Hamilton County Facilities

Records Center – Showers, Washers, Dryers

PM: John Nester, Terry Cannon

12/12/24 – Plumbing drawings for dog washing shower area submitted and construction began last Friday.
01/27/25 – Triton has secured permit and is currently installing the dog showers in the facility. The trench drain has been cut, they didn’t like the cover, we are working getting a grated cover instead.
01/28/25 – Field visit reviewed existing conditions. TTC will send some questions to Triton about the install as a follow-up. The trench drain cover has been replaced and is currently curing.
02/26/25 – Showers and trench drain installed. Washer and dryer work is underway as well.
02/27/25 – Ready to Archive. Move all washer and dryer time to new Records Center Animal Shelter.
03/25/25 – The showers, washers and dryers are installed and being used.
04/23/25 – Space is in use this phase can be archived. New work will be picked up on the Records Center Animal Shelter project.
05/28/25 – Archive this project.