230 – Humidification in Rooftop Unit

04/22/05 – TTC faxed over a letter stating the deficiencies of Application # 01 on this project. All final paperwork is missing.

03/25/05 – TTC completed punchlist on job. There are no items to fix. Geiler submitted final pay application without any final paperwork. TE will ask for closeout documents.

02/25/05 – TTC asked Geiler for update and if they are ready for TE to punchlist this project.

02/11/05 – TTC talked to MF today. Geiler has the piping complete. The insulation is on the piping now. TTC will perform the punchlist next week on Monday or Tuesday.

02/08/05 – TTC visited the site today with Geiler and MF. Geiler should be wrapping up by end of week. Systems are online. Insulation needs to be completed. Geiler is in cleanup stages of piping work. TE to do punchlist within a week. Valve, steam and humidity control appear to be working.

02/02/05 – TE talked to Geiler today. They will be off the job for a couple of days. They have to soak some unions they are having trouble disassembling for re-use. They will be back next Monday for sure if not earlier (I think Bob wants to stop down to soak the unions tomorrow). Elevator and space access issues have been resolved. We were original trying to finish by 02/07 but I believe it will be at least 02/14 before the changes are complete.

02/01/05 – Geiler has started the project during the evening schedule. TE to follow up the MF this week for progress.

01/26/05 – Geiler delivered tools and piping, but wont’ start project until Monday 01/31/05.

01/25/05 – TE and Mike F. walked the project with Bob Burlege of Geiler. We feel as though they won’t be able to start the project unit Wednesday per Bob’s comments but it could be later than that. We are planning on shutting down the steam once in the evening to weld the thread-o-lets on to each header. Then add an isolation valve to shutdown each header and work on each side independently, keeping the building without humidification to a minimum. The pipe machine will be setup on the dock. Piping will be hauled in the elevator. The 230 staff will stay with Geiler the first night to ensure the boiler plant and steam come back online properly. MF will show Geiler how to shutdown and lockout/tagout the AHU’s when working. 120V welder must be used.

01/17/05 – Submittals received by TE. Walk through scheduled for Jan 24, 3:30 p.m. provided that TE approve the control valve submittals.

01/11/05 – Pre Construction Mtg Complete. Geiler projects this to be a 2 week job maximum. They will begin work and stay on site to complete work throughout the project. Pre Construction Notes added below.

09/29/04 – Original Bid Documents have arrived and TE sent to County via UPS on 09/29/04 for approval.

09/23/04 – TE contacted contractor and we are awaiting original bid documents to submit with final contract (3 copies).

09/20/04 – Contract written. Awaiting for TTC to approve and deliver.

09/13/04 – Bids are compiled. Geiler is low bidder. County please advise how to proceed.

230 – Humidification in Rooftop Unit Read More »

230 – Ninth Floor Microfiche Project

03/14/06 – Bill Scholl and Mike Florimonte have both reported that the systems are working great and permits have been approved. This project is being archived at the end of this week.

01/10/06 – HVAC has work above Julie area’s almost complete. They have scheduled an HVAC inspection with Steve Ossege in the coming days. Exhaust was hard to get routed but they are almost complete.

12/28/05 – The microfiche permit was picked up and emailed down to the County approved for use. TE paid and will reimburse the cost to the County.

12/14/05 – TTC setup a meeting for THP to review the space ceiling construction to approve the ductwork hanging method on this job for 12/15. Aaron Bennett will be contacting Mike Florimonte for access to the building. MF reported that the piping, boxes and louvers are nearly installed so far.

12/09/05 – TTC applied for the permit today at the City. The permit number is 2005P09839. It cost $75 to the application fee today and the remainder will be paid when we pick up the permit. All of this cost is a reimbursable cost to the owner on this project for this work.12/02/05 – County trades can’t put the ductwork in as designed on the plans. MF is going to inspect the above ceiling layout and call TTC with details. TTC will stop by the building and give direction as to the best way to proceed to finish the job. TTC informed Tony of the plan. Terry contacted THP by email to verify ductwork loading won’t overstress the ceiling arrangement.

12/05/05 – Terry meet HVAC trades on site to discuss ductwork routing and relocating light fixtures on this job. It was decided the best and easiest way to fit the ductwork into the room was to rotate the lights 90 degrees and remove the remaining light that is interfering with the light fixture. Carpenters will have to do some ceiling work to patch and paint the areas that are affected by the ductwork and fan supports.

11/29/05 – HVAC called with questions about moving the VAV box in Julie’s office because it was interfering with new ductwork. TE said this was fine. HVAC called with a question about framing the fire dampers in one big angle frame and TTC said this was fine also. In email correspondences today, we believe all issues are up to date and the work in on track.

11/21/05 – TE and the County met at the site to discuss Sam’s HVAC design and coordinate with the tenant and trades for making this work out. Everyone was in agreement that if we could bring both ducts into one corner and just create a matching column in Linda’s office that would be fine. The people in attendance were Mark Perry, Tony Matre, TTC, SRB, MS, Dave S, Bill S, Jim E, Ernie, Mike F, Paul and Jerry.

11/16/05 – TTC and Tony discussed the bidding out of this project and the method in which the money and trades would do the work on this project. Wayne would like more controls11/15/05 – Review drawings were sent to the County today. TE would like to get comments back about this job as the County’s convenience.

11/10/05 – Wayne called and said that the draft design is OK and to proceed with a permit set of drawings, so trades can do the work. He will also contact TE when he has set up a Archibus job number, so we can enter a cost estimate.

11/10/05 – Wayne called and said that he would like trades to do the work. He said that he would check with Mike Florimonte to see if draft design is OK. After final client approval, TE will then put together a drawing set for trades.

11/04/05 – TE sent Mike Florimonte a draft of the HVAC layout to see if Manager of that area is OK with design. Design included exposed ductwork in the Vault to avoid redoing the ceiling, to allow for concealed ductwork.

11/02/05 – TE is putting final design together. Sam and Mike will be making a field trip down to the building on Friday to set routing and check clearances.

10/13/05 – TE and CR met with the client to finalize building and design standards for this project. CR has to submit an SOSS. The equipment will be in the building in about 2 months for this job. TE must do the design immediately for bidding.

08/30/05 – TTC received installation manual from vendor in San Diego. TTC sent pdf to County for their use. Heat and Electrical requirements were provided by vendor. TTC got many other calls from salesmen at Anacomp who because ThermalTech was inquiring believe they were somehow being left out of the purchase loop of the equipment. TTC assured them that the County is in control of purchasing the unit and ThermalTech was only designing the room that the equipment when and if purchased would reside in.

08/25/05 – TTC contacted manufacturer today to collect engineering information on unit for installation including btuh rejection, power req’s, exhaust req’s and mfgr’s installation instructions. I had to leave a message with their main office.

08/22/05 – MF called to say that after talking with some people, the belief is that the vault walls are reinforced concrete and not just metal stud walls. TTC and MF talked about airflows in the room and the floor and TTC believes that the design should most likely be to add one separate VAV box for the microfiche machine and exhaust the entire room. The machine should most likely go into the vault area where the room can be separated from the general airflow of the space.

230 – Ninth Floor Microfiche Project Read More »

230 East 9th Street Electric Device Study

01/10/07 – This project is complete and archived on 01/10/07

08/18/06 – Drawings have been delivered to Hamilton County Facilities. There are no open issues on this project.

06/14/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Mike Florimonte). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

230 East 9th Street Electric Device Study Read More »

230 – Boiler Stack Study

03/05/08 – TTC and Tony figured out the billing issues and TTC sent an email to Grady on how to bill for extra services. The actual project is complete. The County has to fix its own PO to pay Triton but TEI work is complete on this project.

01/25/08 – Tony and I talked today about closeout on this project. Grady is to bill the County the remaining balance as a change order to this job. I will write a change order to match the total amount owed to Triton on this job. The County has a PO invoicing issue on this job (JC bill to this PO).

11/16/07 – TTC talked to Mike F today about project status and sent AKM the following email:

The summer boiler flue temperatures are still no where near 310 F so the fix worked to make things better but we are still probably going to have condensation issues.

The winter boilers are on now and they are slightly better also but we are still not getting 310 F at the outlet of the boiler stack. I told Mike that we should re-smoke test the boiler stack just like we did at the start of the project to see if any drafts are still cooling the boiler stack down as the flue gasses go up.

Mike believes that Triton did a pretty good job buttoning everything on the boiler stack from the job that we bid out and the extra work that you had them do on T&M inside the building. We just aren’t getting as good as results as we would have liked.

The summer boiler is slightly over 2,000,000 btuh which means it would take 4 of the Knight boilers to replace it and meet the same load. We could do this if it was the only problem you still had. The large winter boilers are 5mil btuh so those cannot be replaced by these hot water boilers so we are still kind of faced with some of the same problems with temperatures that you have faced from the beginning in that the outlet temperature at the top of the boiler stack is under 310 F.

and told the County that when they were ready to take the next step to let ThermalTech know and we can help with the design or problem solving.

05/22/07 – Triton submitted their final payapp for the project. There is a $980- change order for the extra camera work. This increases the contract amount and TEI needs approval from the County to pay that. Please advise.

05/14/07 – TEI contacted Triton for closeout documents. Grady said they would send them in ASAP. TEI will return a video copy of the boiler stack video to Grady to closeout the project. TEI has been in contact with MF about the type of brick to replace in the chimney wall to maintain integrity and this would be solid lightweight concrete block according to Spencer at Cole Russell. This project is ready to archive. 12/04/06 – TTC questioned the use of the full allowance today ($5000) and requested an itemized breakdown from Triton for the work completed. The dwgs ask for the the wall to be built by the contractor but that has not been completed to date. The additional work that TEI is aware of is sealing the upper stack and the camera record of the interior. TEI asked for the requested change order to seal the outer stack to be taken from the allowance not as a change order.

11/30/06 – TTC asked about writing a change order to the project for Triton to do the stack sealant work. The project itself is complete. We are moving into the next phase for 2007 where we will address insulation the stack in some way to keep air from overcooling the inner shell. The County is going to open up the wall sections to allow Triton to patch the outer wall of the boiler stack. This can happen right away if the PO gets approved for Tony. TTC asked the County for an update today.

11/13/06 – A lot has happened since the last entry to which i will summarize. Triton has been on site and finished the work. A camera was dropped down between the stacks for a record of how they were built. We discovered that the outer shell had 3 large rectangles removed where spaces were welded to the inner stack. The stack was not support to the outside wall as originally intended. We believe these holes are contributing to the excessive draft up the stack causing a high cooling effect on the boiler flue gas. We instructed Triton to seal the top of the outer stack to the inner stack with a metal seal and put the breeching cover back on seal it air tight with caulk. In the basement Triton sealed the inner stack against the outer stack where the new stack enters the side of the old stack. They did this with steel plates and welds. The temperature sensor is installed and monitoring outlet temperatures and we can only see a 2-degree rise in temperature with the stack being sealed top and bottom. This is not surprising since the are three gaping holes in the outer stack wall on the 4th, 8th and 12th floors that may still be an escape route for air movement. As this is the first stage of the fix it plan being used for investigation as well, we are formulating the second stage now. We want Triton to patch the remaining three holes by change order if necessary. In step two we may try to fill the interstitial space between the stacks with concrete and create a permanent insulation space between the two stacks and this way when the inner stacks rusts out, the concrete stack will remain providing a permanent stack for a long time. We have to get a structural involved at that point to help check the loads on the building.

08/28/06 – We held a construction meeting to get a new handle on where the project stands and to review the R&P chimney stack report. Grady brought one copy of the report and Tony asked for 3 copies to be made and given to the County. The report has basically found that the stack is in FAIR condition. The stack was basically constructed in two different segments, the bottom 130 ft and the top 40 ft. In reviewing the original report from 2001 and the new report from 2006 there is considerable degradation from low temperature condensation and corrosion inside the stack. Photographic evidence was provided in the report to support this claim. The wall thicknesses have decreased and will continue to decrease and the new temperature outlet sensor installed in phase 1 of this project has further provided trending and data to prove that decent outlet temperatures at the boiler flue’s in the basement are significantly reduced in their upward travel to leave the building. Mike Florimonte provided a trend that showed summer boiler leaving temperatures of over 500 F but at the outlet of the stack temperatures were only 210 F. This is a condition that will cause low temperature corrosion. R&P is recommending a spray on coating to protect the interior of the stack. Triton and ThermalTech recommend further investigation into the over cooling effect on the boiler stack. For this much temperature loss to occur, we believe it must be related to the high velocity draft witnessed around the boiler stack at a previous field trip by TE. We have scheduled a Saturday visit with Triton to set off a smoke test inside the boiler stack. We want to witness the path of the released smoke and find the air path that is causing the stack losses. In essence the space between the inner stack and out stack should be dead air space. In addition, Triton will investigate the OA paths surrounding the boiler stack to help ensure that no OA is subjected directly to the boiler stack space. Once this data is resolved, we can isolate the boiler room from the chimney stack and address other “sealant” issues with the new and old breeching. We are scheduled to meet on Sat, Sept 9th. MF will alert the building occupants. AKM requested a synopsis of or plan of attack.

