PM: Matt Butz, Paul Bellman/John Millar
12/30/22 – Hamilton County requested SOSS.
02/23/23 – THP Submitted SOSS.
03/22/23 – Hamilton County approved SOSS.
04/27/23 – Design work scheduled to begin 6/1/23 and the project being bid 9/1/23.
07/21/23 – THP needs to schedule a kick-off meeting with the County.
08/21/23 – Kick-off meeting held with Hamilton County and THP.
09/26/23 – THP met with Hamilton County to review site logistics. Preparing Bid Docs for 10/09/2023.
10/04/23 – THP published bid document project manual for final review by the County Facilities.
10/05/23 – THP published bid document drawing for final review by County Facilities.
10/06/23 – County provided comments to the documents.
10/06/23 – THP published final bid documents to Purchasing, Facilities, and Arc.
10/11/23 – Skywalk project advertised to bid.
10/18/23 – Prebid Meeting occurred.
10/23/23 – Addendum No. 1 Issued.
10/26/23 – Bid opening scheduled for 11/15/23.
10/31/23 – Bid questions received by County and forwarded to THP.
11/01/23- Addendum No. 2 issued by THP. Bid opening changed to November 20, 2023.
11/09/23 – Addendum No. 3 issued by THP.
11/20/23 – Bid opening occurred. Browning Chapman and Buckeye Construction submitted bids. One bid was below the advertised budget and the second bid was under the 20% threshold. Purchasing sent bids sent to economic inclusion department for review.
12/07/23 – Bids under review.
12/15/23 – Bids found to be unresponsive.
02/01/24 – THP requested to repackage project for rebid in 2024.
02/29/24 – THP working on DD set.
02/29/24 – THP to issue updated Bid Documents to Hamilton County for Owner review.
03/14/24 – THP issued DD review set with combined roofing project.
03/21/24 – HC Board of Commissioners approved budget for Façade project.
03/21/24 – THP met with Hamilton County to review project DD documents. Based on timing and bid procedure, County requested project bid in early June.
03/28/24 – THP working on documents.
04/25/24 – THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
06/26/24 – THP working on documents and targeting a bid set for July.
07/17/24 – Project is combined with FOO2 – Justice Center Skywalk Roof Replacement.