PM: Matt Butz, Terry Cannon
02/12/26 – DEG kicking project off and setting up fieldwork.
02/25/26 – We’ve confirmed the new heaters are the high temperature laundry and kitchen PK heaters. The SOSS is submitted and DEG is beginning preliminary engineering.
03/25/26 – SOSS submitted, project setup.
04/29/26 – Initial fieldwork started, drawing setup underway. Pat Bemmes will be assisting with this project.
05/27/26 – Drawings are setup, equipment submittals and cost have been requested from vendors.
06/25/26 – Project put on hold. Send final DEG invoice.