01/26/21 – Received signed SOSS from county.
01/28/21 – SOSS and PO approved. We discussed project scope with the team and how to proceed with the new scope and schematic design. CHA and TEI to review proposed furniture layout and make sure their design is permittable and legit, update the cost estimate in Archibus. 19 staff members for new restroom, no men or women signage on new RR.
02/25/21 – TTE to provide opinion of most efficient location for restroom to continue with design
03/12/21 – Furniture meeting on-site attended by County, Autotitle, Champlin and ThermalTech.
03/19/21 – MEP Drawings and cost uploaded to Archibus #2022; extra cost for two bathrooms in comments Section, breakdowns uploaded as PDF.
04/07/21 – Received furniture quote from RCF
04/14/21 – User review meeting. SD estimate modified.
05/27/21 – No Update.
06/25/21 – No Update.