06/16/06 – R&P Industrial Chimney showed up on site. At 2:17 they completed their fieldwork and reported the seems in the stack appear to be the worst off. The took a disposable camera and ultrasonic machine into the stack with them. TTC asked for them to call with a report after they packed up.

05/22/06 – Boiler stack inspection still set for June 19th. Grady is checking on controls and trending.

04/06/06 – Mike called today about getting study complete and temperature sensor in place. Grady replied that the inspection could be the middle of May. The County will need this inspection to be completed either after hours or on the weekend because of hot water reheat. TTC to review and try to find a holiday instead that may work better.

03/09/06 – Pre-construction Mtg was held and notes distributed.

01/17/06 – Wayne reported today that the Bid from Triton did not included a personal property tax statement or a ohio dept statement. TE to check and correct for Wayne.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

12/01/05 – TTC found the original bids for the job (in sbu’s mailibox) and sent them on to Tony for his use. As soon as contract is approved we can have a pre-construction mtg and get the project moving.

11/08/05 – Tony authorized ThermalTech to write the contract for this work. TE will try to get it done in one day.

10/18/05 – All bids came in and contractors are calling for bid results. TTC gave to Tony and Mike on 10/20 for review. Bid Results – PDF

10/14/05 – No addendum had to be issued. Bids are due next week. TE has received a couple of “No Bids” on this project already.

09/29/05 – Final Project manuals have been created. IES information added for controls. Prebid is set for Oct 6 at 9:30 a.m. TE invited Peck, Triton, Process, Geiler, DK and Langdon to bid the project.

09/09/20/05 – TTC is reviewing Sam’s final drawing and project manual.

08/31/05 – MF reported that with their flow hood the outdoor access door when opened drew 1600 CFM with boiler make-up and exhaust running and 650 cfm with the MUA and EF off. This may contribute to extra cooling down of the boiler flue and TE is investigating welding the outer shell closed during our project. TTC cannot explain the huge draft of air up the shaft at all times

08/30/05 – TTC stopped by the site today to review an access door in the side of the building. There appears to be a huge draft from the outdoors into this access door and it apparently is going up the stack and exiting somewhere that in undetermined. This presents a problem with finalizing our design. We can still go about sealing the basement mechanical room as planned but after we are all done there may still be another step to isolating the inner/outer stacks when we are complete and re-measure the infiltration airflow. In talking with Mike, TE may give Mike the cutout for the future access door. If we cut the whole in the drywall now so we can investigate better how the inner and outer stacks are routed through the building. TTC needs to look at original report and talk to contractor about installation method. There are still unknowns about the original design that are affected an effective solution to this problem.

08/25/05 – TTC sent out final bid manual for review today to MF and AKM. Bid opening might be on 9-7-05.

07/18/05 – TE started the small project manual for bids today. TE has to create a new SOSS because the study used up the first SOSS but since so much of the design is already complete TE only wants to write the new SOSS for $2000 instead of the standard $3500 for bid and contract administration.

06/17/05 – TTC and MF discussed the report today and TTC recommended that we put a small packet together now to close up the air space around the stack. An incremental approach to fixing the problem is best. After the space is enclosed, the stack losses should be re-measured at various conditions to asses the new operating characteristics of the boiler plant. This should be done this year if possible. At the same time, a drywall access hole should be cut to inspect how stacks are anchored together. TE will wait for the County to advise.

06/16/05 – TE sent the final report to Tony and Mike for review and use. TE recommended closing off the bottom of the stack leading into the basement and re-creating a dead air space that can be used for isolation the temperature and creating a thermal barrier.

06/06/05 – TE had a meeting today to discuss recommendations. Our report will be out later this week and 2006 estimate will be estimated based on this report. We plan on discussing with Tony and Mike after Mark Miller sends final report to County. TTC and Mike discussed field findings from last week in an impromptu meeting at B-95 today.

05/24/05 – Mike called today and TTC told him that ThermalTech has not done any construction documents yet on this project and that might be due to the fact that we haven’t given Tony a final report on the condition of the stack (awaiting the re-evaluation from either HC Nutting or the other contractor that MF was going to call into survey the breeching) and TE has not provided a written report to Tony and Mike with recommendations about how to proceed. As MF and TTC discussed the situation though, we decided that if something is to be done this year before heating season, the design and SOSS must begin immediately. TTC will email AKM and ask about how to continue work on this project. TE still has $1172 left from the original SOSS that we do not need to used except to provide a written summary to AKM about our findings.

05/11/05 – TTC gave MF HC Nutting as contact for pipe thickness survey.

03/28/05 – TTC & MM met on site and went over boiler stack calcs and heat losses. Too much heat is being loss going up the stack. We need too look at insulating the stack to keep the heat higher throughout the path.

02/22/05 – TTC and MM reported that initial reports look like stack losses primarily are contributed to the low outlet temperature and condensation issues at the 230 building and not stack sizing or entrainment.

02/10/05 – TE received a signed SOSS and posted it to the website today.

02/01/05 – TTC & Mark Miller visited the site for field investigation and SOSS scope.

230 – Boiler Stack Study Read More »

2020 AUBURN – BUILDING ASSESSMENT

05/03/07 – Hard copy report is finished and being delivered to Mark Donnelly.

04/26/07 – TTC told Mark that he would incorporate Don Benbow’s mark up and update the website and give him 6 new hard copies.

04/18/07 – The only comments that we have received are from Don Benbow. We will update the report for the items we are willing to concede and update and send down final copies to Mark Donnelly if he is okay with this approach.

04/13/07 – Issues in disagreement are being worked out.

04/04/07 – Matre forwarded some comments from Don Benbow. TE may incorporate his suggestions into the report. We however disagree with some of them.

03/30/07 – Email copy has been delivered to Mark Donnelly for markup. TEI will provide 6 hard copies upon receipt of HamCo comments.

03/23/07 – Awaiting notification to provide hard copy of report.

03/20/07 – TTC to input report on Wednesday. Report has been input to Archibus. Review set to be hand delivered on Thursday.

03/14/07 – NR created project journal and filled in back data from previous meetings. Report completed, information to be inputted into Archibus on 03/12/07. Hard copy will be delivered during the week of 03/12/07.

2020 AUBURN – BUILDING ASSESSMENT Read More »

2020 Boiler Replacement

01/24/11 – All punchlist and closeout documents have been sent to Bert for this project. Receptacle was moved by Ginter on water softener.

10/1/10 – All work is complete. Seco has not turned in final closeout paperwork yet.

09/22/10 – Peck has scheduled change order work to start at the end of September. ThermalTech has provided answers to the PHB questions on the Change Order work.

08/13/10 – Peck submittals are approved on water heater and all other change order work. Seco change order was sent out for signing. Seco payapps sent to Bert for payment. Siemens payapps sent to Bert for payment.

07/23/10 – Peck change orders are approved. Folck is working on Seco closeout documents and change order forms. Peck is to schedule change order work starting next week. Bert is trying to get PO for water softener.

06/02/10 – Siemens has provided pricing for OM-1 Actuator Option to convert 2-position valves to modulating. Isolation valves will need to be modulating to avoid damaging system shock.

05/28/10 – Boiler installation has been approved by IBI. There are a few minor issues which Seco will complete next week. PH+B has provided pricing to install blank off orifice plates to convert (3) 3″ flanged 3 way bypass valves to 2-way valves for AHU-1,2,3. Blank off plates are 1/16″ thick with a 1/4″ hole in the center for relief and will be installed between the existing valve gaskets and flanges. CB BLR-3 and BLR-4 have been successfully fired and will continue commissioning by Siemens next week.

05/26/10 – Boiler installation has been approved by the State/City and is ready for startup with CB Thursday and Friday (5/27-5/28).

05/24/10 – We had a construction meeting today for the project. All mechanical and electrical work has been completed. Siemens will be on-site all week to install control wiring and begin controls startup / commissioning. Boiler inspections are scheduled for Wednesday (5/26 – State/City) and Thursday (5/27 – Electrical). Boiler startup with CB is scheduled for Thursday and Friday (5/27-5/28).

05/21/10 – HWS/HWR and NG piping have been completed. Condensate drain line and relief valves will be installed Monday (5/24). Combustion air intake has been modified to eliminate 45 degree elbow around conduit rack. All electrical work has been completed including VFD’s, pump, and boiler feeds. Current transformer has been fixed temporarily until new transformer is installed on Monday (5/24). Control panel has been installed and conduit for control wiring was run to boilers and pumps. CC will be on-site all next week (5/24-5/28) to install control wiring, thermal wells, and begin programming with Chris Neff.

05/18/10 – Combustion air and exhaust have been installed for Boiler #3 & #4. (1) 45 degree elbow was used on intake air to avoid conduit rack. TTE recommends (2) 90 degree elbows vs (1) 45 degree elbow for a more appealing installation. To avoid compromising the security bars and make installation more simple, combustion air intake was not installed thru existing louvers. Boiler piping has been started and will be completed by Monday (5/24). Balancing valves or triple duty valves will not be used for this installation. Copper was considered for condensate drain lines to avoid damage by foot traffic, but is not an option due to possible erosion from acidic condensate. If problems occur in the future, condensate drain lines could be changed to sch 80 pvc or stainless steel. Electrician has moved (2) of (4) VFD’s near pumps and will complete installation Wednesday (5/19). Siemens will be on-site Thursday (5/20) for controls.

05/14/10 – Project schedule was updated and meeting notes were sent out from construction meeting on Monday (5/10). All demo has been completed for boiler #2. New Boiler #3 & #4 are currently in the assembly process and will be completed on Monday (5/17). Included boiler legs have been shortened 5″ to accommodate overhead clearance requirements. Boiler #3 & #4 have been positioned on existing concrete pad as shown on TTE drawings. Included boiler exhaust was installed opposite of drawings by factory and will be changed to match TTE drawings. Boiler piping will now be routed between boilers as approved by TTE. HWS valve has been relocated near existing HWS tie-in. TTE considering the addition of balancing valves or triple duty valves for Boiler #3 & #4. Boiler combustion air, exhaust, and piping will be installed next week (5/17-5/21). Electricians will be moving VFD’s near pumps on Tuesday (5/18) to satisfy line of site concerns. Replacement transformer is scheduled to arrive Wednesday (5/19).

05/10/10 – We had a construction meeting today for the project. Peck will begin demolition on Tuesday. Controls and Electricians will be reported next week to start their next phase of work. TTE will work on schedule and meeting notes this week.

05/07/10 – We setup a const mtg for next week on Monday to kick off the demolition on this job and to coordinate the construction issues. The permit has been approved by IBI and City. The real work begins.

04/29/10 – We continue to work on schedule with Peck. PHB came on Wednesday to begin coredrilling for the new vents. The city has the permit held up on 3 issues that TEI sent responses down for reconciliation. The electricians and Siemens are working on a disconnect issue with the VFD’s. Boiler is scheduled to be demolished on May 10 which has been approved by Don Benbow.

03/24/10 – Siemens payapp has been received but the schedule of values is not acceptable. TTC will contact Siemens. Peck payapp has been approved.

03/23/10 – All submittals have been received. All submittals have been returned. We clarified an issue with the boiler vent piping. It can be single wall with personnel protection on this job. A controls meeting is scheduled next week to work on sequences with 2020 and the Siemens. Gary Davies will attend for TEI.

02/22/10 – No word on Siemens. TEI created permit drawings sets for the contractors, as soon as they are stamped and signed, we will give to contractors. Small modifications to venting per the 02/12 visit.

02/12/10 – Met with Peck on site and reviewed project with Foreman. Contact all contractors for submittals. Neff said he could call Siemens for me to find out where their subs are.

01/19/10 – The preconstruction meeting was held on site. TEI has approved the boiler submittals but wants better paperwork. Siemens did not attend the precosnt meeting. PHB and Seco were in attendance and are working on submittals as TEI works on permit drawings for the project.

12/31/09 – Contracts are signed but the BOCC have to approve them before we start. Siemens state term contract is ready. Peck asked for and received an extension on the project completion date. Ballinger informed us through Peck that boiler prices will increase in 2010 if we don’t order in 2009. That is a problem since the contract won’t be approved because of winter hours for the BOCC.

10/19/09 – Bid came in for the project. Peck appears to be the lowest bidder. I confirmed the prices with Bernie. His labor looks low but they are willing to do the project for the price. I know have to look at the LCC for the boilers and see which is best and look at lead times on the equipment.

09/18/09 – Final bid documents were sent to Purchasing and Queen City. The Bid Opening is October 19th. The Prebid is Oct 1. Chris Neff called and wants to go over some drawing details. The controls contract will be given to Siemens under a state term contract. TEi turned over the pdf’s to Siemens but we have not heard any comments from the CC yet. Gary is in the office this week so we need to organize the final details.

