Project Lead: TEI
10/17/13 – Met Jackson at site for fieldwork.
10/25/13 – Vendor provided one for one replacement and rooftop model for bidding Base Bid and Alternate.
10/31/13 – Review drawings to be delivered to County for bidding as small project.
01/24/14 – Final bids came in during November. Waiting on Tony Matre to decide if we are moving forward with this project.
03/26/14 – Project may be on hold or done later. Ameresco work is currently being done at SPHQ.
0/6/20/14 – Project still on hold.
11/18/14 – Project rebid per Tony request. New Bids due Nov 26.
11/26/14 – Bid extended to Dec 3.
12/03/14 – New bids received. PHB was the apparent low bidder this year.
12/11/14 – New contracted drafted and sent to Tony with all the attachments for Prosecutor approval.
01/27/15 – Comments returned by Kerry, updated by TTE and sent back for approval. We are awaiting Pre Const Mtg. Peck has already sent submittals.
03/23/15 – Submittals reviewed. Equipment matches specs, when we kickoff this building.
04/14/15 – Held kickoff meeting for project.
04/28/15 – ThermalTech distributed meeting minutes from kickoff meeting. Submittals have already been approved.
05/25/15 – Contact PHB about status of project and equipment delivery.
05/26/15 – Submittals reviewed by TTC and forwarded to Tony, Mike and Paul. TTE requested an updated project schedule for use on this project.
06/24/15 – TTC checked in on progress with PHB
07/15/15 – Peck met Jackson on site to start laying out new work.
07/28/15 – TTC gave Bert the Energy Impact Study for this project.
08/26/15 – Peck scheduled to do startup on this project this week.
09/18/15 – TTC checked out unit install while on site. Project looks good. Owner can closed out the project as soon as closeout paperwork is received.
10/08/15 – MCB checked out unit while on site. Ready to archive.