Hamilton County Facilities

230-A

230 East Ninth
Archive

230 – Summer Boiler Replacement

PM: Tony Matre, Terry Cannon
07/31/25 – SOSS approved. ThermalTech is conducting fieldwork to see if we can fit a boiler into the elevator and down to the in a size matching the KN boiler 2000 MBH. We did confirm that the boilers intended to be used on the Ameresco will not fit into the elevator, but they are 2500 MBH.
08/20/25- Final review drawings ready to review. TTC will send to County for review.
08/25/25 – Boiler selection is waffling, not sure where guys are going to fit a boiler in the elevator and down to the basement. We decided to have a base bid boiler and an Alternate boiler that matched future boilers.
09/24/25 – Review will be sent to Tony Matre for his review today.
10/29/25 – TTC preliminarily setup prebid meeting but did not get confirmation from bidders except one bidder (Triton) who showed up. TTC to reschedule.
11/14/25 – Prebid meeting with four vendors.
11/26/25 – Bids received, tabulated and sent to County. All bids were overbudget.
12/12/25 – TTC repackaged drawings and sent to DK for State Term pricing.
01/25/26 – County deciding if they want to award this project via State Term to Emcor and Debra Kuempel.  It does sound like it is going that way.
02/25/26 – No update on moving forward on this project yet.
03/25/26 – No update, still awaiting green light from County to move forward with state term work.
04/26/26 – DEG and Ameresco working on new boiler plant, this project can be archived.

230 – Summer Boiler Replacement Read More »

230 – Multipurpose Room Renovation, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Mother’s Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with Mother’s Room.
01/29/26 – Need meeting with COA/Probate/HCFD to review scope.

230 – Multipurpose Room Renovation, Prosecutor’s Office Read More »

230 – Mother’s Room Addition, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Training Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with MultiPurpose/Training Room.

230 – Mother’s Room Addition, Prosecutor’s Office Read More »

230 – Exterior Signage Feasibility Study

PM: John Nester, Eryn Thamann
03/26/25 – SOSS provided and pending approved PO.
04/24/25 – PO provided. HCFD to schedule kick-off mtg.
05/28/25 – Design kick-off meeting held with the Court/Court Admin/HCFD. Elevar to provide timeline for first round of design.
06/26/25 – Elevar to provide zoning code info to HCFD and not signage design options yet.
07/31/05 – Draft code study sent to HCFD for review.
08/28/25 – Renderings provided to HC on 08/25.
09/25/25 – Elevar needs final design and digital seals to proceed with Small Projects bid.
10/30/25 – Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Archive?

230 – Exterior Signage Feasibility Study Read More »

230/800 – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Tony meet and establish project schedule. Project in progress.
02/26/25 – No updates this month
04/23/25 – No updates this month
05/28/25 – No Updates
09/24/25 – DEG and AKM discuss that this goes out to bid mid October. Also discuss 1 year contract with optional 1 year renewals pending the elevator replacement projects.
10/29/25 – Project to be sent to purchasing on 10/31/25 for bidding.
12/10/25 – Prebid occurred on snow event day. A send prebid occurred on 12/08/25 for the bidders that could not attend during snow event. Bids to open on 12/29/25.
01/28/26 – Tony M and Bonita drafted contract and sent to Prosecutor.

230/800 – Elevator System PM Agreement Read More »

230 – Façade Repairs (F016)

PM: Matt Butz, Fateme Shahiyan

08/29/24 – County request THP rebid Alternate Façade repair package from SOSS F003. SOSS Hamilton County.
09/23/24 – THP published review drawing to County.
09/23/24 – County provided review comments to THP.
09/26/24 – Final bid to be released to purchasing with Advertise to bid scheduled for 9/30/24. Bid opening scheduled for 10/30/24.
10/16/24 – THP issued Addendum No. 1 – (prebid minutes and updated prevailing wages).
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received.
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received and BCR was the lowest bid.
11/05/24 – THP had a Bid Review with BCR
11/14/24 – THP sent the bid summery and recommendation letter for BCR to Hamilton County.
01/16/25 – Preconstruction meeting completed.
01/29/25 – Progress meeting completed.
01/30/25 – Project status – BCR has rigged and complete the first knock down survey of the north elevation. Work will progress north to west to south.
02/21/25 – Crew moved to the west elevation to do the knock down and have the spots ready to patch when temperature gets better in the next week.
02/24/25 – BCR send out Pay App No.1 for THP review and THP approved that.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/26/25 – BCR start installing the swing stage on roof for the north return wall of the building.
03/31/25 – BCR completed the work and sounded the north return wall. No major sports or damage.
04/04/25 – BCR submitted pay app No.2 and was approved by THP. BCR needs to provide the closeout documents.
05/27/25 – BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/10/25 – BCR has provided all closeout documents, which have been approved by THP. BCR is in the process of sending the notebooks and USB drive containing the documents to the County. Once that is completed, THP will send the signed final pay application to HC.
07/30/25 – Project status: All closeout documents approved. Waiting on project notebooks.
08/26/25 – BCR planning on complete the closeout documents and send it to the county by end of the next week along with the TPC project.
09/15/25 – BCR dropped off the closeouts documents to HC/Matt Butzz. However, the electronic documents, notarized warranties and 2 payrolls for the project were missing. BCR is planning to provide the documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.

230 – Façade Repairs (F016) Read More »

230 – Exterior Camera Upgrades 2024

PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for review from HCFD.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Project pending completion of installation from DK.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
06/25/25 – DK, DEG and HCFD to meet re final closeout.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

230 – Exterior Camera Upgrades 2024 Read More »

230 – COA Camera System Upgrade 2023

PM: John Nester, Mike Barth
12/06/23 – TEI receives approved SOSS and PO.  COA to provide TEI with locations of cameras that were discussed with vendor.
01/30/24 – TEI to receive the locations and document on documents.
02/28/24 – TEI will document locations upon receipt.
03/27/24 – TEI, HCFD and DK meet, document locations, and develop drawing.  Meeting with all team on 03/26/24 to review and finalize.
04/24/24 – Installation pending material procurement.
05/29/24 – Completion of this project pending punchlist once TEI notified all install work is complete.
06/26/24 – Cameras are installed and the users are working on getting the monitoring functioning (instructions from installer (DK) via email), and Matt Butz helped with Valerus integration to allow end users to utilize the system.
07/24/24 – TEI and HCFD perform punchlist on the project. Tenant confirms views are as desired.
08/28/24 – Project complete pending closeout documents.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

230 – COA Camera System Upgrade 2023 Read More »

230 – Access Control System Upgrades 2023

PM: Matt Butz, Mike Barth
12/06/23 – TEI issues SOSS.
01/30/24 – TEI receives signed SOSS and PO.  Project documents to proceed.
02/28/24 – Project is ongoing
03/27/24 – On site investigation  and kick off meeting with DK occurred on 03/26/24
04/24/24 – Review set will be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD review.
07/24/24 – Construction completed. HCFD and TEI completed punchlist walk.
08/28/24 – Project pending closeout documents.
12/11/24 – No Updates
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – Archive.

230 – Access Control System Upgrades 2023 Read More »

230 – Guard Rail – Safety Gate (F068)

PM: John Nester, Matt Rigdon
09/02/22 – Hamilton County requested SOSS.
09/29/22 – THP and Hamilton County walked the sites.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County meeting to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to send review set of revision drawings that account for existing ductwork interferences. THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
07/17/23 Requested to combine the two safety gate projects for WHT & TPC Buildings into one drawing set. Requested by HamCo to separate Railing at WHT as individual project.
07/26/23 – Documents being finalized and to send July 31.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/31/24 – No updates from THP.
2/23/24 – County sent AIA contracts to ZSR for review and execution.