08/25/09 – Control schemes are finished. SOSS is approved. TEI is working on design. We need to go back and do more fieldwork for verification and start the design on paper. We are bidding 3 alternates for boilers: Clearfire, Fulton, Sync.

07/28/09 – TTC & TZ visited the site and did the preliminary field work. TTC created and sent Tony an SOSS for the project. TTC will hand deliver the SOSS to Bert at the County Partnering Meeting.

2020 Boiler Replacement Read More »

2020 – Boiler Replacement Phase 2

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/25/10 – Contract for Peck has been sent to Tony for approval. Tony said he was going to pay for Boiler #1 repair this year and install the new boilers in Spring 2011.

01/24/11 – Contracts are in approval stages. Waiting for pre const mtg. Labor will start after heating season, March 2011.

02/22/10 – Pre Const Mtg Complete. Mtg notes being sent to contractors. PHB has submitted boiler paperwork for approval. The original rain caps have been removed on the boiler stacks to prevent ice puddling below the stacks. PHB is looking at installing thimble caps on all new vents. New venting and project schedule must be approved.

03/30/11 – Peck is working on boiler order and delivery. Boiler submittals and electrical submittals have been returned to Peck. We are currently trying to work out a change order on the control valves, actuators and flow meter. The project will begin in May-June 2011. We should be finished by the time summer is over.

05/12/11 – Peck is working on new background checks. All change orders have been sent through. Boilers are ordered.

06/07/11 – Boilers are at PHB and the flues should be there in a few weeks. PHB still needs to get background checks back from the State before they proceed.

06/20/11 – PHB is ready to start some sheet metal demo in the boiler room next week, also finalizing the project schedule for this job.

Item #2 – There are a couple of issues with the control equipment that we need to discuss. The acuator and valve by Keystone apparently is out of stock. They have offered a replacement that we can get, it is slightly bigger than the one we specified. The problem is TTC can’t find this model on their website. Asked Chris who they contacted locally for prices and model #’s.

Item #3 – TTC asked if Siemens or someone else preferred make the paddles wheel flow meter needed. Bernie was looking for a local manufacturer that sells the Badger flow meter, but was not aware of any yet. Did Siemens offer the one we get easily?

07/07/11 – Peck is on site performing demo. Chris has been sharing controls and wiring with the Peck for purchase through Seco.

07/21/11 – Pipefitters are complete with their work. Sheet metal guys are waiting for a fitting for the flues, and will continue as soon as they get the rest of their materials. SECO Electric will be on site Monday 7/25. Start up is scheduled for August 12th, that will give enough time to get everything complete and the boilers inspected. ThermalTech has to provide a punchlist and discuss controls with Chris Neff.

08/05/11 – TTC sent out an email punchlist to Peck from a site visit last week. Bernie said they can get this done.

08/08/11 – Peck submitted payapp #1 but the change order paperwork is not signed yet. TEI asked them to modify their payapp so they can bill more quickly on this project.

08/25/11 – All work is complete except for metal pans on louvers. Boiler alarms not part of new boilers, Bill is working on a separate change order for that. Ready to closeout. Chris is writing sequences now.

09/28/11 – Pay App #1 was resubmitted by PH&B. Approved by TTC 3 copies were sent to Tony Matre on this date.

09/30/11 – We resolved Payapp #1 issues and asked PHB for closeout documents. Tony paid the $102,600 invoice already so we voided the later invoice and asked for a #2 for closeout. The change order was signed on May 13.

10/24/11 – Payapp 2 (labeled 3) arrive and was paid. Payapp 3 (retainer arrived and was held for closeout docs). TTC advised PHB the closeout documents are due before final payment can be made.

12/23/11 – This project will be archived for 2012.

02/22/12 – Chris reports all boilers are working great but there is still some programming left for him to change or update. This project is ready to be archived. All closeout and pay applications have been sent to Tony.

2020 – Boiler Replacement Phase 2 Read More »

Elevator Maintenance Bid

01/10/06 – TTC completed the escalator contract per Kerry’s comments and merged with previous comments. TA will hand delivery 4 copies to PBS today at 1:30 p.m.

01/09/06 – TTC delivered PBS elevator to PBS and bid tabs for their use.

01/06/06 – TTC delivered 230/800 contracts to Tony at the 237 WHT pre const mtg.

01/04/06 – Kerry returned electronic copy marked up. TTC to check over and approve.

12/21/05 – TTC returned electronic copy to Kerry for revisions.

12/12/05 – Contract revisions arrived from Kerry Dowling. TTC to make changes and send out ASAP.

12/09/05 – Kone called today to inquire about new contracts and cancelling old contracts for buildings they did not win under the new bid. Terry told them that new contracts should be forthcoming for official use by end of next week.

11/21/05 – TTC answered questions from the County about contracts. Everything appears to be in order.

11/17/05 – All contracts have been given to County for approval. TTC noted that there is no real need to have a supplementary conditions with the project manual as that is all outlined in the maintenance contract and we don’t use AIA contracts with this type of bid.

11/16/05 – TTC finished the elevator contracts for 230, 800 & PBS and sent them to Joe and Tony for distribution. This time, we coordinated issues like termination clauses, contract amounts with the combined bid savings and decided to split the savings 50/50 between the PBS and Facilities.

11/03/05 – After an initial scare that Addendum 01 did not get posted, Gina realized that the bid doesn’t open until 11/08 and therefore Addendum 01 is posted to demandstar and already has been sent from Ohio Blue.

11/01/05 – TTC is writing the Add01 for escalator project. This job should open next Tuesday. The SOSS has been signed for the escalator change order part of the job.

10/25/05 – Abell/Irvine called today to say that their office has been on Colerain Avenue since 1986. They have got their questionnaire answered and turned in with their bid. TTC ask Purchasing to fax a copy of it over to ThermalTech for review. TTC told everyone that the bid spec stated up to 5 buildings with 5 years experience. Tony called and discussed with TTC the new elevator contracts.

10/24/05 – Bids were opened. Fujitec did not bid the job. Kone didn’t their bid bond, Schindler withdrew their bid after TK’s opening bid, ThyssenKrupp and Abel/Lincoln turned in appropriate bids. TTC contacted both vendors for qualifications. TK provided a fax with all the documentation today. I have not heard from A-L but their number turned out to be long distance so I don’t consider that a good thing.

10/18/05 – The escalator bids immediately went back out on the street because no bid against Kone. Joe and Terry set the new bid estimate based on past numbers for the work in an attempt to make sure Kone didn’t try to overbid as they may be the only one entering bids on this project.

10/14/05 – The final addendum was issued to the contractors that dealt with questions from the prebid and mostly insurance and indemnity. TTC incorporated answers from the HamCo prosecutors office and risk managers for those issues. Also there is concern that one of the vendors does not have a full time office in the City as required by the bid. They also have not met the 5 project requirement of the specifications. This will have to be followed up on in the interview process.

10/03/05 – This Wednesday is the prebid meeting. I will meet Tony and Mike at 230 at 10:30 a.m.

09/21/05 – Project Manual completed and sent out for public bid. Bid opening scheduled for Oct 19th. Prebid mtgs scheduled on Oct 5th per everyone’s attendance request. Project budget estimated at $650,000.

09/20/05 – TTC completed the bid manual and sent out for review. All comments came back, TTC incorporated them into the manual and sent back to Maureen for advertising dates and SBA %. TE will turn over to County on Wednesday for bidding.

08/31/05 – Tony emailed today to say that TE is to keep the original insurance requirements from the original bid.

08/30/05 – Finalizing the bid process. Insurance requirements for Kone are final question before setting up public bid forum. Waiting on word back from Todd Dalton at Kone and AKM.

07/18/05 – Meeting went great. TTC has some work to cleanup old bid. AKM to inform TTC about 2020 building. Kone had some verbiage changes to contract. TTC has to modify bid form for combination bids.

07/12/05 – TTC setup a meeting with Tony and the elevator vendor for Friday.

07/05/05 – Project manual built by Sam. TTC has to get new information from Kone on new testing requirements. TTC talked to Sam Kinman today at PBS while on a walkthrough at PBS and was told that October’s escalator work is going to be an additional $30k on top of the standard contract. TTC will talk to Kone about new scope and testing for this bid and project manual.

Elevator Maintenance Bid Read More »

ADAS – Due Diligence MEP Study

11/03/05 – TTC contacted THP for coordination and kickoff on this project. We will wait till they contact us to start working directly with Wes Miller at the site. According to Mike Stiles, the building could certainly use an electrical upgrade that could be upwards of $1mil in cost.

10/25/05 – TTC and Wes Miller setup a walk through today for Sam and Mike to gather info for the SOSS for this project.

10/24/05 – TTC contacted Wes Miller, THP and Diana Supe about finalizing the SOSS for this project. It appears to be much larger than originally thought. KLH has already visited the site and did a walk through with the Facility Director Wes Miller. TTC will re-contact and set up a field trip for TE to build the SOSS by Wednesday.

ADAS – Due Diligence MEP Study Read More »

Energy Manager Project

01/16/07 – TTC compiled new format energy report and sent to Tony & Ralph. After December bills come in, TEI will present year end Energy report for Tony and Ralph.

06/01/06 – TTC sent Governors Award Application out for review. Markups will be incorporated and sent out UPS on June 2, 2006 to ODOD.

05/22/06 – TTC and Tony discussed the Governor’s Award for Energy that is due on June 02, 2006.

05/18/06 – Talked to Compass Energy about being an authorized buying agent for Hamilton County. There are so many things I like about this approach. I typed up and email to Tony to outline his benefits. We are awaiting approval to move forward.

05/05/06 – Strategic is very interested in bidding County work but mostly PBS. TTC sent the indemnity clause to them that County always requires and they want a conference call on 05/16/06 to discuss Q&A.

04/05/06 – After a second conference call, Tony has requested a write up from TTC outlining the possible cost and savings for bidding our dereg electric. TTC shall get this complete in a week.

03/23/06 – TEI sent Tony & Ralph the CCAO Report for 2005 updated with all the latest numbers. TEI sent Tony & Ralph the 2005 Monthly Report through December with the final CCAO numbers included. Next on TTC’s agenda is to update the yearly master and then the 2006 report for CCAO gas cost.

03/20/06 – Terry requested the Nov/Dec CCAO bills again as the latest packet doesn’t have them. TTC also contacted the CCAO for the information and talked to Amanda and she said she would fax them down to TTC but as of 3:40 p.m. they have not arrived. TEI cannot reconcile 2005 gas without this information.

03/15/06 – Talked to Joe Ewing today about Electric Deregulation Bid for county. We setup a conference call next week to discuss possibilities. TTC reconciled the 2006 Cinergy Rate schedule with an actual JC bill for February. This is a very big accomplishment towards reconciling the bills each and every month.

02/27/06 – TTC has to sign up for energy conference in Columbus. TTC and AKM discussed today on phone. TTC will drive up on Wed morning.

02/16/06 – TTC delivered the final report to Tony Matre and Ralph for use a couple of weeks ago but made one final change to the pie chart today. TTC is now working on deregulated electric and updating the individual building charts for a meeting with the bldg managers.

12/28/05 – TTC entered all the 2005 Gas data and got it input into the main spreadsheet for the County. TTC also began answering the CEC questionnaire.

12/09/05 – TTC discovered a billing anomaly in the CCAO billing for FT rate. It is a question that TTC can’t explain. The CH burnertip price is about $2 higher than the rest of the buildings for the same gas (it is all FT from the CCAO). Tony and Terry called the CCAO about the situation and left a message for assistance.

12/02/05 – TTC received the Energy Report packet today from the County that we will use as a template for LCC and this year’s report.

09/27/05 – Tony called and Terry sent our all 2004 Utility Data to Tony for his use. We sent a PDF and and excel file.

09/21/05 – First pass at Energy Star application yielded a grade of 33 for the 230 building. Passing is 75. TTC reviewed all data that Sam put into website. We believe that although we have additional data for additional months, this only hurts the ES score. Sam is removing extra months. The new score was in the mid 40’s. TTC manual calculated the buildings kbuth/sf to be 64.5 which is still lower than required for an Energy Star rating. TE is learning as we go on the application process for this website.

09/20/05 – Sam is currently entering 2004 data for 230 East Ninth.

09/16/05 – Set up user account at Energy Star for Hamilton County. We will be entering data for 230 East 9th Street for qualifications.

07/20/05 – TTC and Tom Kennedy met with Tony Matre and Mike Florimonte to discuss a proactive approach to getting the 230 East Ninth building LEED-EB certified. TE is to put together a business plan to make this work for the County

07/20/05 – TTC received the Alliance To Save Energy rejection letter for our March 2005 submission on the IT rate at the Courthouse. TTC forwarded the letter to Tony Matre.

07/19/05 – TTC finished the electric utility reports up through June 2005 and distributed to the County. TTC will work on reconciling the gas utilities next.

