Patrol HQ – Parking Lot Security

06/14/11 – The Lighting submittals were returned to TJ Williams on 5/19/11 and the fence submittals were returned on 5/27/11. Mike Barth spoke with Andy last week and he is estimating that lights and fence would be coming in over the next few weeks. Mike will call Andy again this week to get update.

06/29/11 – The pole light is not going to be acceptable to be reused on the ground due to size. We are working on a replacement light and updating our drawings to reflect the changes.

07/28/11 – MCB stopped by Patrol HQ and reviewed completed installation of flood lights. Installation of fence is complete. Upon receipt of closeout documentation from TJ Williams, closeout procedures will be completed.