Hamilton County Facilities

125 – Public Defender Relo 3,4,5,8,9

PM: Mike Murphy, Rycca
07/20/22 – SOSS Approved. Site visit to be scheduled.
07/27/22 – TEI to send 230 PD from original renocation.
08/19/22 – Preliminary plans sent to HC for review.
09/7/22 – Kickoff meeting held with Users. Program survey sent out.
09/29/22 – Program sent to county. Scheduling next round of planning meetings in progress.
10/18/22 – Meeting held to confirm Program. One department remaining to confirm. Conceptual planning to begin.
12/15/22 – Work on pause until further notice
01/26/23 – No Update.
02/22/23 – 2 options of test fit plans sent to Rycca. One with Guardian Ad Litem in building, one with Guardian Ad Litem moved to another facility.
03/23/23 – ThermalTech performed fieldwork on the 5th floor this week for HVAC, electrical, fire protection and plumbing.
03/30/23 – Meeting with users. Plans as developed are generally ok. however, the building has signed a 2 year lease with a tenant on the 6th and 7th floor. Meeting scheduled for next week to re-phase the department renovations.
04/27/23 – Site visit to verify all existing conditions. SD development ongoing.
05/21/23 – ThermalTech SD Cost and markups uploaded to Archibus for mechanical systems.
05/25/23 – Champlin plans complete. Estimate will be uploaded to Archibus next week.
05/29/23 – Plans and estimate uploaded to Archibus.
06/29/23 – No Update. In meeting we found out the 8th floor won’t be early occupied. Cost seems high per square foot.
07/27/23 – Provided answers to minor questions and broke down cost estimate further.
08/31/23 – County provided some VE changes. Drawings and estimate to be revised by 9/8.
09/28/23 – Archibus estimate and drawings have been updated with the requested changes.
12/07/23 – No Update.
01/24/24 – Partners responded to Cushman email on lower build-out cost with a review of the design build estimate. Count to use as needed.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
06/27/24 – No Update.
06/27/24 – OK to archive, they will use the 8th floor with minimal renovation. Next steps leasing options.

Scroll to Top