Central – UPS Upgrade
PM: Rycca, Barth
10/29/26 – Project created. Project under design. Have County UPS batteries installed in old UPS room
Central – UPS Upgrade Read More »
PM: Rycca, Barth
10/29/26 – Project created. Project under design. Have County UPS batteries installed in old UPS room
Central – UPS Upgrade Read More »
PM = Tony Matre, Mike Barth
10/28/2026 – HCFD requests SOSS.
2020 – Emergency Gear Upgrade Replacement Read More »
PM – Tony Matre, Mike Barth
10/28/2026 – HCFD requests SOSS.
2020 – ATS Replacement Read More »
PM = Rycca Thacker, Mike Barth
10/28/2026 – HCFD Requests SOSS for project.
Hillcrest – Fire Alarm System Fiber Connectivity Read More »
PM = Rycca Thacker, Mike Barth
08/26/26 – DEG Submits SOSS for approval.
09/23/26 – Project pending SOSS approval and PO.
10/28/26 – Project pending SOSS approval and PO.
Crime Lab – Full Electrical Coordination Study Read More »
PM = Rycca Thacker, Mike Barth
07/29/26 – HCFD requests SOSS. DEG submits SOSS.
08/26/26 – DEG sends fixture model number to HCFD to get trades to check pricing and lead times. DEG finalizing the plans for permitting and trades to install.
09/23/26 – DEG submits drawings to IBI for approval and permit.
10/28/26 – Permit and plan review approved. HCFD trades has approved plans and permit. Trades to complete the install. DEG will call for inspections once work is installed.
230 – East Exterior Lighting Read More »
PM Rycca Thacker, Mike Barth
06/23/26 – DEG receives PO and signed SOSS. Arc Flash Study initiated.
07/29/26 – DEG has nearly the entire single line from the KZF project modeled in SKM software. Next step is to field verify make/model numbers and serial numbers. DEG to schedule with the building manager.
08/26/26 – Study in progress.
09/23/26 – Study progress continues.
10/28/26 – Study complete. Labels to be printed and be scheduled with building manager to apply.
111 – Arc Flash Model and Labeling Read More »
PM = Rycca Thacker, Mike Barth
04/29/26 – HCFD requests DEG to visit the site to discuss issues with exterior lighting circuitry. DEG to submit SOSS for partial electrical coordination study for affected circuits.
06/23/26 – DEG receives PO and signed SOSS. Electrical Study commences.
07/29/26 – DEG conducts site visit to document all existing breaker model and serial numbers to perform the analysis. Project Analysis being modeled in easy power program.
08/26/26 – Coordination study and report draft sent to HCFD for review.
09/23/26 – trades electricians to adjust settings. Project complete.
10/28/26 – Project complete. Can this be archived.
10/29/26 – TTC archived.
Crime Lab – Electrical Coordination Study Read More »
PM: Megan, Barth
02/26/26 – Discussed at Partner meeting. Start an SOSS.
03/25/26 – Draft report Sent to HCFD on 3/23.
04/29/26 – DEG receives comments and resends draft report.
07/29/26 – DEG sends HCFD final report.
08/26/26 – No updates. Ready to archive.
525 – Lighting Study Read More »
PM = Rycca Thacker, Mike Barth
02/25/26 – HCFD requests SOSS. DEG to prepare SOSS for submission.
03/25/26 – No updates. DEG to submit SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – DEG receives signed SOSS and PO. Assessment underway.
Comm Center – Electrical Assessment Read More »
PM = Megan, Mike Barth
02/25/26 – HCFD requests SOSS for project. DEG to Provide SOSS.
03/25/26 – No updates. DEG to finalize and submit the SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – HCFD asked for revised SOSS with Electrical Sub included in price. DEG to receive quote from Edge Electrical Contractor by 10/30/2026 and will then resubmit.
Comm Center – Electrical Device ID and Arc Flash Read More »
PM = Matt Butz, Mike Barth
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending PO and approval of SOSS.
JC – LC Emergency Power Modifications Read More »
PM = Megan, Mike Barth
01/28/26 – HamCo request SOSS for Electrical Upgrades for Kitty City. DEG submits SOSS. DEG receives approved SOSS and PO on 01/28/26. DEG coordinating meeting with Duke.
02/25/26 – DEG meets with Duke to discuss power options. DEG proceeding with load calculations to send to Duke for service sizing.
03/25/26 – DEG develops drawings for electrical upgrades. Final field work scheduled for 03/31 at 7:30 AM to confirm final details.
04/29/26 – DEG submits 100% review drawings and OPCs to HCFD for comment/approval. Upon receipt of comments, ITB will be submitted.
05/27/26 – DEG meets with bldg mgr – adds a couple of alternates for additional outlets and also replace thru wall fans with new with humidistats.
06/23/26 – Drawings sent to HCFD for review.
07/29/26 – Upon receipt of HCFD review comments and/or approval, ITB package will be finalized and issued.
08/26/26 – Meeting scheduled for 08/28/26 with CARES to review and receive approval. Goal setting worksheet submitted (pending approval).
09/23/26 – Project issued for bidding. Prebid meeting occurred on 09/23. Bids are due on 11/12.
10/28/26 – Project in bidding phase. (1) addendum issued.
Colerain – Kitty City Electrical Upgrades Read More »
PM: Rycca, Barth
12/05/25 – Met onsite to gather SOSS data for this project. DEG to submit SOSS for this work.
01/28/26 – DEG receives SOSS and PO. Working to schedule a progress meeting with RT availability.
02/25/26 – DEG submits to the City of Springdale for permit for work. Install pending permit approval.
03/25/26 – DEG receives permits from Springdale. HCFD schedules install with MobilComm.
04/29/26 – Work complete. Closeout?
111 – Antenna Power Upgrade Read More »
PM: Matt Butz, Mike Barth
10/30/25 – Project was sent out for bid, DK sent in questions with options. Security lighting prebid also held.
12/10/25 – Project small projects bids received. Glenwood awarded the bid. Contract in finalization phase. Submittals and construction to commence once the contracts are approved.
01/28/26 – Project contracts and PO sent to subs. Meeting dates for KO meeting requested from contractor.
02/25/26 – DEG and HCFD meet with Glenwood on exterior lighting. Installation of drawings pending light fixture procurement (approx mid March).
03/25/26 – Exterior lighting installed. Play yard lighting levels requested to be increased. DEG performs lighting study to increase the lighting levels. DEG sends to HCFD.
04/29/26 – Play yard lights installed last week. All exterior lighting complete. Security cameras work to commence upon the completion of Central Campus work.
05/27/26 – Play yard lights permitted and inspected (final inspection passed). Cameras are kicking off beginning of June.
06/23/26 – DK has mobilized to the project site to install the cameras. installation is underway. Weekly project meetings scheduled.
07/29/26 – Installation underawy. Most of access control installed. Cameras are being installed and cabling installed with the GSA vendor.
08/26/26 – Installation will be finalized when ISWP installed at the location.
09/23/26 – ISWP installed by technical services. Installation finalization and connections scheduled with DK.
10/28/26 – Installation of cameras nearing completion.
Dane – Security System and Exterior Lighting Read More »
PM: Rycca Thacker, Mike Barth
10/30/25 – The project is out for bid, prebid is scheduled for November.
12/10/25 – Bid opening occurred. Zero bids received.
01/28/26 – HamCo asks DEG to re-package and resend out to bid.
02/25/26 – No updates this month. DEG will compile all data and send list of buildings that information is still pending.