230 – Guard Rail – Safety Gate (F068) Read More »

230 – Magistrate & Mediation Construction

PM: Matt Butz, Sam Hofmann
09/29/22 – Two projects combined into one Construction project. Some furniture will be reused.
10/21/22 – Contracts finalized and Pre-construction meeting held. Kick-off meeting to be scheduled when submittals are returned.
12/15/22 – Kick-off meeting to be scheduled
01/26/23 – Kick-off meeting held. Construction to start in near future. Waiting on all background checks to return.
02/01/23 – Notice to proceed issued.
02/22/23 – Construction on going. First progress meeting held.
03/30/23 – Construction ongoing.
04/26/23 – ThermalTech reviewed the HVAC and Fire RFI’s and discussed final design for these services.
04/27/23 – Construction on going. Will move onto 9th floor this month.
05/25/23 – Punch completed for 11th and 12th floor. Construction started on 9.
06/29/23 – 11 and 12th floor punched. Work is underway on 9th. Everything to be complete by end of month. HVAC and Electric change orders approved, TTE to cover these cost.
07/27/23 – 11 and 12th floor nearly complete. 9th floor to be complete mid august. Waiting on Alpha to provide pricing for potential flooring change order TTE provided a 10″ neck diffuser for Alpha to get installed. Trades will help clean up the 11th floor inefficiencies. Inspections are complete for MEP on 9, 11, 12 floors. 9th floor punchlist coming up soon. Barth talked to Delta and they may be able to provide two can lights for the Reception area from leftover stock.
08/31/23 – Added flooring on order. Install at end of September. Work on 9 is finishing up. a pre-punch list has been submitted to Alpha for less than satisfactory work.
09/28/23 – Alpha has not completed contract work yet. New flooring to begin on 10/3.
10/25/23 – Contract work is still not complete. Flooring has been pushed back until the space can be occupied. No firm install date scheduled.
12/07/23 – All work is complete. Minor punch list items outstanding.
01/31/24 – Closeout documents received. TEI noted there were not redline markups for as-built drawings received for this job.
02/29/24 – Punch list items complete. closeouts in review.
03/28/24 – Hardcopies from Alpha outstanding.
04/25/24 – Closeouts received.
05/30/24 – Waiting on release of liens.
06/27/24 – Closeouts still outstanding.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – Final pay app returned.
09/26/24 – Flooring still not great but ready to Archive.

230 – Magistrate & Mediation Construction Read More »

230 – Sewage Ejector Replacement

PM: John Nester, Terry Cannon

03/31/22 – County reaches out for SOSS for this job.
04/02/22 – ThermalTech reached out to Derek Koogler to get a submittal and quote for the job.
05/24/22 – ThermalTech on site for fieldwork.
05/27/22 – First set of plans created for job.
06/02/22 – Markups complete, given back to TTC.
07/20/22 – Markups returned to TTC again.
07/26/22 – TTC returned dwgs with additional markups. New lid information requested, use the same style as A&D.
08/05/22 – Page created and back-filled with project data. Progress drawing sent to County. We need preferred floor drains for replacement from John or Ernie.
08/22/22 – Met with John and Ernie on site and finalized scope. One new
08/24/22 – Final markups sent in for Cad. Bid in September, maybe August.
09/22/22 – Bid opened, DK apparent low bidder. Pre-Award meeting scheduled for next Tuesday. We have the budget to take all the Alternates on this job.
10/26/22 – Waiting on final contract and PO to begin work.
12/15/22 – Submittals returned for correction, new submittals should be here any day. Pre const meeting was held with Debra and everything went well.
01/24/23 – Pushing the manufacture hard to update submittals with the correct voltage. Other than that the submittal looks great.
02/20/23 – New submittals were returned FAC so the equipment should be on order this week. We still need external disconnects and transducer submittals. DK getting new delivery schedule.
03/29/23 – Pumps are ordered, assembled scheduled to be complete by the end of April. Tigerflow ship date not confirmed.
04/25/23 – Weekly check-ins with the vendor and contractor has not gotten us a firm date when the package will ship from Tigerpaw.
05/12/23 – Schedule of Values submitted, reviewed, and returned for changes.
06/28/23 – Schedule of value resubmitted for approval. Equipment scheduled to arrive at Tigerflow second or third week of July.
07/26/23 – Pump package will be here in August. Pre-Const meeting will be scheduled in August.
08/07/23 – Pre Construction Mtg #2 was held with Debra and the County. Meeting minutes will be distributed later this month. DK supposed to start in August.
09/27/23 – DK will send Dirk to do this job after they wrap up PBS Ice Machines which will be complete by the end of MNF week (this week). They should be mobilizing in next two weeks. I will check on paperwork again.
10/23/23 – Met Dirk onsite for project kickoff. Mobilization and tools today. DK started disassembly of sewage ejector system. Water filled sump about noon from fire pump test, but was pumped out before DK left for the day.
10/24/23 – Work continued on pump replacement no more water issues.
10/25/23 – Pumps are installed and operating. DK jet cleaning floor drains but finding clogs. Floor was hand scanned before saw cutting. DK used jack hammer to install new floor drain near blow down tank. New line and floor drain installed, concrete poured back into placed. We will meet on Friday for punchlist. Corporate equipment coming Friday for startup.
12/06/23 – Work is complete. Punchlist was issued. Backpunch and training completed. The system is up and running. DK to label each pump in field. DK to provide all closeout paperwork for this job.
01/31/24 – Project is complete. Discuss contractor and allowance with John Nester before accepting final payapps ($5k vs $12k).
02/23/24 – Review closeout documents with John.
03/22/24 – Ready to Archive this job but DK has not provided all closeout documents yet.
06/01/24 – Working with DK on closeout.
09/01/24 – Working with DK on closeout.
12/01/24 – Working with DK on closeout.
01/25/25 – Received Consent of Surety for final closeout today, sent that and final payapp to Hamilton County for closeout and processing.

230 – Sewage Ejector Replacement Read More »

230 – City Façade Assessment (F054)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/27/22 – THP Completed a majority of the rappelling survey of the façade.
04/28/22 – Final rappels anticipated first week of June and report to be published in June.
06/30/22 – City Report due 7/1/23. THP to combine final rappel with Portune Center and complete in August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.

230 – City Façade Assessment (F054) Read More »

230 – Magistrates Lobby Security Upgrade

02/08/22 – Signed SOSS Received.
03/29/22 – DD Kickoff meeting.
04/15/22 – Comments received from Scott and plans adjusted accordingly. 100% review meeting mid may.
05/17/22 – Review meeting with With Scott. Plans adjusted according to his comments.
05/26/22 – Project combined with Mediation. Review set due June 2 Arch and MEP.
06/30/22 – Project in bidding phase.
07/28/22 – bidder recommendation letter sent.
08/25/22 – Building Permit applied. Contracts in progress
09/29/22 – Contracts finalized. kick off meeting to be scheduled in the near future. Construction Project move to a combined construction project.

230 – Magistrates Lobby Security Upgrade Read More »

230 – Court of Appeals Mediation Renovation

07/28/21 – Signed SOSS received by Champlin.
08/26/21 – No update.
11/04/21 – Meeting with County and User to review Mediation Renovation scope reduction.
11/15/21 – SOSS submitted for DD-CA work.
11/17/21 – SD Set and Estimate uploaded to Archibus.
12/14/21 – Signed SOSS received for DD thru CA.
01/12/22 – Design review meeting with new administrative judge. No design changes. waiting for wall covering scope of work to be finalized.
02/24/22 – Waiting on official confirmation of wall covering scope. (our understanding is that there will not be any)
03/31/22 – Scope confirmed. DD in progress. Deadline of 3rd week of April to be bid ready.
04/27/22 – Final review meeting to approve final bid issuance.
05/26/22 – Finalizing bid package will be combined with Magistrates now. Final review set due June 2.
06/30/22 – Project in Bidding phase.
07/28/22 – Bidder recommendation letter sent to county.
08/25/22 – Building permit submitted. Contract in progress.
09/29/22 – Contract Finalized. Kickoff to be scheduled in near future. Construction moved to combined project.

230 – Court of Appeals Mediation Renovation Read More »

230 – 11th and 12th Floor Renovation

03/08/21 – SOSS approved.

04/06/21 – Kickoff meeting with users to go over scope.

04/20/21 – Field visit to confirm existing conditions. Working on selecting finishes and furniture.

05/20/21 – User meeting presenting initial room layouts

06/10/21 – Sent updated plans to further define scope

06/22/21 – User responded to refocus efforts in light of new funding. meeting scheduled 6/28

06/28/21 – Sent county plans and estimate for flooring replacement and wallcovering removal and paint. furniture estimate outstanding.

07/28/21 – John to remind users about need for additional information in order to finalize furniture estimate.

08/26/21 – Project part of 2022 Estimates.

10/28/21 – Ready to Archive.

