GABP- Diamond Club Kitchen Epoxy Floor

11/11/18 – GBBN contacted by Director of Operations to review potential two Kitchen Epoxy Floor Replacements. Projects to be constructed by 3/318.

1/11/18 – GBBN contacts manufacturer to inquire about existing product that has begun to fail and preparation required to recoat.

1/21/18 – Samples of colors and slip resistance sent to Operations for selection by Owner.

1/23/18 – Owner color and slip resistance level selections presented to GBBN.

2/1/18- Pre-Bid meeting held at GABP. Three attendees present. RFP documents distributed.

2/3/18 – Addenda #1 distributed.

2/12/18- All three proposals received. GBBN contacts low and responsible bidder to verify scope. GBBN recommends J Wesselman Specialty Flooring, LLC to Owner.

02/19/18 – Contractor to commence work at GABP. Background Checks required by Reds.