Hamilton County Facilities

SPHQ-A

Sheriff Patrol Headquarters – 11021 Hamilton Ave
Archive

SPHQ – AHU-3 Replacement

PM: Matt Butz, Terry Cannon
02/12/26 – Kickoff meeting being scheduled with HamCo.
02/25/26 – The SOSS has been submitted. Barrett meet Ian on site and review existing conditions. This unit is only five years old, do we really want to replace it.
03/25/26 – Waiting on SOSS and kickoff meeting to determine final scope.
04/26/26 – Internal meeting on project progress. We will scheduled next meeting with Ian after 525 RECX gets underway.
05/27/26 – On hold wafting on direction from County on how to proceed. AHU already replaced five years ago.
06/25/26 – Project put on hold, send final DEG invoice.

SPHQ – AHU-3 Replacement Read More »

SPHQ – Parking Lot Repave (F025)

PM: John Nester, Paul Bellman

04/01/25 – County requested SOSS to repaving of the Patrol HQ Parking Lot.
04/02/25 – THP completed a preliminary walk of the site.
04/18/25 – THP coordinated consultant proposals from Kleingers and Terracon.
04/24/25 – THP to publish SOSS for review.
05/07/25 – SOSS approved.
05/19/25 – Design kick off meeting complete.
05/29/25 – Civil survey and underground detective work complete.
06/25/25 – Terracon scheduled for underground exploration. THP coordinating with HC.
07/16/25 – Terracon completed borings and sent Draft report.
08/15/25 – Terracon sent final boring report.
08/28/25 – Meeting scheduled with THP, Kleingers, and Terracon to review boring report to finalize plans. Told Rycca THP can have this out late September.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
12/11/25 – Project on hold till further notice.

SPHQ – Parking Lot Repave (F025) Read More »

SPHQ – ALC Upgrade BAS Commissioning 2024

PM: John Nester, Terry Cannon

01/24/24 – Post created for tracking.
01/31/24 – Two punchlist sent to ALC for work on the current job. Training scheduled for Friday with Mike Bowman and Emcor.
02/02/24 – Training went well. Ian, Kendall, Curtis, Terry and Barrett attended. We made a few adjustments while reviewing.
03/22/24 – Project completed, just waiting on some summertime use before we close it out.
04/24/24 – Emcor onsite this week trying to get AHU-1, AHU-4 worked out for dual circuiting. AHU-1 VFD installed on 4/23. NKYHC replacing refrigerant and ambient.  Emcor wrapping up they Comm Center and starting the 250 WHT building next week.
05/29/24 – Controls work has been completed and VFD installed. We need to check back with Ian to see if its working better.
06/26/24 – DK currently working at 250, will check on progress.
07/24/24 – 250 WHT is almost complete. 486 next, then Comm Center. TTC checks the graphics and there is work to do before we say they are done.
08/28/24 – Working on final stages of 250 WHT.
09/24/24 – 250 WHT graphics are not complete, points are being programmed now. SPHQ appears that most upgrades are complete. Comm Center graphics are intact but no space temperatures are shown on floor plans, none of the mechanical equipment is shown on a site plan anywhere, found it in the Basement but there is no chiller shown on the plans. Public Works Garage has updated controls on the new work from the renovation has not been programmed and we have no feedback on space temperatures yet. The Records Center has no space temperatures on graphics.
10/30/24 – All buildings are complete except for Records Center according to Emcor. They are waiting on an outdoor enclosure for the outdoor RTU.
12/12/24 – TTC reviewed SPHQ and asked that Emcor put space temperatures on the floor plans with the thermal graphics maps like we did at SPHQ.
01/28/25 – Progress ongoing. All buildings are either done or partially complete. Price received for temps on floors and passed along to Tony for consideration.
02/26/25 – TTC reached out for an update from Mike and Steve yesterday.
02/27/25 – Emcor received final IP address for last building. Mike Bowman will be out to add the last building and then TTC to punchlist.
03/25/25 – ALC should be complete with all buildings. TTC will create a punchlist for each building in the next 30 days.
04/23/25 – TTC working on punchlist right now.
05/28/25 – Archived.

SPHQ – ALC Upgrade BAS Commissioning 2024 Read More »

SPHQ – Academy Building Repurpose

PM: Sam Hofmann, Matt Butz
02/22/23 – SOSS received. Kick off to be held soon.
03/30/23 – Kickoff held on site with user. Matt to figure out budget and who pays for furniture. No movement until then.
04/27/23 – Design development on going. We will need one more meeting with users as we finish CDs
05/25/23 – Meeting held on site with users. Drawings in progress.
06/29/23 – Final review meeting held on 6/26. Discussed replacing clerestory windows. Window opening is not a glass block module so aluminum storefront and igu will be specified.
07/27/23 – Final review set submitted to county. Need to redo project manual with updated requirements.
08/31/23 – Project goes out to bid today.
09/28/23 – Bid opens today.
10/25/23 – Project was re-bid due to XBE paperwork not being filled out properly.
12/07/23 – Bids returned. Bid vet to be scheduled for this week.
02/29/24 – Projects kicked off. Submittals received and being returned.
03/28/24 – Construction to begin 4/1.
04/25/24 – Construction ongoing. Romex was found in the building not in conduit. We will get a cost to upgrade the electric to conduit on this job. We have removed the sink from the job and will take a credit for that work.
05/30/24 – Construction ongoing.
06/27/24 – Construction ongoing.
07/23/24 – Const Mtg onsite but little progress from last meeting.
08/29/24 – Progress being made. Tumlin removed wrong water fountain.
09/26/24 – Paint and casework mostly complete. Flooring getting installed next week. New wifi getting installed TTC to follow up.
10/31/24 – Punchlist issues, but additional work is needed. Deteriorated window sills needs to be fixed, EWC question sent today to TTE.
12/12/24 – Punchlist distributed. Sheriff are happy with new space. TTC replaced thermostats and put them on WIFI.
01/30/25 – Project complete. Closeouts to be submitted by Tumlin.
02/27/25 – Tumlin will be onsite for punch items. Closeouts outstanding.
03/27/25 – One punch item outstanding. Closeouts outstanding.
04/24/25 – Closeouts outstanding. Final pay app submitted by Tumlin will be held until closeouts are received.
05/29/25 – Parts missing. Tumlin to complete closeouts.
08/28/25 – No Updates.
09/25/25 – No Updates, we are still waiting on closeout documents.
10/30/25 – Closeout updates have been received from Tumlin. We will review to determine if they are acceptable.
02/26/26 – Closeouts given back to Tumlin to correct and return.
03/26/26 – Closeouts in Countys hands.