 

 

230 – 11th and 12th Floor Renovation Read More »

230 – Cooling Tower Safety Maintenance Stairway (F025)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS. OK to combine bids as long as the bids can be separated or itemized.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
05/27/21 – Project update County located existing drawings which included a previous THP design. THP plans to issue review drawings by June 2.
06/25/21 – THP to send review set next week to County.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse Boiler Room Platform project. Schedule and start date TBD. Most likely March/April time frame.
2/21/22 – Triton to mobilize to site to field measure site conditions.
2/23/22 – Waiting to hear back from City on the Permit Application.
3/2/22 – Permit application has been approved. Approved drawings and approved project manual has been sent to all parties involved.
4/25/22 – Triton submitted crane lifting plan. Hamilton County asked for additional information be provided for County review. Plan is still to crane material to roof on Saturday, May 7th. Roof stairs installation to begin following week.
5/10/22 – Stair posts installed by Neiheisel and roofing repairs performed by Tremco this week before crane lifting the rest of the material onto the roof.
5/14/22 – Remaining stair material crane lifted onto roof and installed onto posts.
5/16/22 – Neiheisel performed final stair installation and detailing. WHT roof stairs installation completed this week.
5/25/22 – THP and Triton to coordinate final cleanup and paint touch up before the final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

230 – Cooling Tower Safety Maintenance Stairway (F025) Read More »

230 – Probate Court Security Upgrade

10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
05/20/20 – Meeting at Taft center to discuss scope. Attended by Sam and Mike from Champlin, Rycca, Jessica, and Bryan from County and Scott from the Taft center.
06/03/20 – additional site visit to verify existing conditions
06/03/20 – Meeting at Taft Center to choose product. Attended by Sam, Mike, and Jose from Champlin. Rycca and Bryan from County and Scott from the Taft Center.
07/02/20 – Draft of ITB sent to County for approval
07/27/20 – final copy of ITB and Plans approved. Prebid meeting set for 08/03/20 at 10 am
08/20/20 – Bids received and apparent low is James Hunt Construction.
09/03/20 – Contract signed by Hunt
09/14/20 – Submittal returned to Hunt
10/29/20 – Construction planned for the weekend of 11/21. Punchlist to be scheduled monday 11/23.
11/21/20 – Project ran into complications. New date of install is the weekend of 12/19-20. Punchlist to follow.
12/26/20 – Installation 12/26-12/27 Champlin performed punchlist 12/27
01/18/21 – Additional punchlist issued.
01/23/21 – Glass and 1 dented post cover replaced. sometime this week 2nd post cover to be replaced.
02/24/21 – Back punch by Sam Hofmann, Danny Rusconi, Rycca Thacker and Scott Weikel. Final touch up items to be completed 2/25 at 4pm
02/25/21 – All punch items completed
03/25/21 – Project essentially complete. Final payment sent. The project can be archived.

230 – Probate Court Security Upgrade Read More »

230 – 2019 Façade Critical Façade Repairs

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/29/19 – Work scheduled to start after F117 complete.
09/16/19 – Work scheduled to start after F117 complete.
10/31/19- See F117 for project status.
01/30/20 – See F117 for project status. Construction work complete. Final closeout paper work in progress.
02/27/20 – Refer to F117 for project status.

230 – 2019 Façade Critical Façade Repairs Read More »

230 – City Façade Assessment (F107)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
04/19/18 – Completed visual survey from grade.
04/20/18 – Rappelled all four elevations.
04/26/18 – Report under development.
05/21/18 – THP completed draft of Cincinnati façade ordinance report.
05/22/18 – THP developed Opinion of Probable Cost for recommended repairs specific to Cincinnati façade ordinance review.
05/24/18 – THP finalized Cincinnati façade ordinance review report and application form.
5/31/18 – County provided verbal comments. THP reviewing comments.
7/26/18 – CORRECTION, comment on 5/31/18 for 800 Broadway assessment. Report approved as submitted.

230 – City Façade Assessment (F107) Read More »

230 – Humidification in Rooftop Unit

04/22/05 – TTC faxed over a letter stating the deficiencies of Application # 01 on this project. All final paperwork is missing.

03/25/05 – TTC completed punchlist on job. There are no items to fix. Geiler submitted final pay application without any final paperwork. TE will ask for closeout documents.

02/25/05 – TTC asked Geiler for update and if they are ready for TE to punchlist this project.

02/11/05 – TTC talked to MF today. Geiler has the piping complete. The insulation is on the piping now. TTC will perform the punchlist next week on Monday or Tuesday.

02/08/05 – TTC visited the site today with Geiler and MF. Geiler should be wrapping up by end of week. Systems are online. Insulation needs to be completed. Geiler is in cleanup stages of piping work. TE to do punchlist within a week. Valve, steam and humidity control appear to be working.

02/02/05 – TE talked to Geiler today. They will be off the job for a couple of days. They have to soak some unions they are having trouble disassembling for re-use. They will be back next Monday for sure if not earlier (I think Bob wants to stop down to soak the unions tomorrow). Elevator and space access issues have been resolved. We were original trying to finish by 02/07 but I believe it will be at least 02/14 before the changes are complete.

02/01/05 – Geiler has started the project during the evening schedule. TE to follow up the MF this week for progress.

01/26/05 – Geiler delivered tools and piping, but wont’ start project until Monday 01/31/05.

01/25/05 – TE and Mike F. walked the project with Bob Burlege of Geiler. We feel as though they won’t be able to start the project unit Wednesday per Bob’s comments but it could be later than that. We are planning on shutting down the steam once in the evening to weld the thread-o-lets on to each header. Then add an isolation valve to shutdown each header and work on each side independently, keeping the building without humidification to a minimum. The pipe machine will be setup on the dock. Piping will be hauled in the elevator. The 230 staff will stay with Geiler the first night to ensure the boiler plant and steam come back online properly. MF will show Geiler how to shutdown and lockout/tagout the AHU’s when working. 120V welder must be used.

01/17/05 – Submittals received by TE. Walk through scheduled for Jan 24, 3:30 p.m. provided that TE approve the control valve submittals.

01/11/05 – Pre Construction Mtg Complete. Geiler projects this to be a 2 week job maximum. They will begin work and stay on site to complete work throughout the project. Pre Construction Notes added below.

09/29/04 – Original Bid Documents have arrived and TE sent to County via UPS on 09/29/04 for approval.

09/23/04 – TE contacted contractor and we are awaiting original bid documents to submit with final contract (3 copies).

09/20/04 – Contract written. Awaiting for TTC to approve and deliver.

09/13/04 – Bids are compiled. Geiler is low bidder. County please advise how to proceed.

230 – Humidification in Rooftop Unit Read More »

230 – Ninth Floor Microfiche Project

03/14/06 – Bill Scholl and Mike Florimonte have both reported that the systems are working great and permits have been approved. This project is being archived at the end of this week.

01/10/06 – HVAC has work above Julie area’s almost complete. They have scheduled an HVAC inspection with Steve Ossege in the coming days. Exhaust was hard to get routed but they are almost complete.

12/28/05 – The microfiche permit was picked up and emailed down to the County approved for use. TE paid and will reimburse the cost to the County.

12/14/05 – TTC setup a meeting for THP to review the space ceiling construction to approve the ductwork hanging method on this job for 12/15. Aaron Bennett will be contacting Mike Florimonte for access to the building. MF reported that the piping, boxes and louvers are nearly installed so far.

12/09/05 – TTC applied for the permit today at the City. The permit number is 2005P09839. It cost $75 to the application fee today and the remainder will be paid when we pick up the permit. All of this cost is a reimbursable cost to the owner on this project for this work.12/02/05 – County trades can’t put the ductwork in as designed on the plans. MF is going to inspect the above ceiling layout and call TTC with details. TTC will stop by the building and give direction as to the best way to proceed to finish the job. TTC informed Tony of the plan. Terry contacted THP by email to verify ductwork loading won’t overstress the ceiling arrangement.

12/05/05 – Terry meet HVAC trades on site to discuss ductwork routing and relocating light fixtures on this job. It was decided the best and easiest way to fit the ductwork into the room was to rotate the lights 90 degrees and remove the remaining light that is interfering with the light fixture. Carpenters will have to do some ceiling work to patch and paint the areas that are affected by the ductwork and fan supports.

11/29/05 – HVAC called with questions about moving the VAV box in Julie’s office because it was interfering with new ductwork. TE said this was fine. HVAC called with a question about framing the fire dampers in one big angle frame and TTC said this was fine also. In email correspondences today, we believe all issues are up to date and the work in on track.

