Hamilton County Facilities

Hillcrest – Birch Cottage Storm Damage Repair (F044)

PM: Bert Watts, John Millar

11/03/21 – Hamilton County requested SOSS to repair Birch Cottage.
12/01/21 – THP, Champlin and Thermal Tech met at Birch Cottage to review scope.
01/27/22 – THP submitted SD proposal. Bert has updated on scope of work on the work for the project for coverage of the damage.
04/22/22 – County reached out to Champlin to restructure the approach with Champlin leading the full effort. Champlin requested an updated proposal.
04/26/22 – THP send an updated proposal to Champlin.
01/25/23 – SOSS requested for Birch Cottage demolition.
02/23/23 – THP following up with contractors for environmental study prior to demo for spoils remediation.