06/23/26 – DEG contacts all building managers to confirm that there have been no modifications to the critical load lists for each building. A review set will be sent to HCFD end of June.
07/29/26 – DEG has not received responses from buildings.
08/26/26 – ITB pending the advertised estimate from HCFD and then goal setting worksheet approval.
09/23/26 – Project in bidding phase. Prebid meeting was held on 09/22. Bids are due 11/12/26.
10/28/26 – Project in bidding phase. (2) Addendums Issued.
All Buildings – Emergency Switchgear PM Read More »
PM: Matt Butz, Mike Barth
11/06/24 – THP update – THP provided an email with budget to rebid the project.
01/30/25 – Restart post to track 2025 project for this project.
01/24/25 – THP update – THP provided a formal SOSS.
02/26/25 – Prebid Meeting occurred on 02/26/25. Attendance by DK, Dunn Electric and Driekast. Bids due on 4/10/25.
03/07/25 – Terracon on site for test boring. Preliminary results included sandy dirt findings. Official report coming later this month.
03/25/25 – Terracon invoiced project for work but final report not here yet.
03/26/25 – Project bidding. Lots of questions being submitted by Glenwood. Bids are due 04/10.
04/23/24 – Project bids received. (2) bidders. Glenwood and Alpha. Glenwood apparent low bidder. DEI approves bids. TEI vets bid ln 04/22/25 – TEI to submit letter of recommendation to start the contract phase.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase. Contract contacts TEI asking about status.
07/30/25 – DEG, HCFD, Bldg Mgr meet with Glenwood Electric for a pre construction KO meeting. at time of bid, the generators and switchgear quoted Glenwood 6-8 weeks for submittals, and then 40 weeks +/- for shipping of gear. Glenwood released the submittals end of last week. Likely startup of construction summer 2026.
08/27/25 – DEG has not received submittals to date.
09/24/25 – DEG receives equipment submittals. Submittals under review and approval.
10/29/25 – DEG working with contractors to get the permits in order.
01/28/26 – Issues with one switch that contractor and DEG working on.
02/25/26 – CO #001 issued. All gear should be on order. Estimated delivery June/July 2026.
03/25/26 – Glenwood submits several RFIs on the project. DEG reviewing RFIs.
04/29/26 – Glenwood submits pay applications for procured material. DEG to visit the crane yards to certify the equipment.
05/27/26 – Project construction pending material procurement.
06/23/26 – DEG speaks with Glenwood, and the gear manufacturer has production delays, the anticipated mobilization date has slid to 09/01. The existing equipment in the areas where the work is to occur needs to be relocated prior to mobilization.
07/29/26 – Project mobilization pending procurement of equipment.
08/26/26 – DEG meets with Glenwood at FDL and Ohio Cat to certify some of the equipment. Gen sets are on site in Dayton Crane Yard. Glenwood to schedule certifying the equipment trip with DEG.
09/23/26 – Pre-construction meeting occurred. glenwood site super has been on site to get knowledge of the building. Construction to begin around 10/01/2026
11/06/25 – THP issued permit drawings to be submitted with Davies set.
10/01/26 – Triton issued RFI No. 1.
10/05/26 – THP responded to RFI No. 1.
10/28/26 – Construction underway. Multiple meetings and discussions re fitting generator on oversized skid into the basement. Skid to be modified to fit into the building. ATS location for North tower is final coordination item at the time.
JC – Emergency Power Upgrade 2025 Read More »
PM Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre met to establish project schedule. The project in process.
02/26/25 – No updates this month
03/26/25 – No Updates this month.
04/23/25 – Project manual near completed. XBE paperwork to be submitted for approval then ITB will be issued.
05/28/25 – No Updates
A&D – Elevator System PM Agreement Read More »
PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Tony meet and establish project schedule. Project in progress.
02/26/25 – No updates this month
04/23/25 – No updates this month
05/28/25 – No Updates
09/24/25 – DEG and AKM discuss that this goes out to bid mid October. Also discuss 1 year contract with optional 1 year renewals pending the elevator replacement projects.
10/29/25 – Project to be sent to purchasing on 10/31/25 for bidding.
12/10/25 – Prebid occurred on snow event day. A send prebid occurred on 12/08/25 for the bidders that could not attend during snow event. Bids to open on 12/29/25.
01/28/26 – Tony M and Bonita drafted contract and sent to Prosecutor.
230/800 – Elevator System PM Agreement Read More »
PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to develop project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – No updates this month.
04/23/25 – No updates this month.
05/28/25 – No updates
TPC – Elevator System PM Agreement Read More »
PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – TEI visits all building sites that are new to inventory/coming online this spring/summer. TEI submits DEI paperwork. As soon as approved by DEI – ITB will be issued.
04/23/25 – TEI issues project for bidding. Prebid meeting was on 04/21/25. In bidding phase.
05/28/25 – Bids received. (2) bidders. Project in contract phase.
06/25/25 – Project in contract phase.
All Buildings – Generator Systems Inspections and Testing Read More »
PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish schedule. Project in progress.
02/26/25 – No updates this month. AKM wants bid out in April ’25
03/26/25 – No updates this month. Work to occur in April 2025.
04/23/25 – Nick (TEI) developing and updating the data sheets for the buildings with newer systems. XBE paperwork in works and ITB to be issued.
05/28/25 – No updates
06/25/25 – No Updates
08/27/25 – DEG going to issue bid package first week of September. Proposed (AKM approved) prebid dates are 9/15 and 9/16.
09/24/25 – DEG issues for bidding. JCI, Siemens and SA Communale indicate interest in project. Prebid dates are 09/23 and 09/24, no bidders attended the prebid walk thrus. bid openings 10/22.
10/29/25 – SA Communale Only bidder. AKM working on Contract.
12/10/25 – Project in contract phase.
All Buildings – Fire Alarm System Inspections & Testing Read More »
PM = John Nester – Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO.
01/29/25 – TEI and HCFD to conduct study walk thru of building in next 2 weeks.
02/26/25 – TEI requests time with HCFD to perform study walk thru
03/26/25 – TEI and HCFD walk the building to locate/document the existing WiFi system devices. Report is in progress.
04/23/25 – TEI to have draft report for review by HCFD/2020 staff by mid May.
05/28/25 – TEI has a draft review meeting with the HCFD/2020 staff. TEI finalizing a few modifications to the draft and will distribute to team for review/comments.
08/27/25 – DEG sends final report with HCJC comments included.
10/29/25 – DEG addresses C Walsh questions via email
12/10/25 – No updates this month
2020 – WiFi System Study Read More »
PM: Rycca Thacker, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (4) elevators in 230 East 9th Street Building. TEI and Elevar meet to discuss roles on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar SOSS provided to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD. SD meeting scheduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team meets with the Courts committee to review security and finishes. DD documents are progressing.
06/25/25 – Team meets with Court Admins. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027). The contract phase and procurement deposit caused the delay.
230 – Elevator Modernization Read More »
PM: Rycca Thacker, Mike Barth, Lauren Schmitz
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (5) elevators in 800 Broadway. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed all field work and work is ongoing.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting was scheduled with HCFD. SD review meeting shceduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to schedule courts committee for design review.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/23/25 – THP – Davies, Elevar, County and THP met to review possible options for getting the elevators in 800 Broadway.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
07/29/25 – THP sent a proposed summary of elevator access plan and THP scope of work for review.
08/13/25 – THP sent an SOSS to Davies for review.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/08/26 – THP issued bid documents.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – THP sent questions for GC post-bid review in March.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay. Due to the obsolescence of the R-410A refrigerant, the Liebert units for the machine room cooling anticipated ship dates are 52+ weeks. The Skill-Aire alternate ($42k deduct) is 16-18 week ship time.