SPHQ – Academy Building Repurpose Read More »

SPHQ – Furnace 1, 2, 3 Replacements

PM – John Nester, Terry Cannon
12/10/20 – SOSS submitted.
12/28/20 – SOSS approved.
01/11/21 – Fieldwork. ThermalTech & Ian.
01/25/21 – Verified furnace units new and old. Talked to Jackson about historical work at SPHQ and what “3” furnace replacement meant back then. He confirmed what we found on site last week. F-3 in the main SPHQ is new circa 2019. F-17 and F-18 are in the Academy and were installed in 2015, 2016. F-19 is in the Fitness area and was installed in 2004. Thse units may a newer condenser. TTE to verify this.
01/26/21 – Reached out to Ian to setup second field trip for TTE to take off HVAC for CAFM drawings and get information on the Property Barn unit so it can be replaced as part of this project.
02/24/21 – Fieldwork and CAD complete on existing Fitness center. Loads complete on all spaces. TTC to review work.
03/25/21 – HVAC design complete, TTC needs to review and share with the County.
04/29/21 – Marked up changes, awaiting CAD changes and TTC will send to JN for review.
05/26/21 – Talked to Ian and agreed that we need to do more fieldwork on the Property Barn before putting anything on paper for that Alternate. Base Bid and Alternates marked up and turned in for edits. I am waiting to get the electrical on board until the HVAC is complete. I am shooting to have this bid out this summer.
06/11/21 – We met on site and discussed basic scope and alternates with Ian and John. It was decided to demo the non-working Reznor unit and replace the three ceiling hung Reznor units on the back wall. Investigate expanding the ductwork in the property barn for additional comfort control as an alternate.
06/25/21 – MEP drawing mostly ready for county review except for the Alternate on the property barn. The Reznor units are obsolete but we found very similar replacement from our local rep. A cost and new venting was provided for our use in the Alternate design.
07/28/21 – Revised design into CAD for final markups. This will go out for bidding in August.
08/26/21 – TTC getting help to finish this project in the next couple fo weeks.
10/28/21 – Project released for bidding. Addendum #1 was issued on 10/27/21. Bids opening 11/08/21.
12/13/21 – Bids were received and Northern KY was the apparent low bidder.  A pre-award meeting was conducted by TTE and NKYHC was recommended for the work  The PO and Contract were approved in late November.  Submittals were sent to TTE and returned on Sunday 12/12 by TTC.  A pre const meeting is scheduled for 12/22 with the County and contractor.
01/25/22 – Revised scheduled sent to County from NKHC for work in February.
02/24/22 – Work is coming along nicely. New furnace is in, two new unit heaters are installed, RTU is on grade.
03/31/22 – Property Barn thermostat replaced and reprogrammed. Temperature swings still happening overnight but we think the unit heater is off. Ian to check for us.
04/28/22 – New thermostat seems to be working fine. Tony asked about heat in garage because door is being replaced and I told him all new units are installed and working. the old Reznor above the bathrooms is defunct and not being replaced. F-3 is complete and working.
05/25/22 – All work complete on the original scope. IBI permitting getting updated by Rick and Holstegge Electric. We are looking at change order work now with Ian and Rick.
06/30/22 – Electric rework is complete. Rick submitted revised change order for new Condensing Units and is fixing a bad fan on one now.
07/26/22 – Change Order #1 was approved and signed for the replacement of two condensing units. We solicited a change order bid for the full ALC control package which came in and was forwarded to the County for review.
08/09/22 – Sent Change Order #2 request to NKYHC for pricing.
08/23/22 – Checked back on CO progress for the condensing units and the reheat pricing. Controls pricing is already here.
09/22/22 – Submittals received from NKYHC. Payapps received and process for payment. Change Order for the condensing units and coils approved. Hot water reheat change order is but not officially approved yet. County working on PO increase for rest of work. Emcor provided reduced prices for remaining control work.
09/29/22 – Meeting on Monday to review change order work at SPHQ.
10/26/22 – Change Order 3 drawing ready for pricing. TTC coordinate with Rick. Permit drawings almost ready to give to rick for permitting on this job. We updated the floor plan to include the additional RHC locations and upsized the piping for the new work.
12/15/22 – Condensers are installed and ready. The initial refrigerant charge is on the new units. We have a controller question on on of the air handlers but both are wired up and running. Additional change orders are out for pricing. Emcor conversion of existing JCI field components came through this week.
01/24/23 – We have been working all week on getting the change order in placed and the submittal for the hot water coils approved. We are working on Rev-3 versions now. All change order #1 work is complete and inspections are approved.
02/22/23 – Revised RHC drawings sent to Rick and CAI for coil sizing and prices with new temperatures and CFM’s. Base bid and change order 1 work is complete.
03/30/23 – Working on repricing the CO#2 and CO#3 cost with Emcor and NKYHC. CO3 came in at $51,000 but ALC offered a $9000 credit for combined work.
04/17/23 – Controls submittals have been received. NM reviewed the RHC, TTC to do the rest.
04/26/23 – Change Order #3 approved for rest of RHC conversion and controls upgrades for the DDC system at SPHQ. The first batch of RHC are here. Check on start time with Rick.
05/21/23 – RHC are in. Piping is complete for all 15 RHC coils to valves . 7 valves are installed. TTE ready to punchlist first phase.
06/28/23 – Punchlist completed and sent to NKYHC. Requested update from Emcor on ALC progress. New compressors need controls update.
07/26/23 – Emcor upgrading controls, this work should be done in August.
08/23/23 – The project is nearly complete, only a couple of controllers are left.
09/27/23 – All work for this project is complete including HVAC, Electrical and Controls. However there are operational issues we are still addressing which include 1) HW pump did not appear to be pumping enough water, contacted vendor reset control sequence. 2) new condensing units did not have the right controller for dual circuit operation, but this is not fixed but led to question in #3. 3) one of the AHU has a VFD on it and NKYHC reset the speed of this fan in the summer for full load but now that it’s fall, they had to reset to fan to a slower speed. We are working on this to fix it for all seasons because it’s too cold in some areas. NKY working on final punchlist items.
10/25/23 – NKYHC is complete and finalizing punchlist. Emcor is complete but controls have not been commissioned. Boiler is going out on high limit. NKYHC has been working on reprogramming the unit with help from Lochinvar. We are meeting Friday to work out control issues with the pumps, boiler and new reheat coils. So far new the boiler had to be reprogrammed because ALC landed new controls on the boiler, a jumper had to be changed on one Admin VAV box, water had to be added to the HHW system. We will find out more on Friday.
12/06/23 – Project is complete and in final punchlist phases. We need to spend some time commissioning with Emcor to get the sequences worked out with them.
01/09/24 – This week we worked on AHU-2 gas heating furnace not working correctly. After several trips and replacements, the furnace is working but may not be working well all the time, the rollout switch was replaced with a non-automatic reset switch, creating more nuisance work for Ian. When the first floor heater is working the building work a lot better. The first floor boiler was not sized for full heating of the entire building, it is sized for heating on the second floor and some reheat on the first floor only. We must have the gas furnace working on the AHU-2 to heat the building in the winter.
01/31/24 – This project is complete and the final programming work moved to SPHQ BAS Recommissioning project.
02/23/24 – Closeout documents sent to NKYHC for use on closeout docs.
03/22/24 – Closeout documents AIA forms sent to County, we need the rest of the closeout paperwork, requested from Lisa today.
04/24/24 – NKYHC doing warranty work on AHU-1 and AHU-4 as part of this project. Emcor commissioning the dual circuit control for the new units. Closeout paperwork submitted to John Nester with a thumb drive. This project is ready to Archive.
05/28/24 – O&M manuals updated and complete, this project ready to archive.

SPHQ – Furnace 1, 2, 3 Replacements Read More »

SPHQ – RTU-5 Replacement

11/14/16 – Prebid meeting was held on site.

11/15/16 – TTC investigate using the existing architectural and mechanical plans to reword the ductwork on RTU-5 so that the unit will keep its ductwork up on the second floor and penetrate the side wall on the second floor and intercept the ductwork where it comes up through the floor. TTC spoke to Kevin Maue, Greg Smorey and Tom Speer about the original build today.

11/16/16 – Addendum #1 was sent out this morning for bidding answering prebid questions.

11/18/16 – Addendum #2 was sent out.

11/22/16 – Addendum #3 was sent out.

12/07/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.

01/13/17 – Discussed equipment vendor selection with Feldkamp and JCI. Carrier was submitted but they are probably going to purchase JCI as an equal vendor for this project. Spoke to Jackson and Tony about this.

