07/28/21 – Submitted SOSS to County.
08/02/21 – SOSS Received.
09/27/21 – Site visit to confirm existing conditions.
10/14/21 – Preliminary plans sent to County for comment.
10/26/21 – Review meeting requested
11/04/21 – Review meeting held. Attended by Champlin, Public Defenders and County
11/29/21 – New layout options sent to County and Public Defenders.
12/23/21 – User meeting to finalize plan.
02/04/22 – SD plan and estimate sent to County.
03/31/22 – No Update
04/28/22 – No Update
05/26/22 – No Update. New information at Partner meeting on project status, still in development.
06/30/22 – Site visit to discuss scope of increased expansion
08/25/22 – Work to be reported in the new project.