07/13/05 – Tony sent the CCAO summary to TTC for inclusion in to the energy files.

06/03/05 – TTC submitted the 2005 Governor’s Award to the State of Ohio. PDF. TTC submitted all 2004 energy data to Ralph for reporting.

05/26/05 – Downtown Six Pack Cinergy bills should started to arrive today at ThermalTech. There is no need to continue to copy Cinergy bills for EM work. I know will receive all the bills I need to do the monthly tracking. This should save Pat and Donna some work each week. If by chance I am missing one or two, I can request those manually.

05/20/05 – TTC has spent the better part of 3 days re-writing the TE software to accept all the new Cinergy Market Generation Riders so that I can correctly calculate and reconcile the energy bills for 2005. I estimate 2 more days of work before they are approved for use.

05/10/05 – TTC picked up Energy Authorization letter and will request data from Bill Fleisnner.

04/27/05 – TTC requested a County release for new energy data and to be authorized for the e-clips program to see Cinergy bills online, plus receive duplicate bills for the main 6-pack of buildings. The County should provide this letter.

03/31/05 – TTC sent in “Stars in Energy Alliance Application” PDF

03/25/05 – TTC startup monthly charts showing electric and gas, usage and cost and plotted on column graphs. TTC synchronized data with Tony’s local disk.

02/25/05 – TTC completed all the 2004 Energy Pulse Data Input. Graphs printed for 6 pack buildings. I am started to reconcile data vs. pulse data. A lot of energy bills are missing from 2004 and I have to contact Cinergy to get the actual bills for comparison. That request should be made on Tuesday.

02/18/05 – TTC attended the 9th Annual Ohio Energy Conference in Columbus and tabulated the 2004 237 WHT Energy Data.

02/11/05 – TTC will be working from TE and attending the Ohio Energy Conference next week for 2 days.

02/10/05 – TE registered TTC for the Ohio Energy Conference today. See you in Columbus next week.

02/08/05 – TTC collected more bills and is having Laurie at TE re-organize the bills by year, building, then service for easier updating..

02/04/05 – TTC got 230 E9th electric input for 2004. Looks like building has started using more energy and more 24/7 hours. TTC pointed out on graph to AKM.

02/02/05 – All 2004 bills have been tabulated. TTC and AKM set a schedule of having Energy Star program applied for by May 2005, having LEED-EB applied for by May 2005 and having Deregulated Electric bid on street by May 01, 2005. Cinergy has provided ALL 2004 interval electric data in an email today.

01/28/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/2 1/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/14/05 – TTC created water spreadsheet for 237 WHT. There are unexplained phenomena that need further investigation.

01/07/05 – TTC requested data from all current registered Cinergy Suppliers for Deregulated Electricity for County Bidding Purposes.

Energy Manager Project Read More »

XPEDX – DUE DILIGENCE STUDY

05/21/07 – The team presented the both phases of the Due Diligence study and the BOE move in programming and cost to Jeff Alluto, Diana Supe, Kevin Maue and John Michel and Bill Stautberg today. We went over existing conditions and possible future costs if the BOE takes occupancy of the building. Phasing plans and cost were turned over to the owner for this report. MEP wise the building is in good shape and will work for this and future needs.

05/14/07 – TE has DK on site for mechanical HVAC testing. TEI visited the site last week to get more FPC, EC and PC information. Report is due for review this Friday with MD and partners.

04/27/07 – TE awaiting signed SOSS.

04/18/07 – TE got prices from one contractor to perform Due Diligence on the AHU’s units at the site for $1900. We have a couple of request still pending.

04/17/07 – TTC & TA visited the site with CRA and THP and County Officials to take pictures, look at equipment and assess the requirements to prepare the Due Diligence Report.

XPEDX – DUE DILIGENCE STUDY Read More »

BLACKOUT/VULNERABILITY STUDY

04/27/07 – The final report is going to be delivered to Hamilton County Facilities Department today, April 27, 2007.

04/20/07 – TE received word from Hamilton County Facilities and are currently working on the final report.

04/13/07 – TE awaiting word from Hamilton County Facilities to proceed with final report.

04/03/07 – TA turned over draft copy report to Mark Donnelly by hand for review.

03/30/07 – Project progressing as expected.

03/23/07 – Hillcrest and Patrol Hdqtrs are complete. 800 Broadway is scheduled for next week.

03/20/07 – Patrol Hdqtrs fieldwork is complete. Hillcrest is scheduled in the next couple of weeks. Whole project is scheduled to be completed by end of March 07

03/14/07 – Patrol Headquarters, 800 Broadway and Hillcrest Campus have been added to the list of buildings to be evaluated. Field work for Patrol Headquarters and 800 Broadway has been performed. Hillcrest will be completed next week.

02/28/07 – 5 out of 6 original buildings have the report completed and turned over the Hamilton County Facilities Department.

02/19/07 – TEI will wrap up this project. 3 buildings are left to complete. CH, CAB, River City, Coroner’s Office are complete.

02/02/07 – The write up is very nearly complete on this project. TA is hoping to finish today.

11/03/06 – Write up is progressing

09/29/06 – Field trip is scheduled for week of 10/02/06

09/22/06 – Field trip is scheduled for the week of 9/25

09/15/06 – 5 out of 6 buildings are complete. Working on 6th next week.

BLACKOUT/VULNERABILITY STUDY Read More »

2010 COST ESTIMATES

07/24/09 – The cost estimates were finished on Wed 07/22 but Bert found several that needed more work or were empty. We finished these today. TTC reviewed every project new and old for completeness. The LEED portion was difficult and I an not 100% sure the data will be totally usable by HamCo fo its 2010 needs but it is the first step towards getting greener buildings. The projects are complete. CRA will be printing manuals for the next 5 days.

06/23/09 – TTC reviewed the Rebuild America and ECM Screening Tool with Tim and issued the original cost and scope documents to the team for updating our scope items for the cost estimate project. I have found several projects that are duplicates and especially have some questions about the Hillcrest site where they appear to be repeated twice and maybe three times. Terry will call Bert to discuss.

06/19/09 – The SOSS is approved and we have begun visiting the buildings. Terry and Mike have been to the 250 WHT building. The remaining projects are being coordinate by several TE employees for field trips next week. For this project we will have Terry, Tim, Andy and Mike Folck performing mechanical estimates. Mike, Danny and George will be performing the electrical estimates. Today we had our internal TEI kickoff meeting and internal Archibus training for input.

2010 COST ESTIMATES Read More »

BOARD OF ELECTIONS Third Floor Renovation

10/16/08 – Bert reports the BOE is very happy and has given Facilities a kudos for the work.

08/22/08 – Permit is in County hands for IBI. Bert said city permit was also received.

08/08/08 – According to City Permit Tracker Website this project is APPROVED.

08/01/08 – TEI has submitted three drawings to IBI for permit for this project.

09/05/08 – Permit approved in August. TEI submitted final payment for permits so final inspection can be scheduled.

BOARD OF ELECTIONS Third Floor Renovation Read More »

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS

02/02/10 – Cintas submitted paperwork for a change order cost to the JC work for 2010 based on building count inaccuracies. TEI may review? No word on Tony on what he needs.

12/31/09 – The only development aside from all contract being approved is that JCI will not agree to the contract published with the project. The Admin bldg is going to have to be inspected outside the scope of this project. TTC recommended Hamco take out a change order on SA Communale contract and get them to do the building for 2009. A separate agreement will have to be reached with one of our vendors to get the 2009 testing complete. Tony is working on final contracts.

09/11/09 – TTC sent final contracts to Tony for delivering to Kerry for review. We have 5 contracts on this job and everything is under budget. SA Communale got most of the buildings, Cintas, JCI and Simplex each got one of the buildings.

08/25/09 – Addendums 1-5 have been sent out and extended the bid to Sept 4. One company protested the bid and forced Addendum 5 and we published the actual service contract with the last addendum for their use.

07/29/09 – We have collected almost all of the building summary sheets for the project back from the building managers. TTC & DPC are working on the new spec, combined bid forms, etc for the large Addendum.

07/15/09 – Addendum 01 went out to bidders and extended the bid opening date to August 19th.

06/23/09 – Today was the first prebid meeting and it was less than stellar. The addendum on this project will be quite large and we have to get better equipment counts in all the buildings. The printouts that were provided do not have all the equipment the contractors want to see for an accurate bid. We will most likely extend the bid opening by one month, detail the scope of work better, combine the bids, rework the building summary sheets, take combined bids for better pricing, add an alternate for the five year required testing and add an alternate for the County workers to self perform all the weekly and monthly testing.

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS Read More »

ELECTRICAL DEREGULATION 2009

01/28/10 – Talk to PBS & Tony. All paperwork should be in. There are some lingering questions about contract signee’s and interval meters at several locations. As these get solved to the satisfaction of DERS these accounts will be brought on line too.

12/31/09 – Contracts are being signed. Interval meters request have been sent out. TTC forwarded the emails to hamco directors for signature and suggested everyone accept option 2 where the cost $446 each of the interval meter be rolled into the monthly bills for 24 months. Bill Fleissner is our contact at DEO for this. There was significant conversation between Matre and Cannon about us believe the entire cost was under $1000 for interval meters. DERS indicated 11 accounts required them. TTC rebuffed that by providing interval data on 9 of those accounts. DEO came back with another 19 that required it because peak demands were over 100kw not 1000kw as TTC believed. In the end written documentation is clear that the threshold is 100kw. PBS has already signed and faxed their approval to DEO. Final contracts and insurance have been worked out between Kerry, Tim and DERS. TEI provided backup savings calcs for the groups approving DERS savings estimates at significantly lower numbers (DERS numbers include cost savings and cost avoidance savings as one lump number).

10/20/09 – We have about five vendors registered and we have extended the contract question phase. We are opening the project on Nov 19. We have no contract questions yet on this project.

09/22/09 – Tony and Terry discussed insurance requirements with Tim Grabenstein for this contract. TTC sent the final copy for review to Tim. TEi asked for comments back by Friday.

09/21/09 – Contract comments came back from Tony and Kerry. Jim and Terry merged them into a final contract. We received the ITB-92-09 for this project. TEi will issue the final documents for public distribution on Oct 1. Contract questions and comments will be due Oct 15th. Bids are due in November.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

ELECTRICAL DEREGULATION 2009 Read More »

Archibus Drawing Updates

6/18/10-Met with Jack Randle of In4 and Michelle Ray of Hamilton County Facilities Department to discuss In4 scope of work verses Architectural Partnership scope of work. First Floor of Alms and Doepke mentioned. Michelle to investigate status.

6/21/10- Received email from Bert Watts with attachment documenting building drawing red-marks for correction.

6/22/10- Verified with Bert Watts the First Floor of Alms and Doepke is to be added to list of drawing corrections.

6/23/10- Submitted SOSS to Bert Watts at monthly Partner Meeting.

6/29/10- Approved SOSS delivered to GBBN.

7/02/10- Drawing updates completed and reported to Bert Watts.

Archibus Drawing Updates Read More »

2011 Project Request Estimating

4/26/10- Bert Watts discussed Estimating Project at Monthly Partner Meeting

5/8/10- Bert Watts email with attachments listing Partner and Project Manager Project List received.

5/12/10- GBBN received estimates for services from Mike Strine at Pinnacle Engineering for Asbestos Abatement Services.

5/13/10- GBBN submitted SOSS to Bert Watts.

6/23/10- Met with Walt Heckel of THP to coordinate all projects involving “All Partners”.

6/23/10- Conference call with Susan Barrett of IPM to discuss Communications Building Projects estimated earlier by IPM.

6/24/10- GBBN submits proposal requests to vendors for printing and assembly of project binders.

7/01/10- GBBN met with Bud Wells at Parkhaus Garage to discuss vegetative roof project request

7/02/10- IPM/GBBN visited Communications Center to discuss two project requests.

7/03/10- GBBN visited 2020 Auburn to discuss and document two project requests.

7/18/10- QCR delivers final binder tab revisions to GBBN to allow for final binder assembly.

7/19/10- Deliver project request binders (9 sets) to Bert Watts at the Courthouse.

7/20/10- Record set of Binders delivered to MEP Partner TEI.

7/22/10- Bert Watts delivers revisions to Binder Summaries for GBBN to insert into sets for partners.

7/23/10- Record set of Binders delivered to structural Partner THP.

7/27/10- Bert indicated the binders are to be slightly realigned from GBBN’s submission. Bert will take the 9th set of binders and realign them for GBBN’s reference. GBBN’s current office copy set of binders will be delivered to IPM for their records.

7/29/10- GBBN to received 9th set of binders from Bert Watts at the monthly partnering meeting.

2011 Project Request Estimating Read More »

Workforce Investment Board Vestibule Renovations

Current Comments (5/26/2010)

Project complete. Working on closeout documentation. CRA completing work.

Past Comments

Masonry repair work in progress.