02/02/17 – Precon schedule for 2/14.

02/17/17 – Met contractor on site to review possible new placement and routing for ductwork on this job. ThermalTech to draw up new location and routing and get THP approval.

02/27/17 – Revised downflow design completed and sent to contractor for pricing on Thursday, revised again on Friday and emailed, revised again on Monday and sent to contractor.

02/28/17 – Final design and schedules revised again and sent to Feldkamp and Owner. Submittals rejected twice this week but third submittal was sent back Furnish as Corrected. Also told Tony today that the redesign used $2040 of the const budget and leaves about $500 for Const Services.

03/09/17 – Unit is ordered, a revised set of submittals was sent to Feldkamp this week. A controls meeting is scheduled for 3/22 at ThermalTech with Alpha and Habegger.

03/15/17 – TEI sent PO provided by Tony to DK for processing and requested project schedule from Feldkamp for this job.

03/21/17 – THP – THP and TTE had a conference call to discuss scope and fee. TTE to review fees with County.03/21/17 – Controls meeting rescheduled until 3/28 at 9am at TEI.

04/03/17 – TTE requested a formal proposal.04/21/17 – Control submittals have arrived. ThermalTech to review and return ASAP.

04/11/17 – THP provide a proposal for review.04/25/17 – Updated Drawings were given to Jackson and Feldkamp was on site locating the curb on the roof per the new structural drawings. Unit schedule to arrive in May for installation.

04/13/17 – THP proposal approved.

04/25/17 – THP analyzed AHU loading and proposed shifted the unit. Unit location was shifted. THP provided roof top support channel detail.

05/19/17 – TTC stopped by for field inspection. Curb looks good, ductwork looks good, fire dampers look good. DK trying to locate electric for new power to pull new feeders. Pictures from roof support work appeared to be acceptable to ThermalTech and THP.

06/27/17 – Project is complete and we are punchlisting the work.

07/19/17 – Punchlist was distributed today to both Debra Kuempel and Feldkamp Enterprises.

08/03/17 – Met Feldkamp on site to get quote for new boiler options using allowance money leftover on this job.

08/17/17 – Met Jackson onsite today and collected more information for the Alpha quote. Talked to DK and they are coming out to change the restrictor plate on SVH-204 soon, they will also be giving Alpha the K values to program into the VAV boxes on the FE system so we can see the correct CFM’s. I also emailed Alpha a full email explaining that I wanted to simplify and reduce their scope and price on this job and that all of the controls we need are already installed and on the graphics.

08/30/17 -All prices are in for the heating boiler and we can award this work to Feldkamp as part of this job. Still working on a cost from Alpha.

09/08/17 – When the electrical inspector (Ken Spille) came to the field for the final, he had the wrong drawings for the work with him. DK contacted TEI (Mike Barth) and we delivered another copy of the correct drawings to IBI. Ken told DK in the field that once those drawings were dropped off and processed at IBI, that he would get the final for the permit. IBI is now telling DK that they have to call and schedule a final inspection for the project (although they have already had a final), and that IBI cannot close out the project. We told DK that we need to get this closed out, and since the inspector is not recalling his field statements, please work this out and get the final completed. DK working with IBI to resolve.

09/25/17 – Feldkamp and DK were both on site last week installing the new hot water boiler form Lochinvar. We went with the 155,000 btuh boiler for this installation in the fire tube design which is a new offering from Lochinvar. The piping is connected, the exp tank is relocated, the gas piping is connected and the venting is hooked. Feldkamp confirmed the venting is ready and clear of caps and ready to use. This week Feldkamp is to startup the boiler and Alpha controls or Feldkamp will complete the installation of the systems. TTC stopped by last Thursday but not contractors were on site, TTC may stop by again to review the work if he can around his meetings and vacation.

10/24/17 – Boiler is up and running. The controls enables and disables the boiler based on outdoor air temperature. The owner has the boiler set to 140F and can adjust as needed seasonally. TTC sent out the allowance usage and change order for this project and asked Feldkamp to close it all out. The roofer came out and applied another patch to the job around the unit to quell a roof leak and hopefully that works. Everything seems to be up and running well.

10/25/17 – Allowance usage came back from Feldkamp and was forwarded to Tony Matre for signature. Boiler went out on alarm this morning. Feldkamp dispatched to investigate.

11/28/17 – In the past month we have had Feldkamp, Alpha and Corken all on site working on the boiler system. The boiler is running well and Feldkamp has upgraded the gas supply to the boiler, added the combustion tee for tuning up the boiler plant and added the neutralizer to the boiler drain. Alpha has reprogrammed the hot water pump to run through the system at all times and we are awaiting the controls upgrade to supply the setpoint to the boiler. Then Corken can come in and provide a full startup on the boiler.
03/30/18 – After a lot of work to get revised O&M’s for this job from the contractor that TTC felt were good enough for the owner, the final PDF was downloaded and printed by ThermalTech and three O&M’s were created for Tony Matre. I am not sure why TEI is making O&M’s for the contractors nowadays but in an effort to bring the project to completion, they were made and UPS ground to Facilities. The only item we know is open is the CAFM updates for these drawings.

SPHQ – RTU-5 Replacement Read More »

Sheriff HQ – Electrical Device Identification and Arc Flash Study

05/30/08 – Ginter sent the panelboard schedule in excel format. TEI forwarded to County and sent allowance usage certificate to Ginter for signing. Ginter has to provide an approved IBI permit at conclusion of this project.

04/09/08 – All Work is complete. TEI will finish and stamp the permit drawing for Ginter. Ginter will get IBI for making the conference room on emergency panel for colonel. This will use the last of the allowance money and closeout the project.

01/07/08 – Ginter has completed punchlist items. MAH will conduct back check when meeting on extra work takes place. The Colonel would like to have some receptacles on emergency power in the conference room so they can use as a command center. The work will be discussed with final approval from Tony Matre.

12/14/07 – Change order was requested for Ginter to access the $2000 allowance. TEI has requested additional itemized backup and an explanation of the additional devices from Ginter. Jim Ginter sent the additional items to TEI and MH is reviewing for approval today. MH created the punchlist for the project and is distributing the punchlist to the contractor today as well.

12/11/07 – Construction meeting was conducted and punchlist was created moving toward a final closeout. Punchlist items will take a few weeks because of the lead time in ordering engraved labels. Aside from some misunderstanding in the labeling requirements the work appears very thorough. Ginter turned over mark-ups. Ginter to submit pay apps and TEI to write a deduct change order for unused allowance.

11/30/07 – As promised Ginter reported today that this project is complete. TTC responded back to their email that we would use the const mtg for our punchlist and to advise about allowance usage on this project so TEI could write a deduct change order for closeout. TTC also sent all the closeout documents to Ginter for use on this job.

11/28/07 – Ginter provided an update today stating the the ID project was going well. TEI will setup a const mtg the week of 12/10.

11/09/07 – TTC distributed Pre Const Mtg minutes from last week. Ginter is on the job and ready to complete by the end of this year.

08/31/07 – TTC received word from HCFD that the insurance issue has been resolved. TEI awaiting word from HCFD so that this project can move into the Construction Phase.

08/15/07 – NR wrote: “Any idea about when this project is going to be ready for construction?” Bert( HCFD) responded: “I am still working out Insurance issues with Michael Ginter, he is working on getting me the correct Certificate of Insurance. Jim and I are working on getting the LEADS background checks completed.” TEI awaiting word from Hamilton County Facilities Department to move into construction phase.

08/10/07 – TEI awaiting word that the contract has been signed by Ginter Electric so that this project can move into the construction phase.

