Hamilton County Facilities

230/800 – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Tony meet and establish project schedule. Project in progress.
02/26/25 – No updates this month
04/23/25 – No updates this month
05/28/25 – No Updates
09/24/25 – DEG and AKM discuss that this goes out to bid mid October. Also discuss 1 year contract with optional 1 year renewals pending the elevator replacement projects.
10/29/25 – Project to be sent to purchasing on 10/31/25 for bidding.
12/10/25 – Prebid occurred on snow event day. A send prebid occurred on 12/08/25 for the bidders that could not attend during snow event. Bids to open on 12/29/25.
01/28/26 – Tony M and Bonita drafted contract and sent to Prosecutor.