Vestibule removed and new vestibule under construction.

New piers anticipated next week.(2/24/10)
Contractor completed demolition of vestibule.(2/24/10)
Sink Hole investigation:
Dug test well to footings and no fill below footing.
Pumped 5 yards of flash fill into void.
Plan to complete second test well on adjacent wall.
All phases of work approved.
THP subconsultant to CR Architects.

Workforce Investment Board Vestibule Renovations Read More »

2012 Project Cost Estimates

06/27/11 – Project 1208 was updated. Barth already had the cost separated as Bert wanted.

06/24/11 – Project estimates are complete. We are currently putting final touches of the estimates for this year.

05/24/11 -started field work on most estimates. Several have been input. Added one based on field work.

04/27/11 – We will be kickoff off this project next Monday and doing the work in May 2011.

2012 Project Cost Estimates Read More »

Emergency Generator PM Bid

06/29/11 – Tony reported today that the contract is approved.

05/03/11 – ThermalTech turned over final paperwork to Blaine for contract writing.

04/27/11 – Engineer’s office is writing a one year contract, Comm Center asked me to looked at three year bids and Tony asked me to write a contract for five years for the Facility buildings.

03/30/11 – Bids are due Thursday at 11am. TTC will attend. Three Addendums have been sent out on this job. We are taking prices on base bid, alternate and unit prices.

02/25/11 – Project is out for bidding. Prebid Mar 11, Bid Opening Mar 24. Note: TTC has to fix bid form for more clarity on bid day.

02/22/10 – Tony and Mike have approved the project manual and TEI will be sending to Jill Williams for bidding on Friday Feb 25.

Emergency Generator PM Bid Read More »

ENERGY MANAGER 2011

08/25/11 – Ameresco work is in final stages for contract negotiations. More controls meetings are schedule. Ameresco is presenting final report early Sept.

07/29/11 – 10 color copies of the final report have been mailed to Ralph per his request. The 2010 Report is complete.

07/07/11 – Energy Star bills have been entered for 230, Admin, and 800 Broadway. Field trips were scheduled for 230 and Admin, but have to be moved back to July 26 to coordinate with Florimonte vacation.

06/24/11 – Ralph said that he is sending Jeff’s questions over for final changes.

05/04/11 – Deliver 2 hard copies to Tony & Ralph today. Ralph said that if Jeff Aluotto approves this report, we can print these in color and be done. Also for 2011 report, he would like Hillcrest added, 237 WHT removed and the water data expanded.

04/26/11 – Delivered the final report to Ralph for 2010 including water from 2009 and 2010 completed for all major buildings. In 2011 we will add water for the remaining buildings and try to back date that information to 2007. We are trying to update the Energy Watchdog website before the final import at the end of May. It is nice to report that we saved over $1,000,000 in 2010 on our 3 major energy conservation measures.

03/30/11 – TTC finished inputting water bills. Thursday Amy will integrate into the report. Friday, Terry will finish the report.

03/14/11 – Duke has confirmed that ThermalTech has correctly included all the Administration Bldg electric into the Energy Star website. With this information, we are going to move forward with Estar approval.

03/01/11 – TTC has to add the deregulated electricity calcs to the report.

02/22/11 – TTC gave Ralph and Tony their final copy to review. Comments are back and TTC will finalize to give to Ralph for review by EOB on Friday.

01/24/11 – Folck has entered all bills that have been received. Terry and Amy are starting the Energy Report this week. Hopefully to be completed early February.

09/29/10 – All bills ThermalTech receives have been input into Watchdog. Next week have to do the bills kept at the CH.

07/28/10 – We are working on the new HamCo RFP with a couple of ESCO. RFP’s are due Aug 16.

05/26/10 – We received the 237 bills. Folck will input them. We will then generate the April bill.

05/06/10 – We modified Energy Watchdog to allow us to start entering electric commodity for Hamilton County ins 2010. Folck will enter all bills to date starting this afternoon.

04/26/10 – We delivered 10 copies of the final report to Ralph last Thursday. We delivered an updated electronic copy with the years of each project added to the Appendix today per Ralph’s request. We will continue to update bills in Energy Watchdog.

03/22/10 – Ralph and Tony have returned the Energy Report with comments. TTC will compile the final report. All previous reports uploaded to web.

03/05/10 – ThermalTech sent the final report to Ralph and Tony for commenting. TEi will compile the final report when comments are returned.

02/24/10 – Attended the 14th Annual Ohio Energy Conference with Tony & Ralph. Got the Energy Report about 50% complete. We are adding new buildings this year which means fixing the baseline model from 1997 and forward. It is harder than expected and taking longer.

02/22/10 – We have collected all utility data for 2009 and input into our worksheets

02/04/10 – Energy Watchdog data is input for 2009 for all buildings except for missing CCAO bills for Courthouse. We are working on the 2009 report and trying to finalize all the bills.

01/28/10 – Terry and Amy will be updating the report in Feb 2010. Andy is putting in the Watchdog data and Energy Star data this week.

12/31/09 – More bills are being input. The energy watchdog website should be up to date by mid January.

09/22/09 – Some bills are missing. TTC contacted Tony about Coroner’s gas bills. Jackson called about Coroner’s office water usage. TTC emailed the 2010 cost estimate report and explained the cost and program to reduce water usage.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

05/22/09 – The final report was turned over to the commissioners and we attended the commissioner meeting on 05/18. Mike Folck is updating all the water bills from 2009 and 2009. All data has been entered into Energy Watchdog through April 2008. We are not updating our monthly sheets until next year.

04/05/09 – The report is ready for TTC to review. I will get this done this week. I emailed Ralph & Tony about working with Ameresco on the 2009 energy projects.

01/26/09 – TTC & MAF finished the ECM Summary table and sent to Ralph Linne & Tony Matre. Ralph forwarded it to Jeff Aluotto for use. We are awaiting and update on how to write the SOSS for the work.

ENERGY MANAGER 2011 Read More »

2012 Project Estimates

Current Comments (9/28/2011)
Past Comments

Project complete.

THP added 250 William Howard Taft assessment into Archibus.

June 6 THP updated Archibus entries for 1431 and 1432.

Project estimates completed and loading into Archibus June 3, 2011.

THP reviewing project estimates, deadline for data entry into Archibus is June 3.

May 5, 2011 SOSS approved.

THP developing SOSS.

March 31, 2011 requested SOSS to complete 2012 project estimates.

2012 Project Estimates Read More »

2012 Project Request Estimating

03/31/11- Kick-off Meeting with Bert Watts during regular monthly Partnering Meeting. Tabulation Lists to be issued to all partners.

04/28/11- SOSS delivered to Bert Watts at monthly partnering meeting.

05/16/11- Met with Scott Lemond of ARC to discuss printing schedule and deliverables.

05/12/11- GBBN and IPM visited with Greg Smorey of the County Engineer’s Office to discuss the CAB 8th Floor Phase 2 Renovations.

05/18/11- Met with Greg Smorey of the County Engineers Office to review scope of project request for the Phase 2 renovation of the 8th floor not renovated in Phase 1.

05/31/11- Meeting with Greg Gelhaussen of the County Engineer’s Office at Ripple Road Engineer’s Garage.

06/14/11- All project Request Estimating is closed and completed.

06/23/11- Bert Watts email indicating three Project Requests have been eliminated.

06/27/11- Bert Watts email indicating one additional Project Request has been eliminated.

06/30/11- Deadline for all consultants to complete any requested revisions to Project Requests.

07/05/11- Delivery of electronic files and lists of projects to ARC printing

07/27/11- Binders received from ARC printing. Bert Watts accepts delivery from GBBN

07/29/11- GBBN delivers and installs corrected spline and cover slipsheets.

08/05/11- GBBN delivers partner sets of binders to THP and IPM.

08/25/11- GBBN delivers partner set of binders to TEI and CD’s of 2011 and 2012 to all partners.

2012 Project Request Estimating Read More »

2011 General Services – GBBN

01/14/11-SOSS submitted.

01/21/11- Bert Watts forwarded the new Contractor Safety and Health Specification section that is to be included in all future HCFD project manuals.

01/24/11-SOSS signed by BOCC and issued to GBBN along with Purchase Order.

01/25/11- Modified Standard Bidding Documents to indicate Christian Sigman as Interim County Administrator.

01/27/10-Attended HCFD Partnership monthly partner meeting.

01/27/11- GBBN forwarded to the other Partners the revised Master Specification Table of Contents and Legal Wrap showing the inclusion of the new Contractor Safety and Health specification section.

02/04/11- The meeting with Amy Hoh to kick-off a new project to modify the existing office partitions was cancelled.

02/14/11-Kick-off meeting with Sean Winfield of CAGIS to initiate an estimate to enlarge the CAB 10th Floor Conference Room.

02/15/11- Bert Watts agreed to perform the CAGIS work under this contract in lieu of a SOSS.

02/18/11- Drawings and estimate for CAGIS project sent to Bert Watts.

02/24/11- Attended the regularly schedule Partnering meeting at the Courthouse.

03/12/11- Met with Bert Watts to review the as-built conditions at Parkhaus Retail spaces. GBBN took measurements and photographs of space

03/15/11- GBBN sent as-builts to Bert Watts for review. Additional MEP input to be performed by GBBN due to lack of involvem,ent by ThermalTech.

03/25/11- Meeting with GBBN, ThermalTech and Duke Energy to discuss potential energy savings and partnering programs.

03/31/11- Attended the regularly schedule Partnering meeting at the Courthouse.

04/28/11- Attended the regularly schedule Partnering meeting at the Courthouse.

05/11/11- Interior Project Management performed background checks at the Justice Center. GBBN delivers results to Diana Supe.

05/12/11- GBBN staff performed background checks at Justice Center. GBBN delivered results to Diana Supe.

05/26/11- Attended the regularly schedule Partnering meeting at the Courthouse.

06/23/11- Corrections for new County Administrator made to standard front-end specifications.

06/30/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated after Partnering Meeting.

07/06/11- Meeting with ThermalTech to review Courthouse Courtroom Ceilings for redesign of the soffits and ceilings with Tony Matre.

07/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

08/25/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

09/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

2011 General Services – GBBN Read More »

2013 Project Cost Estimates

06/06/12 THP submitted SOSS.

06/07/12 SOSS Executed.

06/29/12 THP updated Archibus with project estimates for 1469 and 1471. THP, TTE, and GBBN working on estimate for Revit modeling (1467).

09/17/12 – TTC checked in with Partners to ensure that website is updated with final cost for Bert and it was agreed that we had all of our consultant time entered to do the ThermalTech provided 3D modeling presented at Partner meeting in July with THP and GBBN support for building frame structures done at base level.

09/06/12- GBBN meets with Tremco Roofing on site to finalize the remaining roofs that require restoration or replacement. This is a result of the Project Request Estimate that was cancelled due to inaccurate roof designations for estimating.

2013 Project Cost Estimates Read More »

2012 General Services – GBBN

12/14/12 – SOSS submitted.

12/23/1 1- Signed SOSS returned by Bert Watts to GBBN.

01/26/12 -Attended HCFD Partnership monthly partner meeting.

02/23/12 – Attended HCFD Partnership monthly partner meeting.

03/29/12 – Attended HCFD Partnership monthly partner meeting.

04/26/12 – Attended HCFD Partnership monthly partner meeting.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

05/17/12 – BOCC CAB-6th Floor Security Modification estimate presented to Bert Watts.

05/31/12 – Attended HCFD Partnership monthly partner meeting.

05/23/12 – Bert Watts forwards the list and schedule for the 2012 CIP projects.

05/29/12 – Bert Watts sends letter of Critical Project SOSS requests.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

06/28/12 – GBBN attends monthly partnering meeting.

07/26/12 – GBBN attends monthly partnering meeting.

08/30/12 -GBBN attends monthly partnering meeting and performs website updates.

09/23/12- Bill Scholl of 2020 contacts GBBN about flooring replacement information. GBBN suggests contacting Spectra Flooring for State Term options.

09/27/12- GBBN attends monthly partnering meeting.

2012 General Services – GBBN Read More »

2012 General Services – THP

LEED Partner: THP
Current Status: SOSS
SOSS: F32
Contract Date:N/A

Status: N/A

As-built:

Status:

03/29/12 THP completed initial review the book case load assessment on the 9th floor in the Administration building. Initial assessment was inconclusive; either drawings are needed or testing is required.

THP Staff submitted information to Sheriff on January 30, 2012. Sheriff’s office noted background check can take six to eight weeks.

SOSS submitted; waiting on approval.

04/25/12 – THP working Administrative building load assessment field work to be scheduled with anticipated answer by mid-May. Drawings do not exist, so THP is complete a field survey and tests.

4/30/12 THP provided summary letter of Administrative Building load assessment to Bert Watts.

5/23/12 County provided Capital project list with proposed schedules. THP agreed with the proposed schedule.

