Courthouse AHU-21 Refurbishment

Building Operations Project

08/06/15 – Temperature probes put in space to monitor temperatures. Temps and space seemed to be tempered well. Temp and humidity within reason. ThermalTech collected original design criteria from Trane on AH-21 and all the other air handlers ordered at the same time from Trane and shared this with the County.

08/12/15 – Preliminary report sent to Tony Matre. Unit is undersized for space at full load and number of people for space. Trace load calc shows 12.5 to 15 tons of cooling required. Existing unit is 5-7.5 tons but space seemed conditioned much better than this.

08/19/15 – Tony requested new SOSS to replace AH-21.

09/23/15 – Tony Matre asked for an SOSS to replace AH-21.

10/14/15 – We decided to bid this project as a Small Project bid.

10/28/15 – ThermalTech met with Facilities to start filed work today on this project for small project bid.

11/25/15 – All bids came in above $50,000. Bidders were advised that no contract could be awarded. ThermalTech contact Trane immediately to inquire about a rebuild project under State Term we had discussed previously. Trane started working on a new proposal immediately.

12/04/15 – Trane submitted a new price. TEI approved scope and cost for a preliminary PO for this work. New coil and motor should help meet max conditions in this room.

01/12/16 – TEI sent state term contract in for approval with Tony and Don Webber.

02/17/16 – Don Webber sent back and email saying he was awaiting comments from County to proceed with work.

02/26/16 – Tony says contract just needs to be signed by Trane and we can kickoff the job. TTC will advise Trane.

03/30/16 – Contract and PO approved, equipment is ordered, waiting for Trane to start.

04/15/16 – Equipment is ordered and will be here in a few weeks. Trane getting background checks in order.

05/18/16 – Trane technicians on site setting up project work. There is discussion about the motor upgrade and VFD size.

06/22/16 – TTC sent out the punchlist and asked Trane for feedback on why the bigger motor was not installed. TEI also recommend that Andy increase the SP of AH-21 to 1.5″.

06/30/16 – Trane received the punchlist and thought they many not have add the motor to make the unit work with the the new coil. They are verifying this. TTC dropped off 5 temp sensors on Tuesday to track temperatures in space. Apparently the worst time is coming out of nigh setback on really hot days. TTC and Tony discussed the next steps after the VFD is up and running at 100%.

07/18/16 – TTC sent VFD data to Trane and asked them to continue with the motor replacement as included in the contract. TTC sent summary field report to Andy and Tony for Room 260 showing that the room is not maintaining temperatures when its over 90F outside and cannot reach 72 on Monday until 4:00pm in the afternoon after hot weekends.

07/21/16 – Don Webber from Trane and his technician will be the Courthouse on Friday to look at installing the motor as part of the contract work for AH-21. My fieldwork shows we are not meeting temperatures on over 90F days and coming out of night setback on the weekends.

07/27/16 – Talked to Tony and Andy, Trane was down and checked the motor and VFD and told Tony that something did not match up. I am waiting for more details from Trane as promised.

08/03/16 – TTC check in with Trane on 8/1, no updates yet.

08/11/16 – Trane sent field reports, TTC looked over the reports and responded requesting a phone conference.

08/31/16 – TTC talked to Andy and request more info from Trane. Running the system at 100% still does not cut it on really hot days and hot weekends coming out of nigh setback

09/08/16 – Closeout meeting scheduled with Trane next Friday 9/16.

09/16/16 – ThermalTech met with Trane and Courthouse to discuss next steps. Trane will resheave the fan, ThermalTech will take the air readings next week.

09/27/16 – ThermalTech was on site tonight getting airflow measurements on this unit. TEI to issue field progress report to Tony and Andy. The basic readings were that AH-21 is delivering at least 2500 cfm so it meets the original design.

11/10/16 – We have contacted Trane to resheave the motor again. The extra duct was traced out by Andy and Terry and fees only the hallways, it can probably be throttled back.

11/16/16 – TTC contacted Don Webber again for a status update on this project. He is out until 11/21.

11/25/16 – Trane said that they were sending at technician down to resheave on 11/17.

12/09/16 – Work is complete by Trane and unit is resheaved. TTC and Andy to verify next spring for cooling load capability.

Courthouse AHU-21 Refurbishment Read More »

COURTHOUSE – Server Room Study

Partner Lead: ThermalTech

08/12/15 – Bert sent approved SOSS to ThermalTech to update the Archibus cost estimate for this project.

08/16/15 – ThermalTech transferred all three old estimates into one new estimate in Archibus for partners to start working on.

08/21/15 – GBBN coordinated new scope with Bert and ThermalTech for estimate phase of project.