11/21/05 – TE and the County met at the site to discuss Sam’s HVAC design and coordinate with the tenant and trades for making this work out. Everyone was in agreement that if we could bring both ducts into one corner and just create a matching column in Linda’s office that would be fine. The people in attendance were Mark Perry, Tony Matre, TTC, SRB, MS, Dave S, Bill S, Jim E, Ernie, Mike F, Paul and Jerry.

11/16/05 – TTC and Tony discussed the bidding out of this project and the method in which the money and trades would do the work on this project. Wayne would like more controls11/15/05 – Review drawings were sent to the County today. TE would like to get comments back about this job as the County’s convenience.

11/10/05 – Wayne called and said that the draft design is OK and to proceed with a permit set of drawings, so trades can do the work. He will also contact TE when he has set up a Archibus job number, so we can enter a cost estimate.

11/10/05 – Wayne called and said that he would like trades to do the work. He said that he would check with Mike Florimonte to see if draft design is OK. After final client approval, TE will then put together a drawing set for trades.

11/04/05 – TE sent Mike Florimonte a draft of the HVAC layout to see if Manager of that area is OK with design. Design included exposed ductwork in the Vault to avoid redoing the ceiling, to allow for concealed ductwork.

11/02/05 – TE is putting final design together. Sam and Mike will be making a field trip down to the building on Friday to set routing and check clearances.

10/13/05 – TE and CR met with the client to finalize building and design standards for this project. CR has to submit an SOSS. The equipment will be in the building in about 2 months for this job. TE must do the design immediately for bidding.

08/30/05 – TTC received installation manual from vendor in San Diego. TTC sent pdf to County for their use. Heat and Electrical requirements were provided by vendor. TTC got many other calls from salesmen at Anacomp who because ThermalTech was inquiring believe they were somehow being left out of the purchase loop of the equipment. TTC assured them that the County is in control of purchasing the unit and ThermalTech was only designing the room that the equipment when and if purchased would reside in.

08/25/05 – TTC contacted manufacturer today to collect engineering information on unit for installation including btuh rejection, power req’s, exhaust req’s and mfgr’s installation instructions. I had to leave a message with their main office.

08/22/05 – MF called to say that after talking with some people, the belief is that the vault walls are reinforced concrete and not just metal stud walls. TTC and MF talked about airflows in the room and the floor and TTC believes that the design should most likely be to add one separate VAV box for the microfiche machine and exhaust the entire room. The machine should most likely go into the vault area where the room can be separated from the general airflow of the space.

08/19/05 – TA & TTC met Tony on site for field work.

230 – Ninth Floor Microfiche Project Read More »

230 East 9th Street Electric Device Study

01/10/07 – This project is complete and archived on 01/10/07

08/18/06 – Drawings have been delivered to Hamilton County Facilities. There are no open issues on this project.

06/14/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Mike Florimonte). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

230 East 9th Street Electric Device Study Read More »

230 – Boiler Stack Study

Journal:

03/05/08 – TTC and Tony figured out the billing issues and TTC sent an email to Grady on how to bill for extra services. The actual project is complete. The County has to fix its own PO to pay Triton but TEI work is complete on this project.

01/25/08 – Tony and I talked today about closeout on this project. Grady is to bill the County the remaining balance as a change order to this job. I will write a change order to match the total amount owed to Triton on this job. The County has a PO invoicing issue on this job (JC bill to this PO).

11/16/07 – TTC talked to Mike F today about project status and sent AKM the following email:

The summer boiler flue temperatures are still no where near 310 F so the fix worked to make things better but we are still probably going to have condensation issues.

The winter boilers are on now and they are slightly better also but we are still not getting 310 F at the outlet of the boiler stack. I told Mike that we should re-smoke test the boiler stack just like we did at the start of the project to see if any drafts are still cooling the boiler stack down as the flue gasses go up.

Mike believes that Triton did a pretty good job buttoning everything on the boiler stack from the job that we bid out and the extra work that you had them do on T&M inside the building. We just aren’t getting as good as results as we would have liked.

The summer boiler is slightly over 2,000,000 btuh which means it would take 4 of the Knight boilers to replace it and meet the same load. We could do this if it was the only problem you still had. The large winter boilers are 5mil btuh so those cannot be replaced by these hot water boilers so we are still kind of faced with some of the same problems with temperatures that you have faced from the beginning in that the outlet temperature at the top of the boiler stack is under 310 F.

and told the County that when they were ready to take the next step to let ThermalTech know and we can help with the design or problem solving.

05/22/07 – Triton submitted their final payapp for the project. There is a $980- change order for the extra camera work. This increases the contract amount and TEI needs approval from the County to pay that. Please advise.

05/14/07 – TEI contacted Triton for closeout documents. Grady said they would send them in ASAP. TEI will return a video copy of the boiler stack video to Grady to closeout the project. TEI has been in contact with MF about the type of brick to replace in the chimney wall to maintain integrity and this would be solid lightweight concrete block according to Spencer at Cole Russell. This project is ready to archive. 12/04/06 – TTC questioned the use of the full allowance today ($5000) and requested an itemized breakdown from Triton for the work completed. The dwgs ask for the the wall to be built by the contractor but that has not been completed to date. The additional work that TEI is aware of is sealing the upper stack and the camera record of the interior. TEI asked for the requested change order to seal the outer stack to be taken from the allowance not as a change order.

11/30/06 – TTC asked about writing a change order to the project for Triton to do the stack sealant work. The project itself is complete. We are moving into the next phase for 2007 where we will address insulation the stack in some way to keep air from overcooling the inner shell. The County is going to open up the wall sections to allow Triton to patch the outer wall of the boiler stack. This can happen right away if the PO gets approved for Tony. TTC asked the County for an update today.

11/13/06 – A lot has happened since the last entry to which i will summarize. Triton has been on site and finished the work. A camera was dropped down between the stacks for a record of how they were built. We discovered that the outer shell had 3 large rectangles removed where spaces were welded to the inner stack. The stack was not support to the outside wall as originally intended. We believe these holes are contributing to the excessive draft up the stack causing a high cooling effect on the boiler flue gas. We instructed Triton to seal the top of the outer stack to the inner stack with a metal seal and put the breeching cover back on seal it air tight with caulk. In the basement Triton sealed the inner stack against the outer stack where the new stack enters the side of the old stack. They did this with steel plates and welds. The temperature sensor is installed and monitoring outlet temperatures and we can only see a 2-degree rise in temperature with the stack being sealed top and bottom. This is not surprising since the are three gaping holes in the outer stack wall on the 4th, 8th and 12th floors that may still be an escape route for air movement. As this is the first stage of the fix it plan being used for investigation as well, we are formulating the second stage now. We want Triton to patch the remaining three holes by change order if necessary. In step two we may try to fill the interstitial space between the stacks with concrete and create a permanent insulation space between the two stacks and this way when the inner stacks rusts out, the concrete stack will remain providing a permanent stack for a long time. We have to get a structural involved at that point to help check the loads on the building.

08/28/06 – We held a construction meeting to get a new handle on where the project stands and to review the R&P chimney stack report. Grady brought one copy of the report and Tony asked for 3 copies to be made and given to the County. The report has basically found that the stack is in FAIR condition. The stack was basically constructed in two different segments, the bottom 130 ft and the top 40 ft. In reviewing the original report from 2001 and the new report from 2006 there is considerable degradation from low temperature condensation and corrosion inside the stack. Photographic evidence was provided in the report to support this claim. The wall thicknesses have decreased and will continue to decrease and the new temperature outlet sensor installed in phase 1 of this project has further provided trending and data to prove that decent outlet temperatures at the boiler flue’s in the basement are significantly reduced in their upward travel to leave the building. Mike Florimonte provided a trend that showed summer boiler leaving temperatures of over 500 F but at the outlet of the stack temperatures were only 210 F. This is a condition that will cause low temperature corrosion. R&P is recommending a spray on coating to protect the interior of the stack. Triton and ThermalTech recommend further investigation into the over cooling effect on the boiler stack. For this much temperature loss to occur, we believe it must be related to the high velocity draft witnessed around the boiler stack at a previous field trip by TE. We have scheduled a Saturday visit with Triton to set off a smoke test inside the boiler stack. We want to witness the path of the released smoke and find the air path that is causing the stack losses. In essence the space between the inner stack and out stack should be dead air space. In addition, Triton will investigate the OA paths surrounding the boiler stack to help ensure that no OA is subjected directly to the boiler stack space. Once this data is resolved, we can isolate the boiler room from the chimney stack and address other “sealant” issues with the new and old breeching. We are scheduled to meet on Sat, Sept 9th. MF will alert the building occupants. AKM requested a synopsis of or plan of attack.

