TTC reached out to Daryl Meadows at the CFD about what the Fire Watch would include during the City Water shutdown and TEI will update the drawings accordingly. Also, however, TTC reached out to SA Comunale for the actual failure points. The low water cutoff means (i.e. if the pump can’t pump 125% of the flow, that doesn’t mean it can make 100% of the flow and that may be critical in the fire watch work over the weekend). The sensor turned the pump off before the pump reaches maximum by design.
01/25/21 – TTC sent latest drawings to Nester.
01/26/21 – TTC printed out final set, met with TAB to start final layout, planning on having review set to County on 2/5.
02/24/21 – Project going to bidding today with a prebid on March 12 and a bid opening of March 31.
03/22/21 – Addendum #1 issued last Monday. TTC has been coordinating with CFD on alternate methods to keep the fire pump running while the work is completed but no definite direction was agreed upon between CFD and ThermalTech so the fire watch will remain in the base bid and used for this project. Add 2 will increase the budget to $100,000. The final Addendum is due today.
04/29/21 – QCM was apparent low bidder on project. ThermalTech held a post bid summary with QCM and recommended them for this job. Base Bid and Alternate for Fire Tee accepted, contract in for review.
05/26/21 – Final contract sent to QCM. Site Safety, safety, and tax-exempt certificates have been shared. We are ready for a pre-const meeting with Facilities and QCM.
06/17/21 – Kickoff meeting with contractor on-site at 800 Broadway. Schedule, submittals, SOV, background checks all requested from QCM. TTE to submit plumbing drawings to city for permitting with QCM.
07/28/21 – Waiting on QCM background checks to clear so they can do the work in August.
08/06/21 – QCM preparing project site.
08/10/21 – Trench work underway and mostly done. Fire watch set for Saturday.
08/12/21 – Final connection work at CWW tee has issues. TEI on-site surveying the issues. New water line cannot be connected to existing water line with Duke electric duct bank in the way of our water line. Weekend cutover postponed to Aug 20. Hydro excavating is scheduled for Monday.
08/16/21 – Hydro excavation revealed more pipe, valve, and tee structure. QCM is not comfortable connecting any of the existing piping and suggest getting CWW involved to allow us to replace the valve and tee. TEI working with CWW on solution and approval.
08/22/21 – Working with CWW to resolve the new connection.
08/24/21 – Approvals received from CWW on replacing CWW valve and tee to extend out new water main into the building. QCM change orders received.
08/25/21 – QCM remobilizing for rest of 800 work. Valve and tee on order.
09/27/21 – CWW permitting discussions went well. CWW process requires fire calls. TEI to reach out to city to get the original 1992 fire protection calcs.
10/15/21 – TEI reached out to Dalmatian, Dalmatian fire companies for original calcs. Dalmatian reported they don’t have them. TTC asked a local fire protection to help with the calcs if we can’t find them, they will help.
10/22/21 – City came through with 800 permit drawings from 1992. They sent us over 1000 files and Coty found the fire calcs in the downloads. We are working on fixing the contrast so we can submit them for this job. This is good news.
10/28/21 – We are working with CWW and City permit office to submit a FA Calc plan to city and CWW for approval of changing the fire pump feed. We have the city permit documents and found the original calcs. We will get this out in a week.
11/23/21 – ThermalTech working with City and QCM for revised fire protection piping change for fire pumps. GCWW rejected the first permit application due to non-licensed plumber being selected in the application process.
11/30/21 – GCWW permit has been resubmitted to the water works. No update on city permit status yet.12/01/21 – Weekend work postponed for approved city and GCWW permit.
12/08/21 – TTC spoke with GCWW on permit and it is on hold until the city water main can be brought up to current standards. TTC emailed John and Rick and needs to set up a follow-up call with John about the feasibility of the GCWW request.
01/25/22- TTC needs to update the drawing for the GCWW review for the remote valve they want on the property line. TTC going to do his own cad for this work.
02/24/22 – Revised drawing is ready for review. Rick Seaver has left QCM, TTC will call and coordinate with Bryan Gilbert who is taking over for Rick.
03/31/22 – Drawings and study complete.
04/28/22 – No updates this month, try as I might.
05/25/22 – Met with the GCWWW last week on potential updates to give them what they want on this job. They will not accept either of the proposals that we gave them to modify the fire and domestic water feed. ThermalTech working on acceptable domestic water solutions that gives the county some savings for the cost needed to meet GCWW requirements.
06/25/22 – Created change order drawing for QCM to provide pricing on city water valve option.
07/22/22 – Change order received from Queen City and forwarded to the County for consideration.
08/19/22 – We are moving to close out the project. We are getting final prices from QCM for closeout. TTE working with Bryan on closeout documents.
09/22/22 – Keeping this open for QCM to do some selective valve replacements at 800. Coty working on the final list and cost for us.
10/26/22 – Project closeout documents received. TTC has final change order to review to close out.
12/15/22 – OK to close out.

800 – City Water Main Replacement Read More »

A&D – Cooling Tower Replacement

01/07/19 – ThermalTech met onsite with BAC representative and reviewed condition of existing towers. TEI sent in an SOSS for the study for approval to Facilities later that day in hard copy and email.
01/21/19 – SOSS approved TTC setting up report and getting prices for replacement and repairs.
02/28/19 – All prices are in and preliminary report has been written. TTC to review, updated and send to Bert and Steve for their use.
03/27/19 – TTC must review final cost estimate tonight to share with County tomorrow.
04/25/19 – TTC will submit report today.
05/27/19 – Prices and Study submitted to County. Awaiting County decision on repairs.
06/27/19 – Talked to Tony Matre about bidding out the replacement of the cooling towers this year and he said check in with Bert about project viability. The schedule would be to start after cooling season and be complete prior to 2020 cooling season.
07/24/19 – Meeting schedule with County on 7/25 to discuss options. TTE fieldwork is complete for the cooling towers. PID has been converted to CAD for use on this project. There are questions about the design and cooling tower sizes to be discussed at Thursday meeting.
08/28/19 – Project is in to the owner for review. Funding is set for approval from JFS in August.
09/24/19 – Project undergoing some funding and County review. TTE will have project ready to bid when final okay comes from Owner, looking to mid November.
10/30/19 – Project on hold. TTC checked with lead times on Evapco towers who claim to still be two to three weeks.
12/11/19 – Had some movement on this project this week. TTE to submit a small SOSS for some additional services for extra design work.
12/12/19 – The money has been approved for this project but the paperwork is not fully approved at this time.
01/24/20 – ThermalTech putting final bid documents together for bidding in February 2020, award in spring, be read to construct in November 2020. TTC discussed project with Steve Terheiden last week on Ameresco walk through.
02/20/20 – SOSS and PO should be on their way for work in Feb/Mar.
03/19/20 – Prebid meeting at the site with about 6 bidders. Several items to be released on Addendum including a 6th Floor drawing clarifying sweeper piping.
04/23/20 – Bids were open to five bidders, most were underbudget. TEI conducted a post bid review with Debra Kuempel and found them to well recommended bidder for this project. They have the scope covered, would really like to start the job early if possible and have all of the Alternates covered in the bid.
04/28/20 – TTC spoke to Tony Matre about Alternates on this job and awarding the rest of the work. We will need contracts and a PO to get started, County thinking about allowing the CT to be replaced over the summer long weekend.
05/25/20 – Project in for approval. Debra Kuempel check on approval of job on Monday. We are accepting several of the Alternates but not the extra basin heater extras.
06/22/20 – Project setup and communication this month with RT this month for doing the work this fall. TEI updated Debra on project status and assured them this project is still a go. I don’t think this work will be done over the summer even in multiple parts over weekends, but this is something we can discuss at the Pre-Const mtg.
07/23/20 – Pre Const Mtg held on site with Debra Kuempel, TTE and County. We are getting all things in place for this job and potentially look for an earlier than fall start if we can get the equipment earlier. TTE issued the Const Mtg notes this night.
07/29/20 – 3D scanning schedule for Thursday. Submittals have been preliminarily worked out with Stoermer Anderson, Debra and TTE. The SS towers will weigh less than the existing towers and fit on the existing steel. We are discussing ladder and drainage details for the final submittal which should be next week. The delivery time for the towers may be as fast as 6 weeks per our discussions with Marley. DK has submitted the SOV, Schedule and Employee list for review.
07/30/20 – Lightning protection questions on the A&D was discussed. We have enough UL listing verification and THP will fix the drainage issues when they do their project.
08/24/20 – Debra inquired about roof build. TTC contacted GBBN for basic roof layout and send photos showing the roof structure from underneath to DK for this job. DK also inquired about submitted a payapp for this project this month which TTC said would be okay.
08/26/20 – No payapp has been submitted that TTE has seen yet.
09/18/20 – This month we approved final submittals. DK should have the CT on order with Marley. Now we are prepping for install.
09/24/20 – We got 30-day electric data back from DK. MCB says we will work with this data for the IBI permit. BW mentioned that we have to check the LED light pattern on the new CT so we don’t affect the historic district lighting effects.
10/28/20 – Checked in with Debra this month, got a handle on final background checks. Cooling Towers scheduled to ship Nov 11, being confirmed. TTC to check on permit status with Debra tomorrow.
11/18/20 – THP – as part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers. As part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers.
11/20/20 – THP completed site visit.
11/24/20 – THP published a letter addressing the City’s letter.
12/02/20 – THP submitted a SOSS for the work completed.
12/09/20 – THP received approved SOSS.
12/10/20 – We have been working on permitting, submittals and structural steel approvals with DK and THP this month. The permit appears to be approved at the City for DK to pick up. We need an update on the background checks, which seem to be taking longer than anybody would like. The county issued a PO direct to THP for their work getting the permit through the City office. All the equipment is in town for the job and TEI went to the rigging yard to approve it and send pictures of it for invoicing.
12/29/20 – Working with Debra to get guys through background checks to get started. Bert and Rycca have followed up with several emails on the subject. Phone conversation with DK has them starting in January and completing the job in January as well.
01/23/21 – Contractors on-site removing cooling towers today. Some issues with disassembly prevented them from getting both towers off the roof but they were able to get west tower, piping, and ladder removed. And for the east tower they removed the piping and ladder and full prepped the CT to be removed. The next crane lift is scheduled for Jan 30 and DK will remove the old tower and put up both new towers. The structural will be wire brushed and repainted and we are getting a change order to replace some more of the CWR piping.
02/24/21- DK moved inside during cold weather and started working in the basement. Slow progress as of last week. Weekly const mtgs set for Thursday until the project is complete.
03/23/21 – Punchlist Tuesday by Terry and Mike. TTC has been following up with Debra & Marley this week on several items pertaining to the construction of the tower. DK pricing replacement of the final platform behind the east tower. Punchlist due out Friday, County comments welcomed.
03/25/21 – TTC to check on OSHA compliance on the top of the tower including the gate, and kickplate. TTC to reach out to THP and get contact information for LJB.
04/20/21 – Change Order #2 approved for additional painting, grating and hot tap from high pressure city water system.
04/28/21 – DK reports all change order work is complete, final cleanup being done.
04/29/21 – Project is complete, punchlist is distributed, DK finalizing clean up on project.
05/26/21 – Change Order for electrical and controls work is in final approval. DK controls punchlist work has been complete and the system is running under revised control. Electrical and Mechanical inspections are complete and approved. Steps are not installed. Change Order control work to monitor the condenser water pumps via CT is not complete yet.
06/25/21 – We’ve checked in with DK several times on the final items to complete this job. (1) Steps are in fabrication. (2) Control programming is complete. (3) CWP circuit monitors are ordered but not installed yet. The good news is that the cooling towers are working well.
07/28/21 – Project is complete minus the steps. Safety docs sent to Rycca for record. DK is starting closeout manuals.
07/29/21 – Debra reported in today with updates. Warranty set for 5/26, closeout manuals being created, safety reports were sent to Rycca and steps over sweeper piping will be fabricated this week.
08/26/21 – DK is complete except for the steps which Joe is bringing over this week for the building.

