Hamilton County Facilities

P&D – Office Renovation

PM: John Nester, Sam Hofmann
06/24/19 – Krutarth and Christy from Champlin meet with County Facilities and P&D Garage manager to review scope of work on-site
07/02/19 – Christy from Champlin sends concept sketch and scope of work description to Bert Watts for his review
07/18/19 – Christy from Champlin met with County Facilities and PD Garage manager to refine scope of work in CAB building
07/24/19 – Christy from Champlin sends preliminary SOSS to Bert Watts for his review for SD scope of work and cost estimating
07/25/19 – TTC created category and Champlin drafted SOSS for SD and Cost Estimates.
08/22/19 – Christy from Champlin sends revised SOSS to Bert Watts for his approval for SD scope of work and cost estimating, revised to include THP
08/28/19 – TEI created preliminary HVAC load calcs and HVAC upgrades prior to the job starting to make sure the existing equipment can be reused if this project moves forward. It is our belief that the existing air handler can be reused with a new VAV with Elec RH for this job.
09/20/19 – SOSS is approved via email from Jessica Powell.
09/24/19 – No updates on this project from ThermalTech this month.
10/16/19 – Meeting w/ Jessica Powell, Mohammad Islam, Bruce McClain & Greg Smorey at P&D Garage to review SP-02.
10/21/19 – Champlin issued SP-03 plans in response to meeting comments.
10/23/19 – Greg commented on SP-03 plans.
10/23/19 – Champlin revised SP-03 and reissued based on Greg’s comments.
10/24/19 – Greg approves SP-03 drawing.
12/12/19 – We discussed in detail how to price up the expansion of the storage room with THP recommendations from their fieldwork. Bert suggested we put together the cost to do the storage room work as two alternates for this work. We then discussed how to do that work and what to price up in the Alternate. TTE to give new prices to CA for this change.
12/16/19 – Project is given new job number 19-PDFO-0486-2040
01/24/20 – Champlin Cost Estimate is uploaded.
01/29/20 – THP’s opinion of probable cost uploaded to Archibus. DD drawings to be sent to Champlin by 1/31/20.
01/30/20 – CA, THP and TTC to edit the estimate one more time and potentially upload drawings. TTC and JM to discuss with Jessica after Partner Meeting.
02/26/20 – Alternate estimates added to comment section. Waiting on P&D decision.
03/24/20 – Cost estimate updated to reflect flooring changes.
07/30/20 – On hold.
08/27/20 – On hold.
03/25/21 – Facilities to circle back on renovation with Engineers next month. It has been on Covid hold.
04/29/21 – No Update.
05/27/21 – No Update.
06/25/21 – No Update.
08/26/21 – No Update.
01/27/23 – THP – Champlin requested structural proposal for Garage improvements.
02/02/23 – THP provided draft proposal to Champlin for review.
02/22/23 – SOSS is at P&D approval.
02/20/23 – THP provided final structural proposal to Champlin.
03/30/23 – SOSS returned. Kickoff meeting to be scheduled
04/27/23 – Kickoff meeting held on site. Minor changes in scope. Design development in progress.
05/25/23 – Drawings and re-estimate to build budget in progress.
06/28/23 – CD documents by 6/30/2023.
06/29/23 – Met with users on 6/26 to finalize plans. Estimate and complete set to be sent next week.
07/14/23 – THP sent Opinion of Probable Cost and Owner Review Set of drawings to Champlin. Waiting to hear back on comments and bid date.
07/27/23 – Owner review set and opinion of probable cost to be submitted on friday.
08/23/23 – THP no updates.
08/31/23 – Project to go out to bid 9/5.
09/01/23 – THP sent Bid Set drawings to Champlin.
09/28/23 – Project is out to Bid.
10/25/23 – K&T construction won the bid. Contract phase until further notice.
11/27/23 – No updates from THP.
12/07/23 – Project scheduled to kickoff in March.
02/01/24 – Submittals under review, permits submitted on this project.
02/26/24 – THP – Pre-construction meeting held on site. Preliminary schedule for construction to start 03/19/24. TTE has responses ready for review, TTC to look over.
03/28/24 – Submittals returned. Background checks mostly complete. Waiting Permit approval.
04/22/24 – Building permit has been approved and picked up by the contractor. Tentative mobilization date 04/24/24.
04/25/24 – K&T mobilized Wednesday. They will work Mon-Thur starting at 8:30AM.
05/29/24 – Structural scope of work has been completed. THP to attend Progress Meeting on 6/4 to review work and punchlist with contractor. Still on tract for Phase 1 to move on schedule. Emcor submitted change order cost to move the electric disconnect, controls enclosure and add controls to the duct heaters. TTC discussed with Tony.
06/27/24 – Construction in progress. Phase 2 to be complete in 2 weeks.
07/24/24 – Phase 1 complete and ready to start Phase 2.
08/29/24 – Phase 2 complete. Furniture to be delivered next week. Punch to be scheduled.
09/26/24 – Final punch list provided to K&T. Closeouts received.
10/31/24 – Closeouts under review.
12/12/24 – Closeouts complete and final pay app processed.

Scroll to Top