07/28/21 – Signed SOSS received by Champlin.
08/26/21 – No update.
11/04/21 – Meeting with County and User to review Mediation Renovation scope reduction.
11/15/21 – SOSS submitted for DD-CA work.
11/17/21 – SD Set and Estimate uploaded to Archibus.
12/14/21 – Signed SOSS received for DD thru CA.
01/12/22 – Design review meeting with new administrative judge. No design changes. waiting for wall covering scope of work to be finalized.
02/24/22 – Waiting on official confirmation of wall covering scope. (our understanding is that there will not be any)
03/31/22 – Scope confirmed. DD in progress. Deadline of 3rd week of April to be bid ready.
04/27/22 – Final review meeting to approve final bid issuance.
05/26/22 – Finalizing bid package will be combined with Magistrates now. Final review set due June 2.
06/30/22 – Project in Bidding phase.
07/28/22 – Bidder recommendation letter sent to county.
08/25/22 – Building permit submitted. Contract in progress.
09/29/22 – Contract Finalized. Kickoff to be scheduled in near future. Construction moved to combined project.