10/28/21 – This job cannot be closed out until Maxwell provide actual pay stubs for their work. County will not pay final invoice until this is resolved. Debra contacted today to get this resolved.

A&D – Cooling Tower Replacement Read More »

JC- Room 120 HVAC Study

09/04/18 – Pulled the original Trace Calc to show we are using 11.5 tons of a 20 ton chiller, this chiller can do more work.
09/21/18 Met Andy and took off all fieldwork in the Room #120 area tracking down the piping and ductwork associated with the new fan coil units for the 20-ton system and the single zone system. The fieldwork showed us that there are more FCU’s than in the original PO with Motz and these are connected to the 20-ton chiller unit. TEI is certain the old ductwork and diffusers are still in place providing ventilation to the space and the new FCU were added for additional space conditioning. We will update the load calculation and look at expanding this system into the Employee Services area across the hall with additional FCU’s. Bill this to the AKM General Service number.
10/22/18 – Sent Tony and Andy a full schematic design and cost estimate for Room #120 expansion and replacement project using the existing chiller. Raw cost was about $58k and about full cost including engineering and permitting was about $90k.
11/29/18 – No updates this month.
12/31/18 – No updates this month.
01/22/19 – No updates this month, TTC has decided to archive for now.
03/08/19 – Andy contacted Terry about report and TTC reissued email to Andy and Tony with cost and floor plans.

JC- Room 120 HVAC Study Read More »

CH – Room #160 HVAC Study

07/16/18 – Sent Tony and updated summary of the fieldwork and load calculations associated with Room #160. Provided basically four options for possible HVAC changes that may help with cooling issues.

  • Unit appears to size large enough for the design day load
  • Add reheat to all interior zones for additional comfort control
  • Replace the unit and add zoning
  • Add DX unit to just #160
  • Relocate Judges to rooms that match their cooling request

08/01/18 – AAB provides hard quote for work based on ThermalTech drawings; they are estimating three to four days of field work to rebalance everything and test it.
08/03/18 – Tony contacts ThermalTech about moving forward with project.
08/23/18 – TTC sent a follow up email to Tony and Rob outlining what Honeywell found while on site performing additional research. Al the existing VAV boxes are pneumatic and any control strategy with intelligent reset design is not possible unless they are upgraded to DDC boxes. Hot water not available on this floor but is available in the basement with the unit. TTE provided a general estimate to upgrade the boxes and extend hot water reheat to the new spaces. What we have not found is what temperature the hot water is disabled based on OAT and what that may do to this design.
09/27/18 – Court decided to wait for funding before they do anything and what they have now will work for the foreseeable future.
10/23/18 – This project archived by TTC.

CH – Room #160 HVAC Study Read More »