800 – Elevator Modernization Read More »
PM – Rycca, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (9) elevators in Courthouse. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI has design schedule. Field work ongoing.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to notify when courts committee are ready for review meeting.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule with RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Bids still under review by HC.
04/30/26 – Low bidder vetting meeting occurred. Contract in process with HC Purchasing. Notification of TKE buyout forwarded to HCFD.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay.
CH – Elevator Modernization Read More »
PM = John Nester, Mike Barth
08/28/24 – ThermalTech Issues SOSS for approval.
09/25/24 – Project pending SOSS approval.
10/30/24 – Project pending SOSS approval.
12/11/24 – Project pending SOSS approval. Work picked up in different project, okay to close this one.
CH – Courtroom 580 Electrical Upgrades Read More »
PM = Matt/ Trades, Mike Barth
08/28/24 – ThermalTech submits SOSS for all sirens in Zone 4.
09/25/24 – TEI receives signed SOSS and PO for project. TEI to schedule kick off meeting with HCFD.
10/30/24 – TEI contacts Duke Energy for available fault at each location. TEI coordinates with HCFD for addresses of each siren. Model in Progress.
12/11/24 – Zone 4 sirens are modeled and the labels are ready for printing. TEI will print and deliver to HCFD.
01/29/25 – TEI to deliver the labels to HCFD.
02/26/25 – TEI delivers Arch Flash Labels for Zone 4 sirens.
03/26/25 – TEI delivers SOSS for zone 5 sirens. TEI receives PO to start the Zone 5 package.
04/23/25 – TEI to start the arc flash study for zone 5 sirens.
06/25/25 – No updates this month.
07/30/25 – DEG receives available fault from Duke for Zone 5 sirens and modelling is in process.
08/27/25 – Modeling of all sirens in progress.
10/29/25 – Modeling complete. Pending MCB and CMI review.
12/10/25 – No updates
01/28/26 – HamCo requests SOSS for next zone (assuming Zone 6).
02/25/26 – DEG submits SOSS for Zone 6.
03/25/26 – DEG receives PO and signed SOSS for Zone 6. DEG gathering data from duke and developing model. Zone 5 arc flash stickers to HamCo Trades.
04/29/26 – DEG completes modeling of zone 6 sirens. On Barth’s desk for review and approval, and then send to CMI for approval prior to printing labels for trades.
05/27/26 – No updates.
06/23/26 – DEG reviews model with CMI (Charlie) and gets CMI approval of model. DEG prints all zone 6 labels and delivers to Trades Electricians.
07/29/26 – Project deliverables complete until next years zone 1 SOSS approved.
EMA – Tornado Sirens Arc Flash Study Read More »
PM = John Nester, Mike Barth
08/28/24 – ThermalTech submits SOSS for approval.
09/25/24 – TEI receives signed SOSS and PO. TEI contacts Bldg Mgr to schedule site eval (tentatively 9/30 or 10/1).
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – TEI develops drawings for County review.
02/26/25 – TEI develops permit documents and HCFD solicits quote from Glenwood (emergency on call electrician), Glenwood submits drawings for permit.
03/26/25 – Plan review complete and approved. Glenwood pulls electrical permit and to schedule install.
04/23/25 – Glenwood proceeding with the removal of the raceway and installation of the new conduit system. HCFD to notify TEI when complete and a punchlist visit will be conducted.
05/28/25 – Project completion pending punchlist.
06/25/25 – HCFD and TEI complete punchlist. No items identified on punchlist. Project complete.
Colerain – Animal Shelter Electrical Investigation Read More »
PM: John Nester, Mike Barth
05/29/24 – HCFD requests SOSS from TEI on 5/29/24.
06/26/24 – TEI submits SOSS. Project pending SOSS approval and PO.
07/24/24 – TEI receives signed SOSS and PO. Study in development in conjunction with the JC Study.
08/28/24 – TEI meets with vendors to discuss industry trends and current offerings. Report in development.
09/25/24 – TEI finalizing report to send to HCFD for review.
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – HCFD and TEI meet with HCSO to review draft report. Final report to be submitted.
01/29/25 – Final report to be submitted with the JC report. JC report pending 1 item.
02/26/25 – TEI sends final report. HCFD sends additional final comments. TEI to incorporate and resubmit final report.
04/23/25 – TEI receives budgetary numbers from suppliers for additional features. TEI finalizing report and to submit draft.
05/28/25 – TEI Submits finalized reports to HCFD.
06/25/25 – TEI submits final report. HCFD requests cost for engineering (not an official SOSS at this time)
07/30/25 – DEG submits estimated SOSS cost to HCFD for review.
08/27/25 – No updates. County has all closeout documents. Ready to Archive. Put study into Archive Room.
CH – JAX Door Control System PLC Study 2024 Read More »
PM: John Nester, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives approved SOSS and PO. Documents in Process. Trades will be doing this work, TE to send final dwgs in for review. It will permitted through City of Blue Ash.
07/24/24 – TEI sends drawings to HCFD for review.
08/28/24 – TEI obtains permit from Blue Ash. TEI delivers permit and approved drawings to Keith Otis. Electricians state that material procurement stage – once materials arrive – will get installed.
09/25/24 – HamCo Trades Electricians to notify TEI when they are ready for inspections.
10/30/24 – TEI coordinates breaker types with trades. TEI to arrange inspections when notified by trades.
12/11/24 – Inspections pending call from trades re completed installation.
01/29/25 – Inspections pending call from trades re completed installation.
02/26/25 – Trades calls TEI and are ready for inspections. TEI to schedule with trades and Blue Ash.
09/24/25 – DEG and trades meet with blue ash and has approved inspection. Blue ash did not have records for final inspections for re-circuiting work. that inspection is scheduled for 10/01
10/29/25 – Revised documents in plan review stage.
12/10/25 – Permit applied for – pending approval for final inspection.
01/28/26 – DEG follow up with the City of Blue Ash.
02/25/26 – DEG and trades gets final inspections. All inspections and work passed with City of Blue Ash. Project complete.
02/26/26 – Give County as-built drawings and archive the project.
Crime Lab – Emergency Power System Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives signed SOSS and PO for project. Study initiated and TEI is prepared to schedule meetings with the correct stake holders at the HCSO.
07/24/24 – TEI and HCFD discuss scheduling kick off meeting the week of 08/05.
08/28/24 – TEI meets with system suppliers to discuss latest industry trends and current offerings. Report is in development.
09/25/24 – TEI reviewing report and will send to HCFD for comments.
10/30/24 – TEI sends report to HCFD for review and comments.
12/11/24 – HCFD and TEI meet with HCSO to review report. HCSO asks if the Telecor cell intercom system is compatible with a new PLC. The PLC system will accommodate, TEI to investigate any potential modifications to the Telecor system that would be required and the potential cost implications, then the report will be finalized.
01/29/25 – TEI contacts ICS multiple times to get cost schedule implications. ICS not responding. Per Matt – we will issue the final report after 02/01/25 if no response from ICS by then.
02/26/25 – TEI submits final report to HCFD. HCFD sends additional comments to TEI to incorporate. TEI to resubmit upon completion of updates.
03/26/25 – TEI working with suppliers to get budget numbers for alternatives that were included.
04/23/25 – TEI receives budgetary numbers on 04/21/25 from suppliers. Final updates to be completed and returned to HCFD.
05/28/25 – TEI submits finalized reports to HCFD.
