01/09/15 – GBBN attends interview with Selection Committee at County Administration Building, Room #605
01/30/14 – GBBN attends monthly Partnering Meeting.
01/29/15 – GBBN is notified of their successful renewal of the Architectural Partnership.
02/20/15 – GBBN sends Exhibit B to Facilities Department for use in authoring new contract.
02/24/15 – GBBN sends Exhibit A to Facilities Department for use in authoring new contract.
03/13/15 – Final Approved Contracts received from Hamilton County. Contract initialized with Public Defender’s Office 2/3 Floor Renovation Project. No General Services SOSS requested.
05/12/15 – General Services SOSS requested by Bert Watts.
05/26/15 – SOSS hand delivered to Bert Watts.
06/25/15 – GBBN attends monthly Partnering Meeting.
07/30/14 – GBBN attends monthly Partnering Meeting.
08/27/15 – GBBN attends monthly Partnering Meeting.
09/24/15 – GBBN attends monthly Partnering Meeting. Delivered new SOSS for extension.
10/29/15 – GBBN attends monthly Partnering Meeting.
11/03/15 – GBBN delivers SOSS #F010 for 2016 General Services to Facilities.
12/07/15 – Facilities transmits approved SOSS to GBBN.
12/09/15 – GBBN attends monthly Partnering Meeting.
01/28/16 – GBBN attends monthly Partnering Meeting.
02/19/16 – GBBN and Facilities agree to terms for Construction Administration Submittal Review scope for CAB Lobby Building Security to be billed to General Services.
02/25/16 – GBBN attends monthly Partnering Meeting.
03/23/16 – Facilities inquires about potential services for the IFM/WebCentral Space Plan updates for the 800 Broadway northwest corner. GBBN sends an estimate of hours required for the services.
03/31/16 – GBBN attends monthly Partnering Meeting.
04/18/16 – GBBN reviews and approves CAB Lobby Security Millwork Submittals.
04/26/16 – GBBN performs Hamilton County Internal Contract Updates.
04/28/16 – GBBN attends monthly Partnering Meeting.
05/26/16 – GBBN attends monthly Partnering Meeting.
06/28/16 – GBBN completes website updates.
06/29/16 – GBBN attends monthly Partnering Meeting.
07/27/16 – GBBN completes website updates.
07/28/16 – GBBN attends monthly Partnering Meeting.
08/24/16 – GBBN approved for CAB Monitor Relocation services via the General Services.
08/25/16 – GBBN attends monthly Partnering Meeting.
09/29/16 – GBBN attends monthly Partnering Meeting. GBBN asked to inquire about renewel of 800 Broadway LEED EB+OM Certification verses new LEED version.
10/04/16 – GBBN responds to Facilities about the Recertification requirements for 800 Broadway after research by GBBN’s LEED specialist.
10/27/16 – GBBN attends monthly Partnering Meeting.
12/05/16 – GBBN submits SOSS for 2017 General Services.
01/07/17 – GBBN received approved SOSS.
01/17/17 – THP sends BOCC Title Sheet updates to GBBN.
01/26/17 – GBBN attends monthly Partnering Meeting.
01/30/17 – Facilites sends updated Purchase Orders for LEED Specifications and ADA Assessment (CAB) due to erroneous closing of both SOSS.
02/02/17 – Facilities sends Small Business updates to GBBN
02/16/17 – Facilities sends Green Seal Paint Information to GBBN.
02/17/17 – Facilities sends OSHA Fact Sheet to GBBN
02/23/17 – GBBN attends monthly Partnering Meeting.
03/23/17 – GBBN attends monthly Partnering Meeting.
04/24/17 – GBBN discussed with Facilities, generating renderings of 800 Broadway, for the suggested security camera installations on this project. The intent is to interface with the City of Cincinnati Historic Preservation Department for approval.
04/04/17 – GBBN participates in “History In Your Own Backyard” filming for the Alms and Doepke Building.
