11/19/19 – SOSS approved for Downtown Fire Rated Door Inspection RFP
11/19/19 – SOSS approved for Auxiliary Buildings Fire-rated Door Inventory
12/18/19 – Champlin sent Fire Rated Door Inspection Bid Documents draft to County
12/31/19 – Champlin began inventory at 250 Taft
01/03/20 – Champlin visited Juvenile Center
01/06/20 – Champlin completes rest of field visits
01/15/20 – Champlin received instructions from Tony Matre to combine both projects into one.
01/21/20 – Champlin receives access to archives for existing drawings of Auxiliary buildings
02/07/20 – Champlin expected to send bid documents to County
02/14/20 – Kru and Sam met with Bert, Tony, Jessica, and Rycca to discuss scope of work to be included in documents. Champlin is waiting for service agreement draft from Bert.
11/20/20 – CA reached out to DHPace in Columbus for a unit price per door. No response after initial call. Reached out again last week and still no response. Looking for new contact to advise.
02/25/21 – No update.

03/25/21 – Preparing Bid package

04/29/21 – Bid package ready for review.

05/27/21 – No Update

06/25/21 – No Update

07/29/21 – No Update

08/26/21 – No Update

10/26/21 – Final bid set completed. Submitted to purchasing.

03/31/22 – Plans marking 0ut doors to be provided to county

04/28/22 – Plans sent to county. TPC Door schedule from GBBN incorrect (Appears to have been entirely copied from Taft Center). Champlin can provide review of TPC if directed.

05/26/22 – Champlin to review TPC friday or monday depending on availability.

08/25/22 – Champlin reviewed reports and door count discrepancy. A&D doors need further discussion.