Energy Manager

04/03/18 – TTC updated the Duke Proposed Rate increase in the Energy Outlook section and incorporated all of RWL notes into the Rev 2 file and created Rev 3 and sent to Ralph and Tony for approval.
04/04/18 – Rev 3 of the 2017 Energy Report is complete. The editable Word file was sent to Ralph for approval by Judi prior to submission to the BOCC. 04/26/18 – Ralph reported that the final report is in the editing stage and he will return as soon as Judi has markups.
07/04/18 – All Energy Impact Studies updated and sent to Bert and Tony for approval and use.
07/14/18 – All Energy Star submitted to the EPA for approval.
08/01/18 – All buildings Energy Star Reports are complete. We were able to get SPHQ certified this year with some good work with the EPA folks on how to model the building. 230, 800, Admin, A&D, Courthouse, 250 and SPHQ all qualified this year.
08/29/18 – Bracken review the Archibus versus Watchdog reports this week and there are some discrepancies we need to fix.
09/24/18 – Verified the first six months of 2018 in Watchdog and Archibus this month, started putting together the 2019 Energy Report format, pulled all the Watchdog data down into TEI excel forms. Grace, Bracken and Laurie have updated pretty much everything from Watchdog into our forms for future use.
10/23/18 – ThermalTech has created a excel file database to mimic Watchdog data given the vast changes in the Watchdog database format, I may recommend that we abandon the Energy Watchdog Website if its too complicated to use and doesn’t display the data as Tony likes – we will either give it to him manually or use the Archibus Watchdog Reports. We also reconciled the first six months of 2018 for all energy data and fixed a multitude of smaller errors and reports. It is very important to keep two database of the information to ensure Archibus reports the data use accurately so we can’t abandon the manual entry or Watchdog entirely in our opinion. I have also met with Bracken and Amy Crousey to cross train more TEI people on the energy manage duties to assist me in my efforts to keep up with the data.
11/29/18 – We have started the 2018 Energy Report and are waiting on an updated SOSS for next years activities.
01/09/19 – Spoke with Tony and we are shooting for a draft report of the Energy Report to Ralph at the Ohio Energy Conference on Feb 19, 2019. Final report due in March 2019.
01/22/19 – TTC and AEC working on final report, requested curtailment from the County for report.
02/28/19 – TEI attended the 23rd annual Ohio Energy Conference with Ralph and Tony Feb 19/20. TEI also send the draft Energy Report to Ralph to make edits for this year final report yesterday.
03/11/19 – Ralph returned comments to ThermalTech on final report updates. TTC received Ameresco M&V data for report. TTC to make final edits and finalize report for printing.
04/24/19 – TTC started final edit soon Energy Report for Ralph and Tony.
05/03/19 – Printed final copy for Facilities and dropped off downtown for distribution.
05/10/19 – Terry met with Ralph and picked up final round of comments, made edits, printed final and returned final set to Facilities this day.
06/18/19 – Talked to Tony and mgrs about getting access to data rooms for modify the energy star model for new data center requirements. Those field trips can probably happen next week for Ryan J.
06/27/19 – Worked with Duke to get 230 meter converted to remote reader. They installed new devices on 6/21/19 and sent a new bill showing non estimated readings yesterday to our accounts.
07/25/19 – TTE attended RFP for new energy savings last week. Collecting data and preparing for more work.
08/28/19 – This month had some billing issues for us to work one. Admin water was unusually high which we worked on with Tony and in the field at the meter. Data was sent to Tony with TTC review of existing conditions. Coroner Gas was zero creating several issues in Archibus and for billing. We contact David Hiser and discovered that Duke will rebill several accounts. We have decided to wait until the new bills are entered into Archibus to approve and correct these bills. However the usage was not out of historical norms.
09/19/19 – Coroners bills retroactively getting updated by Duke due to a metering issue. ThermalTech will update the Archibus database. Admin Water bill had high usage one month but apparently back down to previous usages. The low water meter side of the meter does not seem to be registering low water usage at this time based on TTC fieldwork.
09/25/19 – The CCAO is apparently changing gas suppliers in November 2019 to IGS. TTE preparing for these changes in Archibus and approving bills.
10/04/19 – TTC meets David Johnson on site and collects data from Courthouse PLC system. TEI prorates missing dates and months for CH steam usage from last three year. Amy populates the district heating plan in Energy Star. Courthouse only increases to 59. TTC informs County that the Courthouse will not qualify this year for the Energy Star Award.
10/11/19 – Ryan, Terry, and Amy are working on Energy Star submissions for 230, 800, Admin & A&D.
10/22/19 – Energy Star submission are uploaded to the EPA.
10/29/19 – Energy Star approvals come back for 230, 800 Broadway and A&D Building.
10/30/19 – Admin Building Estar is signed and uploaded.
12/12/19 – We are performing end of year work and preparing the Energy Report for next year.
01/24/20 – ThermalTech started compiling the worksheets for the Energy Report for Calendar Year 2019 in an effort to have a preliminary draft ready for OEC with Ralph and Tony. Archibus bills for IGS still getting entered and sorted out, Admin electric bills still need fixed for 2019 estimated and new meter data.
01/28/20 – Ralph sent TTE work on sharing Energy Star with the Green Umbrella people.
02/17/20 – Mark and Terry finish draft Energy Report for Tony and Ralph to review. Great progress this year and we are farther along then usual. Executive Summary write up and calculations not done yet.
02/18/20 – TTC, Ralph and Tony at the Ohio Energy Conference this year and several items will find their way into the Energy Report this year. This was a two day seminar on a variety of topics related to energy futures and managing energy and renewables in Cincinnati.
02/20/20 – Three main things to work on this week for Energy Report. (1) securing the rebate for the wrong tariff at the Courthouse, (2) Opting out of the Duke Energy EE riders and (3) exploring the Building Performance for Energy Star.
03/23/20 – Sent final copy Rev 5 to Ralph and Tony for final review.
03/24/20 – Got comments back from Ralph, picked up comments and send final Rev 6 to Ralph for approval.
03/25/20 – Got approval to print 16 color copies of the final Report and two thumbs up from Tony and Ralph. I’m going to send this one out to Phipps because we are not in the office to print this year.
03/30/20 – Submitted full package to Energy Star for Audit for Dec 2019 submission for Energy Star.
04/20/20 – 250 Energy Star Certification was sent to Ralph and Team. energy Reports were delivered by Phipps to the County.
05/27/20 – Updated Energy Star website with latest data from bills, trying to reconcile some bills from Duke and found the JC gas usage was very high last month but that turned out to be the exercising of the hot water boilers.
06/11/20 – Met JCI on site for Facility Explorer training and to work on 800 Chiller scheduling issues. Worked about half the day on site and finished updating the control book back at the office. Followed up with Tom and JCI about changes made onsite.
06/24/20 – Updated all the Watchdog reports at ThermalTech this month for electricity, gas, water. Found some accounting errors and fixed those. Updated links in the master worksheet and updated data for the 2020 Energy Report worksheets on our network. Work with 800 Broadway and chiller scheduling and water issues on the 16th floor. Followed up with Tom at 800 several times to verify chiller schedule is off on nights and weekends. After a couple of more tweaks, removing override and delete exception schedules, the chillers as of yesterday are off when unoccupied. JCI did not have the service contract in place yet.
07/29/20 – Performed some minor work this month on Energy Manager, check Ralph’s emails and read up on HB 6 for County implications. Duke finally gave the A&D an actual bill and reconciled the estimated months; county gets money back.
08/26/20 – Not a whole lot going on with Energy Management this month. TTE keeping up with RWL emails and reading reports. Energy Star webinars basically say to hold until October November for resubmissions.
09/18/20 – JC bills are coming in too high. TTE figured out this is related to a rider from Duke but it doesn’t make sense because the riders appear to be equal or less than last year. We created a worksheet to share with Duke of mind out why this is happening.
10/28/20 – Worked with Duke on the Opt-Out program this month and got all accounts over 200,000 kWh annually should be out of the program by November 1, 2020. TEI to confirm.
12/10/20 – Started end of year EM work and County issue request for several new PO for additional work. Energy Stars are started, TTC waiting to review.
12/30/20 – 2020 Energy Star SEP underway for TTC review.
01/26/21 – All Energy Star SEP are complete and printed. TTC to review and send to Ralph for signature. The deadline is February 10, 2021 for 2020 submissions.
02/24/21 – Bracken helping with 2020 Energy Report, made good progress this week, hopefully turn around on Friday.
03/25/21 – Ralph and Tony reviewing final report this month, they are submitting final edits today EOB.
04/29/21 – TTC assisted in edits on the BOCC Energy Report PowerPoint for Ralph.
05/26/21 – Still working on the refund from Duke or IGS on double billing back in October.
06/18/21 – Work Thursday and Friday creating 2022 budget estimates for Tony.
06/25/21 – Rebate from IGS on its way, just waiting on paperwork.
07/26/21 – Budget sheets created and sent to Tony Matre.
08/25/21 – Energy Star getting started for buildings.
12/15/21 – Five buildings certified for Energy Star in 2021. 230, 250, 800, Admin, and the A+D building.
01/25/22 – Utility bills are being verified for 2021 for the Energy Report 2021. TTC registered for the Ohio Energy Conference in person along with Tony and Ralph.
02/24/22 – Just got back from OEC with Bert, Tony, Ralph. Decarbonization.
03/31/22 – Final edits and calculations were completed yesterday, the final report will be sent to Tony and Ralph this week.
07/22/22 – Assisted Ralph with edits on PowerPoint for BOCC presentation. Sent final edits.
07/27/22 – Working with Tony on high water usage at 800, CH and 250. 250 building Duke bills are currently under investigation by Duke for billing issues with the Duke electric rates. The last three months may have to be corrected and rebilled.
10/26/22 – Energy Star for 2022 to be completed in early November.
01/24/23 – Courthouse electric bill was corrected March to December for new meter but billed on the wrong tariff. ThermalTech asked Duke to credit $26,000 and rebill the county.
02/22/23 – TTE working on Energy Report and calls for rough draft next week OEC.
05/01/23 – Report is complete and sent to Ralph for comments. Ralph texted back wrong version. TTC sent actual 2022 report.
05/21/23 – Tony asked for budgeting information for 2023 for T+D and Commodity.
06/28/23 – Received final edits from Ralph two weeks ago. Jimmy picked up half of the comments, TTC needs to pick up remainder.
07/26/23 – 2022 Hard copy reports delivered to Ralph today, quantity 15.
01/31/24 – 2023 Energy Report about 50% complete.
05/28/24 – Ralph received Impact Energy Award for Facilities on May 2, 2024.
06/26/24 – Forecasting for 2025 sent to Tony, including the Master work files.
07/24/24- Energy Star up to date, working on new City aggregation request from BW email.
10/30/24 – Energy Star work fieldwork complete. SEP sent to Tony for signature.
01/27/25 – Energy Report 2024 has been started. We are proposing a new coversheet to celebrate Mr. Bert Watts taking over the the Directorship of the Facilities Department. I will send to Tony and Bert for voting on the best new coversheet 🙂
04/23/25 – The first draft of the Energy Report is ready for Tony and Bert Review.
05/28/25 – Waiting on comments back from Tony and Bert on Energy Report.
06/25/25 – Waiting on comments from Bert before finalizing the Energy Report and printing.
08/26/25 – TTC updated and sent back for comment Final Energy Report in PDF. Hard copies have not been printed yet.
09/24/25 – No comments or updates on front end sections. Report has been submitted for final approval.
10/29/25 – Energy Star SEP are complete and sent to Tony for signatures.
12/12/25 – Five buildings received the Energy Star award for Hamilton County this year 250, 230, 800, A&D and TPC. Congratulations!
01/15/26 – Send Tony utility forecast to electric, gas and water for 2026. Had to take a stab at 111 and 1701 because they are not occupied.
01/19/26 – DEG going to self print two energy reports and send to Tony for 2025. We are still planning on created a 2025 report this year.
01/21/26 – TTC talked to Anthony about getting access to 1701 on our myduke1@davieseg.com account and hopefully to move 111 and 525 to the same account.
01/25/26 – SPHQ currently qualifies for Energy Star, but we have to verify the gas data is correct because for months Duke listed 0 usage. Once that is verified, we may certify this building early in 2026.
02/25/26 – 2025 utility reconciled in the DEG master files. The 2025 Energy Report is ready for first Draft Mode. the Performance Guarantee sections has been removed because Ameresco is not keeping that data any longer. TTC in printing two copies of the 2024 Energy Manager report to give to Tony Matre.
03/25/26 – 2025 Energy Report Draft ready for review.
04/29/26- Small changes requested on Energy Report, going to Tony soon.
05/27/26 – Report ready for TTC review then to Tony.
06/25/26 – Energy Star for Courthouse and SPHQ completed and sent in for approval. 525 and 1701 also have scores above 75 but must wait to be certified for occupancy and working equipment.
08/26/26 – We are closing work on the A&D building. Final bills mean we need to unarchive bills from March so we can fix them.
09/23/26 – Working on updated all locations for electrical, water, gas, and getting bills for new sites. We are also trying to navigate the changes on CCAO and IGS from coming in on the new Duke bills.
10/27/26 – TTC sent Energy Report to Tony in email per his request. We are working on integrating Hillcrest and 1701 into the future Energy Modules

Energy Manager Read More »