5/29/12 County requested SOSS for the following projects: Memorial Hall, 800 BW Roof, and 250 WHT windows and concrete repair. SOSS due June 1, 2012.

2012 General Services – THP Read More »

2012 General Services – TEI

09/17/12 -Joann Cramer sent a new PW packet without the Terrorist statement included. TTC will udpate and distribute.

09/26/12 – SOSS-F056 Approved. TTC received, reviewed, updated and sent out the revised Prevailing Wage packet for Hamilton County Purchasing. Several edits were made by TTC. TTC updated the website for the new design with all buildings in facilities, black bar titles and updated projects for use and unloacked all building files for others to work on.

2012 General Services – TEI Read More »

Master Space Plan

Partner: GBBN

Status: Inactive

Status:

04/12/10- An email from Bert Watts requested a Kick-off meeting with Bud Wells in Courthouse B-90. First Phase of three to be performed in2010 requiring SOSS submittal.

04/15/10- Kick-off Meeting held with Bud Wells and Bert Watts. Handouts included Survey Form, Project Activity Timeline, Charter for Space Utilization Study and Buildings to be incorporated into study.

04/27/10- Clarification emails from Bud Wells and Bert Watts answered questions related to SOSS.

04/28/10- SOSS to be submitted to Bert Watts at Monthly Partnering Meeting.

05/21/10- Signed and Approved SOSS returned. Email from Bert Watts indicates schedule is to commence 6/24/10- Archibus Drawings to be updated are sent to GBBN from Bert Watts. Progress is on hold until In4 completes all Archibus polyline revisions and Michelle Ray completes all reviews.

08/04/10- Attended kick-off meeting to change this SOSS to another masterplan for the 237 Internalization study.

Master Space Plan Read More »

Master Plan Internalization Study

Partner: GBBN

Status: Inactive

Status:

08/04/10- Attended Kick-off meeting with Ralph Linne and Diana Supe.

08/18/10- Internal Kick-off meeting with Keven Speece, Thomas Rottinghuas, Jack Herbet Ralph Linne and Diana Supe along with Craig Landers and KEvn Maue of DDS.

08/30/10- Meeting with Ralph Linne and Diana Supe to discuss changes to the scope of this project. Project will now contain five options for relocation.

08/31/10- Met with Tony Matre and Bill Scholl at 237 WHT to walk the entire building and field verify the existing drawings.

09/01/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss all the various options, including those generated by GBBN, and decision affecting data to be considered.

09/01/10- Meeting with Craig Landers and Kevin Maue of DDS to discuss programming issues and schemes for possible relocation to 237 WHT for their existing employees in lease facitlities.

09/09/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss variations in options to be considered including possible tenants into 237 WHT.

09/17/10- GBBN met with Ralph Linne and Diana Supe to restructure the options to be investigated for the study. A report was requested to summarize the options and all data to be considered for the approval of the options to be developed further.

10/25/10- Kick-off Meeting with Ralph Linne and Diana Supe. SOSS requested for additional Options for Jeff Alutto to review for Masterplanning Studies.

11/03/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to review report and options documented in Partner study.

Master Plan Internalization Study Read More »

2013 GENERAL SERVICES THP

12/24/13 – SOSS Requested

01/03/13 – SOSS Submitted to County.

01/07/13 – SOSS Executed.

03/20/13 – THP met with County to review beam condition in the basement of the Administration building. Based on the initial visit an additional assessment needs to occur to determine the effect of the active deterioration on the beam. The assessment will determine the need to stabilize or repair the beam.

06/04/13 – Coroner building is reporting long term leaks in the basement under the entry slab. Bert requested THP contact Mike Jackson and determine the possible leak/scope.

06/14/13 – Coroner building – THP reviewed entry after short term heavy rain. Evidence of long term water infiltration was evident, but entry did not leak. Reported findings to County with to recommendations: water test or wait for soaking rain to determine water leak. County directed THP to wait for a soaking rain; then publish a letter of findings.
10/31/13 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work.

01/30/14 – THP plans to archive project.

2013 GENERAL SERVICES THP Read More »

2013 GENERAL SERVICES GBBN

01/16/13 – SOSS submitted.

01/23/13 – Signed SOSS returned by Bert Watts to GBBN.

12/24/12 – THP – GBBN issues permit drawings; THP documents included.

01/23/13 – GBBN confirms to Millay & Company there is to be no Mechanical Permit initiated by the Owner due to no work required unless required by the Building Department.

01/31/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers signed General Services Contract to Bert Watts.

02/28/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers CD to THP and IPM for 2013 Estimating binder.

04/25/13 – GBBN attends monthly HCFD monthly partner meeting.

05/30/13 – GBBN attends monthly Partnering Meeting.

05/30/13 – We discussed the SBE packet for new bids. If we are 0% we do not have to include the actual packet in the bid specification to save paper.

05/30/13- County requests GBBN submit payment on Alms and Doepke Building Pinnacle Engineering Invoice on the General Services SOSS,

06/26/13 – GBBN performs Website updates.

06/27/13 – GBBN attends monthly Partnering Meeting.

07/25/13 – Monthly Partnering Meeting is suspended.

08/29/13 – GBBN attends monthly Partnering Meeting.

2013 GENERAL SERVICES GBBN Read More »

2013 GENERAL SERVICES THERMALTECH

Contact: Terry Cannon

Status: Active

Status:

11/19/12 – SOSS submitted.

11/29/12 – SOSS Approved.

12/12/12 – TTC updated front end documents to remove Terrorist documents.

02/01/13 – TTC updated front end bid documents to remove change President to Chris Monzel.

02/12/13 – TTC & SJ updated front end documents to add the non English speaking language to the Supplemental Conditions.

02/15/13 – TTC updated font end documents to remove the SBE paperwork and language.

03/14/13 – 800 Broadway Vacuum Pumps – TTC recommends doing the following after tracking down some factory information and meeting with Process Construction: 1. Temperatures coming back in the condensate piping are high indication leak-by at the traps: Recommendation-do a full trap survey and repair dysfunctional traps. 2. Temperature in “hurling” chamber start low when system is off and then rise to 190F. The aquastat on the hurling chamber is set at 190F so this tank will quench and drain continuously when the temperature is above 190F. We changed the MUW to this unit from softener water to standard city water because it is typically drained upon use. There is no need to use soft water for this mark up. This work was already completed today when I was there. 3. The condensate pumps are on a mechanical alternator and take turns pumping condensate in the lower chamber to the DA tank for boiler feed water make-up. 4. The vacuum pumps however are lead/backup. VP-1 is always the first pump on when the system vacuum gets close to 0″HG. It provides up to 4″ HG of vacuum, if this pump cannot provide vacuum, it automatically turns on the second pump and both VP-1, VP-2 run together to provide 4″HG. The vacuum limits are between 4″ to 8″HG. 5. Please leave all four HOA switches in the Auto position at all times. 6. With this knowledge, I believe I can report the Vacuum Pump Package on the left in the boiler room is working properly. 7. The vacuum package on the right appears to have a pump seal leaking and should be repaired prior to putting back into service. 8. Please repair the building steam traps to reduce the inlet temperatures from the traps to approximately 180F. Process stated that the vacuum system must be used when the building has low loads but you may find that under high loads (32F or lower) the steam system has enough pressure to push the condensate through the system and you can turn them off the vacuum pumps-that is for your users to decide if that can be done without leaving so much condensate in the building systems.

03/26/13 – Updated Website. Sent out some new formatting rules for users.

2013 GENERAL SERVICES THERMALTECH Read More »

ROYAL GLEN PUMPING STATION Pump Station

Lead Partner: ThermalTech

Current Status: Construction

Status:

10/05/12 – IBI approved 98% inspection today. MB at TEI called Steve Twehues of Duke and requested power get restored ASAP. Steve to contact IBI, get release letter, and schedule restoration of power with Steve Wessels (likely early next week). Project can then be closed out.
10/31/12 – IBI released approval. Duke energy powered the pump up, but there is no meter at this time. Duke energy is insisting that the exiting PT’s are relocated up approximately 2-3 feet on pole, they feel that this is a safety issue once the platforms are installed, they will be too close to be within reach. TTE and trades argued that this area is only accessed by “qualified personnel”, and Duke CPC agreed, but metering division is requiring that they are moved, stating that kids are thrift and can climb fences and that this is a safety issue.

08/28/13 – TE met with Steve Wessels and FD Lawrence. FDL pulled report on soft start, and determined that the soft start was starting/stopping every time that the pump ran. TE sent wiring diagram to Steve Wessels to wire a stop float and a start float.

01/24/14 – Back punchlist complete. This project is complete.

ROYAL GLEN PUMPING STATION Pump Station Read More »

2014 COST ESTIMATES

Partner: All Partners

Status: SOSS

Status:

04/25/13 – Bert reported that we are still probably doing estimates for next year but it may be later this year than most. They will handle resubmitted projects and the partners will get the new projects.

05/30/13 – BW reported that they are getting close to releasing the list to the partners but RWL has to review several items. This list may be bigger than usual if we get to do the entire list this year. This may include some work on the 20 year project.

07/08/13 – GBBN receives the “Capital Roof Plan” showing the historical replacement data and estimated pricing of the six downtown campus buildings from Tremco Roofing.

07/11/13 – GBBN submits SOSS to County for approval.

07/30/13 – GBBN receives approved SOSS from County.

07/23/13 – GBBN meets with Darnell Edwards to review elevator replacement estimating scope.

07/25/13 – GBBN meets with Joe Merkt to visit the Justice Center Roof for the roofing replacement estimate.

07/26/13 – GBBN meets with Mike Florimonte to visit the CAB and 230 WHT Law Center Roofs for the roof replacement estimates.

08/08/13 – GBBN meets with Aluminum Resources to discuss the Window Replacement estimates for the six downtown campus buildings.

08/09/13 – City of Cincinnati Elevator Inspection Department responds with Elevator Code Requirements applicable to the 800 Broadway Elevator Equipment Replacement.

08/10/13 – Kone Elevators responds with Estimating data to GBBN for the 800 Broadway Elevator Equipment Replacement. Existing equipment is Montgomery-Kone.

08/13/13 – GBBN meets with Maria Karvelas to discuss the 230 WHT Pre-Trial Estimating Scope.

08/15/13 – GBBN sends preliminary plans to Maria Karvelas for review.

08/16/13 – Maria Karvelas indicates preliminary drawings for the Pre-Trial estimate meet the requirements.

08/21/13 – GBBN receives pricing back from Seeger Glass for the replacement of the Justice Center High Security Windows.

08/26/13 – GBBN completes all estimating into Archibus.

08/28/13 – TEI reviewed combined estimates and made minor changes.

09/03/13 – GBBN contacts ARC to notify of impending printing requirements within the next two to three weeks.

07/08/13 – County provided list of project estimates for 2014.

07/17/13 – THP submitted SOSS for review.

08/08/13 – County approved SOSS.

08/27/13 – THP completed structural estimates and entry into Archibus.

2014 COST ESTIMATES Read More »

BOARD OF ELECTIONS ADA Ramp Entrance

Lead Partner: GBBN

Current Status: Construction

Status:

12/07/12 – THP 824 ADA upgrade project requested from the County. THP to provide structural services for entry ramp. Building Owner forwards existing PDF files of building floor plans.

12/08/12 – GBBN- issued SOSS to Hamilton County.

12/10/12 – GBBN, THP and TEI kick-off meeting and building tour.

12/12/12 – Existing hard copies of original building drawings received from Owner. ARC creates electronic copies for GBBN who distributes to TEI and THP.

12/13/12 – GBBN receives signed SOSS from Hamilton County.

12/14/12 – THP – THP issued SOSS to Hamilton County.

12/17/12 – GBBN meets with Building Owner and Contractor to discuss scope and walk existing building.

12/18/12 – THP – County executed THP SOSS. Building Contractor sends Otis Elevator ADA upgrade estimate to GBBN.

12/18/12 – GBBN sends ADA handicap access ramp layout to TEI and THP. CUH added by TEI and steel structure added by THP.

12/19/12 – Meeting with BOE staff that changes scope of work to include Lobby lift not ramp, no 2nd or 3rd floor restroom renovations and modified 3rd Floor renovations. Drawings generated by GBBN and circulated to BOE/ Facilities and Building Owner/Contactor.

12/19/12 – THP entry scope modified to allow for lift in lobby vs. constructing a room with a ramp adjacent to the entry.

12/20/12 – Ralph Linne notifies GBBN to proceed with generation of construction documents based on Building Owner original scope drawings.

12/21/12 – Small changes request to new scope drawings on the3rf Floor Office Area. Changes made by GBBN and sent to BOE. BOE signed off on new scope drawings.

12/28/12 – Final pricing and scope drawings sent to Millay & Company by GBBN.

01/02/13 – GBBN forwards new card reader lockset to BOE for approval.