07/30/07 – NR received word from Bert Watts at the Hamilton County Facilities Department that the contract was sent to Ginter Electric last week for their signature. TE is awaiting word that the contract has been signed so that this project can move forward with the construction phase.

06/29/07 – TE awaiting word that the contract has been signed to that this project can move into the construction phase.

06/22/07 – Contract has been awarded to Ginter Electric. The contract has been sent to Mark Donnelly; TE is awaiting signed contract to proceed with pre-construction meeting.

06/15/07 – Hamilton County Facilities is reviewing the bid tabulation. TE is awaiting word about which contractor has been awarded the contract so that we can move forward with this project.

06/08/07 – This project opened for bid yesterday. TE is awaiting the bid tabulation from the Hamilton County Purchasing Department.

06/01/07 – This project is set for bid opening on June 7, 2007.

05/25/07 – The pre-bid meeting was held on site today. Those in attendance included Kevin and Steve Kallmeyer of Kallmeyer Electric, Jim Ginter of Ginter Electric, Nick Richmond of ThermalTech Engineering, and Walt Hendrick/ Mike Jackson/ Ken Caruso of Hamilton County. A site tour was given as well as a specification and drawing review. This project is expected to go to bid on June 7th of 2007.

05/21/07 – Project went out for bid on May 18, 2007. Pre-bid meeting has been scheduled for Friday, May 25 at 10:00am. Meeting place is the lobby of the Patrol Headquarters. NR contacted Captain Mark Hendrick to discuss working hours. It was decided that normal working hours would best suit this project because of limited access to certain areas of the facility. NR sent an email to Mark Donnelly informing him of this.

04/27/04 – Drawings for the Device Identification portion of this project are complete and will be present for Hamilton County review in the meeting today, April 27 of 2007. The Arc Flash Labels are at the printer and should be completed within the next 2 weeks.

04/20/07 – Arc Flash Labels are being dropped off to the printer next week. The Device Identification portion of this project is complete and the drawings will be complete next week.

04/13/07 – Single Line Diagrams have been established and Arc Flash Study has begun. TE found discrepancies with the As-Built drawings and what was found in the field so they are making another field visit today, April 13, 2007. This visit is meant to trace the source of the panels in the barns and out-buildings. There is an automatic transfer switch in the Property Room that needs to be traced also. Dan Myer of TE will also be on site to meet with a county employee to locate above ceiling equipment.

04/06/07 – Kick-off meeting was held. Project is moving along as expected.

03/30/07 – Kick-off meeting is scheduled for next Thursday, April 5th of 2007.

03/23/07 – Project progressing as expected. Kick-off meeting tentatively scheduled for the first week in April. TE to set up meeting with Hamilton County Facilities.

03/20/07 – Fieldwork is progressing and is about 80% complete.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE. 90% of field work has been completed for the Device Identification portion of this project. Field notes not inputted electronically per awaiting signed SOSS.

Sheriff HQ – Electrical Device Identification and Arc Flash Study Read More »

SHERIFF PATROL HQ Street Widening

09/29/10 – Project closed and archived.

08/16/10 – We talked to Debra Kuempel today. O&M’s were submitted and I believe sent to the County last November. We have been holding for the final change order. Kevin and Donna at DK agreed the Change Order Credit was going to be $5761 for this job. Laurie is typing, we will delivery for signature to DK today and then they can get their closeout docs in order and we can close this job.

08/13/10 – Payapps updated for both contractors. As Built dwgs completed by TEI. QCM needs to sign the change order and send to Bert.

07/28/10 – Check on DK change order work and approve as-builts for project completion.

05/26/10 – DK is installing the fiberglass pan in June. We are awaiting QCM closeout docs.

05/15/10 – TTC is working on closeout documents for QCM. We have the final payapp but I don’t know if we have the O&M manuals so I contacted QCM again to check the status.

04/26/10 – Project is complete save the fiberglass pan issue.

03/23/10 – DK got an okay to provide pricing for a new fiberglass drip pan for the panel as we wait for THP to work on better site drainage.

02/22/10 – TTC signed additional payapps for QCM and DK for payment on this job. We are ready to close it out. There is an issue about a ground fault alarm and wiring on the fire pit. DK said they may just replace the wire and be done with it.

12/31/09 – Debra Kuempel did the overnight work on the conduit sealant upgrade and I believe we are down to final closeout. We have a warranty issued with the pit having a grounding issue at the fire alarm panel. DK has sent a technician to repair.

10/20/09 – TTC sent out punchlist today to contractors with instructions to closeout project. We are accepting CO#09 for blacktop from QCM. We have to work out the $10,000 allowance with Debra Kuempel and the $7500 with QCM for this project to write the final Change Orders. The email included instructions to closeout and finalize change orders and allowances.

09/22/09 – The project is nearly complete. TEI will be performing the punchlist in the next few weeks. DK is going to be on site on Thursday to finish up their work. Queen City Mechanical submitted change orders for processing today. We received a new COR #8 for piping. TEi asked for more info on this change order. We should be able to close out in a month.

08/26/09 – Final tie-ins for both fire protection and fire alarm are being made. By the end of this week, everything should be 99% complete and ready for punchlist.

07/27/09 – Bert and Terry talked last week about having TEI modifying our permit to list the Fire Pit as existing equipment. TTC called but the Inspectors office was closed. I will try back again later. The County has asked for the CWW to submit their drawings and apply for a permit for the work separately.

06/23/09 – All the permit issues have been resolved. TTC contact QCM mechanical by email and phone to get an update on status of fire main trench. No update but TTC will check on 06/24 when he visits the site for the FA project. DK has not been back to the site since the new power was brought back online. We believe they will return when they work on the trench with QCM.

05/22/09 – DK has finished the transformer relocation. The building is back up on Duke power from the new transformer. The cables are being collected for pickup. Prus provided the new fire main and fire pit for us. QCM will be out 05/26/09 to begin trenching the parking lot for the remaining work on fire alarm and fire sprinkler work.

04/03/09 – TTC sent an email update to the team for the pit, given it is located in the parking lot. Tony is going to look at the final location. Bert and Tony to advise. Luckily, we talked about this happening in the pre construction meeting.

02/19/09 – GCWW has brokered a deal to have Ray Prus provide the water tap to the R/W for QCM from the new water main. Ford Development will build the pit from that location. We have asked for a credit from QCM for the smaller scope.

02/0509 – QCM informed us that a new water main is being installed in Hamilton Ave. I advised QCM to investigate using that main instead of the one we originally projected for use.

02/02/09 – TTC modified the project schedule and sent out for approval to all the vendors. Jackson questioned the actual shutdown and switchover date but TTC told him that was not set in stone yet. The City has approved the water permit. We are waiting on ODOT approval of the plans before digging.

01/05/09 – Payapp #3 came in for DK and ThermalTech approved and sent to Bert. This payapp went to Bert first which may delay this payment.

10/16/08 – ThermalTech sent profile drawing to QCM for submission to state. TEI sent new permit drawings to Debra Kuempel for permit application. DK is getting price from Duke for work on this project per the scope of work on the specs as TEI wrote.

08/29/08 – Contracts approved. Pre Const Set for next Thursday.

08/22/08 – No update from County. TEI inquired about proceeding. Tony answered that contracts will be in front of the Board next Wed. 08/27.

08/08/08 – Tony reported the Prosecutor has contracts for approval. They are pushing hard.

07/31/08 – County reported that all contracts are at Prosecutor’s Office awaiting approval.

