06/09/20 – Site visit to see existing conditions. SOSS submitted. Waiting for authorization to proceed.
09/08/20 – Received authorization to proceed. CA to schedule site visit
10/29/20 – Site visit to confirm existing conditions. Broadloom carpet made it difficult to confirm extent of cracks. Bid package in process with reasonable assumption for scope of work.
12/9/20 – SD Drawings and Estimate uploaded into Archibus.
01/21/21 – Structural Allowance added to cost estimate.
02/25/21 – No Update
03/25/21 – No Update
04/29/21 – No Update
05/27/21 – No Update
06/25/21 – No Update
07/13/21 – SOSS submitted to County
08/26/21 – No Update
10/27/21 – Bid set sent to County for approval. Ready to bid.
11/10/21 – Pre-bid held on site. flooring replacement scope added to be alternate #1, #2 and #3.
11/19/21 – Bids came in. Triton was the low bid. Waiting for contract now.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
05/26/22 – No Update.
06/30/22 – Kickoff meeting held. Notice to proceed issued. Submittals received and returned.
07/28/22 – No Update.
08/25/22 – Kickoff meeting held. subcontractor to provide schedule.
09/29/22 – Ready to begin project when materials arrive
10/27/22 – Construction began.
12/15/22 – Construction ongoing. should be complete by end of next week.
01/26/23 – Punchlist conducted last week. Corrections to be fixed in the near future.
03/30/23 – Damaged doors discovered from flooring repair. Triton to correct.
04/27/23 – Triton to remove and replace wood veneer on doors.
05/25/23 – Doors have been refinished. They need a final sealant coat and will be installed next week.
06/29/23 – Doors installed. Closeouts received.
07/27/23 – Closeouts need final approval.
08/31/23 – Final pay app sent to county and closeouts approved. Waiting on Triton to provide hard copies.