Hamilton County Facilities

2020 – Floor Patching

06/09/20 – Site visit to see existing conditions. SOSS submitted. Waiting for authorization to proceed.
09/08/20 – Received authorization to proceed. CA to schedule site visit
10/29/20 – Site visit to confirm existing conditions. Broadloom carpet made it difficult to confirm extent of cracks. Bid package in process with reasonable assumption for scope of work.
12/9/20 – SD Drawings and Estimate uploaded into Archibus.
01/21/21 – Structural Allowance added to cost estimate.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

05/27/21 – No Update

06/25/21 – No Update

07/13/21 – SOSS submitted to County

08/26/21 – No Update

10/27/21 – Bid set sent to County for approval. Ready to bid.

11/10/21 – Pre-bid held on site. flooring replacement scope added to be alternate #1, #2 and #3.

11/19/21 – Bids came in. Triton was the low bid. Waiting for contract now.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

05/26/22 – No Update.

06/30/22 – Kickoff meeting held. Notice to proceed issued. Submittals received and returned.

07/28/22 – No Update.

08/25/22 – Kickoff meeting held. subcontractor to provide schedule.

09/29/22 – Ready to begin project when materials arrive

10/27/22 – Construction began.

12/15/22 – Construction ongoing. should be complete by end of next week.

01/26/23 – Punchlist conducted last week. Corrections to be fixed in the near future.

03/30/23 – Damaged doors discovered from flooring repair. Triton to correct.

04/27/23 – Triton to remove and replace wood veneer on doors.

05/25/23 – Doors have been refinished. They need a final sealant coat and will be installed next week.

06/29/23 – Doors installed. Closeouts received.

07/27/23 – Closeouts need final approval.

08/31/23 – Final pay app sent to county and closeouts approved. Waiting on Triton to provide hard copies.

Scroll to Top