07/30/08 – TEI has delivered all contracts to Contractors for signing. TEI sent stamped permit drawings to Queen City Mechanicals for CWW permit application. QCM stated that CWW will want permit tap fee as soon as permit is awarded. This process may be the longest lead item of the whole job.

07/18/08 – Pre Award Meeting complete. All contractors recommended for project. Debra and Queen City Mechanical both stated they understood the project, the schedule and agreed their price was valid for this scope.

SHERIFF PATROL HQ Street Widening Read More »

SHERIFF PATROL HQ Signage Upgrade

01/24/11 – TTC asked for a written letter from KFI to proceed with closeout as the punchlist is not fully complete as the scratches on the sign have to be touched up.

10/28/10 – We have visited the site several times as the foundation has been poured, electrical has been run and masonry work is ready to begin.

09/29/10 – Holding for State to complete road work.

08/13/10 – Payment 1 has been sent.

07/28/10 – TEI to approve payapp and send to Bert. It looks good, have to visit the site to see the sign.

04/26/10 – We are on hold until June.

03/23/10 – It has been reported that the sign is complete.

02/24/10 – John Brockman called with a question about backlighting the can. TEI will return the call.

02/05/10 – TTC visited Ernst signs and worked out final details on the sign building scheduled for April. TTC updated all parties.

12/31/09 – TTC submitted a permit answer to HamCo building inspections. The next step is theirs. We may have to resubmit to start the project again.

09/22/09 – The new street is very close to the sign. The County is working with ODOT to finalize the sign work. Our contractors are preparing a new shop drawing to the County permit office with the galvanized steel frame.

07/29/09 – No updates because Street Widening is still on hold.

06/23/09 – KF has not returned our call or emails about sign permit approval. At this time it is being held for review by Marty in HamCo Bldg Dept awaiting our clarification on how the sign post will be embedded into the sign base and what material it will be. We may need a meeting or conference call with KF and Brockman signs.

05/22/09 – Zoning has approved our sign permit. The bldg department is questioning the supports for the sign. Tom Speer is checking his design for us.

03/02/09 – Pre-Construction meeting held. KFI will order materials and store sign at HQ to allow invoicing. On hold until street widening is complete.

SHERIFF PATROL HQ Signage Upgrade Read More »

PATROL HQ Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads. Electronic drawings for SPHQ campus had to be generated for Facilities CAFM partner to input into Archibus. TEI and Facilities deliver existing drawings and electronic files to GBBN for creation of electronic drawing files.

07/01/14 – GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre on final invoicing for these projects.

PATROL HQ Asbestos Study Read More »

Sheriff HQ – Electrical Device Identification and Arc Flash Study

05/30/08 – Ginter sent the panelboard schedule in excel format. TEI forwarded to County and sent allowance usage certificate to Ginter for signing. Ginter has to provide an approved IBI permit at conclusion of this project.

04/09/08 – All Work is complete. TEI will finish and stamp the permit drawing for Ginter. Ginter will get IBI for making the conference room on emergency panel for colonel. This will use the last of the allowance money and closeout the project.

01/07/08 – Ginter has completed punchlist items. MAH will conduct back check when meeting on extra work takes place. The Colonel would like to have some receptacles on emergency power in the conference room so they can use as a command center. The work will be discussed with final approval from Tony Matre.

12/14/07 – Change order was requested for Ginter to access the $2000 allowance. TEI has requested additional itemized backup and an explanation of the additional devices from Ginter. Jim Ginter sent the additional items to TEI and MH is reviewing for approval today. MH created the punchlist for the project and is distributing the punchlist to the contractor today as well.

12/11/07 – Construction meeting was conducted and punchlist was created moving toward a final closeout. Punchlist items will take a few weeks because of the lead time in ordering engraved labels. Aside from some misunderstanding in the labeling requirements the work appears very thorough. Ginter turned over mark-ups. Ginter to submit pay apps and TEI to write a deduct change order for unused allowance.

11/30/07 – As promised Ginter reported today that this project is complete. TTC responded back to their email that we would use the const mtg for our punchlist and to advise about allowance usage on this project so TEI could write a deduct change order for closeout. TTC also sent all the closeout documents to Ginter for use on this job.

11/28/07 – Ginter provided an update today stating the the ID project was going well. TEI will setup a const mtg the week of 12/10.

11/09/07 – TTC distributed Pre Const Mtg minutes from last week. Ginter is on the job and ready to complete by the end of this year.

08/31/07 – TTC received word from HCFD that the insurance issue has been resolved. TEI awaiting word from HCFD so that this project can move into the Construction Phase.

08/15/07 – NR wrote: “Any idea about when this project is going to be ready for construction?” Bert( HCFD) responded: “I am still working out Insurance issues with Michael Ginter, he is working on getting me the correct Certificate of Insurance. Jim and I are working on getting the LEADS background checks completed.” TEI awaiting word from Hamilton County Facilities Department to move into construction phase.

08/10/07 – TEI awaiting word that the contract has been signed by Ginter Electric so that this project can move into the construction phase.

07/30/07 – NR received word from Bert Watts at the Hamilton County Facilities Department that the contract was sent to Ginter Electric last week for their signature. TE is awaiting word that the contract has been signed so that this project can move forward with the construction phase.

06/29/07 – TE awaiting word that the contract has been signed to that this project can move into the construction phase.

06/22/07 – Contract has been awarded to Ginter Electric. The contract has been sent to Mark Donnelly; TE is awaiting signed contract to proceed with pre-construction meeting.

06/15/07 – Hamilton County Facilities is reviewing the bid tabulation. TE is awaiting word about which contractor has been awarded the contract so that we can move forward with this project.

06/08/07 – This project opened for bid yesterday. TE is awaiting the bid tabulation from the Hamilton County Purchasing Department.

06/01/07 – This project is set for bid opening on June 7, 2007.

05/25/07 – The pre-bid meeting was held on site today. Those in attendance included Kevin and Steve Kallmeyer of Kallmeyer Electric, Jim Ginter of Ginter Electric, Nick Richmond of ThermalTech Engineering, and Walt Hendrick/ Mike Jackson/ Ken Caruso of Hamilton County. A site tour was given as well as a specification and drawing review. This project is expected to go to bid on June 7th of 2007.

05/21/07 – Project went out for bid on May 18, 2007. Pre-bid meeting has been scheduled for Friday, May 25 at 10:00am. Meeting place is the lobby of the Patrol Headquarters. NR contacted Captain Mark Hendrick to discuss working hours. It was decided that normal working hours would best suit this project because of limited access to certain areas of the facility. NR sent an email to Mark Donnelly informing him of this.

04/27/04 – Drawings for the Device Identification portion of this project are complete and will be present for Hamilton County review in the meeting today, April 27 of 2007. The Arc Flash Labels are at the printer and should be completed within the next 2 weeks.

04/20/07 – Arc Flash Labels are being dropped off to the printer next week. The Device Identification portion of this project is complete and the drawings will be complete next week.

04/13/07 – Single Line Diagrams have been established and Arc Flash Study has begun. TE found discrepancies with the As-Built drawings and what was found in the field so they are making another field visit today, April 13, 2007. This visit is meant to trace the source of the panels in the barns and out-buildings. There is an automatic transfer switch in the Property Room that needs to be traced also. Dan Myer of TE will also be on site to meet with a county employee to locate above ceiling equipment.

04/06/07 – Kick-off meeting was held. Project is moving along as expected.

03/30/07 – Kick-off meeting is scheduled for next Thursday, April 5th of 2007.

03/23/07 – Project progressing as expected. Kick-off meeting tentatively scheduled for the first week in April. TE to set up meeting with Hamilton County Facilities.

