PM: Mike Murphy, Mike Barth
01/08/21 – SOSS Submitted to county for approval.
01/28/21 – PO and SOSS approved.
03/10/21 – Field visit by Sam Hofmann and Tracy Pohl. Further developing plans and selecting finishes.
04/01/21 – Sent renderings and finish options to Bert. A review meeting to select finishes is necessary before continuing.
05/27/21 – No Update.
06/25/21 – Design review committee meeting scheduled for 6/28
07/21/21 – Design Committee review meeting #2.
07/27/21 – Revised rendering and light fixture cut sheets sent to Bert.
08/26/21 – No update.
10/28/21 – Drawings and rendering completed. Estimate in progress.
11/02/21 – Updated Renderings and executive summary sent to County.
01/26/22 – No Update. We should have an update next Tuesday.
02/24/22 – No Update.
03/31/22 – Deadline of end of April to be bid ready.
04/26/22 – field visit to review artwork to be replaced. Bert supplied some additional information. Champlin to provide a suggested strategy for owner approval.
05/26/22 – Final Review set submitted to county. Changes have been made according to Berts comments. To be determined if this project will be combined with the elevator renovation project.
06/30/22 – Project to be bid out separately from Elevator Modernization project on July 7th.
07/28/22 – Project in bidding phase.
08/25/22 – Triton awarded the bid. Contract in progress.
09/29/22 – Contracts in progress
10/27/22 – Contracts in progress
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Kick off meeting held. Submittals being returned.
02/22/23 – Submittals returned, ready to issue notice to proceed.
03/30/23 – Notice to proceed sent and schedule received.
04/27/23 – Preconstruction meeting held. Phase plan finalized. Mobilization to start 4/28.
05/25/23 – Construction ongoing. Triton has had issues with staffing and maintaining a properly maintained work area. Phase 1 and 2 complete. Phase 3 in progress.
06/29/23 – Abatement is complete. Triton submitted new schedule.
07/27/23 – Construction ongoing. Axis was on site to begin floor leveling and could not continue due to current state of the floor. Triton to further demo the floor to acceptable conditions. Sconces have been turned rightside up on one column. Mike in contact with King lighting to provide sconce solution.
08/31/23 – County to make decision on installing light kit themselves, sending back to the manufacturer or leaving the fixtures as is. Flooring to be complete early next week. Wall tile installation to begin next week. Reviewed tiling work with County and small changes in how it was tiled is okay. Streetcar scheduled was discussed and posted in the Admin.
09/28/23 – Construction ongoing. Flooring and wall tiles to be complete next week. Second Mural approved.
10/25/23 – Construction ongoing. Murals to be hung this week. Floors to be polished the next week.
12/07/23 – Punch list complete. Additional signage installed. Back punch to be scheduled in near future.
02/29/24 – Triton to provide closeouts.
03/28/24 – No update.
04/25/24 – No update. Triton getting closeouts in place, discussing some extra from the work on the job.
05/30/24 – No update. Triton owes us about five closeouts for projects, this one included.
06/27/24 – No Update.
07/24/24 – Triton owes us closeout documents for this job.
08/29/24 – No update.
09/26/24 – No update.
12/12/24 – No Update.
01/30/25 – Triton and County held meeting to review all outstanding documents needed.
02/27/25 – No update.
04/24/25 – Closeouts requested from Triton. No response.
05/29/25 – No Update.