PM: Bert Watts, Mike Murphy
07/12/27 – SOSS approved, kickoff meetings scheduled.
07/17/23 – Fieldwork started with Architect & MEP. Cottages will be first.
07/27/23 – All fieldwork is completed. Top 10 list has been shared. Champlin working on consolidated list. County will take control of site on 8/1/23 per email.
08/31/23 – Pavement condition report and tree maintenance report have been received. Architectural report nearly complete. MEP system report sample draft of some buildings has been received and acceptable. Other buildings in process. On target for mid September submission.
09/12/23 – Sent final reports to Champlin for Hillcrest including cost estimates for use on final report.
09/28/23 – Final report submitted to County
10/25/23 – Champlin to provide estimate for interior painting of cottages.
02/01/24 – Ready to Archive.