JC – Switchgear AC Unit Project

01/08/16 – Met with Merkt on site to kickoff new AC unit in UPS room.
01/26/16 – Discussed scope of work with Tony and Joe over email today. Requested quote from Ray Weyman on Mitsubishi split at 4 tons for this room. This work may be a change to existing elevator work for cooling with Debra or owner will self-perform this work.
02/08/16 – The 4-ton unit only comes in a heat pump option but that heating can be locked out to provide cooling only. The 3-ton unit is a single wall unit with a single condensing unit. The 3.5 ton unit is ceiling cassette with a 3.5 ton condenser.
05/18/16 – Tony requested new SOSS for this work.
06/23/16 – ThermalTech was onsite performing fieldwork for equipment layout for about 3 hours today. We tracked down equipment locations for the Liebert and Mitsubishi Units and possible power sources for both.
07/18/16 – Phone conference today between Cannon, Merkt, Denton and Matre has decided to use an inline DX coil for HV-9 to cool this space similar to the work we are doing in the elevator room upstairs for additional cooling when the CHW plant is down. ThermalTech will modify the design.
07/20/16 – TTC on site for more fieldwork and duct measurements for new coil design.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/27/16 – We changed the design of the switchgear room AC to a coil and condenser unit and started requesting new cuts from Carrier. We are updating the plans now. The Data Room AC unit was changed for low supply and top return and we will try to collect the hot aisle air with a return duct above the data racks.
08/03/16 – Some progress made on design. Cad files received from Liebert this week, we are updating outdoor equipment.
08/25/16 – Design will be complete and ready for bidding in mid September for both phases.
09/01/16 – Review drawings due Sept 16.
09/23/16 – Project set to bid on 9/29/16. Prebid Oct 6, Bid opening Oct 20.
09/28/16 – Project is issued for bidding. Switchgear AC unit is the base bid. Liebert Unit and Medical Unit are Alternate bids.
11/10/16 – Contracts are written and sent to Tony.
12/09/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/21/17 – Submittals are in for approval. We are definitely having some trouble finding the medical valves but Peck is working with us to find them.
03/09/17 – TTC to finish submittals this week.
03/21/17 – Submittals are marked up and ready to go back to Debra.
05/17/17 – Submittals returned, equipment ordered, waiting for DK to get started.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Equipment is ordered and en-route. We have agreed to use a ceiling mounted cassette on this project. DK submitted a change order allowance usage for this work.
07/24/17 – Equipment should be here next week per Debra Kuempel.
08/10/17 – Coil is installed downstairs in UPS room. Medical unit is installed upstairs.
08/30/17 – Work is progressing well, Cassette is installed upstairs. Coil is installed downstairs, balance report is short on airflow from existing unit.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Debra reports that most work is complete. TTC checking on progress on the electric and controls portion of the job.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.
04/26/18 – Purchase order came out this week. ThermalTech agreed to perform the airflow readings for Debra and will share the results with the team. Then we will setup that conference call to discuss the results and proposed upgrades with the new motor.
08/01/18 – New motor is installed. Balance report shared by DK, commented on by TTE and send to County. Project is complete and DX unit is working well so far. Project is ready to archive.
09/04/18 – Systems are working well per Facilities. Project should be ready to archive.
10/25/18 – TTC delivered O&M’s to Tony Matre for closeout at Thursday Partner Meeting. The final permit is not approved and closed yet on the City website, TEI email Debra instructing them to close it out ASAP.
11/29/18 – The electrical permit is ready for DK to get the final inspection for closeout on this job.
01/10/19 – Final inspection appears to still have issues according to the website. TTC contacted Debra Kuempel to resolve. 9070-FINAL INSPECTION 11/26/2018 Defective (14X) Defective: 1. Label unit on roof. 110.22 2. Accurate panel schedule. 408.4 3. Bonding bushing on 480V. 250.97.
01/22/19 – According to DK the inspections are complete and they will send in all final paperwork ASAP for closeout.

JC – Switchgear AC Unit Project Read More »

JC – Liebert Unit Replacement Sheriff Data Rm 3rd Fl.

11/14/16 – Final Addendum went out to bidders. Bid opening is schedule for Thursday.
12/07/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/28/17 – No updates from Tony on approved contract.
03/09/17 – Waiting for kickoff on this project.
03/15/17 – PO and Contracts are ready, TTC requested meeting times from contractors and owner.
03/21/17 – We are ready to have the kickoff meeting for this project.
04/26/16 – Submittals requested. Pre Const Mtg was held.
05/17/17 – Submittals approved. Equipment ordered.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Unit is on order and should arrive late July.
07/24/17 – Equipment should be here next week, DK people approved for access but some JCI people not approved yet.
08/10/17 – TTC met Debra and Andy on site to discuss break down and reassembly of the Liebert unit in the data room today. Debra not a fan of breaking down the unit, we are exploring the option of taking out the window and
08/30/17 – We are going to order the door for the replacement of the single door. TTC to work out allowance with Debra.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Piping is ran to the unit. The scaffolding is coming down this week. Insulation appears to be installed as well. Outdoor unit is set. The interior door work is underway. KFI ran into a frame issue today and is having the frame modified for a Wednesday install. Once we get the double doors installed the Liebert should be rolled into the place the rest of the job can commence.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.
04/25/18 – Project is complete and I believe final training is complete. Final payapps are being delivered to Tony on Thursday.
08/01/18 – Project is complete and running as design; ready to archive.

JC – Liebert Unit Replacement Sheriff Data Rm 3rd Fl. Read More »

CAB – Chiller Rebid Project

03/05/18 – Terry and Colin onsite doing additional fieldwork for redesign. We are investigating new piping connections and existing pipe routes for new configuration. The good news is that some of the piping we thought had to be extended and modified already exist for AHU-1 & 2. The piping changes required on the tenth floor and roof are possible albeit a little tough to do.
03/24/18 – TEI submitted revised SOSS for new design and bid cost for TEI and THP. LCC equation is ready for bidding for air cooled chillers. Revised design is about 50% complete for mechanical changes for the new design.
04/19/18 – ThermalTech release LCC bid documents to manufacturers for rebidding this project for Air Cooled chillers only. Trane, JCI, Carrier and Daikin all invited to bid. The nominal tonnage of the chillers will be 200 tons. Bids and performance numbers are due to ThermalTech April 30 at noon.
04/25/18 – Addendum #1 release today with updated calculations and some other updates to the bidding worksheet.
05/17/18 – The LCC results were published to the bidders, Facilities and Purchasing. Carrier High Efficiency Option #2 was the best LCC chiller for standard refrigerant, model 30XV-2006M40–4-2 using R-134a. And the Next Generation Chiller best LCC went to the York JCI chiller using R-513A model number YVAA0213.
05/23/18 – Terry and Colin perform fieldwork to wrap up new piping changes for new chiller design. We go everything we needed and marked up all the piping on the 10th floor for future changes. We are confident we can do all the piping changes required for convert the building to Air-Cooled Chillers.
05/25/18 – Mechanical drawings are ready for TTC review. Final chiller equipment has been sent to THP for structural design and upon initial review, all seems to be in order. Good news on the piping front, we can find a decent path from the penthouse to the new chillers and route the piping about 41″ above the room and miss the Liebert unit piping rack, found a space to create a walk over the new piping for easy access and can make a new door in the penthouse using existing louver material.
06/26/18 – TTC has marked up final mechanical drawings for editing. Electrical drawings are being updated now for bidding. TTC will get new ITB this week and put the project out for bidding first week of July. I need to coordinate prebid with Bert and John Gilbert.
07/26/18 – Rebid project is on the street. Prebid meeting schedule for August 2 and Bid Opening scheduled for August 23.
08/29/18 – Bid were opened on schedule. Triton Services was the apparent low bidder on the project. TTE held a post bid interview with the bidder and sub-contractors on Tuesday at our offices and reviewed the project is detail. Most everything was covered and Triton appears to understand the project well good sub-contractors for this project. They would like to get submittals started ASAP on this project.
09/24/18 – Contract appears to be approved and on its way to Triton for signature. Duke released some data on next year’s rebate program which we should be inline for with this chiller purchase. THP review the structural proposed questions and returned satisfactory answer to keep the job moving forward.
10/23/18 – PO in for approval and then TEI will schedule the Pre-Const Mtg with Triton.
11/27/18 – Pre Construction meeting was held onsite with Triton Services. Permit response came back and we are working with Triton to get the four responses answered for this job. Terracon must be engaged as a special inspector on the job, and we provided some additional permitting material to take to the city, plus the city will require a General Permit for the structure.
12/31/18 – Two construction meetings so far. Project is underway. Submittals are moving along and being approved. Background checks are almost completed. Triton is mobilizing to site. Crane lift being scheduled for early January. Chiller delivery is February and we are working on getting that moved up. Steel and piping are being fabricated now and that will be the first lift up t the roof.
01/10/19 – Triton directed to get CHLR-3 online first for hot days. Control meeting was conducted with TEI and Emcor on Monday for coordinating control sequences on new chillers. TEI issued updated sequences to Owner, Triton and Emcor for use on this project from this meeting.
01/21/19 – Glenwood found that a 1000A breaker with the correct lug alignment was not available from GE at this time. They submitted a change order for the work. TEI contacted CE power to find a direct replacement for the breaker that will hopefully be less expensive than the submitted change order.
01/22/19 – Control submittals have been received and return immediately. TEI and Emcor worked through specific control questions and TEI issued an updated sketches for 10th floor piping that has to be coordinate with Triton during installation. We also approved a ball valve in the bypass even thought that technically won’t be used until the three way valves are replaced later.
01/31/19 – THP update: Structural steel shop drawings reviewed and returned.
01/29/18 – Const Mtg #4 held. Project is moving along well. Glenwood is setting the transformers today. Piping is connected in 10th floor and along roof to structural steel location. Basement piping is demolished. The 5″ bypass will be started in the mechanical shaft and then routed over the ceilings to the mechanical room. ThermalTech will use Terracon fro the special inspections on the structural platform for this project.
02/17/19 – Steel was erected by 2/17, inspected, fixed and reinspected. Chillers were set on frame on 2/19 without incident. Everything looks good.
02/26/19 – Glenwood pushed to power outage to the backup date of 3/9/19 due to ship date of the circuit breaker being 02/28/19, and Glenwood was not confident that the breaker would be on site in time for the original outage date. TEI and Glenwood revised drawings and submitted to IBI engineering change for the revised plan. TEI to schedule a meeting with Triton and Glenwood for pre-outage conference the week of 3/4/19. Const Mtg #6 was held and Triton reported almost all their work is complete. They are waiting on Glenwood and Emcor to finish up the job. the glycol feeder and chemical test company should be on site within the next week for their work.
03/01/19 – Triton reports that glycol feeder is here and being installed. Emcor workers have their background checks in place and will start controls. Glenwood reports after Nester checked in that the breaker should have arrived yesterday and today for sure.
03/11/19 – TEI attended Admin Chiller Startup with County.
03./12/19 – TEI attended Admin Chiller startup for second day with County. Items brought up during startup are weatherguards, heating circuit, convenience outlet, trouble light, local disconnects, additional support on chiller base, additional glycol and differential pressure reader. ThermalTech to start working on these items for resolution. TEI can start the punchlist on the job as well.
03/26/19 – Electrical transformer and breakers installed and turned on. The electrical final did not pass. TE and Triton/Glenwood working to resolve issues on project to pass inspections.
03/27/19 – TEI held conference call with Glenwood to discuss change orders. TEI went to site and measure disconnect locations and redoing the work to make it easier for contractor and Owner.
03/28/19 – Barth, Glenwood and Nester met at the building to discuss final location of the new 600A disconnects this morning. Chiller #1 disconnect will be mounted on the West Side of chiller. on Chiller #2 we are basically doing the same thing but we need a junction box and extend the feeders in seal tight.
04/22/19 – TEI releases electrical and mechanical punchlist for final wrap up of project. TEI reviews and gets approved balance reports from vendors and factory for this project.
04/24/19 – Change orders approved for the power items that IBI required. TEI performs and issues electrical punchlist. Glenwood on site week of 4/22 making all corrections and CO work with the exception of ground detectors, which are on order but not received to date. Upon receipt, ground detectors and final IBI will occur. Triton on site doing punchlist items and TEI meets them for new pipe label coordination. TEI asked for Training to be complete ASAP.
04/25/19 – Send Bert change order prices for CT and Chlr. Duke rebate check received and credited to the account, however this money probably can’t be used for additional change order work.
05/27/19 – Glenwood wrapping up change order work and final permitting of electric work for the project. Weather panels are coming very soon. There is a breaker setting we have to coordinate with Glenwood and then we should be able to get our final inspections in the next week or too.
06/27/19 – All construction work in complete. Glenwood set to call for final inspection next week to get final permit closeout for this project. TTC and Emcor meeting on July 9 to do some functional testing of the chillers. Triton approved via change order to remove abandoned and old piping on the project site prior to closeout.
07/25/19 – Triton finalizing all permits. IBI is approved. Triton also performing alternate work for the owner this week. Project ready for closeout.
08/28/19 – Project is complete and final inspections were approved on 8/12. However the owner called with glycol feeder issue with the Pulsafeeder unit. We met last Friday and review the installation with the salesman. They requested we remove all the control interface to the unit and put it back to factory conditions or else they consider the unit “tampered with”. We did everything they asked and then spent another two hours trying to make the unit work with limited success. We contacted the vendor and asked him to bring in the manufacturer to assist. To me this is all warranty work for Triton on this job.
09/20/19 – TTE met Triton on site and verify an AAV on the CHW glycol feed does seem to fix the issue. Triton will install and pipe the overflow back to the glycol tank.
09/24/19 – TTE verified the work is done. This project is ready to Archive.
01/27/20 – Bert called for final closeout confirmation today. TTC checked and all the paperwork and O&M’s are in. However the final payapp is not process. it was found that #10 and #11, balance of contract must be submitted. TTC confirmed with Triton on needed closeout documents.

