Hamilton County Facilities

JC – Courtrooms A&B Upgrades

PM: John Nester, Derrick King
07/27/22 – Project created. SOSS is approved. Fieldwork started with Champlin and TEI. Champlin has updated & sent Revit model to TEI for design purposes. The ceiling in one of the rooms will be lowered 24″ in one Courtroom and will stay the same in the other Courtroom. We may need more fieldwork for the non-lowered ceiling for spacing below utilities.
08/22/22 – Review set sent to county
09/29/22 – Project out to Bid
10/27/22 – Triton awarded bid. Contracts in progress.
12/15/22 – Submitted for permit. Still waiting on contract.
01/26/23 – Contract finalized. Background checks submitted.
02/22/23 – Kick-off meeting scheduled for next week.
03/30/23 – Schedule updated, Triton to start next week on this job. Some submittals have been received and returned.
04/25/23 – ThermalTech met Triton onsite for plumbing routes and final connections in closet.
04/27/23 – Construction on going.
05/25/23 – Construction on going. Triton working on getting the steel sub on site.
06/29/23 – Drip pans are on site but not installed, we are waiting on sealing to be completed and reviewed. Construction is ongoing.
07/12/23 – Pans arrived, TTE rejected them due to size and configuration. Triton is taking back to fabricator for reforming. TTE suggested Triton go pick one up for immediate installation.
07/26/23 – Meeting cancelled and moved back one week.
07/27/23 – Construction ongoing.
08/31/23 – Construction ongoing. Courtroom B finishing up. Construction on A started.
09/28/23 – Punchlist for B to be scheduled soon. Drip pans to be installed in A next week.
10/25/23 – Drain pans installed. Finish work ongoing.
10/26/23 – Sprinkler contractor should be onsite this week to start moving and reworking sprinkler heads and systems. JW checking on final sealant for pipe penetrations from second to first floor for us (below and above). Drain pipe in hallway not complete as of last meeting.
01/31/24 – Both courtrooms at punchlist stage. Triton working on final details. New change order submitted for new pans for additional leaks discovered during first use. TE and JN agree new price is better than original submission. Bench refinishing change order work still ongoing. New anchors are being installed on benches when they are reinstalled. New bullet proof glass has been installed but needs to be cleaned by Triton for the full height of the glass. Need change order for back hallways.
02/29/24 – Change order approved for pans above magistrate benches. Triton needs to insulate domestic water piping repair and provide change order for work above ceiling tiles. John asked for construction meeting before demolition. TTC to check on electrical work.
04/25/24 – New leak found. Punch items in progress.
05/28/24 – Ceiling tile fell in Courtroom B. JN, Triton and TTE responded to see and cleanup the damage. An Acorn valve failed up on the third floor.
05/30/24 – Change order work wrapping up.
06/27/24 – Work to be completed this week. Closeouts in progress.
07/02/24 – Triton submitted air balance report today and it was rejected by TTC. Airflows were fine, project data was wrong and AHU data are missing.
07/08/24 – Balance report submitted and accepted by ThermalTech.
07/18/24 – Triton reported all the work in the back hallways was complete
07/19/24 – Nick reported that the plumbers will be back third shift to install the final plastic pan above the ceiling next week.
07/25/24 – Work complete. Closeouts received. Need to be reviewed.
08/29/24 – No update.
09/26/24 – No update.
02/27/25 – Final closeouts received. Need to be confirmed complete.
03/27/25 – No update.
04/24/25 – No update.
05/29/25 – No update. We need Triton subs Release of Liens and certified payrolls affidavit.
07/31/25 – John says closeout documents look good but they need final payment for this job.
08/28/25 – Ready to Archive.