Hamilton County Facilities

TPC – Rail and Gate Project (F073)

PM: John Nester, Matt Rigdon
08/26/22 – Hamilton County requested SOSS.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County met to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
08/31/23 – THP to send review of the new lapeyre stair at TPC which is to be included in the WHT Railing package.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/23/23 – ZSR Contracting and Restoration was awarded the project at the end of November. Email received from Hamilton County that the contracts are still being processed. Lead time for materials to be 5-6 weeks once contract is received.
2/28/24 – No updates from THP.
3/26/24 – THP received SOV and Project Schedule. Pre-construction meeting to be set closer to delivery time of prefab stair. Prefab stair expected to be delivered first week of May.
04/24/24 – Preconstruction meeting completed.
05/23/24 – THP received revised shop drawings for stair at Portune Center.
09/26/24 – First Progress meeting held on 09/23/24. ZSR to mobilize this week and begin demolition of existing stair at TPC.
12/03/24 – ZSR has addressed outstanding items at the new staircase. THP to begin close out procedures with ZSR.
01/29/25 – Closing out – beginning phase. Doug (ZSR) sent everything over to their office manager last week and he is getting AIA docs together. Doug is hoping to have everything to me this week to review.
3/26/25 – Finalizing Closeout documents. Should be ready to forward to HC soon.
04/24/25 – THP dropped off final closeout documents.
04/24/25 – Archive project.