06/16/06 – R&P Industrial Chimney showed up on site. At 2:17 they completed their fieldwork and reported the seems in the stack appear to be the worst off. The took a disposable camera and ultrasonic machine into the stack with them. TTC asked for them to call with a report after they packed up.

05/22/06 – Boiler stack inspection still set for June 19th. Grady is checking on controls and trending.

04/06/06 – Mike called today about getting study complete and temperature sensor in place. Grady replied that the inspection could be the middle of May. The County will need this inspection to be completed either after hours or on the weekend because of hot water reheat. TTC to review and try to find a holiday instead that may work better.

03/09/06 – Pre-construction Mtg was held and notes distributed.

01/17/06 – Wayne reported today that the Bid from Triton did not included a personal property tax statement or a ohio dept statement. TE to check and correct for Wayne.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

12/01/05 – TTC found the original bids for the job (in sbu’s mailibox) and sent them on to Tony for his use. As soon as contract is approved we can have a pre-construction mtg and get the project moving.

11/08/05 – Tony authorized ThermalTech to write the contract for this work. TE will try to get it done in one day.

10/18/05 – All bids came in and contractors are calling for bid results. TTC gave to Tony and Mike on 10/20 for review. Bid Results – PDF

10/14/05 – No addendum had to be issued. Bids are due next week. TE has received a couple of “No Bids” on this project already.

09/29/05 – Final Project manuals have been created. IES information added for controls. Prebid is set for Oct 6 at 9:30 a.m. TE invited Peck, Triton, Process, Geiler, DK and Langdon to bid the project.

09/09/20/05 – TTC is reviewing Sam’s final drawing and project manual.

08/31/05 – MF reported that with their flow hood the outdoor access door when opened drew 1600 CFM with boiler make-up and exhaust running and 650 cfm with the MUA and EF off. This may contribute to extra cooling down of the boiler flue and TE is investigating welding the outer shell closed during our project. TTC cannot explain the huge draft of air up the shaft at all times

08/30/05 – TTC stopped by the site today to review an access door in the side of the building. There appears to be a huge draft from the outdoors into this access door and it apparently is going up the stack and exiting somewhere that in undetermined. This presents a problem with finalizing our design. We can still go about sealing the basement mechanical room as planned but after we are all done there may still be another step to isolating the inner/outer stacks when we are complete and re-measure the infiltration airflow. In talking with Mike, TE may give Mike the cutout for the future access door. If we cut the whole in the drywall now so we can investigate better how the inner and outer stacks are routed through the building. TTC needs to look at original report and talk to contractor about installation method. There are still unknowns about the original design that are affected an effective solution to this problem.

08/25/05 – TTC sent out final bid manual for review today to MF and AKM. Bid opening might be on 9-7-05.

07/18/05 – TE started the small project manual for bids today. TE has to create a new SOSS because the study used up the first SOSS but since so much of the design is already complete TE only wants to write the new SOSS for $2000 instead of the standard $3500 for bid and contract administration.

06/17/05 – TTC and MF discussed the report today and TTC recommended that we put a small packet together now to close up the air space around the stack. An incremental approach to fixing the problem is best. After the space is enclosed, the stack losses should be re-measured at various conditions to asses the new operating characteristics of the boiler plant. This should be done this year if possible. At the same time, a drywall access hole should be cut to inspect how stacks are anchored together. TE will wait for the County to advise.

06/16/05 – TE sent the final report to Tony and Mike for review and use. TE recommended closing off the bottom of the stack leading into the basement and re-creating a dead air space that can be used for isolation the temperature and creating a thermal barrier.

06/06/05 – TE had a meeting today to discuss recommendations. Our report will be out later this week and 2006 estimate will be estimated based on this report. We plan on discussing with Tony and Mike after Mark Miller sends final report to County. TTC and Mike discussed field findings from last week in an impromptu meeting at B-95 today.

05/24/05 – Mike called today and TTC told him that ThermalTech has not done any construction documents yet on this project and that might be due to the fact that we haven’t given Tony a final report on the condition of the stack (awaiting the re-evaluation from either HC Nutting or the other contractor that MF was going to call into survey the breeching) and TE has not provided a written report to Tony and Mike with recommendations about how to proceed. As MF and TTC discussed the situation though, we decided that if something is to be done this year before heating season, the design and SOSS must begin immediately. TTC will email AKM and ask about how to continue work on this project. TE still has $1172 left from the original SOSS that we do not need to used except to provide a written summary to AKM about our findings.

05/11/05 – TTC gave MF HC Nutting as contact for pipe thickness survey.

03/28/05 – TTC & MM met on site and went over boiler stack calcs and heat losses. Too much heat is being loss going up the stack. We need too look at insulating the stack to keep the heat higher throughout the path.

02/22/05 – TTC and MM reported that initial reports look like stack losses primarily are contributed to the low outlet temperature and condensation issues at the 230 building and not stack sizing or entrainment.

02/10/05 – TE received a signed SOSS and posted it to the website today.

02/01/05 – TTC & Mark Miller visited the site for field investigation and SOSS scope.

230 – Boiler Stack Study Read More »

125 East Court Street Public Defenders Renovation Eighth and Ninth Floors

Project Lead: GBBN

06/18/14 – Kick-off Telephone Meeting with Diana Supe of the Facilities Department to request the SOSS (F105). Clarifications made on scope in follow-up emails and calls from PDO.

06/19/14 – Kick-off Meeting with Ralph Linne and Diana Supe with Terry Cannon of ThermalTech.

06/19/14 – Contract Scope Question document authored by GBBN with input from Interior Project Management and ThermalTech.

06/23/14 – GBBN visits 125 East Court Street with CBRE, PDO and Facilities Department.

06/23/14 – GBBN receives electronic drawings and programming documents from CBRE and distributes to consultants.

06/24/14 – GBBN distributes Meeting Minutes to all attendees.

06/25/14 – IPM and GBBN conduct a field verification site visit to the 125 Court Street Facility. IPM and TEI submit scope hours and descriptions to GBBN for SOSS.

06/26/14 – SOSS hand delivered to Bert Watts at monthly Partnering Meeting.

07/09/14- GBBN makes public records request for existing building Code Information to the City of Cincinnati Planning and Buildings.

07/28/14- Bid Opening for Peripheral Furniture. Office Furniture Source is low responsible bidder. GBBN authors AIA contract for submittal to Prosecuting Attorney’s Office.

08/21/14- GBBN makes revisions to AIA contract and resubmits originals to Public Defender’s Office.

09/08/14- Biweekly construction administration teleconference.

09/09/14- Change Order #001 issued to Office Furniture Source to raise new systems furniture panels for higher countertops at the pass through window.

09/10/14- Biweekly construction administration teleconference.

09/11/14- Panic button logistics and hardware finalized iwth Sheriff’s Department.

09/17/14- PDO requests a change order to install a second door into Storage File Room #803.

09/23/14- Keidle Appliance is awarded the purchase order for the two refrigerators and microwave.

09/24/14- Biweekly construction administration teleconference.

09/26/14 – Spencer says that move in date is set 10/13 for furniture move and appliances will come the week after. Both floors will occupy at the same time. 230 and 800 personnel are both moving over. There may be one group staying behind. SJ needs to see Steve Sears about getting proximity cards programmed. SJ says IPS is the County contractor.

10/01/14- Jack Herbert sends updated staff list for production of signage.

10/08/14- Biweekly construction administration teleconference.

10/17/14- First semi-truck of furniture delivered to building. Cardboard packaging materials removed the following day.

10/22/14- Second semi-truck of furniture delivered to building. Cardboard packaging materials removed the following day.

10/27/14- Appliances delivered for the Eighth and Ninth Floors.

10/28/14- Final signage installed on both floors.

11/3/14- Owner moves into finished spaces.

125 East Court Street Public Defenders Renovation Eighth and Ninth Floors Read More »

230 WHT Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/11/13 – GBBN sent drawings for the field work to Pinnacle upon their request.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

05/29/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/26/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

07/24/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/27/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14- GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications to finalize the remaining invoices to close out these projects.

230 WHT Asbestos Study Read More »

230 WHT Public Defenders Renovation Study

Project Lead: GBBN

04/02/13 – Kick-off Meeting with Public Defenders and Facilities Department

04/05/13 – Design Team Kick-off Meeting with IPM.

