Partner Lead: THP

02/03/16 – County staff reported masonry cracking throughout the building, and requested THP investigate.

02/25/16 – THP visited the site, confirmed the conditions, and is developing a SOSS.

03/24/16 – THP provided an SOSS for review.

04/04/16 – County approved the SOSS.

05/26/16 – THP completed field investigation of the facility. THP developing analysis and final recommendations.

09/09/16 – THP published draft report. County provided draft comments the same day.

09/28/16 – THP anticipates publishing final document 9/30/16.

10/11/16 – Final report published.