06/25/25 – Finalized reports are submitted. HCFD asks for an approx cost for engineering. Not an official SOSS at this point.
07/30/25 – DEG submits estimated design engineering costs to HCFD.
08/27/25 – No updates.
09/24/25 – No updates.
09/25/25 – OK to Archive.
JC – PLC System Replacement SD & Estimate Read More »
PM = Matt, Barth
04/24/24 – TEI submits SOSS for approval.
05/29/24 – Project Pending SOSS approval.
06/26/24 – TEI receives signed SOSS and PO. TEI has conversed with building manager re existing system and electrical needs.
07/24/24 – Project in progress.
08/28/24 – TEI to meet with building manager to discuss updated model and options.
09/25/24 – TEI meets on site with building manage and Matt Butz. A list of possible upgrades developed. TEI sends schematic dwg and costs to HCFD for review and direction.
10/30/24 – TEI issues project for bidding. Prebid meeting scheduled for 11/12/24 at 11:00 AM.
12/11/24 – Bids open at 11:00 AM on 12/12/24.
01/29/25 – No bids received. HCFD to advise if re-bid funds are available.
02/26/25 – No updates on rebid funding.
03/26/25 – No updates on rebid funding.
04/23/25 – No updates on rebid funding.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No updates on rebid funding.
08/27/25 – No updates on rebid funding
09/24/25 – Project pushed to 2026 project.
01/28/26 – DEG to submit SOSS for re-package and rebid for 2026 project.
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending approval of SOSS
04/29/26 – DEG receives signed SOSS and PO. Reaching out to bldg mgr to confirm scope.
05/27/26 – DEG meets with Ian Zellner – confirms scope. Finalizing drawings and OPC for HCFD review.
06/23/26 – DEG to submit 100% review set to HCFD by end of June.
07/29/26 – Per HCFD – Project on HOLD until further notice.
08/26/26 – DEG to update labels and apply then close out the project.
09/23/26 – No updates
10/28/26 – All labels have been applied to the gear on site. Project complete.
SPHQ – Arc Flash Remediation 2024 Read More »
PM: Matt/Trades, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – TEI develops Clifton (#81 W Nixon) drawings and submits plans to IBI for permitting. We will notify county trades once permit is approved.
06/26/24 – TEI secures permit for #81 West Nixon. HCFD to notify when the work is completed and ready for inspections.
07/24/24 – No updates this month.
08/28/24 – No new work this month.
09/25/24 – IBI inspection passes and EMA and Duke to connect power. Work on Siren #81 complete.
10/30/24 – No updates this month.
12/11/24 – Ben (EMA) sends Alex GPS coordinates for siren that needs to be permitted. TEI working on the permit documents.
01/29/25 – No Updates this month.
02/26/25 – No updates this month.
03/26/25 – No updates this month.
04/23/25 – Wes and Ben (EMA) coordinate location. Upon approval of location and connections by Duke, permit drawings will be issued.
05/28/25 – TEI finalizes permit drawings and submits to IBI for plan review.
06/25/25 – Plan review passed. Permit applied for on line. Ready to schedule work with trades.
07/30/25 – Permit was delivered to HCFD (Electricians). Inspection pending installation. DEG will call for inspection when notified that the siren has been installed by trades.
08/27/25 – IBI inspection occurred and passed on 08/27/25.
09/24/25 – No updates.
10/29/25 – No updates this month.
12/10/25 – No updates this month. Pending issues with existing poles. etc.
01/28/26 – No updates this month. Pending issues with existing poles. etc.
02/25/26 – No updates this month. Pending issues with existing poles. etc.
03/25/26 – No updates this month. Pending issues with existing poles. etc.
04/29/26 – No updates this month. Pending issues with existing poles. etc.
06/23/26 – No updates this month. Pending issues with existing poles. etc.
07/29/26 – No updates this month. Pending issues with existing poles. etc.
08/26/26 – EMA reaches out to Wes about possible relocation of pole in Wyoming (Chisholm Park).
09/23/26 – EMA and DEG are working on (2) siren locations for 2026, and (1) for 2027.
10/28/26 – (2) Sirens are in for QC review. Then will be issued for installation.
EMA – Tornado Sirens Gen Services 2024 Read More »
PM: Megan, Mike Barth, Mike Murphy
04/24/24 – TEI receives signed SOSS and PO.
5/29/24 – HCFD, TEI and Judge Jenkins Visits Montgomery County CH to see system in action. Champlin and TEI visit all courtrooms to develop plans and take measurements of existing benches for install locations of equipment.
06/26/24 – Weekly meetings are conducted every Wednesday afternoon. The most current EV equipment has been sent from BIS to the team. TEI has Design documents well developed and will be conducting a final walk thru of each of the courtrooms on 06/27/24 as soon as the docket clears.
07/24/24 – TEI will provide HCFD a final review set on 7/26/24. HCFD will review and get comments back to TEI by 8/2/24. Project to be issued for bidding on 8/7/24.
08/28/24 – Project has been issued for bidding. Prebid meeting was held on 08/23 – (2) bidders attended. Bid opening scheduled for 09/19.
09/25/24 – Received (1) bid from DK, (39% over budget). Rejected the bid, repackaged and re-issued for REBID. Rebid Prebid meeting scheduled for 10/18 and Bid opening on 11/06. TEI reaching out to area ECs by phone and notifying of bid opportunity.
10/30/24 – Final addendum issued on 10/30/24. Bid Opening 11/06/24 at 11:00 AM.
12/11/24 – Bids open. DK low bid. TEI vets the DK bid and sends letter or recommendation to HCFD. project pre-const meeting to occur upon contract approval.
01/29/25 – DK, HCMC, HCFD, BIS and TEI are in the pre-construction/procurement phase of the project. DK to provide project schedule.
02/26/25 – DK, HCFD, BIS, TEI and HCCPC have weekly meeting to update status and tracking.
03/26/25 – Work on CR 580 has started. Next CR’s were discussed at the meeting this week. BIS to ship the next 2 rooms equipment week of 4/10.
04/23/25 – Work continues in CR 580. End of this week DK to be ready for carpet install (HCFD covering carpet install). Floor slab xray scheduled for 04/26/25 (Saturday).
05/28/25 – BIS sends technician to CR 580 today for coordination with DK. All DK field issues/concerns addressed. Field visit to fire up the system on 05/30 at 1:00 PM.
06/25/25 – CR 580 complete, pending training on equipment and demo to other Judges.
07/30/25 – CR 580 training completed. CR 580 in use and DK is now working on CR 320. Tweaks are happening as the systems are being placed into service. Rycca asked if we should order the AV equipment and set it back in the Archive room and they can use them out of the boxes on the sixth floor. Punchlist scheduled for 8/5 at 3PM.
08/27/25 – Punchlist for room 580 completed. DEG issues the Punchlist to DK. Installation of BIS equipment installed this week.
09/24/25 – Finalizing CR320. Moving on to CR 380 next. At const meeting, it was discussed to ship all equipment as soon as ample storage space for 16 more rooms equipment. Arpa funds must all be spent by 12/31/2026.
10/29/25 – Programming installed in Room 320. Work starting in rooms 300 and 380.
12/10/25 – Work continues with CR 300 and 380. Punchlist scheduled for 12/10/25 cancelled due to court session running long.
01/28/26 – Project continues.at the meeting today discussed the next 2 rooms to be worked on (340 and 360). This will finish the CRs on the 3rd floor.
02/25/26 – Project continues. Work on 3rd floor progressing. Speakers swapped out in 580 and sound quality substantially improved. DK brings in “sound expert”, Leo Little form ICS, to evaluate rooms. Leo to provide quotation to DEG for sound engineering services.