CAB – Chiller Rebid Project Read More »

JC – Backflow Preventer Replacement

03/23/18 – TTC met with John Nester and Andy Stafford about replacing the BFP at the Justice Center.
03/24/18 – TTC talked to City plumbing department and Blue Chip plumbing about replacing the BFP and what it would take. The city is not keen on downsizing the BFP at all and Blue Chip agreed they don’t need to be dual detector check but they do need to be reduced principal backflow preventers. TTC code research agrees.
05/21/18 – TEI Issued 30% review set and begins working on 4″ BFP replacement scenario. TEI sets up additional fieldwork on site for this project, TTC & RAJ.
05/22/18 – TEI puts together equipment cost differences after receiving Vendor quotes form Watts for this project. TTC and JN discuss bidding options. TEI to further design on 4″ scenario vs 6″ scenario for backflow preventers. There are two major issues with the first being if we need a full building shutdown to do this work and the second deciding if we are going back with 4″ BFP or 6″ BFP.
05/30/18 – Review drawings are complete and ready for TTC review but fitting to fitting work not complete by TEI quite yet in TTC opinion.
06/14/18 – ThermalTech create full 3D model to try to fit the BFP in this building without a building shutdown. Nothing aside form $20,000 in additional fittings worked so far. WE just don’t have enough room.
06/24/18 – We did a lot of design and fitting work this month on this project and confirmed neither 6″ nor 4″ BFP’s fit into the existing piping without shutting down the building and removing the existing gate valves which are not holding watertight. The team came up with the idea of changing the BFP model to a smaller skinner model with less flange to flange dimensions. We are still 6″ short of keeping the existing valves installed and reusing the old valves. Dan ordered a fire hose that we can test bypassing the inlet of the water piping to the filtration units, keep one set of valves and replace one set of valves and do this work without a complete building shutdown. This will be tested prior to bidding out this work.
07/26/18 – Revised drawings are complete and ready for review by County for Small Project Bid with latest BFP and bypass design included.
08/23/18 – Prebid held on site with five bidders. Bids are due 8/31.
08/27/18 – Addendum 1 released to bidders.
09/27/18 – PO approved, contract over at Prosecutors Office for approval. Project is moving forward.
10/23/18 – TEI to setup kickoff meeting with DK next Wednesday at 10am. TEI to submit small SOSS for additional services.
11/27/18 – TEI returned submittals earlier this week and equipment should be ordered for this project.
11/07/18 – Site safety plan issued for this job. Equipment is ordered. Proejct schedule should be finalized shortly.
01/22/19 – HC checked in with DK on project schedule again today. So far background checks are in place and we are awaiting on the equipment to arrive to perform the work.
01/31/19 – We are shooting for 2/14 or 2/21 for doing this work. Prework will happen that week during they day.
02/21/18 – Debra Kuempel completed the backflow preventer replacement by 1:30am and had the city water back online and the building up and running. TEI was on site from 6pm to midnight for const assistance.
02/28/19 – Debra is performing the annual test on the BFP for the city paperwork, finishing the drains off the BFP and the insulator is coming down to insulate to wrap up the project.
03/27/19 – O&M have been received and approved and sent to County for closeout. Final payapp has been received and approved. No PW rates on this project to approve.
05/27/19 – Project completed and ready to archive. Annual test is complete and passed, good until next year. It’s working great.

JC – Backflow Preventer Replacement Read More »