04/08/13 – SOSS submitted to Bert Watts

04/09/13 – Bert Watts calls to request modified SOSS for Schematic Design and Construction Opinion of Probable Costs only.

04/10/13 – GBBN resubmits SOSS (F086) to Bert Watts.

04/22/13 – GBBN receives approved SOSS with Purchase Order.

04/24/13 – GBBN coordinates with PDO for site visit the following day to field verify existing systems furniture.

05/29/13- Revision made to Archibus estimate as a result of additional programming data from Public Defenders Office.

06/06/13- Revised drawings sent to Public Defenders Office based on changes requested by the PDO.

06/13/13- Revision made to Archibus estimate as a result of the drawing change approvals from PDO on the additional programming data from Public Defenders Office.

230 WHT Public Defenders Renovation Study Read More »

230 WHT Public Defenders Relocation to CAB Study

Project Lead: GBBN

06/13/13 – Kick-off Meeting via conference call to the Facilities Department

06/13/13 – Call to Jack Herbert to ask programming questions per Diana Supe’s request.

06/14/13 – Design Team meeting to discuss scope and deliverables.

06/17/13 – Bert Watts escorts Design Team around CAB 9th Floor Computer Room and adjacent spaces.

06/19/13 – GBBN submits list of scope questions to Diana Supe to finalize scope for SOSS (F088) preparation..

06/21/13 -GBBN finalizes Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney.

06/27/13 – Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney held in B-90.

230 WHT Public Defenders Relocation to CAB Study Read More »

230 WHT Public Defenders Renovation 2/3 Floor

Project Lead: GBBN

08/14/13 – Kick-off Telephone Meeting with Diana Supe of the Facilities Department to request the SOSS (F092). Clarifications made on scope in follow-up emails.

08/14/13 – SOSS hours solicited from Interior Project Management and ThermalTech. TEI indicated three separate prime contracts required for the bidding process.

08/15/13 – Diana Supe confirms contract authoring will not be required.

08/16/13 – GBBN submits SOSS to Bert Watts for processing.

08/19/13 – GBBN submits SOSS consultant scope and hour break downs to Bert Watts.

08/28/13 – Kick-off meeting with Public Defenders Office and Facilities Department.

02/25/14 – IPM was contacted by the Public Defenders Office to estimate the move costs of only the staff (Juvenile from 230 WHT and Guardian Ad Litem from 800 Broadway) to the 125 Court Street Facility.

02/26/14 – At the Master Plan Meeting this afternoon Ralph Linne indicated this project is still on hold.

06/26/14 – Project still on hold.

08/26/14 – Project CIP set for start in first quarter 2015.

02/20/15 – GBBN forwards updated SOSS to Bert Watts. SOSS renumbered (F001) for new Architectural Partnership.

03/13/15 – GBBN gets confirmation from Ralph Linne project will be approved soon.

03/20/15 – GBBN, TEI, IPM and Facilities meet with Public Defenders staff to kick-off project. Design of upgrades starting immediately.

03/25/15 – GGBN receives call from Jack Herbert establishing programming meeting to review staffing locations and changes to scope for Friday 03/27/15 at 8:30 am.

03/25/15 – Telecom will assist with coordination on I/T but contractors and associated rates are to be used for estimating.

04/14/15 – ThermalTech on site to conduct MEP fieldwork with GBBN working on RCP for updated background drawings.

04/22/15 – 50% Review drawings sent by ThermalTech to GBBN for Thursday Meeting.

04/23/15 – GBBN held 50% review with client. HVAC zoning was approved. Electrical comments including removing an abundance of convenience outlets on the walls. Small modifications are required to the 2nd Floor Receptionist/Admissions area and Third Floor Conference/Storage area

04/28/15 – GBBN meets with client to review and receive approval for modifications required to floor plan

04/29/15 – Design Team to meet to discuss Phasing and Reflected Ceiling Plan coordination between Architecture and MEP discipline scope.

04/30/15 – During PM meeting we discussed how to handle the room number changes at 230. When room numbers change, how do we want to handle this in the renovation? Bert says that once a number is created it can never be removed because records were assigned in the past. Don’t update the exit signs, discussed the relock lighting system and reusing it. State term contract is okay for buying new furniture but 2nd and 3rd floor have different systems. MB asked about putting in receptacles in all 4 walls and BW said that if PDO is okay with not having convenience on every wall of the new offices, Bert said get this in writing. Carpet tile discussion came up, PDO asked for a color scheme that is not in the carpet tile selection, BW asked if we can get Broadloom pattern in carpet tile. PDO would like to match the 125 color and carpet schemes. Fire Protection work would be best to be done after hours. If the system is down for more than 8 hours, Facilities have to notify Risk Management. If night work is done, the contractor has to hire an evening security guard for the work or use the County private security services.

05/13/15 – 90% Final Review Sets delivered to the PDO and reviewed prior to final bidding. Final comments to be ready for final bid documents by 5/18/15.

05/19/15 – Project Issued for Bid. Prebid scheduled for 5/28/15 at 2:30pm at the building.

05/28/15 – Pre-Bid Meeting to be held at 2:30 pm in the Third Floor Media Room.

06/11/15 – Bids accepted at Purchasing Department. Six bids were received.

06/11/15 – GBBN interviews apparent low bidder, Kramer and Feldman Inc. All appearances are that bid is responsive and KFI will hold their bid. GBBN recommends to Hamilton County that KFI bid is to be accepted.

06/12/15 – Hamilton County accepts GBBN recommendation and authorizes GBBN to author contract for KFI, accepting all Alternate Bids but without any additional allowances added to contract.

06/15/15 – GBBN files Building Permit Application with City of Cincinnati.

06/16/15 – Facilities department requests GBBN make requested modifications, from Prosecuting Attorneys office, to KFI contract. GBBN makes modifications and delivers to Facilities.

06/24/15 – Bert sent out signed contract for KFI today. Contract date established at 6/24/2015. The accompanying Purchase Order was also sent.

230 WHT Public Defenders Renovation 2/3 Floor Read More »

230 WHT East 9th Building Facade Assessment

Project Lead: THP
09/23/15 – County requested an SOSS to complete a façade assessment with 10 year master plan.
12/09/15 – Ground and roof survey complete.
01/28/16 – THP working on the report.
02/25/16 – THP has completed a draft and anticipates delivering a final March 9th.
04/14/16 – THP provided a draft report for review and comment.
04/18/16 – County provided review comments to the report.
04/28/16 – THP provided final copy of the report.
05/26/16 – Ready to archive.

230 WHT East 9th Building Facade Assessment Read More »

230 WHT Public Defender Office Renovation Construction Administration

05/22/15 – Bert Watts requested a new SOSS be issued for the Construction Administration portion of this project.
05/26/15 – SOSS submitted in person to Bert Watts.
06/15/15 – GBBN submits the Building and Mechanical Permits to the City of Cincinnati.
07/10/15 – PDO send along a staffing schedule showing phasing and staff involved with each phase move.
07/13/15 – PDO indicates they need the 3rd Floor Media Room until August 5th. GBBN distributes information to team. John Nester and KFI meet with the building manager to discuss demolition debris removal from the building.
07/14/15 – GBBN receives letter from the City of Cincinnati requesting additional information for building permit.
07/16/15 – GBBN sends response letter back to the City of Cincinnati with additional requested information.
07/16/15 – TEI sends VAV submittal back to GBBN with concerns about the manufacturer of the VAV boxes not matching the existing. Heights above the existing ceiling could be an issue.
07/17/15 – GBBN returns approved OKI Wall and Ceiling Submittals. Ceiling tile, to match existing, is a deduct credit to be handled on the first change order.
07/21/15 – GBBN receives carpet samples from KFI.
07/23/15 – GBBN returns approved carpet submittal to KFI. GBBN sends request to KFI for change order request to order Knoll wall cleats for systems furniture that are no longer available on State Contract. KFI pricing is approved for ordering.
07/24/15 – Signage Submittal received by GBBN. GBBN has requested from PDO a complete list of staff names for the sign inserts.
07/25/15 – GBBN received Door Submittals. GBBN requested information from KFI on millwork shelf for Dutch Door gap between leaves.
07/27/15 – Pre-Construction Meeting held at PDO Media Room.
07/28/15 – GBBN receives requested detail on millwork shelf for Dutch Door. Approved submittals are returned to KFI the same day.
07/29/15 – Pre-Construction Meeting Minutes distributed to attendees via email. TTC provided Energy Impact Study to Bert for project. Titus VAV and Air Device submittals received marked up and returned to vendor as FAC.
08/06/15 – GBBN issues Construction Change Directive #1 to KFI for VAV and other submittal changes.
08/07/15 – GBBN is notified the Building Permit is ready for payment and pick-up. GBBN notifies KFI and Owner.
08/11/15 – GBBN returns Casework Submittals to KFI indicated as “Revise and Resubmit”. Addendum changes to millwork scope are missing from submittal.
08/11/15 – GBBN authorizes door hardware vendor to reduce heavy-duty hardware requirements from standard Office doors to match existing conditions in building.
08/12/15 – GBBN responds to RFI for additional Office dimensions.
08/14/15 – TEI issues RFI response to return air source for Office #23, Room #03188.
08/14/15 – Construction Meeting held at 230 WHT, Second Floor.
08/18/15 – TEI issues Change Directive for I/T upgrades to 1 gigabyte system.