03/25/26 – Electrician changes necessitated for the project. DK to update situation ASAP. finishing CR 330 and moving to 360 and 340 next.
04/29/26 – Work continues in Rooms 340 and 360. Walk for 485 and 496 scheduled for 5/5.
05/27/26 – work continues in room 340 and 360. Rooms 485 and 495 are next (waiting on floor boxes to be fabricated). Walking locations on the 5th floor 05/27/26.
06/23/26 – Sound Guy (Leo Little) models room 485 and returns proposed layout with the speakers that were purchased from BIS.
07/29/26 – Sound guy visits room 300, modelling the room. HC directs Leo to only use the bill of materials for the rooms, and to not give recommendations for improved sound quality with equipment not in the original BOM.
08/26/26 – Room 300 sound recommendations installed. Sound quality greatly improved. ICS states that next 2 rooms are scheduled to be sent today.
09/23/26 – Work continues on the installation. ICS completes all room sound models and recommendations. There are 2 rooms (320 and 380) that HCFD sent comments back to ICS for tweaks.
10/28/26 – All sound models received on all rooms. Punchlist walk occurred on 10/26/2026. Work starting on Jenkins CR on Monday 11/02.
CH – Common Pleas AV Upgrades Read More »
PM: Matt Butz, Mike Barth
04/24/24 = TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD to review.
07/24/2024 – HCFD moves location of NWS to 3rd floor data room. TEI updates the drawings.
08/28/24 – Project pending installation from DK.
10/30/24 – DK installs camera.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Finalizing binders.
06/25/25 – DK, DEG and HCFD to me re final closeout
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
A&D – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for review from HCFD.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Project pending completion of installation from DK.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
06/25/25 – DK, DEG and HCFD to meet re final closeout.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
230 – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to review scope of work and locations for equipment. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – project pending Historical society review of proposed mounting hardware and installation by DK.
12/11/24 – Historical Society approves installation. Project pending installation by DK.
01/29/25 – Project installation nearly complete. DK states that there is an Injector issue to resolve and project will be ready for punchlist.
02/26/25 – Project complete pending closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Project pending closeout.
04/23/25 – Project pending closeout docs from DK.
05/28/25 – Pending closeout documents.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
CH – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS ands PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Cameras installed last week. TEI and HCFD to schedule punchlist and review of camera views on the system.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
TPC – First Floor Lobby Cameras Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives approved SOSS and PO. Kick off meeting occurred on site on 04/23/24.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small, projects bid. Prebid meeting occurred. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received on project (2 bids Glenwood and DK), DK apparent low bidder. TEI vets the bid from DK.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for pre-construction meeting. Anticipated construction to start 11/11/24
12/11/24 – DK states that the installation of the system in the JAX area is approx 90% complete.
02/26/25 – Project complete pending punchlist and closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Pending closeout.
04/23/25 – Project pending closeout.
05/28/25 – Project pending closeout.
07/31/25 – OK to Archive, send final bill.
CH – JAX Camera Upgrades Read More »
PM: John Nester, Mike Barth
02/29/24 – Bradley Bedacht contacted TE for new project. Project added to website.
03/27/24 – HamCo requests SOSS for Study of existing system and requested upgrades.
04/24/24 – TEI submits SOSS. JN and TEI discuss scope and HCFD to confirm total scope.
05/29/24 – TEI and JN to confirm scope.
05/30/24 – This project returned to the Courts for their coverage. We can archive this job.
PM: John Nester, Mike Barth
02/29/24 – Project created for tracking. MCB says we have all we need.
03/27/24 – Project docs to be sent to JN ASAP.
04/24/24 – BW and TEI review ODOT documents and submit what we can. Balance of data required from tenant.
05/29/24 – Project pending data from tenant.
06/26/24 – Project pending data from tenant.
07/24/24 – Project pending data from tenant.
08/28/24 – TEI and HCFD develop a package to send to ODOT for review and commentary including bid documents, project manual and OPC. Package sent to ODOT on 08/28/24.
09/25/24 – Project pending ODOT approval.
10/30/24 – Pending ODOT approval
12/11/24 – No Updates from ODOT.
01/29/25 – No updates from ODOT.
02/26/25 – No Updates from ODOT.
04/23/25 – Received Stage 3 approval from ODOT. HCFD investigating funding gap from the grant and the updated costs. Then notify TEI on next steps.
05/28/25 – Next steps to be coordinated with HCFD.
06/25/25 – TEI sends updated opinion of probable cost to HCFD for county to discuss grant funding/cost differential.
07/30/25 – No Updates
10/29/25 – DEG receives email from HCFD that this project is cancelled. OK to Archive.
Comm Center – EV Charging Project Read More »
PM: John Nester, Mike Barth
02/28/24 – HCFD requests SOSS for project.
03/27/24 – Project designed, permitted, and installed. IBI inspection passed on 03/27/24. EMA Calling Duke to Energize the Siren.
04/24/24 – TEI has received no updates on this siren.
05/29/24 – TEI has received no updates on this siren. This project can be archived.
EMA – Siren #607 Relocation Read More »
PM: John Nester, Mike Barth
12/06/23 – TEI receives approved SOSS and PO. COA to provide TEI with locations of cameras that were discussed with vendor.
01/30/24 – TEI to receive the locations and document on documents.
02/28/24 – TEI will document locations upon receipt.
03/27/24 – TEI, HCFD and DK meet, document locations, and develop drawing. Meeting with all team on 03/26/24 to review and finalize.
04/24/24 – Installation pending material procurement.
05/29/24 – Completion of this project pending punchlist once TEI notified all install work is complete.
06/26/24 – Cameras are installed and the users are working on getting the monitoring functioning (instructions from installer (DK) via email), and Matt Butz helped with Valerus integration to allow end users to utilize the system.
07/24/24 – TEI and HCFD perform punchlist on the project. Tenant confirms views are as desired.
08/28/24 – Project complete pending closeout documents.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
230 – COA Camera System Upgrade 2023 Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI receives signed SOSS. Design kickoff to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to kick off project. Locations and desired coverages discussed. TEI can develop documents based on meeting on 01/30. Roof camera replacements are first priority.
02/28/24 – TEI developing plans based on meeting. Will coordinate the issuances with HCFD.
03/27/24 – Drawings to be completed in April/May.
04/24/24 – Drawings in process.
05/29/24 – No updates
06/26/24 – TEI hand delivers drawings to HCFD for review.
08/28/24 – Project complete pending closeout documents.
12/12/24 – OK to Archive.
JC – Exterior Camera System Upgrade 2023 Part II Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Design Kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to discuss project objectives and kick off project on 01/30. Options and existing conditions were discussed. Card reader to be connected to the VAX system in the building managed by Risk Management. Door across the hall from Lincoln Base to be added to access control system as an alternate.
02/28/24 – TEI developing plans for this project. Based on kick off meeting for Council Rooms – the VAX controller may be upsized to accommodate additional doors that are desired to be on VAX system.
03/27/24 – TEI Proceeding with documents. Upon VAX confirmation, will complete documents.
04/24/24 – Documents in progress. Review set to be sent to HCFD upon completion.
05/29/24 – no updates.
06/26/24 – Documents near complete. TEI will send HCFD review set in next couple of weeks.
07/24/24 – TEI to deliver review set by end of week of 8/5/24.
08/28/24 – TEI sends documents to HCFD for review. Will issue bid package once review comments received and included in documents.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Documents sent to DK for GSA Pricing.