CH – Server Room Consolidation

06/25/17 – Hamilton County requested SOSS for a consolidated server room on the second floor of the Courthouse.
06/30/17 – THP – TEI notified THP will be needed for a new Courthouse server room.
07/27/17 – Team going to meet and discuss revised scope in the next couple of weeks for brainstorming kickoff meeting.
08/31/17 – Partners meeting to kickoff scope and design meeting for this project at Courthouse.
08/31/17 – THP – Hamilton County defined server room requirements for SOSS.
09/14/17 – THP met with Terracon to assist with SOSS.
09/18/17 – GBBN begins field verification and Project Request Estimate research.
09/20/17 – GBBN researches Abatement Report from Pinnacle Engineering related to this project and distributes information to Design Team.
09/20/17 – THP published proposal to TEI and provided Terracon proposal.
09/22/17 – GBBN completes base electronic drawing file composition to verify scope and extent of work.
09/22/17 – THP published updated proposal to TEI.
09/25/17 – ThermalTech mailed a full copy of the revised SOSS for Schematic and Budget estimates to Facilities this week.
10/24/17 – SOSS still in approval stages. Team regular discusses status of project and we are working on verifying existing background data for this space. ThermalTech has briefly discussed the QC process internally and have assigned two owners and department heads to review the project given its high visibility.
11/28/17 – We held our first SD design meeting today with the client. New worksheet and equipment request need to be sent out for work and the preliminary project schedule created with the partners for this project. GBBN sent out proposed office layout for 263. If asked we are hoping to use only two parking spots only.
01/20/18 – Terracon and ThermalTech were on site for the first round of soil boring test and underground detective. Underground locations went fine and were marked by the company. A follow up report and drawing is forthcoming. Data found matched up with the drawing provided by the owner. However existing condensing units were too close to one of the AC units so it was relocated. The drill team had concerns about snow hanging off ledge above and with the weather so the drilling was postponed to February 24.
02/22/18 – ThermalTech release the first meeting notes from the design meeting along with progress to date on the schedule. Terracon will be back on Saturday to drill the soil bore test pit. We are also are going to need two test pits to determine the construction and shape of the footers around the courtyard for the design of the future platform. Terry scheduled to meet Kirby after partner meeting on Thursday.
02/24/18 – THP: Terracon rescheduled for test boring. Only 1 boring will be done due to small site and existing equipment. (2) Boring were not required, but cost was minimal for backup boring. Terracon to schedule (2) test pits to gather soil conditions information.
02/26/18 – Underground utility report release to the project team by Terracon. TEI forward to owner.-
03/06/18 – Test bore results are release to the project team. TEI sent to owner and THP.
03/16/18 – Revised SOSS for additional services for GBBN and Terracon sent to County for approval.
03/24/18 – TEI to meet with GBBN on new room configuration next week.
03/28/18 – THP: County has approved Terracon to do test pits. THP on hold waiting on soil/existing condition information to design foundation and platform. Column location will be determined partially by foundation system.
03/29/18 – THP waiting on the test pits to start design. Team discussed location of Egen on this project and TEI to adjust the schedule for new design issues.
04/21/18 – TEI, THP and Terracon on site for two test pits. Pits were dug and completed on Saturday. Updates and photos sent to County on Monday. GBBN updated the site plan with the footers found on site. ThermalTech started working on new site plans and will have a conference call setup for the partners to discuss or findings and platform designs.
04/23/18 – THP – Terracon completed test pits in the Courtyard. Footing depths of the west and south walls were discovered to be at different levels. TEI started working on new site plans.
04/25/18 – Archibus number was enabled for editing again by the partner team. ThermalTech sent existing cost and sketches to everyone prior to editing.
04/26/18 – Bert said to get the worksheet for loads updated first and then TEI to select a week to meet with CAGIS and update new inventories. TEI needs to show some hard copy progress for Bert to review. THP, GBBN, and TEI to work with Terracon for platform design.
05/17/18 – TEI contacts CMSnet to discuss data rack sizes and loading.
05/18/18 – TEI and THP discuss and share design concepts on the platform for this project. TTC and SJ send column locations to Ken for discussion. I believe we are leaning towards spread footers on this project.
05/25/18 – TTC creates Option #2 layout for incorporating the JC data center servers into the Courthouse and stumbles on what may be a better location for the CH Data Room with or without the additional servers. TEI discussed benefits with GBBN on new location.
05/29/18 – Relocating the JC Sheriff data center to the CH was explored by TEI and an email summary sent to BW for use on the JC Recovery Four Pod scenario. TEI completes estimate for relocation and sends to Facilities at $184,000 to relocate 7 racks to CH Server Room build-out. CRAC units change in size to 50 tons each and require four condensing units instead of two, UPS, generator and the platform all must get larger.
06/25/18 – TEI has developed two platform designs for 30T and 40T condensing units. We have laid out all the servers in the new racks giving at least one rack to each department, this will need to be coordinated with departments. We have contacted CMS to see the server rooms with the technicians and confirm the CMSnet racks on Wednesday at 9am. Terracon final soils report is forthcoming.
06/29/18 – THP – Terracon published soils report.
07/26/18 – THP and ThermalTech working through design development issues of platforms. In the past month TTE has collected server information from CMSnet and contacted all other departments for final server loads. A preliminary layout was completed after the CMSnet survey and found that 21 Racks are sufficient for the new design. Facilities has reached out to other County departments for additional tenants that may want to be move over prior to the final cooling and electric load worksheets are complete. Sizing for the cooling units leaning towards 30 ton units. Fuel oil routing SD drawing, Admin 9th Floor and Roof SD drawings being drafted by TTE for Archibus update. We will update the original #1827 project number. TTE meeting with JII fire today for an updated vendor quote on the Fire Suppression work on Admin 9th floor at 11:30am. A lot of work going into wrapping up the SD design and cost estimate phase currently.
08/03/18 – GBBN confirms CAB-9th Floor Computer Room Abatement (ACM) scope with Pinnacle Engineering.
08/07/15 – Facilities answers final SD questions on scope to design team.
08/09/18 – Design Team wraps up Schematic Design Phase with updates to Archibus Project Request Estimate.
8/15/18 – Facilities confirms the displacement of the four workstations and blade walls in the east CMS area off the entry. GBBN makes the corrections to base drawings and distributes to TEI.
08/23/18 – Bert met with CMSnet and Department Heads at monthly meeting and reviewed the SD plan with the latest information.
08/29/18 – Met with CMSnet twice this month and updated drawings and final calculations. Only a couple of department still remain for verification. We will attend next PM meeting with CMSnet for presentation.
09/20/18 – The basic revised estimating is complete minus coordination on some of the final bidding number and cost for new scope items. Comments from CMS and Owner welcomed for final adjustments. One thing TTC noticed was that the design fees on the new estimate can be reduced to TEI. ThermalTech request additional funds to completed next phases of project including Construction Design Documents and Bidding. TEI collecting SOSS’s for next phase from partners for submission.
10/15/18 – ThermalTech has submitted the Construction Design and Bidding SOSS for all partners for the next phase of this project.
10/22/18 – Bert sent an updated Probate court inventory worksheet for ThermalTech to use. TTC to incorporate next week.
11/28/18 – TEI, THP and GBBN met at GBBN offices and reviewed the SD phase scope, cost estimate and schedule. We finalized the scope and schedule between the partners, assigned drawing responsibilities, and requested a setup meeting with Bert to discuss details on the structure. We will put some preliminary dwgs together and meet on Dec 11 at 9am.
12/20/18 – TEI, THP and GBBN hold design team meeting to discuss scheduling and deliverables.
12/28/18 – TEI and GBBN perform above ceiling MEP field verification. Photos taken.
01/10/19 – GBBN sent updated floor plan for the server room and Room 263 today for ThermalTech to use in design. ThermalTech is marking up new plans for design with latest changes.
1/11/19- GBBN meets with door hardware consultant to discuss door hardware and specifications for this project.
01/22/19 – TEI has setup all new drawings for hvac, elec, plumbing and fire to the new floor plans and started designing in earnest to the new designs. THP turned in four drawings for the new drawing package and will try to have draft dwgs ready later next week. GBBN has the floor plan complete and is updating the Life Safety drawing for our use on this project. TTC contacted the city about the use of water in this space and requested a face to face meeting. We will advise what we find.
01/31/19 – TEI to setup fiber meeting with telecom, cms, and facilities for new fiber connection with CBS.
02/25/19 – GBBN visits Rooom #263 with Facilities to review and measure ceilign and bulkhead heights. Existing ceiling and new SAT ceilings scope coordinated iwth TEI and Facilities.
02/28/19 – TEI/THP and GBBN to meet for coordination review of each firm’s drawings. Electronic drawing files sent to TEI in advance.
02/28/19 – Bert and Terry met with CMSnet and Dept Heads and presented a 75% complete working set of review drawings for the group. We discussed scheduled and Const on the project and they city specifically inquired about the crossover fiber between the Admin and CH to which TEI answered that we will be working on putting in a parallel redundant fiber to make sure that connections stays live.
03/07/19 – Design Meeting held. TEI produces Agenda and proposed Project Schedule.
03/15/19 – GBBN sends drawing updates to TEI for Owner Review.
03/22/19 – TEI sends list of changes required to documents and requests input on Construction Sequencing.