08/19/15 – GBBN issues Construction Change Directive #2 to KFI for changes to Office 03153 north wall.

08/20/15 – TEI issues RFI response for 1″ to 3/4″ VAV water supply piping change.

08/21/15 – Construction Meeting held at 230 WHT, Second Floor.

08/24/15 – GBBN visits Hathaway Warehouse to inspect carpet tile delivery. Delivery approved for billing on next Application for Payment.

08/24/15 – TEI returns HVAC Controls Submittals to GBBN. GBBN forwards to KFI the same day.

08/25/15 – TEI received, reviewed and returned Fire Alarm drawings and submittals for the project to GBBN.

08/25/15 – GBBN returned casework resubmittals to KFI marked “Furnish As Corrected”

08/26/15 – Emcor resubmitted HVAC controls submittals updated to TEI marks and TEI re-approved them in an email back to KFI and GBBN.

08/28/15 – Construction Meeting held at 230 WHT, Second Floor.

08/28/15- Wood flush door submittal returned “No Exceptions”.

09/04/15 – Construction Meeting held at 230 WHT, Second Floor.

09/08/15 – GBBN finalized signage details with CPS.

09/09/15 – Mitch Penick distributes list of Second and Third Floor Cable drops to be installed.

09/11/15 – Construction Meeting held at 230 WHT, Second Floor.

09/16/15 – GBBN visits CPS for validation of signage completion for inclusion onto Application for Payment.

09/17/15 – TEI returns Fire Protection Submittals to GBBN. GBBN forwards to KFI.

09/18/15 – Construction Meeting held at 230 WHT, Second Floor. GBBN approves pencil copy of Application for Payment #1.

09/22/15 – GBBN receives Change Directive pricing from KFI on new blinds, wall mount channels and finalized 1 GB I-T system upgrades.

09/25/15 – Construction Meeting held at 230 WHT, Second Floor.

09/29/15 – GBBN issues Change Order #001 to KFI for signatures.

09/30/15 – GBBN makes site visit to TPC for verification of acoustic wallcoverings for billing. GBBN approves Application for Payment #1.

10/02/15 – Construction Meeting held at 230 WHT, Second Floor.

10/05/15 – GBBN receives change order request from KFI for Receptionist glass type change.

10/09/15 – GBBN attends Construction Meeting. GBBN approves Application for Payment #2.

10/16/15 – Construction Meeting held at 230 WHT, Second Floor.

10/13/15 – KFI sends pricing document for ASI-1.

10/21/15 – GBBN receives call from PDO about making proposed changes for Drug Felony Court staff on Second Floor Lobby.

10/22/15 – TEI sends electrical and mechanical proposed changes to Drug Felong Court Offices to GBBN.

10/23/15 – Construction Meeting held at 230 WHT, Second Floor.

10/26/15 – Facilities responds to KFI that only the second floor restroom ceilings need to be painted.

10/27/15 – GBBN delivers and submits the Engineering Change for the Drug Felony Court Offices to the City of Cincinnati. The processing fee of $46 was paid.

10/28/15 – GBBN issues Change Directive #3 to KFI for the Felony Drug Court Office Changes.

10/28/15 – John inquired about thermostat style. Emcor has been contacted.

10/30/15 – GBBN issues Change Directive #3 to KFI.

11/06/15 – Design Team attends construction meeting. Walk-through performed on Third Floor before meeting.

11/09/15 – GBBN approves Application for Payment #3 and delivers to Bert Watts.

11/12/15 – GBBN submits Engineering Change to City of Cincinnati Buildings and Inspections.

11/13/15 – Design Team attends construction meeting. Walk-through performed on Third floor.

11/18/15 – GBBN issues Change Directive #4 to KFI.

11/20/15 – Design Team attends construction meeting. Walk-through performed on Second Floor.

11/27/15 – Design Team attends construction meeting. Walk-through performed on Second and Third Floors.

12/04/15 – Design Team attends construction meeting. Walk-through performed on second floor. Owner requested more office furniture changes. GBBN approves Application for Payment #4 and delivers final copies to Owner. Keying meeting held with Acme Lock.

12/08/15 – Project is progressing very nicely. ThermalTech collected pricing on changing out the VAV box valves from Triton and sent to Spencer and County. No call from the fire protection vendor about replacing the existing fittings – I am not sure this was done.

12/21/15 – GBBN receives extension of SOSS for additional construction administration.

01/05/16 – GBBN authors and delivers Construction Change Directive #5 to KFI.

01/06/16 – IPM forwards change order pricing from Planes Commercial Services for Owner requested changes for furniture relocation changes.

01/08/16 – Design Team attends construction meeting. Walk-through performed on second floor.

01/10/16 – KFI meets with Building Department Inspector to discuss and attain approval for request to move Second Floor, West Office walls one foot to the east. Inspector approves change request but insists on Engineering Change be submitted to City.

01/11/16 – The owner approves request to move Second Floor, West Office walls one foot to the east.

01/11/16 – TEI and GBBN resolve issue with Triton over incorrect VAV intake air duct sizes. Inspector noticed a 8″ verses 10″ duct installation on the second floor. Triton to replace incorrect 8″ ducts with the correct 10″ sizes.

01/12/16 – GBBN issues Change Order #002 to KFI. GBBN approves, signs and delivers Application for Payment #5.

01/15/16 – Design Team attends construction meeting. Walk-through performed on Second and Third Floors.

01/17/16 – GBBN issues Change Directive #006 to KFI.

01/18/16 – Change Order work for rusted sprinkler lines was not performed due to failure of materials to be delivered onsite.

01/21/16 – IPM issues change order request for changing of Resource Room work surfaces per owner’s request.

01/22/16 – GBBN issues request to Contemporary Plastics, Inc for additional signage along with clarified artwork file and suggested layout drawing at 3rd Floor Receptionist area.

01/22/16 – GBBN attends weekly construction meeting. Approves Application for Payment #6.

01/24/16 – KFI forwards to GBBN the pricing documents for additional owner requested furniture relocation changes.

01/25/16 – ThermalTech discusses MEP issued with Emcor and Triton about balancing and controls. Triton is checking on leaks in third floor and cold calls for us and will open all balance vales. TTC inquired about other changes to existing systems.

01/26/16 – GBBN applies for Engineering Change #2 with the City of Cincinnati Building Department. PDO request made to County Sheriff’s Department for additional panic buttons. Trilogy lock has been programmed by the County Trades Department and security closure problem is solved.

01/28/16 – GBBN paid for and picked up the approval for Engineering Change #2. Final set of approved documents delivered to KFI at weekly meeting on Friday.

02/16/16 – GBBN authors and distributes Construction Change Directive #7.

02/18/16 – GBBN authorizes Contemporary Plastics to execute large additional sign for 2nd Floor Receptionist. Resends digital files.

02/18/16 – TEI issues Electrical Punch List to GBBN.

02/19/16 – GBBN directs contractor to ignore CCD#7 due to additional owner directed changes. GBBN to revise and resend.

02/19/16 – PDO sends directive for relocation of proposed millwork at Admissions scanner location.

02/19/16 – Facilities approves authorization for contractor to make revisions to Admissions Counters and L-shape scanner counter at Receptionist.

02/22/16 – Owner sends Excel File for names to be printed on sign inserts.

02/23/16 – TEI completes electrical punchlist visit and sends the report to GBBN. Per previous conversations, GBBN to collect all of the punch lists from all trades and the owner, and issue at once.