01/04/13 – Ralph Linne notifies GBBN to proceed with amended scope from original SOSS per BOE Staff requests. GBBN sends approval to commence to TEI/THP. GBBN calls City Transportation and Planning to ask about handicap parking space in front of building. Left voice mail. No return call ever received.

01/07/13 – GBBN and TEI perform reflected ceiling field verification.

01/08/13 – GBBN meets with Midwest Accessibility Products to discuss details on lift installation and code approval.

01/12/13 – Ralph Linne confirms Prevailing Wage Rates required in specifications for contractor work on this project.

01/14/13 – Millay & Company confirms storefront replacement to be from existing horizontal door header and down. Existing transoms to remain.

01/15/13 – TEI sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – THP sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – GBBN notifies Millay& Company that stamped drawings, electronic CD and permit application available for pick-up at GBBN offices. Millay & Company requests electronic drawing files sent for review. GBBN complies.

01/21/13 – Millay & Company pick-up drawings from GBBN offices.

02/20/13 – Milay & Company sends a copy of the City of Cincinnati Permit Center building application response letter to GBBN. Most issues deal with existing building conditions.

02/22/13 – GBBN contacts Norwood Hardware about response letter issue on access control

02/25/13 – TEI reports findings concerning existing outside air repairs by building owner and test results from TEI research on existing units.

03/13/13 – Millay & Company receives letter from The City of Cincinnati Permit Center. Two items require further information for building permit approval.

03/14/13 – GBBN issues directive to BOE and Building Owner about front door over-swinging existing steps as code violation that must be addressed.

03/25/13 – GBBN receives return call from Plans Examiner with additional information concerning front door potential solution.

03/26/13 – The Building Owner and BOE agree upon GBBN Scheme B solution for addressing front entrance existing code violation solution.

04/12/13 – GBBN submits City of Cincinnati Permit Center requested Response letter and drawing corrections.

04/19/13 – City of Cincinnati Plans Examiner requests Mechanical Permit drawing for submission for earlier Mechanical Permit.

04/23/13 – TEI delivers stamped and signed Mechanical Drawing to GBBN for submittal to the City Permit Center.

08/22/13 – GBBN and THP attend meeting with Millay and Company to discuss structural coordination of steel support steel under the existing Lobby for lift elevator installation.

BOARD OF ELECTIONS ADA Ramp Entrance Read More »

2015 20-YEAR PROJECT ESTIMATES THERMALTECH

Lead Partner: TTE

Current Status: SOSS

Status:

09/17/14 – SOSS submitted.

09/26/14 – Prep work started for these estimates. Waiting on Administrator approvals.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

12/12/14 – BW called with an SOSS update. This project is approved for work at a new SOSS. TTC marked approved and gave Becky the PO for future billing. Coroners office 20 Year cost to be added to scope.

01/19/15 – All 20 year estimates are complete. TTE coordinate with THP and GBBN for roof estimate at Coroners Office to complete the entire list.

01/21/15 – GBBN reported that Coroner’s Roof Estimate was complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 20-YEAR PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES THP

Lead Partner: GBBN

Current Status: SOSS Approved

Status:

07/22/14 – THP issued SOSS.

08/04/14 – County requested SOSS for 20 year project estimates.

08/05/14 – GBBN issued initial SOSS for County review.

08/21/14- GBBN submits revised SOSS with 20-Year projects removed from the Annual Estimating

08/22/14 – County approved Revised SOSS.

09/03/14 – County approved SOSS.

09/23/14 – THP published Archibus estimates.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THP Read More »

2015 PROJECT ESTIMATES THERMALTECH

Lead Partner: TEI

Current Status: SOSS Approved

Status:

09/26/14 – Many estimates completed. Fieldwork underway. Project due 10/5/14.

10/05/14 – Most projects complete. Some stragglers and large projects remain to be estimated.

10/23/14 – ThermalTech down to Courthouse Server project remaining to be estimated. TTC to finish this week.

12/13/14 – TTC to review final project status and coordinate with GBBN. I believe all projects are complete and estimates are in.

01/19/15 – 2 leftover projects were completed by ThermalTech in Jan 2015. All projects are now truly complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES GBBN (20-Year and 2015)

Lead Partner: GBBN

Current Status: SOSS- F107

Status:

0717/14 – Bert Watts sends email to partner with initial listing of projects.

07/18/14 – GBBN inquires about 20/30 year projects, cost of living increases and approaches for delivery of these estimates. Bert Watts responds to GBBN.

07/21/14 – Bert Watts responds to questions via email and deliverable date.

07/22/14 – THP initials email and spreadsheet for discussion on lead partner roles in shared project estimates. GBBN responds back to THP.

07/29/14 – GBBN informs ARC Reprographics of probable schedule for deliverables of printing and binder assembly.

10/07/14- GBBN visits Burlington Garage and completes roof replacement estimate.

10/09/14- GBBN completes all 20-year Capital Improvement Estimates.

10/17/14- GBBN coordinates with Bert Watts on scope for the Technology Estimates at the Courthouse and Justice Center.

10/23/14- GBBN completes all 2015 Project Estimates including LEED Silver Estimates.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

03/22/15 – GBBN picks up empty binders from Facilities department for pickup by ARC Reprographics.

03/24/15 – ARC Reprographics picks up empty binders from GBBN for assembling final volumes of Project Request Estimating Volume Sets.

2015 PROJECT ESTIMATES GBBN (20-Year and 2015) Read More »

ADA Building Assessments

Partner: GBBN

Status: Active

Status:

05/04/11 – Bert Watts notified GBBN of prospective project via email.

05/19/11 – GBBN attended the SWOBOA seminar in new ADA requirements.

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings. See the SOSS’s F045 through F052 below.

02/12/12 – Otis Elevator declines to assist GBBN in Elevator Assessment due to liability reasons. Suggests local consultant for assistance.

08/21/12 – GBBN completes last ADA Assessment Report for the Courthouse.

08/28/12 – GBBN begins estimating portion of Assessment Reports.

08/24/13 – GBBN completes estimating impacts of ADA Assessment findings on each building.

02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.

ADA Building Assessments Read More »

BURLINGTON RD GARAGE Damaged Wall Panel Replacement

Lead Partner: GBBN

Current Status: Close-out

Status:
10/14/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

10/18/14 – Project manual cover from original building construction sent to Metallic Building Company

02/24/15 – County requested a full letter report and authorized additional field work.

10/24/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

11/18/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building color samples

11/25/14 – County Engineers reported existing overhead door stuck and has been closed temporarily not to be used until repairs completed.

12/15/14 – Metallic Building Company delivers quote for replacement part list to GBBN.

12/26/14 – GBBN authors and delivers SOSS to Bert Watts.

02/25/15 – Bert Watts emails approved SOSS and Purchase Order to commence work.

03/13/15 – GBBN attends Owner Review Meeting to review bid package documents.

03/13/15 – GBBN issues informational requests to five (5) selected bidders for project.

03/17/15 – GBBN sends invitations to Bid to all five (5) selected bidders. Electronic copies of documents included in email.

03/24/15 – GBBN holds Pre-Bid Meeting at Offices of County Engineers’ Burlington Road Garage. Hard copies of bid drawings and specifications handed out to potential bidders and owner.

03/25/15 – John Nester forwards scope quote from Overhead Door Company for overhead door repairs.

04/02/15 – Bids received and bid tabulation compiled for Facilities Department. GBBN commences interviews with those bidders submitting bids.

04/03/15 – GBBN forwards Recommendation Letter to Facilities for lowest and responsible bidder.

04/03/15 – Hamilton County approves recommendation and instructs GBBN to author contract to Century Construction Inc.

04/03/15 – GBBN hand delivers hard copies of AIA contract to Facilities Department.

04/07/15 – Century Construction delivers signed copy of Safety Receipt Form to Facilities Department.

04/10/15 – GBBN receives color samples chips from Century requiring approval.

04/13/15 – GBBN visits building and approves color samples from manufacturer and sends approved submittals to Century.

04/21/15 – GBBN receives Schedule of Values from Century, via Facilities Department.

04/29/15 – Pre-Construction Meeting held at site. Signed and executed contract hand delivered to Century from the Facilities Department. This date established as the contract commencement date.

05/15/15 – Century reports all construction work is completed. Facilities performs site inspection and punch list. One item, caulking bead at overhead door jamb is required.

05/19/15 – Facilities performs site inspection back punch list. The one item, caulking bead, has been installed as requested.

05/20/15 – GBBN signs first/final Application for Payment.

05/26/15 – GBBN sends email to Century requesting all close-out documents be processed and executed.

06/03/15 – Change Order #1 for additional signage scope, authored by GBBN and sent to Century for signatures.

06/15/15 – GBBN receives close out documents from Century Construction.

06/16/15 – GBBN receives executed Change Order #1.

06/16/15 – GBBN receives Application for Payment #0002 from Century but without Change Order #1 included. Century to revise and sent to GBBN once project change order work is completed.

07/20/15 – GBBN receives Application for Payment #0002 with Chan ge Order #1 included. GBBN signs and delivers to Facilities Department.

07/20/15 – Century Construction announces the change order signage has been installed on the building facade. John Nester confirms the work has been completed to the User Group’s satisfaction.

BURLINGTON RD GARAGE Damaged Wall Panel Replacement Read More »

2015 Electric Deregulation Bid

12/11/14 – Bert requested new SOSS this week for several end of year projects including A&D General Service, BW General Service, and 2015 Dereg Services.

03/31/15 – TTC requested updated account numbers for the Elec Dereg project from all clients for the 2015 bid.

04/01/15 – Greg Gelhausen replied to my account number request and wants to add one account to the bid. TTE said no problem.

04/14/15 – ITB 010-15 has been assigned to this project.

04/15/15 – TTE requested billing data from Duke on all accounts included in this bid.

04/20/15 – David Hisser returned all billing data to TTE for Calendar Year 2014.

05/25/15 – First Draft should be ready this week for Ralph and Tony to review and approve.

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/16/15 – Dynegy contract approved for all four departments. Service starts in Jan 2016.

08/26/15 – Dynegy offered all Hamilton County employees a Preferred Discount plan on home electricity through 2015 or 2017.

2015 Electric Deregulation Bid Read More »

2016 Project Request Estimating ALL

05/16/15 – County requested SOSS from Partners.

05/18/15 – Bert Watts forwards email with “List of Projects by Partner” to all partners.

05/26/15 – GBBN hand delivers SOSS to Bert Watts.

05/29/15 – THP anticipates issuing SOSS.

06/02/15 – THP issued SOSS

06/05/15 – County executed SOSS for THP

06/24/15 – ThermalTech is complete with all but 3 estimates which are to be worked on tomorrow. Bert added #1824 for 800 Broadway Emergency Generator to TEI scope today. THP completed estimates and data entry into Archibus.

06/25/15 – GBBN completed with all but four estimates. ADA/Title II/III Projects Request Estimates are ongoing. Bert said that all projects must be done by 6/25 so he can make the early July deadline for the County.

07/20/15 – Facilities Department sends binder summary documents to GBBN for printing. GBBN informs ARC of the impending printing schedule.

08/26/15 – A call to ARC Reprographics confirmed the binder printing and assembly is nearly complete. ARC expects to deliver the binders to GBBN on Monday August 31st right on schedule.

08/31/15 – ARC Reprographics delivers all binders and existing documents to GBBN Offices.

09/01/15 – GBBN delivers Hamilton County copies of binders to Facilities Department.

2016 Project Request Estimating ALL Read More »

Fire Alarm & Sprinkler Testing

Partner: ThermalTech

Status: Active

Status:

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/29/15 – Two day prebids complete. Add01 is issued. Add02 will be issued tomorrow. Bid opening on schedule for August 27.

08/27/15 – Bid opening scheduled for today. 2 Addendums issued total on this project.

09/23/15 – Tony selected SA Comunale form base bid initial term as the recommended bidder for this project. ThermalTech to author the contract for Facilities.

10/28/15 – Contracts approved. Project can be archived.

Fire Alarm & Sprinkler Testing Read More »

2017 Project Cost Estimates

All Partners

Status:

04/18/15 – Bert sent out estimate list for SOSS pricing. Facilities sends list of Project Request Estimating “Project by Partner” list to GBBN.

04/22/16 – Facilities sends email clarifying number of “standard” binders and “summary” binders along with CD’s to be delivered. Also clarification to other estimates are provided.

04/25/16 – IPM sends proposal for hours to be incurred for interiors scope of estimating.

04/25/16 – Facilities requests two separate SOSS, one for the estimating and one for the binder assembly and reimbursable expenses.

04/26/16 – GBBN hand delivers both SOSS to Facilities.

04/26/16 – Facilities requests that GBBN/IPM contact Facilities first for initial estimate contact on each Project Request and for any RFI.

05/25/16 – TEI proceeding nicely on cost estimates. We are hoping to be complete by 5/27/16 with all engineering estimates.

06/01/16 – TEI complete with 2017 estimates. We updated a few and added one after discussing with Bert Watts.