02/26/25 – DK sends GSA pricing for project to HCFD and TEI. Project pending contract.
03/26/25 – Pending contract approval.
04/23/25 – Pending contract approval.
05/28/25 – Project in contract phase.
06/25/25 – DK, DEG and HCFD have construction KO meeting. Construction to commence approx 06/27.
07/30/25 – DEG reaches out to DK for installation update.
08/27/25 – All equipment installation nearly complete.
09/24/25 – Base bid work complete. Pending CO work (added door).
12/10/25 – Change order issued for additional work. Pending procurement and installation of additional devices.
01/28/26 – Project pending the completion of the CO work.
02/25/26 – No update
03/25/26 – no update.
06/23/26 – Project closeout and final pay apps requested from DK.
07/29/26 – DEG follows up with DK for Closeouts.
08/26/26 – no updates
09/23/26 – Grant extended. Additional security measures drawing by DEG and priced by DK.
10/28/26 – Installation of additional items in progress.
JC – Server Room Access Control Upgrades 2023 Read More »
PM = Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Project kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet on 01/30 to discuss project objectives and kick off the project. Network switches for the Kiosks and Camera systems shall be put in a lockable rack that will prevent local CO’s from tampering with them. The outlets that serve the overhead rack and the floor mounted Telecor Intercom racks will have lockable covers over them such that they can not be unplugged.
02/28/24 – Project is ongoing.
03/27/24 – Project is ongoing with documentation.
04/24/24 – Review set to be sent to HCFD upon completion.
05/29/24 – no updates
06/26/24 – TEI selects lockable racks. TEI recommends racks with solid doors (versus glass doors), but the glass doors are slightly less costly. ($100-$150 per rack).
07/24/24 – TEI to deliver review set to HCFD end of week of 08/05.
08/28/24 – TEI submits documents to HCFD for review and comments. Project will be issued for bidding upon receipt of comments.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Small projects bid to be issued on 01/31/25
02/26/25 – Project in bidding phase.
03/26/25 – Received (2) bids. Dunn Electric and DK. Dunn apparent low bidder. TEI vets Dunn bid.
04/23/25 – Project in contract phase with prosecutors office.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase.
07/30/25 – Const KO to be scheduled with Dunn and HCFD.
08/27/25 – HCFD, HCSO and DEG have const kick off with Dunn Electric. Materials roughly a month out.
09/24/25 – DEG approves submittals. Dunn Electric orders equipment. Dunn sends an email to DEG re equipment cost increase from bid time.
12/10/25 – All LC racks are installed, except G22. Ceiling by rack needs to be raised for the proper NEC clearances for the existing solenoid panels.
01/28/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
02/25/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
03/25/26 – Triton on site moving ceiling 03/25. Dunn to install new enclosed rack upon completion of ceiling work.
04/29/26 – All work completed. Punchlist completed. Contractor to submit closeouts.
07/29/26 – Project in closeout. DEG discusses with EC closeout docs needed.
08/26/26 – no updates.
09/23/26 – Project complete – pending closeouts.
JC – LC Server Rack Upgrades 2023 Read More »
PM: Matt Butz, Mike Barth
02/28/24 – TEI, HCJC, and HCFD meet on site to discuss the project objectives and locations where coverage is needed. Review set to be sent to HCFD on 3/1/24.
02/29/24 – Jaime will get Mike a set of review drawings EOD today, sent to Matt tomorrow hopefully.
03/27/24 – Documents completed and Dent to HCFD. Meeting with Juv Ct, HCFD, Telecom, and Jason/Todd on site to review and adjust. Documents completed for installation.
04/24/24 – installation pending material procurement.
05/29/24 – TEI has received no updates. BW asked if O’Rourke has provided any of county paperwork yet? Answer, no.
06/26/24 – DK arrives on site to begin installation. Installation ongoing. Risk Mgmt has decided that the NVR will be located on the downtown campus and feed will come back downtown.
07/24/24 – HCFD and TEI to perform punchlist pending HCFD availability.
10/31/24 – Need change order to relocate NVR to Security Bldg.
12/11/24 – Punchlist issued and DK sends back signed completed punchlist.
02/26/25 – project complete pending final closeouts.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.
Hillcrest – Door Access and Camera System Upgrades Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI issues SOSS.
01/30/24 – TEI receives signed SOSS and PO. Project documents to proceed.
02/28/24 – Project is ongoing
03/27/24 – On site investigation and kick off meeting with DK occurred on 03/26/24
04/24/24 – Review set will be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD review.
07/24/24 – Construction completed. HCFD and TEI completed punchlist walk.
08/28/24 – Project pending closeout documents.
12/11/24 – No Updates
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – Archive.
230 – Access Control System Upgrades 2023 Read More »
PM: John Nester, Mike Barth
12/06/23 – TEI submits SOSS.
01/30/24 – TEI receives signed SOSS and PO. Project to Proceed.
02/28/24 – TEI and HCFD discuss project schedule based upon system needs (existing system failures and parts unavailability). TEI commits to getting project upon MCB return from medical issues.
03/27/24 – Project in the works. TEI Submits SOSS for Small Projects bid for installation costs
04/24/24 – Project documents in progress. review set to be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small bids project bidding. Prebid meeting conducted. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received opened for project (2 bids, Glenwood and DK). DK apparent low bid. TEI vets bid on 08/28/24.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for preconstruction meeting. Anticipated start date at completion of Jax cameras (Mid December)
12/11/24 – Construction to commence upon completion of the JAX camera Project.
01/29/25 – Project construction kick off occurred on 01/28/25. Construction to commence upon receipt of people to integrate into the system and access levels from Risk Mgmt.
02/26/25 – Construction ongoing on this project.
03/26/25 – Construction complete. HCFD and TEI perform punchlist.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – No updates.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.
TPC – Access Control System Upgrades 2023 Read More »
PM: Rycca, Barth
07/27/23 – County requested SOSS for this project.
08/24/23 – TEI submits SOSS. Project pending SOSS approval.
09/26/23 – Project Pending SOSS Approval.
10/26/23 – Project pending SOSS Approval.
12/06/23 – Project pending SOSS Approval.
01/30/24 – TEI receives signed SOSS and PO. Project proceeding with Documents.
02/24/28 – No updates on this project this month.
03/27/24 – Project waiting on direction from HCFD.
04/24/24 – Project pending direction from HCFD.
05/29/24 – No updates.
06/26/24 – No Updates.
07/24/24 – No Updates.
01/30/25 – Ok to Archive this project.
A&D – Digital Clocks Read More »
PM: John Nester, Mike Barth
03/29/23 – TEI Submits SOSS. Project pending approval of SOSS and PO.
04/27/23 – TEI receives PO and Signed SOSS. TEI finalizing drawings for HCFD review and then will get permits for installation by trades.
05/23/23 – TEI sends review set to HCFD. Will apply for IBI permit upon receipt/implementation of owner’s review comments.
06/28/23 – TEI meets with John Nester, Andrea Hatton, In Zelner and the HC Electricians to review. Minor changes were made and the drawings were submitted to Blue Ash for plan review and permit. Plan review passed and permit is ready for pick up at Blue Ash with a balance of $50 +change. TEI to pick up permit for HC and work can commence.
7/26/23 – TEI picks up permit and delivers to trades. Trades is working on the modifications to the branch circuits.
08/24/23 – Trades to notify TEI when work is completed and TEI will arrange for inspections.
09/26/23 – County electricians reach out to TEI for review of as-built documents. Tentative meeting the week of 10/02.