03/20/07 – Fieldwork is progressing and is about 80% complete.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE. 90% of field work has been completed for the Device Identification portion of this project. Field notes not inputted electronically per awaiting signed SOSS.

Sheriff HQ – Electrical Device Identification and Arc Flash Study Read More »

SHERIFF PATROL HQ Street Widening

09/29/10 – Project closed and archived.

08/16/10 – We talked to Debra Kuempel today. O&M’s were submitted and I believe sent to the County last November. We have been holding for the final change order. Kevin and Donna at DK agreed the Change Order Credit was going to be $5761 for this job. Laurie is typing, we will delivery for signature to DK today and then they can get their closeout docs in order and we can close this job.

08/13/10 – Payapps updated for both contractors. As Built dwgs completed by TEI. QCM needs to sign the change order and send to Bert.

07/28/10 – Check on DK change order work and approve as-builts for project completion.

05/26/10 – DK is installing the fiberglass pan in June. We are awaiting QCM closeout docs.

05/15/10 – TTC is working on closeout documents for QCM. We have the final payapp but I don’t know if we have the O&M manuals so I contacted QCM again to check the status.

04/26/10 – Project is complete save the fiberglass pan issue.

03/23/10 – DK got an okay to provide pricing for a new fiberglass drip pan for the panel as we wait for THP to work on better site drainage.

02/22/10 – TTC signed additional payapps for QCM and DK for payment on this job. We are ready to close it out. There is an issue about a ground fault alarm and wiring on the fire pit. DK said they may just replace the wire and be done with it.

12/31/09 – Debra Kuempel did the overnight work on the conduit sealant upgrade and I believe we are down to final closeout. We have a warranty issued with the pit having a grounding issue at the fire alarm panel. DK has sent a technician to repair.

10/20/09 – TTC sent out punchlist today to contractors with instructions to closeout project. We are accepting CO#09 for blacktop from QCM. We have to work out the $10,000 allowance with Debra Kuempel and the $7500 with QCM for this project to write the final Change Orders. The email included instructions to closeout and finalize change orders and allowances.

09/22/09 – The project is nearly complete. TEI will be performing the punchlist in the next few weeks. DK is going to be on site on Thursday to finish up their work. Queen City Mechanical submitted change orders for processing today. We received a new COR #8 for piping. TEi asked for more info on this change order. We should be able to close out in a month.

08/26/09 – Final tie-ins for both fire protection and fire alarm are being made. By the end of this week, everything should be 99% complete and ready for punchlist.

07/27/09 – Bert and Terry talked last week about having TEI modifying our permit to list the Fire Pit as existing equipment. TTC called but the Inspectors office was closed. I will try back again later. The County has asked for the CWW to submit their drawings and apply for a permit for the work separately.

06/23/09 – All the permit issues have been resolved. TTC contact QCM mechanical by email and phone to get an update on status of fire main trench. No update but TTC will check on 06/24 when he visits the site for the FA project. DK has not been back to the site since the new power was brought back online. We believe they will return when they work on the trench with QCM.

05/22/09 – DK has finished the transformer relocation. The building is back up on Duke power from the new transformer. The cables are being collected for pickup. Prus provided the new fire main and fire pit for us. QCM will be out 05/26/09 to begin trenching the parking lot for the remaining work on fire alarm and fire sprinkler work.

04/03/09 – TTC sent an email update to the team for the pit, given it is located in the parking lot. Tony is going to look at the final location. Bert and Tony to advise. Luckily, we talked about this happening in the pre construction meeting.

02/19/09 – GCWW has brokered a deal to have Ray Prus provide the water tap to the R/W for QCM from the new water main. Ford Development will build the pit from that location. We have asked for a credit from QCM for the smaller scope.

02/0509 – QCM informed us that a new water main is being installed in Hamilton Ave. I advised QCM to investigate using that main instead of the one we originally projected for use.

02/02/09 – TTC modified the project schedule and sent out for approval to all the vendors. Jackson questioned the actual shutdown and switchover date but TTC told him that was not set in stone yet. The City has approved the water permit. We are waiting on ODOT approval of the plans before digging.

01/05/09 – Payapp #3 came in for DK and ThermalTech approved and sent to Bert. This payapp went to Bert first which may delay this payment.

10/16/08 – ThermalTech sent profile drawing to QCM for submission to state. TEI sent new permit drawings to Debra Kuempel for permit application. DK is getting price from Duke for work on this project per the scope of work on the specs as TEI wrote.

08/29/08 – Contracts approved. Pre Const Set for next Thursday.

08/22/08 – No update from County. TEI inquired about proceeding. Tony answered that contracts will be in front of the Board next Wed. 08/27.

08/08/08 – Tony reported the Prosecutor has contracts for approval. They are pushing hard.

07/31/08 – County reported that all contracts are at Prosecutor’s Office awaiting approval.

07/30/08 – TEI has delivered all contracts to Contractors for signing. TEI sent stamped permit drawings to Queen City Mechanicals for CWW permit application. QCM stated that CWW will want permit tap fee as soon as permit is awarded. This process may be the longest lead item of the whole job.

07/18/08 – Pre Award Meeting complete. All contractors recommended for project. Debra and Queen City Mechanical both stated they understood the project, the schedule and agreed their price was valid for this scope.

SHERIFF PATROL HQ Street Widening Read More »

SHERIFF PATROL HQ Signage Upgrade

01/24/11 – TTC asked for a written letter from KFI to proceed with closeout as the punchlist is not fully complete as the scratches on the sign have to be touched up.

10/28/10 – We have visited the site several times as the foundation has been poured, electrical has been run and masonry work is ready to begin.

09/29/10 – Holding for State to complete road work.

08/13/10 – Payment 1 has been sent.

07/28/10 – TEI to approve payapp and send to Bert. It looks good, have to visit the site to see the sign.

04/26/10 – We are on hold until June.

03/23/10 – It has been reported that the sign is complete.

02/24/10 – John Brockman called with a question about backlighting the can. TEI will return the call.

02/05/10 – TTC visited Ernst signs and worked out final details on the sign building scheduled for April. TTC updated all parties.

12/31/09 – TTC submitted a permit answer to HamCo building inspections. The next step is theirs. We may have to resubmit to start the project again.

09/22/09 – The new street is very close to the sign. The County is working with ODOT to finalize the sign work. Our contractors are preparing a new shop drawing to the County permit office with the galvanized steel frame.

07/29/09 – No updates because Street Widening is still on hold.

06/23/09 – KF has not returned our call or emails about sign permit approval. At this time it is being held for review by Marty in HamCo Bldg Dept awaiting our clarification on how the sign post will be embedded into the sign base and what material it will be. We may need a meeting or conference call with KF and Brockman signs.

05/22/09 – Zoning has approved our sign permit. The bldg department is questioning the supports for the sign. Tom Speer is checking his design for us.

03/02/09 – Pre-Construction meeting held. KFI will order materials and store sign at HQ to allow invoicing. On hold until street widening is complete.

SHERIFF PATROL HQ Signage Upgrade Read More »

Patrol HQ – Parking Lot Security

06/14/11 – The Lighting submittals were returned to TJ Williams on 5/19/11 and the fence submittals were returned on 5/27/11. Mike Barth spoke with Andy last week and he is estimating that lights and fence would be coming in over the next few weeks. Mike will call Andy again this week to get update.

06/29/11 – The pole light is not going to be acceptable to be reused on the ground due to size. We are working on a replacement light and updating our drawings to reflect the changes.