08/24/15 – GBBN completed GC estimate in Archibus. ThermalTech completed Fire Protection estimate in Archibus. GBBN sent updated floor plans to ThermalTech with new door locations and walls to update estimate.

08/25/15 – ThermalTech updated part of the HVAC estimate and finished the plumbing estimate n Archibus.

09/24/15 – ThermalTech meeting with Facilities and CMS on Friday to discuss scope and estimates.

10/14/15 – Previous survey data shared with team. ThermalTech to update report and give to Bert for review.

12/08/15 – ThermalTech has started editing the revised copy of the report. Still waiting on return data from Owner, will follow up with Bert on what to do next. We discussed updating the report and floor plans. Revisit the equipment required, floor plan, cooling units, ups systems and structure.

01/25/16 – ThermalTech will finish this report in the first quarter of 2016.

03/09/16 – Bert provided server room worksheets for ThermalTech to begin working on new server room report.

03/29/16 – Bert provided a Duke Rebate for Server room idea for ThermalTech to investigate.

03/30/16 – TTC tabulated the new data sheets and shared them with Bert. New load is about 40 tons maximum including 25% future growth. We are going to verify server counts from other departments. [PDF]

05/18/16 – Bert to schedule a meeting to discuss funding on this project. Design will begin later this year.

06/27/16 – TTC check a minor change to the load calc sheet based on a formula he updated in the JC Server Room project. TTC and Bert discussed adding data rack and cabling cost to estimate #1827. County is discussing funding availability for this project. Cost are in put and updated.

07/15/16 – TTC schedule design time in third quarter 2016. All cabling and additional charges are in the Archibus estimate except possibly a core switch.

07/27/16 – Archibus estimate updated to include racks, fiber installation, and core switches. Facilities sends Municipal Court Courtroom suggested modifications for adding new offices. Facilities requests Archibus estimate to be updated to include these suggested changes. GBBN to update this final piece of work. We will look at room after partner meeting Thursday.

08/25/16 – Cost estimates updated with additional offices.

09/28/16 – No current updates. All information is into the Archibus system and we are on hold.

10/27/16 – Roof 10 being laid up with new roof membrane. Approximately 75% complete.

10/27/16 – Roof 10 change order work includes new steel posts beneath steel stair to provide bearing to structural roof. Also getting price to truncate four 2″-3″ diameter pipes abandon atop roof slab from old RTU. truncating pipes below structural slab to remove additional curbs/saddles from new roof.

10/27/16 – Roof 6 existing roofing system demolished and temporary roof membrane installed. Contractor may start work laying up new roof as early as next week.

10/27/16 – Subcontractor completed sealant work at terra cotta water table adjacent to Roof 10.

10/27/16 – Subcontractor preparing quote for additional 200 linear feet of sealant work at cracked terra cotta. Pieces adjacent to Roof 10. Work needs to mitigate water intrusion behind new roof membrane.

12/29/16 – Awaiting direction from Owner on this and related projects.

02/22/17 – Awaiting direction from Owner on this and related projects.

COURTHOUSE – Server Room Study Read More »

COURTHOUSE – Fire Alarm System Study

Partner Lead: ThermalTech

04/27/16 – ThermalTech Submitted SOSS to Bert Watts – SOSS was approved and PO issued to ThermalTech.

05/25/16 – TEI is instructed by Building Ops that the full replacement of the system will not be completed at this time and that the balance of the SOSS shall be used for CA assistance with Honeywell replacing the non functioning components only at this time.

08/23/16 – BW indicated at last months meeting that the replacement of the Fire Alarm System will be included in a project request with the Server Room Project when the Server Room Project commences.

12/29/16 – Awaiting direction from Owner on this and related projects.

02/22/17 – Awaiting direction from Owner on this and related projects.

COURTHOUSE – Fire Alarm System Study Read More »

COURTHOUSE Facade Exam

Partner Lead: THP

02/24/17 – Hamilton County requested SOSS.

03/02/17 – THP provided Hamilton County with a SOSS.

03/09/17 – County approved SOSS.

04/27/17 – THP working on report.

05/25/17 – THP working on report.

06/29/17 – THP anticipated to issue final report.

07/07/17 – THP Final Façade Assessment Report to County.

07/11/17 – THP issued an opinion of probable cost for City façade repair work.

07/17/17 – THP submitted report to City along with fee.

08/17/17 – THP received an approval letter for the submitted Façade Assessment report. In addition, the letter included a violation notice for work to be performed within the next year. Once the work is complete, a report noting the completion of the work needs to be submitted to the City. The due date for the completion of the work and submission of the letter is August 9, 2018.

COURTHOUSE Facade Exam Read More »