03/27/19 – TEI and Bert met with the Steering Committee to review the current drawings, scope, phasing, cost, and schedule for the project. Drawing were issued for review along with the schedule. We are shooting for bidding in end of April.
03/29/19 – TEI sends email with additional requested changes to design and documents. Construction material delivery logistics are discussed.
04/01/19 – TEI sends requiest for Server Room duct opening patching scope.
04/09/19 – TEI sends documentation discussing pros and cons of changing sizes of the Liebert Units to be used on the project.
04/15/19 – GBBN recieves Door Hardware Consultant Hardware Set documentation from vendor.
04/17/19 – Meeting with Telecomm, TEI send meeting notes out for review.
04/23/19 – TEI indicates all three existing window openings, in the Server Room permiter, are to be infilled iwth new louvers for consistency. Future Liebert Unit replacement will not be done through the existing window openings. GBBN revised background drawings accordningly and relocates new double door relative to resized Liebert Units and locations.
04/25/19 – Four Liebert configuration has been incorporated into the floor plans, the doors have been shifted to accommodate the additional CRAC unit, THP provided revised platform drawings with new ladder layout and hinged cover information (TEI reviewing now), THP finalizing load study with four units (TEI provided new weights with only refrigerant). We need to set final scheduled for review drawings and bidding with the County.
05/27/19 – Telcomm meetings have been held, we are working on final details for the project design. final answers and comments due back from County on June 10 with the intent of bidding this project late June or early July.
06/27/19 – Final design is almost complete. We are planning on issuing final design review drawings end of day on 6/28. TTC revised the schedule to distribute at the Steering Committee meeting on 6/27 with new completion date of April 2021. Cost estimate is partially updated with the hopes of completing updating by end of day Friday. Project should be bid in July and August 2019.
07/25/19 – Final design is complete. ThermalTech dropping off a revised set of final review documents today at the Partner meeting including all specifications for the project. Pricing effort, review and update underway to find a cost that matches the scope and is within budget. We are trying to bid this project as soon as possible.
08/15/19 – GBBN sends SOSS data, for Construction Administration services, to TEI for inclusion into the SOSS, to be submitted to Facilities.
08/16/19 – GBBN receives email from TEI concerning new listing of Alternate Bids for documentation on Construction Documents. GBBN updates CD’s to reflect CAB 9th Floor Computer Room scope of work, to now be listed as Alternate Bid G-1.
08/28/19 – The budget and dates have been finalized with Facilities and Purchasing. We will have this project ready for bidding by 9/4 with the revised budget. The Admin building has been moved to an Alternate and TEI renumbered the Alternates and combined a few of them to make the project easier to understand and bid for the vendors. Final drawings and specifications are being reviewed and prepared for the Issued for Bid data listed above. All partners have agreed to the date of Issuance for this project.
09/20/19 – The prebid meeting was held and well attended by GC, MC, EC and FPC alike. TTE will prepare Addendum #1 and issue from the prebid meeting discussions.
09/25/19 – Addendum 1 Issued.
10/03/19 – Addendum 2 Issued.
10/17/19 – Addendum 3 Issued.
10/23/19 – Addendum 4 Issued.
10/24/19 – GBBN creates Addenda #5 revised scale drawing for issuance.
10/25/19 – Addendum 5 Issued.
10/28/19 – Addendum 6 Issued.
10/30/19 – County Issues Addendum 7 and extends the Bid Opening to November 12, 2019. ThermalTech working on additional items for concrete, hot aisle design, plumbing drain pan submitted by contractors.
12/11/19 – The bids have been opened last month and we received three qualified bids. ThermalTech has met with the apparent low bidder, Graybach, and found them to be responsive to the bid. The recommendation for approval was emailed to Bert and the County has started preparing the contracts and moving forward with the project. TTC and BW have a meeting scheduled with the Steering Committee later today for an update.
12/12/19 – Prosecutor has approved the contract for this job and it has been sent to Graybach for approval.
01/24/20 – Graybach contract has been approved by the BOCC, PO was received by Facilities. BW emailed TTC to release the bidders on the submittal process. Paperwork is forthcoming.
01/27/20 – ThermalTech contacted Graybach with approval information and asked them to start the submittals, Schedule of Values and Project Schedule for this job. We would also like to setup the Pre-Const meeting with the Contractors. TTC Create Project Team distribution group and additional people have been invited to Procore site for management of this job.
02/18/20 – GBBN returns approved submittals for Doors, Frames and Door Hardware.
02/20/20 – TTC and BW met with CMSNet project managers and provided a project updated stating that construction should begin in late March or early April on this project.
02/24/20 – Three submittals have been sent to the design so far. 1) Structural was rejected due to a Missouri not Ohio stamp, 2) Doors and Hardware was reviewed by GBBN, TTC to forward back to Graybach, and 3) HVAC submittals #1, TTE reviewed and will send back to Graybach on 2/22 of their use. Geiler used Liebert for this project which is the basis of design.
03/04/20 – TEI distributes update on Project Progress status.
03/11/20 – GBBN receives a copy of the Plan Review Response letter with indications of scope for each design team.
03/24/20 – Submittals and Permitting are working their way through the process. The County shared some data about access to the site and the building for the contractor that may impeded access to the building for the original start time. Graybach asked about background check progress which was provided yesterday to Graybach. We are working on new details for the Kohler generator submitted by DK and this week we have confirmed the generator is smaller, the same weight and almost the same size belly tank. We have a meeting tomorrow with Graybach and DK to discuss final details before we review the submittal again.
04/30/20 – Background checks not complete yet, County checking on LEADS checks during Covid. ThermalTech received Hot Aisle Containment, Lighting and Generator this month. We are waiting on resubmittals for the structural steel and gratings for the clarifications we provided last month to the vnedors for updating the submittals. We are waiting on the final schedule and Schedule of VAlues for this job for approvals. Graybach submitted a not cost not time extension change order noting the delays at the beginning of this work so far due to Covid.
05/25/20 – ThermalTech and GBBN finalizing permit response drawings and remarks for 5/29/20. Graybach working on project schedule based on background check protocols. County working on LEAD background check procedures. Hot aisle containment submittal retuned Furnish As Corrected, Lighting submittal returned Revise & Resubmit, Structural submittals are waiting on resubmittal, and Generator re-submittal returned as Approved as Noted.
06/17/20 – The Permit Response letter and drawings has been submitted to the city for consideration and approval. This was a large package that required a 100% digital submission for the city this year.
06/24/20 – Lighting submittals were updated twice and returned to DK in their final approved form on 6/19. Structural submittals are awaiting stamp updates before THP takes another crack at that and TEI owes JCI a return on the Clean Agent Fire Suppression submittal. The SOV has been sent to the County for approval. Background checks were revisited and potentially could be 8 weeks out for approvals. Graybach is working on the revised schedule for an Aug 1, 2020 start date.
07/23/20 – Clean Agent submittals have been reviewed and returned to JCI. We also inquired about the wet sprinkler system submittals which were not included. JCI said they have to get another guy in the company to finish them but they are underway. TTE checked on coordination drawings status and permit status from the Partners.
07/29/20 – GBBN and THP have resubmitted permit responses to ThermalTech today. TTE will get the new upload link for the city and complete the resubmission process. Graybach wondering about background check status and updates.
08/19/20 – City contacted TTC with news the permit is approved and some special instructions on the door hardware set control that has to be installed. TTC followed up with Barth and Johnson on that requirement and I think what we have will be fine. Rycca and Bert shared additional background checks information with Graybach and inquired about getting the safety plan in place too.
08/20/20 – Permit is Approved (1000 MAIN – 2020P01574). There is a balance left on the permit that we forwarded to Graybach so they have the information to get the permit in place when the project restarts. We checked on the status of the SOV, Project Schedule, Wet Sprinkler submittal Drawings, Coordination Drawings, and first Payapp with Graybach.
08/26/20 – Graybach asked for SOV comments for this project. After checking old emails it was found that Graybach requested that TEI collect all the SOV comments and submit them in one block. TTE to follow up on today. County provided SOV updates immediately. TTC will get them out to Graybach today.
09/18/20 – This month the FPC came down for fieldwork in the space. New Clean Agent drawings were resubmitted for approval and FPC RFI was sent in on atrium ceiling access.
10/28/20 – This month the LEADS checks go one step closer to being ready. Rycca reached out and started coordinating background checks with Graybach. The wet fire sprinkler submittals arrived for review yesterday. TTC updates Spencer and Ken on CH Server Room progress.
12/10/20 – TTC reached out to Graybach at the end of November to follow up on Structural submittals for this project as we have not heard anything new. DK has UPS equipment in town for this job. TEI instructed them to work billing through Graybach if funds are needed to be paid. Graybach working on background checks and a revised project schedule for Jan 2021 start times. County says a large number of LEAD checks are approved, we must be started by Feb 1, 2021.
12/30/20 – TTC reached out to Graybach for updated schedule, final submittals and Pre Const #2 schedule.
12/31/20 – Archive the Design and Bidding, move January 2021 to Courthouse Server Room Construction.