07/28/11 – MCB stopped by Patrol HQ and reviewed completed installation of flood lights. Installation of fence is complete. Upon receipt of closeout documentation from TJ Williams, closeout procedures will be completed.

Patrol HQ – Parking Lot Security Read More »

PATROL HQ Grease Interceptor

Project Lead: ThermalTech

06/25/13 – Drawing complete

04/10/13 – TTC met Dan on site and walk the scope. TEI owes Bert the SOSS for the work to be done internally and permitted by TEI.

05/24/13 – Approved SOSS received. Design has begun.

08/19-13 – Permit is approved with comment. Blue Chip has sent an invoice to ThermalTech for payment which we will pay and reimburse. We may need to install a backwater valve between the interceptor and the main sanitary drain line in the Sheriff Patrol HQ. TTC to find elevations on site survey that he thinks he has from Tom Speer for this area and give to permit office.

09/26/13 – All permit questions answered. Permit approved. Stamped drawings provided to County for work.

10/15/13 – Dan says interceptor is ordered but will be installed next season.

06/20/14 – Multiple Record drawings created and stamped and dropped off to County for plumbing dept approval. We believe the interceptor is installed and working and approved by the County Plumbing Dept.

07/30/14 – Checked on permit status. City website says Permit not approved but final inspection

09/25/14 – Blue Chip contacted to initiate permit closeout. Additional fees requested and approved by TEI, BC says final permit closeout is started and should be finished in a week or two according to Kathy at Blue Chip.

10/23/14 – Project and Permit are both final and closed out. Website list permit as “Final”

PATROL HQ Grease Interceptor Read More »

PATROL HQ Kennel Project

Project Lead: GBBN

09/30/14- GBBN receives email invitation to visit Patrol Headquarters to investigate addition for a Kennel and to investigate an operable partition renovation to the Comm. Center.

10/07/14 – Met at site for field kickoff meeting. Got tentative layout from deputies on site. Two cost estimates are required. With and without Trades doing work.

10/07/14- GBBN receives email from Bert Watts about estimate project requests created in Archibus for estimating.

10/09/14- GBBN sends first iteration of Patrol Headquarters Kennel addition floor plan to Facilities and TEI for review.

10/14/14 – ThermalTech spoke with Hamilton County Plumbing Department and MSD to confirm no special plumbing requirements are necessary for the trench drain outlet at this project. A removable cover trench drain wit interior FD cap was requested by Plumbing Dept. ThermalTech to update estimate.

10/15/14- GBBN completes estimate for Patrol Headquarters Kennel addition.

10/16/14- GBBN receives comments and suggested floor plan revisions for the Patrol Headquarters Kennel estimate.

10/20/14- GBBN sends updated Patrol Headquarters Kennel floor plan to TEI and Facilities for review and estimating.

10/20/14 – Received updated Kennel drawing. Estimate needs to be updated in Archibus for both projects 1771 and 1772. We will need two Mitsubishi type units, one for the office and one for the main kennel area.

01/30/15 – Facilities Department requests GBBN and TEI revise preliminary plans based on Sheriff’s Department review comments and to update estimates in Archibus.

02/04/15 – GBBN and TEI notifies Facilities the preliminary plans and Archibus estimates have been revised and updated.

02/14/15 – Preliminary design costs sent to Facilities at their request.

03/25/15 – Project on hold.

04/07/15 – Project still on hold.

PATROL HQ Kennel Project Read More »

PATROL HQ Reznor Heater Replacement

Project Lead: TEI

10/17/13 – Met Jackson at site for fieldwork.

10/25/13 – Vendor provided one for one replacement and rooftop model for bidding Base Bid and Alternate.

10/31/13 – Review drawings to be delivered to County for bidding as small project.

01/24/14 – Final bids came in during November. Waiting on Tony Matre to decide if we are moving forward with this project.

03/26/14 – Project may be on hold or done later. Ameresco work is currently being done at SPHQ.

0/6/20/14 – Project still on hold.

11/18/14 – Project rebid per Tony request. New Bids due Nov 26.

11/26/14 – Bid extended to Dec 3.

12/03/14 – New bids received. PHB was the apparent low bidder this year.

12/11/14 – New contracted drafted and sent to Tony with all the attachments for Prosecutor approval.

01/27/15 – Comments returned by Kerry, updated by TTE and sent back for approval. We are awaiting Pre Const Mtg. Peck has already sent submittals.

03/23/15 – Submittals reviewed. Equipment matches specs, when we kickoff this building.

04/14/15 – Held kickoff meeting for project.

04/28/15 – ThermalTech distributed meeting minutes from kickoff meeting. Submittals have already been approved.

05/25/15 – Contact PHB about status of project and equipment delivery.

05/26/15 – Submittals reviewed by TTC and forwarded to Tony, Mike and Paul. TTE requested an updated project schedule for use on this project.

06/24/15 – TTC checked in on progress with PHB

07/15/15 – Peck met Jackson on site to start laying out new work.

07/28/15 – TTC gave Bert the Energy Impact Study for this project.

08/26/15 – Peck scheduled to do startup on this project this week.

09/18/15 – TTC checked out unit install while on site. Project looks good. Owner can closed out the project as soon as closeout paperwork is received.

10/08/15 – MCB checked out unit while on site. Ready to archive.

PATROL HQ Reznor Heater Replacement Read More »

PATROL HQ Heliport Windsock

Lead Partner: TTE

06/24/15 – TTE requested support for Heliport project and THP providing budget numbers for SOSS. ThermalTech updated SOSS to deliver at Partner Mtg on Thursday.

07/22/15 – Bert watts requests SOSS from TEI (with THP as sub) for relocation of existing fuel E-Stop which is in a bad location and makes take-off and landing difficult. Also want to relocate the windsock to a location that is more visible on approach for landing. Project pending approval of SOSS and PO.

02/23/16 – Revised SOSS submitted to Bert Watts this week for approval. Project pending approval of SOSS and PO.

03/29/16 – Project pending approval of SOSS and PO.

04/27/16 – Project PO and signed SOSS received. ThermalTech to provide drawings suitable for “Safety Inspection” for IBI inspection of work.

05/25/16 – TEI meets with Rocky Mullins at the Heliport to review work completed. TEI working to complete the plans for IBI review and approval.

06/27/16 – TEI sends BW for review and comments. ThermalTech receives BW’s TTU to proceed. TEI to coordinate with IBI and Sheriff’s staff for Safety Inspection.

08/23/16 – TEI, Rocky Mullins and IBI meet at project site for safety inspection. The inspector passed the inspection contingent on the relocation of the junction box inside the attic to eliminate the 8″ +/- of SO Cable inside of the building. Mike Barth communicated this information to John Nester – and John Nester initiated a work order to correct the issue. Project complete otherwise.

09/28/16 – Project ready to archive.

PATROL HQ Heliport Windsock Read More »

Sheriff Patrol HQ AHU-2 & RTU-6 Replacements

Building Operations Project

04/17/15 – Met on site this month to discuss with contractor, vendor and mfgr scenarios to replacing the existing condensing units. Sent email to Tony. R-22 not available any longer. Dual circuited condensers can’t be used unless the AHU are converted back. Replacing the existing condensing with a one for one does really help with unloading.

05/25/15 – Project will probably be submitted for cost for 2016 Project Cost Estimates.

06/24/15 – Project was submitted and priced by Terry Cannon of ThermalTech in 2016 Project Cost Estimates.

07/28/15 – Tony discussed moving forward with direct one for one replacement for CU-2 and CU-5. TTC to get small project quotes for Tony.

08/26/15 – Trane was out to do a compressor replacement on CU-2 again to try to fix the issues.