06/10/16 – GBBN completes all estimates.

06/20/16 – Facilities approves GBBN to begin estimate printing for final binder assembly.

06/28/16 – GBBN completes electronic project request estimate printing and notifies ARC for pick-up of all materials for binder assembly.

2017 Project Cost Estimates Read More »

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly

Lead Partner: THP

Current Status: SOSS

Status:

04/18/16 – County requested GBBN complete project estimates for new 2017 work.

04/28/16 – GBBN provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – GBBN reports to Facilities that it has completed estimates and entered them into Archibus for all assigned projects.

06/01/16 – Project estimates completed printing to pdf. Progress reported to Facilities.

06/14/16 – Facilities sends completed Binder Summary sheets to GBBN.

06/20/16 – GBBN completes packaging of al materials for ARC pick-up. ARC instructed to send deliveryman. Facilities confirms final numbers of binders and CD to be processed.

06/22//16 – ARC makes pick-up of all materials.

07/05/16 – ARC requests one pdf file be reprocessed and emailed. GBBN processes and emails back.

07/27/16 – GBBN sends request for status to ARC concerning printing and binder assembly.

07/28/16 – ARC responds the binders should be delivered between August 1 and the 4th.

08/01/16 – ARC delivers the binders and materials to GBBN. GBBN delivers one set of each binder to Facilities for review. Modified end binders required but approval given to GBBN to deliver all remaining binders.

08/02/16 – All final assembled binders and CD’s delivered to Facilities. CD delivered to IPM and TEI.

08/25/16 – GBBN delivers CD to THP at Partnering Meeting.

09/23/16 – GBBN receives final ARC invoice for printing services.

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly Read More »

2017 STRUCTURAL PROJECTS Estimates

Lead Partner: THP

Current Status: SOSS

Status:

04/14/16 – County requested THP complete an investigation of slab settlement and cracking observed in the building.

04/18/16 – County requested THP complete project estimates for new 2017 work.

04/27/16 – THP provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – THP has completed estimates and entered them into Archibus for all assigned projects except 17-FAC-2020-1847 and 17-FAC-5035-1848. Also confirmed Archibus entries for 17-REC-0138-1633 (entered by GBBN, LEED estimate currently $0.00 – not entered) and 17-FAC-1021-1845 (entered by THP and Thermal Tech).

05/27/16 – THP’s goal for having remaining two projects estimated and entered.

06/01/16 – Project estimates complete.

2017 STRUCTURAL PROJECTS Estimates Read More »

Emer Generator PM Bid

02/24/16 – Tony called and said that this project and PO are approved. Bid in March, Award in April, current contract runs out in May.

03/30/16 – Barth has made progress on the specifications they are about 90% complete. We are ready to get dates and an ITB and for Owner review.

04/26/16 – Project manual is ready. Date of Issuance will be 4/28/16. Bid Opening 5/26/16.

04/27/16 – Bid package sent to purchasing on 04/26/16. Pending bidding process.

05/25/16 – Bids open tomorrow. Two Addendums on project so far. All seems to be going well.

06/17/16 – Bids opened and there were anomalies. Tony to get information to ThermalTech as to which bidder each of the user groups has selected (Facilities, Cell Towers, Engineers).

06/27/16 – TTC to write a contract for Cummins for the Facility project. OK to share this contract with other departments if they need this. I told Tony this would be done last week, I will try to finish today.

07/18/16 – Tony is discussing with Kerry and is trying to stick with Cummins for the this contract. Kerry questioned the Alternate no bids by Cummins as legitimated on this job.

07/22/16 – Kerry and JoAnn and Tony are discussing rebidding this project due to Cummins not submitted Alternate bids for years 4 & 5.

07/25/16 – Talked to Tony and Gina today about the Alternate items in the Egen bid and we are going to rebid this project and we have change front ends to the standard county non-prevailing wage front end document and change Alternates to Optional Years. New ITB is 059-16.

07/28/16 – Talked to Tony and we are going to rebid all departments. I discussed a small SOSS to just pay for the the hours of this bid. We have a new ITB but no bid schedule yet.

08/03/16 – Tony said he approved my SOSS-A for rebidding this work. TTC to proceed.

08/25/16 – Egen PM Rebid sent out for bidding.

09/02/16 – No substantial questions on rebid yet. Bid opening scheduled for 9/8/16.

09/08/16 – Bid opening is today. Results to follow.

09/23/16 – IC won the second bid but didn’t include any battery replacement in year three. After several emails and reviews with Purchasing and the Prosecutors department, they are going to let their bid stand if they provide the battery replacements in year three.

10/25/16 – Post bid and Pre-Award meeting was held last Friday. Everything seems to be in order and TEI will write the contract for IAC today.

11/10/16 – All three revised contracts sent to Tony today for use on the Rebid work. IAC is the new vendor.

Emer Generator PM Bid Read More »

ELECTRICAL SWITCHGEAR PM SPECS

Lead Partner: TEI

Current Status: Approved

Status:

07/22/15 – TEI develop preventative maintenance specifications for Electrical switchgear in the following buildings. Alms and Doepke, Courthouse, 800 Broadway, 230 East Ninth Street, 250 William Howard Taft, and the County Administration Buildings.

10/28/15 – TEI working on specifications and coordinating with John Nester. TEI developed a scope matrix to review with John Nester, and also has written PM procedures. John Nester to confirm with HamCo PM procedures that the specs and the procedures are all encompassing.

12/07/15 – TEI sends John Nester preliminary specifications, questionnaire, and scope matrix for review and discussion.

04/27/16 – ThermalTech and John Nester meet to review specs. Information required from each building on “Mission Critical” equipment in building that can not see an outage. John Nester and Mike Barth are scheduled to attend next Building Managers Meeting on May 4th to facilitate the acquisition of information. Upon receipt of data from all buildings, specifications will be completed.

05/25/16 – Data from building managers due to John Nester at the June 1 building Managers meeting. Upon receipt of the data from all of the buildings, specifications can proceed.

06/27/16 – Data from building managers not all submitted to John Nester to date. ThermalTech provided JN a list of building that data still missing for. JN following up with Bldg Mgrs.

07/27/16 – ThermalTech met with John Nester just before MB Vacation. JN and MB concluded that specific data from building managers will not be obtained, and that the specifications need to be written in such a manner that we will give the overall concepts at each building, and we will size the emergency egens accordingly, but then state that building specifics will be worked out on a building by building basis.

10/27/16 – Comments back from John Gilbert this week, now ThermalTech can assist in getting the quotes together for the switchgear cleaning in the upcoming year. John Nester will lead this for HamCo.

01/27/17 – Specs are complete, project is ready to archive. Project can be be at any time, no dates were specific in the bid documents.

ELECTRICAL SWITCHGEAR PM SPECS Read More »

Burlington Garage Storage Shed Expansion

Lead Partner: GBBN

Current Status: SOSS

Status:

08/17/16 – Facilities confirms GBBN has no As-Built scope for this project on the SOSS.

08/18/16 – GBBN discusses <30% existing structure addition requirement for full existing building structural analysis. GBBN reports findings to Facilities. 08/22/16 - GBBN gets SOSS scope from TEI for Electrical scope of work. Hard copies delivered in the mail. 08/23/16 - GBBN consults with THP to discuss structural SOSS and permitting requirements for the project. 08/24/16 - GBBN forwards contact information from original contractor of Pole Barn Shed for investigation into alternative delivery method.

Burlington Garage Storage Shed Expansion Read More »

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION

Lead Partner: THP

Current Status: SOSS

Status:

03/16/16 – County requested THP investigate a deteriorating lintel at the service garage.

03/18/16 – THP visited the site to review field conditions.

03/31/16 – THP provided an SOSS for review.

07/08/16 – County approved SOSS.

07/28/16 – THP to schedule field work and complete field work in August.

08/22/16 – Field Assessment trip completed.

09/28/16 – THP anticipates final report being released 10/15/16.

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION Read More »

Energy Star Validations

09/02/16 – Buildings should be ready for certification after August bills are entered in late September. ThermalTech to draft SOSS for each building for approval.

10/14/16 – All fieldwork is complete for the certifications.

10/18/16 – TTC has reviewed all the SEP and found most to be compliant. The Courthouse requires some changes prior to submitting to the EPA. TTC contacted Tony Matre to discuss and make changes.

10/19/16 – TTC to meet Dave Johnson on site to reocver steam usage data for Courthouse Energy Star.

10/21/16 – These buildings have, 230,250,800,Admin, A&D have been uploaded to Energy Star. The Courthouse is not ready for SEP yet until we work out some occupancy issues that TEI is flagging as potential issues.

10/25/16 – TTC created a new SEP for the Courthouse with the updated numbers agreed upon between Tony and Terry. TEI will take to Ralph for signing on Thursday and hopefully upload to Estar on Friday.

11/10/16 – All six buildings have been submitted. Five buildings have been approved. We are waiting on the Courthouse approval at this time.

Energy Star Validations Read More »

Board of Elections- Training Center Renovation Study

Partner Lead: GBBN

Current Status: SOSS submitted

08/08/17 – Hamilton County requested Kick-off Meeting at BOE SOSS.

08/22/17 – GBBN and TEI meet with Facilities and BOE to discuss project, measure, photograph and field verify the existing space. Hamilton County requested SOSS.

08/25/17 – GBBN authors and provides Hamilton County with a SOSS.

08/26/17 – GBBN contacts Architect from RFP project to inquire about MEP drawing files from RFP Project. Architect responds sending along contact information for CM. CM is contacted and and sends files to GBBN.

08/26/17 – GBBN receives field verification dimensions from TEI for existing sanitary drain cleanout locations.

09/12/17 – Facilities communicates Project Request Estimate number to GBBN.

09/13/17 – GBBN communicates with Property Manager and CM related to RTU and Plumbing information.

09/14/17 – GBBN researches codes and Plumbing Fixture Unit requirements.

09/15/17 – GBBN finalizes the concept floor plan and circulates to Design Team. TEI finalizes HVAC concept approach with Facilities.

09/19/17 – Property Manager forwards information on Mechanical and Plumbing Contractors that worked on last renovation.

09/20/17 – TEI confirms contact with Mechanical Contractor.

09/22/17 – GBBN finishes Architectural and General Construction input into Archibus Project Request Estimate.

09/25/17 – TEI confirms contact with Plumbing Contractor and confirms concrete was placed in abandoned underground plumbing lines. Estimates are complete by ThermalTech for this project.

10/06/17 – BOE confirms to GBBN that tables used for trainees may be only 3 feet wide.

10/09/17 – BOE requests changes to the table and Training Room configurations. The Lobby is decreased in size and extra space dedicated to both Training Rooms.

10/10/17 – GBBN sends updated drawing to BOE for review.

10/11/17 – BOE confirms to GBBN which modified option has been selected for use. Decision on how to eventually pursue real project, if approved, is still pending discussions with Building Owner.

11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters.

Board of Elections- Training Center Renovation Study Read More »

Board of Elections- Training Center Renovation Study

Partner Lead: GBBN

08/08/17 – Hamilton County requested Kick-off Meeting at BOE SOSS.

08/22/17 – GBBN and TEI meet with Facilities and BOE to discuss project, measure, photograph and field verify the existing space. Hamilton County requested SOSS.

08/25/17 – GBBN authors and provides Hamilton County with a SOSS.

08/26/17 – GBBN contacts Architect from RFP project to inquire about MEP drawing files from RFP Project. Architect responds sending along contact information for CM. CM is contacted and and sends files to GBBN.

08/26/17 – GBBN receives field verification dimensions from TEI for existing sanitary drain cleanout locations.

09/12/17 – Facilities communicates Project Request Estimate number to GBBN.

09/13/17 – GBBN communicates with Property Manager and CM related to RTU and Plumbing information.

09/14/17 – GBBN researches codes and Plumbing Fixture Unit requirements.

09/15/17 – GBBN finalizes the concept floor plan and circulates to Design Team. TEI finalizes HVAC concept approach with Facilities.

09/19/17 – Property Manager forwards information on Mechanical and Plumbing Contractors that worked on last renovation.

09/20/17 – TEI confirms contact with Mechanical Contractor.

09/22/17 – GBBN finishes Architectural and General Construction input into Archibus Project Request Estimate.

09/25/17 – TEI confirms contact with Plumbing Contractor and confirms concrete was placed in abandoned underground plumbing lines. Estimates are complete by ThermalTech for this project.

10/06/17 – BOE confirms to GBBN that tables used for trainees may be only 3 feet wide.

10/09/17 – BOE requests changes to the table and Training Room configurations. The Lobby is decreased in size and extra space dedicated to both Training Rooms.

10/10/17 – GBBN sends updated drawing to BOE for review.

10/11/17 – BOE confirms to GBBN which modified option has been selected for use. Decision on how to eventually pursue real project, if approved, is still pending discussions with Building Owner.

11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters.

Board of Elections- Training Center Renovation Study Read More »