CH – Server Room Consolidation Read More »

CH – AHU-51, 53, 54 Replacement

01/25/17 – TEI submits SOSS for project. Project pending SOSS approval and PO.
11/17/16 – Hamilton County requested SOSS.
02/16/17 – TEI, Facilities and Building Manager meet on site to kick off project.
02/22/17 – Trane has provided first cut sheet on modular unit for this job, we are trying to fit it into different locations, we are going with a 20 ton unit.
03/01/07 – ThermalTech sent preliminary equipment locations to the County and requested fieldwork to follow up on schematic design. We could potentially have a design meeting at this point and solidify where the unit will be installed.
03/09/17 – ThermalTech updated the floor plans after another field trip down to the site and proposed a final location of one 20-ton unit on the 6th floor with locations for new ductwork and a new wall to enclose the new unit. The county to follow up with Sheriff about using this space for a new unit. TTE moving forward with schedules and Trace runs.
03/15/17 – Revised cost estimates sent to Bert. We are still overbudget but not as badly after electrical modified their cost. We are waiting on revised data from GBBN and THP prior to making additional changes to the estimate. We can make the 6th floor unit work but now its a capital investment issue. Load calcs are complete and we can serve these spaces with a 20 ton, 10,000 cfm unit and we believe we can fit all the adjoining ductwork together to make that happen, the unit would go on the 6th floor.
03/17/17 – TEI contacts GBBN and THP, requesting Architectural and Structural respectively, assistance on this project and included the 5th and 6th floor proposed work drawings for reference.
03/20/17 -50% design dwgs were sent for review to Bert, Tony and Andy. The construction estimate is a little higher than the 192,000 originally budgeted. We are currently trying to finalize the general and structural numbers.
03/20/17 – GBBN sends estimating input to ThermalTech on Architectural implications of the project.
03/21/17 – Spoke to John Milar at THP and we will meet on Thursday to review the AHU locations for the Alternate bids.
03/23/17 – THP – Project explored different approaches not to provide platforms. Meeting now planned to evaluated platforms on 3/23/17.
04/26/16 – Jail Holding unit was added to the design and added as an Alternate to the job. New review drawings were sent to County on 4/25. Additional budgeting was requested for additional design and change orders by owner.
04/27/17 – THP reviewed field conditions and analysis original drawings. Proposed unit and location do not require modification to the structural frame.
05/12/17 – Project is 90% designed but in holding pattern awaiting bid results from the JC Platforms.
06/26/17 – Received revised budgets from Trane on this project and worked on relief air scenario a little bit more. Bid opening could be in July for this project.
06/28/17 – Render the Jury Room for Judge Shannon to see the new ductwork and VAV box.
07/20/17 – GBBN and TEI meet with Facilities for a Field Verification session on site.
07/24/17 – Design team met on site with GBBN to start wall and ceiling work. Some abatement is required at windows we are using for this project. Wall layout confirmed. ThermalTech updated HVAC drawings and they are ready for review. It was decided the Jury room would have an L Soffit instead of a new ceiling, TEI to work with GBBN on this and add access panels for VAV box maintenance.
07/24/17 – GBBN meets with Pinnacle Engineering and Facilities to examine the extent of abatement required around the existing windows and wall peeling paint. Facilities confirms abatement will be included in the Bid Package for this project. Abatement required is the removal of the interior window glazing putty (with window removal), scraping of the peeling and loose lead paint and removal of all pigeon droppings on the sills and wall surfaces. This will be the same for all four (4) windows in this area affected by the scope of work.
07/27/17 – Controls price came in yesterday for $20,000 to upgrade the system for the new layout. This includes removing three units and extending new controls to the new unit named AHU-53N. ThermalTech proposed new smaller soffit and VAV in mezzanine, county okay with this approach.
08/21/17 – Meeting with TEI and GBBN to view area and existing windows to the south of the visitation booths.
08/30/17 – TEI will get ITB and estimate complete this week, project to be Issued for Bid on 9/7/17.
08/31/17 – BW stated that he thinks the drawings are good to go. TTC stated he needed to update the HVAC details for access through the visitation booth add notes for painting the louvers to match the outside of the building color on that row.
09/19/17 – The prebid meeting was conducted today with good turnout by many contractors, some mechanical and some general contractors attended.
09/25/17 – Addendums 1 & 2 have been issued for this project. The bid opening is scheduled for Oct 12 for this project.
10/24/17 – Addendums 3,4,5 have been issued and the Bid Opening extended to Nov 2 for budget issues and equipment clarifications.
11/14/17 – TEI and GBBN attend Post Bid Meeting with Apparent Low Bidder at TEI’s Offices.
11/28/17 – GBBN and ThermalTech have update the drawings to Permit status and removed all the work not being installed and updated the floor plans to make the fifth floor room the new Mechanical Room. Some work remains and some coordination still remains but we believe it will definitely work it is just small spaces and not a lot of free room around the equipment.
02/08/18 – Const Mtg held. Submittals are coming in and being returned to contractor. ThermalTech met Triton on site for fieldwork.
02/19/18 – All HVAC submittals returned. Permit cost worked out with Triton, they can follow up with the City for costs.
02/20/18 – Door, Frame and Door Hardware submittals stamped “Approved as Noted” and returned to ThermalTech.
03/12/18 – Pre-construction meeting held with Triton for this project. Project schedule, SOV, and additional submittals required from Triton. Permit not ready yet, Triton to work out final cost with city, ThermalTech has worked out all the details with the city plans examiner. Triton to distribute meeting notes and revised schedule.
03/21/18 – VAV submittal returned for Tuttle and Bailey with revised btus per TEI markups. Fire Protection & Controls submittals still need review by TEI.
03/24/18 – HVAC Permit is Issued per EZ-trak. Electrical permit is reviewed and on hold for pickup by EC. Next Meeting is Monday. Triton reported today that the room is not clear for construction yet.
04/23/18 – Const Mtg #4 – Triton is on site working on demo and new work. AH-53 has been removed from KP area. New ductwork is being installed. Existing pipe has been turned off and some of the existing piping has been capped off. A leak in Cooper area may be related to our work and shutting down our heating hot water to AH-53. Work is on schedule.
04/09/18 – Const Mtg #3 held and meeting notes distributed. We worked on some of the supply duct routes and return paths.
04/23/18 – Const Mtg #4 held and meeting notes distributed. Reroute return duct KP area, submit CO for sprinkler piping change, finalize HHW and CHW lines to and from units and some of the piping in Shanahan area will be below the duct.
05/07/18 – Const Mtg #5 held and meeting notes distributed. Honeywell on site and starting to work, interior lighting in AHU discussed, const mtgs changed to weekly for final run, Triton to cover all vents in Shanahan’s area and clean debris up daily in work area.
05/14/18 – Const Mtg #6 held and meeting notes distributed. Triton asked to submit change orders for extra work on this project so far. Shanahan soffit will be converted to rigid board ductwork and pants fitting to be fixed before insulation.
05/21/18 – Const MTg #7 held and meeting notes distributed. We are wrapping up Shanahan courtrooms and moving over to Cooper area. Honeywell controls are in place and starting to control the unit. IBI inspection schedule for next week KP ceiling should be going back up, change orders approved, painting has started and we are moving into the final phase of the project.
06/26/18 – Final inspection was approved last Monday. Mechanical and Electrical punchlist have been distributed. Request for Change Order Work #2 has been designed by TEI and sent to Triton for pricing. We have a rough idea of contingency monies left on this project and will try to fashion the changes with that remaining funding.
07/16/18 – Met AAB on site for testing of the airflow through the AHU. We tested the unit at various speeds and took videos on the inner workings of the unit and discovered at 45hz water migrates from the drain pan to the fan section under the drain pan divider. We will contact the manufacturer to rectify this issue.
07/25/18 – Final punchlist was back checked this month. The water leaked returned to which TTE and Triton have been working to resolve with JCI almost daily – there is a lot of behind the scenes work and communications Facilities not included on discussing issues and remedies for this problem. As of yesterday, Triton has increased the depth of the trap, resealed the interior of the unit, and tested interior drainage. JCI tested the levelness of the unit and found it to be installed properly, water was poured into the drain pan and found to drain back and down to the outlet of the unit and at 40hz all seemed to be well.
07/26/18 – The unit was set up to 45Hz and allowed to run overnight at the higher speed. If the unit is still dry we will release it to automatic operation.
08/28/18 – TTC went on site with Triton to work out the reheat coil fitting above the mezzanine in Shanahan’s area. It’s a very tight fit and the two other VAV boxes have to have their supply ducts move so the new zoning works. Other than that one coil, everything else was fitting well. TTE approved controls submittals last week and confirmed with Randy Waddell yesterday for final order.
08/29/18 – Triton reported things are going well but contacted Honeywell to see when they will be on site adding controls and piping to the system.
09/24/18 – ThermalTech met with Triton last week to hash our some piping changes that were not making sense in the field and Triton is making those changes this week, followed by insulator and controls contractor wrapping up. All work to be done by Thursday September 27. Triton still working at night. TEI still looking for hot water reheat lockout temperatures from Honeywell.
10/23/18 – All change order work is complete and the system is programmed into the controls. Space temperatures look good today and the heating appears to be on. All spaces are 72 and above. TEI will start the closeout process on the project.
11/29/18 – Triton dropped off the OM’s yesterday to ThermalTech and TTC hand delivered them to the County including final payapps and closeout paperwork at the Partner Meeting. This project can be archived.
01/22/19 – Project running good. TEI collected all sensors from the space except for the one in the Sheriff surveillance space. Hopefully Barth will recover that for me.
01/23/19 – Project Ready to Archive.

CH – AHU-51, 53, 54 Replacement Read More »

TEI – General Services

01/26/21 – Website updated, jquery issued addressed, 3 plugins updated, PHP security issued researched.
02/25/21 – Updated all proejcts for virtual partner meeting. Updated PW rates.
03/25/21 – TTC archived previous contract general service post to the TEI-General Services- Archive.
04/29/21 – Domain Name renewed with locking. Website updated. New scripts updated but TTC still to update more features this month after meeting.
05/26/21 – Updated the website this month, uploaded the PW rates for the month, udpated the legal wrap for Jill becoming the Interim Purchasing Director.
06/25/21 – Website updated, Partner meeting moved to Friday and it will be in person this month.
07/29/21 – Partner meeting. Website updated.
08/05/21 – Website down, TTC working repairs.
08/12/21 – Website restored through Doteasy, although WebFeat was also contacted.
08/16/21 – TTC backing up website locally in the hopes of moving to the WordPress.com servers, website down again. TTC working on restoring.
08/18/21 – TTC restored the website from my local backup and will start backing up monthly after the partner meeting. I need to address jquery degradation soon.
10/04/21 – Bert contacts TTC informs him the website is down again. TTC restores but the website keeps crashing again daily.
10/25/21 – TTC spends most of the day troubleshooting and restoring website backups, isolates issues to plugins on the website. I disabled all plugins and started enabling them one a time. Eventually got the website working, but the formatting was not quite right. I reached out to WebFeat to fix formatting by partner meeting.
10/28/21 – Website crashes again and TTC restores website. TTC and MCB attend Partner Meeting.
02/24/22 – Website updated. Scripts need to be updated soon. PW rates uploaded.
03/31/22 – Attended PM meeting.
04/28/22 – Attended PM meeting in person.
05/25/22 – Final Energy Report sent to Ralph for sharing with Holly and Jeff.
05/26/22 – Afternoon meeting. Website update last two days.
06/30/22 – Website updated for meeting.
07/28/22 – Website updated for meeting.
08/25/22 – Website updated for meeting.
09/29/22 – Website updated for meeting.
10/26/22 – Website plugin not working, TTC reached out to WebFeat for repairs, now we have a security issue in items, TTC reached out again with screenshots.
04/26/23 – Elementor plugin needs updated, TTC to do when after Partner Meeting.
12/15/23 – TTE to provide JC and CH CAD Background updates for Archibus. Start conversation with new partner for this work.
03/28/24 – Go Reds, Opening Day 2024. Barth wins Design Partner of the Month! Hahahaha.
04/12/24 – Webfeat finished updates on the HamCo website. Fixes Elementor, Jquery and other pending updates. Backs up website and gets rids of all update prompts.
04/20/24 – TTC creates access for Elevar on website.
07/17/24 – Website hacked. Support ticket submitted. Website repaired in two days and additional securities added.
07/24/24 – New website securities added and users edited with new system. Target Range not working, new support ticket submitted by TTC. I disabled GBBN access to website but left all their post intact.
08/01/24 – Updated Prevailing Wage Rates.
08/01/24 – Updated Prevailing Wage Rates.
09/01/24 – Updated Prevailing Wage Rates.
10/01/24 – Updated Prevailing Wage Rates.
11/01/24 – Updated Prevailing Wage Rates.
12/01/24 – Updated Prevailing Wage Rates.
01/01/25 – Updated Prevailing Wage Rates.
01/09/25 – Updated Prevailing Wage Front End document shared with everyone.
02/01/25 – Updated Prevailing Wage Rates.
03/01/25 – Updated Prevailing Wage Rates.
04/01/25 – Updated Prevailing Wage Rates.
05/01/25 – Updated Prevailing Wage Rates.
05/19/25 – Downloaded new MEP RFQ.
06/01/25 – Updated Prevailing Wage Rates.
07/31/25 – All Partners were instructed to reinforce the County requirements for construction including but not limited to no parking onsite, Badges displayed at all times, do not visit HC spaces outside of the project scope, no using county tools, no using county supplies.
12/11/15 – Website updated, PW rates updated and sent, mid-month updates being sent by Ted.
08/27/26 – New County Bid Advertisement & Front End Released
09/04/26 – Small Project Quotes packet updated by Kerry and Jill.
09/23/26 – DEG getting badges updated Q4 2026.
10/27/26 – Worked on creating a new category parent category to separate projects into Active, Closeout and Archived. Category is created, navigation is updated, but operation is not quite right yet.

TEI – General Services Read More »