10/26/23 – TEI and county electricians meet to review as-built documents. TEI incorporates the as-builts onto the CAD files. TEI drawings will be sent to HCFD upon completion of QC review.
12/06/23 – HamCo electricians indicate that there are a few more changes that the facility is wanting to make. Electricians to get modifications to TEI to incorporate in the AS-builts.
01/30/24 -The Sally Port Doors were moved to EM power. Electricians Told TEI circuitry information to include on as-builts.
02/28/24 – TEI updating permit drawings and will submit to Blue Ash for engineering review and final final inspections.
07/24/24 – REFERENCE OTHER STRING FOR UPDATES.
Crime Lab – Emergency Power Upgrades Read More »
PM: Rycca Thacker, Mike Barth
03/29/23 – TEI submits SOSS for project. Project pending Approval and PO.
03/30/23 – SOSS and PO approved, RT will send.
04/27/23 – TEI starting field work and will develop SD/Cost estimates.
05/23/23 – TEI meeting building manager and HCFD to provide field investigation. TEI evaluates (2) options – direct MCC replacement and replacing with PDP since the motors are served with VFDs now. TEI submits SD PDFs and costs for the work. HCFD to provide next steps.
09/26/23 – TEI submits design drawings to HCFD for review. TEI receives review comments. Drawings finalized.
10/26/23 – Upon determination of XBE requirements, this project will be issued as a small projects bid.
12/06/23 – Project issued for small projects bid. Prebid conducted and Addendum published. Bids due to TEI on Friday 12/08/23 at 4:00 PM.
01/30/24 – Project bids received and vetted. Project in contract approval phase. lead time for equipment will be roughly 12 weeks.
02/28/24 – Glenwood electric is sent the PO and signed contract. Submittals yet to be received/approved by TEI.
03/27/24 – TEI receives submittals and approves. Equipment is being procured.
04/24/24 – Construction kickoff scheduled for 4/29.
05/29/24 – Construction kickoff meeting occurred. Glenwood orders electrical equipment (Scheduled ship date = 11/20/24)
06/26/24 – No Updates.
07/24/24 – No Updates.
08/28/24 – No Updates.
12/11/24 – HCFD, TEI and Glenwood meet on site for Pre-construction meeting. Panel in Glenwood shop – Enclosure no with Panel. Glenwood looking at early January for installation.
01/29/25 – HCFD requests installation schedule form Glenwood.
02/26/25 – Installation to begin in next week or so.
04/23/25 – Project installed, complete and punchlist completed. Pending punchlist and closeout.
05/28/25 – Pending closeout documents.
06/25/25 – TEI approves closeout documents. Project completion pending delivery of binders.
07/30/25 – TEI reaches out to Glenwood for binders.
07/31/25 – OK to Archive, all done.
A&D – Chiller Room MCC Replacement Read More »
PM: Matt Butz, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – TEI receives signed SOSS and PO. Project Kick off to be scheduled with HCFD.
03/29/23 = TEI and HCFD to schedule project kick off.
04/27/23 – TEI performs preliminary review of existing model. TEI and HCFD to meet to discus next steps.
05/23/23 – TEI and HCFD to set up meeting to discuss next steps. Proposed time of 9:00 AM on 6/2/23.
06/28/23 – June 2 meeting did not occur. TEI requested availably from building manager.
7/26/23 – TEI, Matt Butz and building manager meet to discuss building electrical issues. biggest issue is with breakers for floor machines tripping regularly. TEI looking for ways to mitigate this issue.
08/24/23 – TEI determines that there are 2 options for moving forward. The existing gear has built in transformers in the panels. The cost to replace the is approximately 2 times the cost of sperate equipment. The transformers are at the end of the manufacturers standard life expectancy. The transformers are not problematic at this time. An option would be to install sub panels and pick up the added circuits from them and address the transformers as they become an issue.
09/26/23 – TEI developed drawings with the sub-panel option. Review drawings to be sent to HCFD by 09/29.
10/26/23 – TEI issues project for bids. Prebid meeting for project occurred on 10/25/23. Bids scheduled to open on 11/22.
12/06/23 – Bids received and Stem Electric is apparent low bidder. TEI vets the bid and sends recommendation letter. Contracts at prosecutors office for approval.
01/30/24 – Project waiting BOCC approval.
02/28/24 – Stem Electric receives signed contract and PO. Preconstruction kick off to be scheduled in next 2 weeks and TEI awaiting submittals.
03/27/24 – Pre construction meeting scheduled for 04/15/24
04/24/24 – Preconstruction meeting occurred. Project pending material procurement.
05/29/24 – Stem electric has mobilized to project site and construction has commenced. working on floor to floor core drills and initial installation .
06/26/24 – Stem mobilized on site and work in progress. Vertical raceways installed through buildings. Wiring to begin with anticipated completion of installation end of July.
07/24/24 – Stem anticipates completion of base bid work by 08/02/2024. HCFD asked for CO pricing to add electric for equipment per the request of the HCSO.
08/28/24 – Stem complete with work pending closeout documents. TEI to print out new Arc Flash Labels and label the building.
09/25/24 – Waiting on Closeouts from Stem.
10/30/24 – Project completion pending closeouts from STEM. TEI provides new AF labels in both towers.
12/11/24 – TEI delivers (3) copies of Arc Flash report to HCFD with tables and single lines in the report.
02/26/25 – Project complete pending closeout.
03/26/25 – Project complete pending circuit breaker that was ordered with allowance $$. Can not close until breaker is delivered.
04/23/25 – Project waiting on breaker delivery.
05/28/25 – Project back punchlist walk scheduled for 5/30.
06/25/25 – Project backpunch completed. Stem completes items and sends pics to TEI and HCFD of completed items. Pending Closeout documents.
07/30/25 – Closeout documents submitted and provided to HCFD. (3) hard copies and (3) Thumb drives.
08/28/25 – Ready to Archive.
JC – Arc Flash Mitigation 2023 Read More »
PM: Matt, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – Project pending SOSS approval and PO.
03/29/23 – TEI receives signed SOSS and PO. Project kickoff to be scheduled with TEI and HCFD.
04/27/23 – TEI performs preliminary review of existing model. TEI and HCFD to meet to discuss next steps.
05/23/23 – TEI to set up meeting with HCFD to discuss next steps. Proposed time of 9:00 AM, on 6/8.
06/08/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
07/26/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
08/24/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC
09/26/23 – TEI develops drawings and submits to HCFD for review.
10/26/23 – TEI issues project for bids. Prebid meeting occurred on 10/25/23. Bids are scheduled to open on 11/22.
12/06/23 – Bids received and opened on schedule. Stem Electrical is apparent low bid. TEI vets bid and submits letter of recommendation. Contracts are at prosecutors office for approval.
01/30/24 – Project awaiting BOCC approval
02/28/24 – Stem Electric receives signed contract and PO. Preconstruction meeting to be scheduled in the next couple of weeks.
03/27/24 – Pre-construction meeting scheduled for 04/15/24
04/24/24 – Pre construction meeting occurred. submittals receieved , and approved. Project pending procurement of materials (approx 12 month ship date). Stem electric to confirm shipping schedule.
05/29/24 – Project pending material procurement. TEI requests Stem Electric to send in Ship date.
06/26/24 – No Updates. Project pending material procurement.
07/24/24 – No Updates.
08/28/24 – No Updates, project pending procurement of materials.
09/25/24 – Project pending material procurement.
12/11/24 – Project installation pending material delivery.
02/26/25 – Project installation pending material delivery.
04/23/25 – Project installation pending material delivery.