04/27/17 – GBBN attends monthly Partnering Meeting.
05/16/17 – GBBN emails City of Cincinnati Historic Conservator about impending Security Camera placement on front facade of building.
05/18/17 – GBBN calls City of Cincinnati Historic Conservator about impending Security Camera placement on front facade of building. A voice mail is left.
05/19/17 – City of Cincinnati Historic Conservator emails GBBN to indicated this building is not “locally registered, but is Federally Registered”. This results on no requirement for evaluation by the City of Cincinnati, only Federally but only if Federal Funding is used for the project. GBBN reports findings to Facilities.
05/25/17 – GBBN attends monthly Partnering Meeting.
06/08/17 – GBBN attends meeting at Courthouse, Room #115 to discuss potential Reconfiguration of southern space in office. Facilities determines this can be handled through State Term contracting in lieu of a new SOSS.
06/29/17 – GBBN attends monthly Partnering Meeting.
07/18/17 – GBBN attends City of Cincinnati Buildings and Inspections seminar on Accessibility. Discussed changes with Facilities as an update to the Accessibilities Assessments.
07/27/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
08/31/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
09/25/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
10/26/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
11/30/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
01/25/18- – GBBN attends monthly Partnering Meeting and completes Website Updates. After Partnering Meeting a separate meeting for the new Website Software was held.
02/21/18 – GBBN updates Website using new software.
02/22/18 – GBBN attends monthly Partnering Meeting.
03/22/18 – Facilities authorizes GBBN to author a Gantt Chart for Administration showing the entire anticipated project Schedule for the HCJC Recovery Unit Build-Out.
03/23/18 – GBBN sends Gantt Chart to Administration for review.
03/26/18- GBBN attends Justice Center Space Augmentation Project Meeting.
03/29/18 – GBBN attends monthly Partnering Meeting and completes Website Updates. After Partnering Meeting a separate meeting for the new Website Software was held.
04/23/18 – Facilities determined Justice Center State Grant Budget and Schedule Analysis would be separate SOSS and not part of General Services.
05/31/18 – GBBN attends monthly Partnering Meeting.
06/28/18 – GBBN attends monthly Partnering Meeting.
07/26/18 – GBBN attends monthly Partnering Meeting and completes website updates.
08/29/18 – GBBN completes updates to Website.
08/30/18 – GBBN attends monthly Partnering Meeting.
08/17/18 – Facilities requests three (3) copies of the Master Plan Phase II printed and delivered to Facilities.
08/21/18 – Copies ordered from Phippps. Facilities confirms printing can be billed to General Services.
09/25/18 – Invoice for printing received by GBBN.
09/27/18 – GBBN attends monthly Partnering Meeting.
10/25/18 – GBBN attends monthly Partnering Meeting.
11/29/18 – GBBN attends monthly Partnering Meeting.
01/03/19 – Facilites confirms CH Room #205 Permit Reimbursable Expense may be billed to this General Services SOSS.
01/31/19 – GBBN attends monthly Partnering Meeting.
02/28/19 – Monthly Partnering Meeting moved to tomorrow due to conflicts.
03/01/19 – GBBN attends monthly Partnering Meeting.
03/28/19 – GBBN attends monthly Partnering Meeting.
04/25/19 – GBBN attends monthly Partnering Meeting.
05/30/19 – GBBN attends monthly Partnering Meeting.
06/27/19 – GBBN attends monthly Partnering Meeting.
07/22/19 – Facilities agrees to invoice #F072 CAB 10th Floor Conference Room Community Developmenmt project, with unapproved SOSS. to General Services.
07/25/19 – GBBN attends monthly Partnering Meeting.
08/29/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
09/26/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
10/31/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
12/12/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
01/30/20 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
01/31/20 – Facilities confirms GBBN can discontinue attending any future Partnering Meetings after the March meeting.
02/27/20 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
03/26/20 – GBBN completes website updates. The regular Partnering Meeting is cancelled due to COVID-19 and State of Ohio shutdown.