02/23/16 – Owner sends revisions to GBBN on sign insert name list.

02/24/16 – Owner directs contractor to clean existing wallcovering at Media Room in lieu of replacement.

03/03/16 – Facilities sends PDO Punch List to GBBN for inclusion into overall punch list.

03/07/16 – TEI sends itemized change orders from HVAC contractor to GBBN and Facilities.

03/09/16 – GBBN releases copy of Change Order #3 for comments. County and ThermalTech provide comments.

03/09/16 – KFI sends updated Cincy Electric Change Order #3 pricing to GBBN.

03/10/16 – KFI responds with correction recommendations to GBBN Change Order #3 comments.

03/11/16 – County Facilities requested new SOSS to capture As-Built Documents and IFM Data input for record drawings.

03/15/16 – GBBN contacts KFI about painting chipping issue on second floor.

03/21/16 – Facilities agrees to have another change order, #4, to capture any additional items including the additional signage.

03/21/16 – Planes responds to request for modesty panel installation dates to be on site.

03/22/16 – TTC released Mechanical Punchlist Rev 2 to contractors.

03/23/16 – GBBN meets with Contemporary plastics for Large 2nd Floor Reception sign installation. 2nd Floor Signs are to be installed and the inserts, for both floors, are given to PDO for installation. 26 additional signs are requested by PDO via change order.

03/28/16 – TTC discusses status of Mechanical Punchlist Rev 2 with Doug Emery of Triton who reports that the balancer and recommissioning agent were never given authorization to perform the Alternate work. This has been rectified and they will be on site to do this work soon. TTC instructed the contractor to coordinate this work with Ernie Hedricks and make sure he was present for all of this work.

04/11/16 – GBBN forwards full punchlist to KFI.

04/12/16 – GBBN adds the repair and repainting of the northwest stair (material routing) to the punchlist for KFI.

04/14/16 – GBBN authors the preliminary Change Order #3 reflecting pricing that is still missing. KFI requests meeting of all interested parties to discuss change orders.

04/18/16 – Hamilton County indicates they need not be present in the meeting to discuss the change orders.

04/21/16 – Hamilton County sends list to Planes for items, currently stored off-site, to be returned to the building.

04/22/16 – Planes responds to request with proposed schedule for item return.

04/26/16 – KFI indicates all subcontractors have been contacted by KFI for submittal of all remaining change order items and pricing.

04/26/16 – KFI requests on site meeting with GBBN to discuss locations of acoustic wallcovering in the second floor Admissions area. Meeting scheduled for 04/27/16.

04/27/16 – TEI discusses with HamCo Data/Comm department (Mitch) the punchlist items that Tele/Comm has for the project and issues punchlist to GBBN.

04/27/16 – GBBN forwards Tele/Com Punchlist to KFI.

05/23/16 – GBBN requests final back-up from KFI for Change Order #3 and status of Punch List completion.

05/25/16 – KFI sends final back-up for final change order paperwork. KFI indicates punch list work should be completed by end of this week.

06/03/16 – GBBN authors, and mails, Change Order #003 to KFI.

06/14/16 – The final executed Change Order #003 copy is received by GBBN.

06/27/16 – GBBN receives the final copies of Application for Payment #8 from KFI.

06/30/16- GBBN approves Application for Payment #8 and delivers to Facilities Department.

12/29/16 – Project archived by TTC.

230 WHT Public Defender Office Renovation Construction Administration Read More »

230 WHT – Public Defender Office Renovation Project Closeout and As-Built

Project Lead: GBBN

02/29/16 – GBBN submits SOSS to Facilities for approval.

04/08/16 – GBBN sends as-built drawings to Facilities for review.

04/12/16 – Facilities sends approved SOSS to GBBN.

04/15/16 – Facilities indicates the as-builts need to be slightly revised for website access and manipulation. More information to follow.

04/26/16 – KFI requests meeting to discuss locations of acoustical wallcovering to be installed in Second Floor Admissions Suite.

05/13/16 – Planes reports that final modesty panels have been installed, related to their scope of work.

05/18/16 – Bert Watts forwards email with additional directives and answers to GBBN questions related to as-built and IFM input.

05/25/16 – ThermalTech done with mechanical and electrical as-builts. We are moving on to fire protection and plumbing. Ryan working directly with TJ on electronic cad files.

05/23/16 – GBBN requests final back-up from KFI for Change Order #3 and status of Punch List completion.

05/25/16 – KFI sends final back-up for final change order paperwork. KFI indicates punch list work should be completed by end of this week.

06/03/16 – Facilities Department requests scheduling dates and times for final punch list work.

06/24/16 – KFI reports the final Triton change order work will be scheduled for 7/9 and 7/16.

06/22/16 – GBBN completes As-built electronic drawings and uploading to the County IFM/WebCentral database.

06/26/16 – TEI requests Triton coordinate with KFI for warranty’s start dates related to change order work completion.

06/27/16 – GBBN sends copies of all final Punch Lists, from all disciplines and PDO, to Facilities for their records.

07/06/16 – KFI confirms stairwell change order work to be completed by the end of the week.

07/11/16 – TEI informs the team that the change order work scheduled over the weekend was not completed due to existing restrictions.

07/13/16 – John Nester confirms Triton shipment of Terminator Strainers by the end of the day.

07/18/16 – ThermalTech sent revised As-Built CAFM drawings to TJ at GBBN for reprocessing.

07/21/16 – TEI indicates Triton has confirmed the change order scope with their intentions.

07/25/16 – John Nester confirms Triton did not arrive on site for Mechanical Change Order work. Also work to repair material delivery damage in the northwest stairwell was not completed as originally scheduled.

07/26/16 – John Nester communicated the new dates for Triton to perform the change order work will be 8/2/16, 8/4/16 and 8/6/16.

07/27/16 – ThermalTech has Triton has O&M’s under review and has requested new equipment cuts.

08/08/16 – Triton reported today that all the change order work on the valves and unions is complete. They will be back to finish up the diffusers and thermostat after they coordinate with Josh.

08/22/16 – TTC stopped by and performed another back punchlist on the Terminator valves which were found to be complete and spot checked. A couple of other items were emailed to the contractors for changes and the t-stat and Admissions office diffusers were not done. ThermalTech sent email to project team outlining the findings.

08/23/16 – KFI was contacted to confirm that all suspended acoustic tile was used in the construction project. TEI reported a rear hallway has a section of existing suspended acoustic tile sagging and required corrective work. Facilities reported back that Trades has been issued a work order to repair the ceilings due to a potential safety issue.

08/25/16 – Bert asked for us to push for all closeout documents for this job. TTC emailed Triton for new warranty letter for new parts, the rest of the Triton O&M look good.

09/07/16 – GBBN receives pencil copy of Application for Payment #9 from KFI. Facilities approves payment with amount of retainage remaining on application.

09/09/16 – GBBN Signs and Delivers Application for Payment #9 to Facilities.

09/16/16 – GBBN receives executed copy of Application for Payment #9 from Facilities.

09/28/16 – ThermalTech is waiting on O&M’s Cincinnati Electrical Services. Bert request all final bills from all partners and contractors by end of October.

10/18/16 – KFI delivers record set of drawings from City of Cincinnati and three sets of O&M binders to GBBN. GBBN’s In4 Group meets with Facilities to discuss as-built drawing uploading logistics.

10/21/16 – KFI delivers via mail the Close out AIA documents to and red line as-built drawings to GBBN.

10/24/16 – GBBN delivers As-Built Drawings, Record Drawings, AIA Close out Documents and Application for Payment #10 (Final) to Facilities.

10/24/16 – GBBN delivers electronic updated MEP xref as-built drawings to Facilities.

10/27/16 – TTC will hand deliver some additional warranty paperwork from Triton to John Nester for Terminator Valves.

03/21/17 – GBBN confirmed to Facilities all three SOSS projects related to this project have been 100% completed, invoiced and paid.

230 WHT – Public Defender Office Renovation Project Closeout and As-Built Read More »

230 – ADA Assessment

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/17/11 – SOSS submitted in person to Bert Watts.
09/16/11 – Signed SOSS received from Bert Watts.
10/27/12 – Preliminary Report completed and sent to Bert Watts for review. Estimating portion of study yet to be completed.
08/24/13 – Estimating completed on the impacts of the ADA Assessments.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Estimating Project Requests.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – Project Request Estimates are printed and ready for insertion into final reports.

230 – ADA Assessment Read More »