05/19/16 – ThermalTech met with Bill Scholl and review the CT installation.

05/25/16 – TEI recommended to Tony to rebuild the towers and add an equalizer line for more efficient operation.

06/23/16 – Spoke with Bill Scholl and confirmed he is correct that the off chiller needs to be isolated from the chilled water system or else there are large inefficiencies in the chilled water system and a blending of cooling water return temperatures.

06/27/16 – Sent drawings to Tony and Bill for possible ECM project.

02/01/17 – Project on hold as far as I know.