09/23/15 – Tony requested SOSS to replace RTU-2,5 and possibly RTU-6 as an alternate.

10/08/15 – ThermalTech was onsite performing more fieldwork for design.

10/27/15 – Project issued for bidding.

11/24/15 – Bids were opened today. County has several awardable projects. Base Bid and Alternate #2 seem to be solid bids.

12/08/15 – TEI sent Matre a Triton contract for Base Bid and Alternate #2 work. Project total is $141,000 which includes a $4100 allowance. Carrier equipment is listed as the manufacturer for this job.

01/26/16 – Contracts are at Prosecutors office for final approval. Waiting on vendors signatures to begin.

02/08/16 – Contracts are still being approved for Triton on this job. TTC inquired about status.

02/26/16 – Contract is awaiting approval.

03/22/16 – Submittals approved and sent back to vendor for ordering. Project schedule approved and sent to owner for use on this project. Fencing change order sent in for owner record. Schedule of Values approved.

03/30/16 – Permit office called and requested structural note from THP. Jackson requested fans in Detective Area during outage. Triton agreed that would be no problem.

04/15/16 – This week was spent coordinate the THP structural work for the plans examiner and the integration between the CC and the Vendor of the RTU. Lots of coordination work.

04/26/16 – Triton on site and starting work. Phone conference worked out several details with Doug from Triton and schedule of work at site. Triton to check on bldg permit today.

05/25/16 – Contractors are working out structural steel issues at SPHQ on RTU-6. AHU-2 and RTU-6 replacement to begin in earnest on June 1, 2016. Triton will provide fans and crane that day for work. county to coordinate parking needs and communication with Sheriff.

06/10/16 – TTC on site to check construction and take photos of ductwork supports.

06/29/16 – TTC on site to check installation of RF-1 in return ductwork and examine safety concerns of ductwork support system.

07/09/16 – Jackson sends new photos of RF-1 with concerns of attachment to ductwork and sealant issues.

07/21/16 – ThermalTech rejected the steel structural supports on the ductwork for this project after THP provided recommendation last weeks. TTC had long conversation with Triton about the rework scope of the project and modifying the change order submitted for the work. Doug Emery is working on reworking picking up punchlist items, dropping ductwork down tot 6ft above grade, modifying elbows, putting light back where it was originally installed, redoing insulation on ductwork, modifying condensate drain and grading the landscape will be done at end of project. Triton asked that ThermalTech and owner release a detailed drawing on what would be considered an acceptable support system for the ductwork.

07/27/16 – ThermalTech and Triton discussed the rework at great length. TEI to release itemized drawing for new ductwork support, this is about 50% done. We have to do a new section and a duct support details dwg for Triton.

08/03/16 – ThermalTech released Bulletin #1 drawing outlining changes in structural duct supports for Triton to rectify work in field and checked up on some other punchlist issues. 08/15/16 – Remote monitoring devices installed at SPHQ for temperatures. https://www.imonnit.com un: thermaltech_hamco pw: Engineer5721

08/04/16 – Triton contacted for change order cost update for RTU-5 on next email.

08/17/16 – Triton sent in revised change orders,

08/18/16 – ThermalTech sent back a list of questions and clarifications on the cost.

08/19/16 – Triton sent back answers and a change order usages.

08/22/16 – ThermalTech asked Triton if there was anyway to get this work completed with only allowance money.

08/23/16 – ThermalTech sends changes to Tony Matre for discussions.

09/01/16 – There is not enough space to fully explain everything going on at SPHQ. Triton turned in several change orders to redo duct supports. In the end they were all using allowance monies to finish the job. Tony rejected them all. TEI has drafted an official ASI instructing Triton to put the duct supports in as design and noted on the bid drawings. Work should start next week hopefully. Air balancer is calling to balance units for closeout on this job. Tony said that RTU-5 may be a go for design this year.

09/08/16 – Tony gave ThermalTech direction to send out official ASI instructing Triton to install the ducts as designed.

09/23/16 – Triton has installed the new supports and is working on remaining closeout items.

09/28/16 – ThermalTech visited the site twice since the rework started. Rain has slowed progress. TEI has asked for updates from Triton but have not received any updates as of this date. ThermalTech contact THP to assist with RTU-5 work and new SOSS requested by Tony.

10/24/16 – ThermalTech contacted Dave Deger and expressed our extreme dissatisfaction with progress on closing this project out. And asked for him to get an update to us ASAP. TTC also spoke to Mike Jackson at some length about bidding out the RTU-5 vs Change Order and what the scope of work will be for the rebid (boiler, safety rails, etc).

10/25/16 – Doug Habegger replied via email with a controls update at SPHQ. They will be on site 10/31 to make changes. Here is a transcript of that email: All – Regarding the SPHQ project, Rick Wiener (Habegger) & Steve Schinkal (Alpha) met on-site earlier this week. Per my conversations with them, the factory-installed RTU Open controller (Part # OPN-RTUM2) apparently communicates and controls just fine with the Johnson DDC system via BACnet. However, there are several issues with RTU BACnet feedback:
ISSUE #1: The economizer is controlled by a stand-alone Honeywell JADE controller that came with the economizer package, and thus isn’t monitored via BACnet. ThermalTech would like the economizer to be monitored by the DDC system.
SOLUTION: The RTU Open model has the capability of controlling the economizer. Habegger will remove the JADE economizer module, change the existing economizer actuator to a 2-10VDC actuator and wire the new actuator back to the RTU Open module. The DDC system will then be able to monitor economizer position, and adjust the minimum economizer position. Rick Wiener will be on-site Monday Oct 31 (weather pending) to install and wire the actuator.
ISSUE #2: Space CO2 should be monitored for Demand Control Ventilation and visible through DDC. Currently the DDC system cannot read the CO2 level.

SOLUTION: Habegger will replace the RTU Open’s existing wall-mtd. temp sensor with a combination Temp/CO2 sensor. Both sensors only require 4 wires so no physical wiring adjustment is necessary. Once the sensor is replaced the CO2 level can be monitored by the DDC system. Rick will change out this sensor on Monday as well.
ISSUE #3: The unit includes two-speed fan control. The VFD speed signal is not wired up the RTU Open controller, so the fan speed is not monitored via BACnet. The RTU Open does not control the fan speed, the unit automatically increases fan speed from 66% to 100% when the unit enters 1st or 2nd stage heat or 2nd stage cool. ThermalTech would like VFD speed feedback to be read from the DDC system.
SOLUTION: Alpha will connect one of the free inputs on their system to the VFD to monitor fan speed (per my conversation with Steve earlier today).

10/26/16 – ThermalTech updated the team with the latest changes and updates to closing out this project.

11/10/16 – We are working on controls, closeout, payapps and punchlist.

11/26/16 – Triton sent the painting CO#7 to ThermalTech which was forwarded to Matre and Jackson for approval.

12/07/16 – Triton approved for painting the steel with allowance money, updating the final pay application and closing out the job.

12/29/16 – TTC sent final paperwork, O&M’s, updated warranties and such to Tony Matre for closeout on this job.

Sheriff Patrol HQ AHU-2 & RTU-6 Replacements Read More »

SPHQ Roadway Signage

Lead Partner: ThermalTech

04/26/17 – TEI and facilities meeting on site on 04/27/17 for SOSS kickoff meeting at 2:30 PM.

05/22/17 – Project pending SOSS approval and PO.

07/25/17 – Project pending SOSS approval and PO.

08/28/17 – Project pending approval of SOSS and PO. Project on hold.

10/25/17 – Project on hold.

11/29/17 – Project on hold.

SPHQ Roadway Signage Read More »