05/28/25 – No updates.
05/25/25 – No updates.
07/30/25 – Stem electric and DEG and HCFD meet to KO project. Gear has arrived and DEG certifies at Crane yard.
08/27/25 – Stem to begin the construction phase of this in first week or two of September.
09/24/25 – Gear is rigged into place. Outage/tie in to be coordinated.
10/30/25 – MCB to call Stem to schedule a shutdown meeting.
12/10/25 – DEG to follow up with Stem again to schedule the shutdown.
01/28/26 – Stem ready for the outage. John Nester requested pricing on refurbish breaker in the main gear. Stem is sending email of availability to DEG for meeting to discuss/schedule outages.
02/25/26 – Stem to send in proposed schedule and timelines.
02/25/26 – Stem sends in multiple proposed dates in May for tie in schedule. DEG, HCFD, Tech Svrcs, and Juv Courts to meet to discuss outage plans and select date.
04/29/26 – DEG and HCFD meet with all building tenants and discusses power outage plans. Tentative dates for outages are 5/30 for the 2nd floor and 6/19 for the sub-basement gear.
05/27/26 – 5/30 outage cancelled due to the contractor not having BGC staff. 6/19 outage still on the schedule.
06/23/26 – Second floor switch tied in on 06/19. TJW Electric provided staff that had current BGC and badge to perform the work. Basement level work to be scheduled.
07/29/26 – DEG has a virtual meeting with HCFD and Stem Electric. A list of possible Saturdays was emailed to HCFD and Stem to coordinate the next outage. HCFD to confirm the procurement of bad breaker for the distribution panel serving the computer room to be replaced by trades during the outage.
08/26/26 – HCFD states that the replacement breaker has been purchased by trades. Stem has confirmed 09/26/26 date with ESI, still pending confirmation from TJW. DEG states lets work towards making outage #2 happen on 09/26/26 so not to delay other projects. Stem to confirm with TJW and finalize the date.
09/23/26 – 9/26 date was postponed due to staffing issues with Stem Electric. New Date is 11/11/26 – starting at 07:00 AM. Pre-outage conference call scheduled for 10/28/2026.
10/28/26 – Outage is scheduled for 11/11/26. Meeting held with courts, HCSO and HCFD to discuss outage on 10/28/26.
800 – Arc Flash Mitigation 2023 Read More »
PM = Rycca Thacker, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO. Project kickoff to occur and work to be completed.
04/27/23 – TEI to submit review set to HCFD by 05/03/23
05/23/23 – TEI submits drawings to HCFD for review. TEI receives comments from HCFD. TEI to update the drawings from the comments and develop bidding documents.
06/28/23 – TEI and HCFD PM finalized small projects bid package and issues to selected XBE companies for bidding. Bids due back to TEI on 07/13/23.
07/26/23 – TEI invites 8 XBE and 1 non-XBE bidders to give costs on project. Recieved (1) bid. bids came in higher than expected. TEI sends bid information to project manager and waiting for further decisions.
8/24/23 – TEI vets bid from Glenwood electric, and makes recommendations to HCFD. Project pending contract approval.
09/26/23 – TEI approves submittals. Installation pending product procurement.
10/26/23 – Glenwood electric has equipment ordered and scheduled to ship beginning of November. Upon receipt of all materials, installation will be schedules.
12/06/23 – Glenwood working on install schedule.
01/30/24 – Project install complete. TEI and HCFD perform punchlist. Upon completion of all punchlist items, and receipt of closeout documents, project will be complete.
02/28/24 – The Original bid portion of the project punchlisted. CO work waiting on material procurement and scheduled install date.
03/27/24 – The Air Curtian Fan is installed. Final punch items be completed this week. Then project can be closed.
A&D – South Entrance Access Control Read More »
PM: Matt Butz, Mike Barth
01/25/23 – TEI submits SOSS. Project Pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO. DK to procure equipment and project in commencement phase.
03/29/23 – DK has initiated the installation. TEI and HCFD to provide punchlist upon Notice of substantial completion.
04/27/23 – DK working on project. Const progress meeting scheduled for 05/03/23.
05/23/23 – TEI, DK, HCSO and HCFD provide punchlist. TEI documents locations of cameras and network switches for record drawings. TEI to submit the record drawing to HCFD upon completion.
06/28/23 – upon receipt of all close out documentation from DK, project will be closed out.
10/26/23 – TEI reached out to DK (Electrical division at DK under major changes – several EEs have transitioned out of DK) for final closeout documents so project can be closed and archived.
12/06/23 – TEI to document the as-built conditions for this project with the Exterior Camera project II.
02/29/24 – Ready to archive.
JC – Exterior Camera System Upgrade Read More »
PM: John Nester, Mike Barth
12/15/22 – ThermalTech submitted SOSS and it’s approved. TEI to schedule fieldwork next week.
01/06/23 – TEI met Ian on site for kickoff meeting. MCB, Alex, TTC onsite to review.
01/25/23 – Bert said to concentrate on immediate needs first.
02/23/23 – TEI submits immediate needs draft report to HCFD.
03/29/23 – TEI to develop schedule for Phase II of report. TEI submits SOSS for implementation of Phase I study results.
04/27/23 – See Emergency Power upgrades for Phase 1 updates. TEI and HCFD to develop schedule for phase 2 study.
10/26/23 – TEI and HCFD develop schedule (preliminary with options focusing on emergency heat in winter) to be sent to Bert on 10/27/23, and final draft sent to Bert on 11/10/23
Crime Lab – Emergency Power Study Read More »
PM = Matt Butz, Mike Barth
09/26/22 – HCFD requests SOSS for the Project. TEI Submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project. TEI meets with Matt Butz to discuss project. Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing in design. Will schedule a 75% design review with HCFD and 2020 staff after the holiday break.
01/25/23 – TEI, HCFD and HCJC meet to review project design. TEI schedules working “Mock up” with Vicon rep on 02/01/23 so the staff at 2020 can see the views that will be provided with new system. Design will be finalized after Mock up meeting.
02/23/23 – TEI, HCFD and HCJC meet with rep for mock up. Camera types selected. TEI has documents 90+% complete for issuance. All new camera locations have the view area inserted on plans. Upon final review with HCJC, Project will be issued for ITB.
03/29/23 – Project will be sent to purchasing on 03/31/23 for a 04/03/23 Out to bid issuance. Prebid meeting is scheduled for 04/20/23 at 2:00 PM. Bids will be due on 05/04/23.
04/27/23 – Project in bidding phase. Prebid meeting was 04/20/23. Well attended prebid. Addendum 1 already issued. Addendum 2 to be issued 04/28/23.
05/23/23 – Bids received for project. (2) bids, DK and Glenwood. Glenwood Electric Apparent low bidder. TEI vets the bid, and recommends contract with Glenwood. Project is in contract approval phase. Upon contract approval and PO issuance, the project construction can commence.
06/28/23 – Project was approved at the BOCC meeting on June 15. Glenwood recieves PO and is now working on submittals for approval. Upon submittal approval, construction schedule will be developed and mobilization will be scheduled pending product procurement.
07/26/23 – Project construction kickoff meeting to be scheduled week of 8/7. Construction schedule to be issued from Glenwood at kickoff meeting.
08/24/23 – Glenwood electric scheduled to mobilize to project site on 8/28/23. Construction to commence.
09/26/23 – Construction commenced on project. Multiple meetings with IT to discuss the network configuration. Glenwood continuing installation of backbone of system.
10/26/23 – Construction under way. 4th Floor New Cameras are installed, as well as POD 203. Juv Crt IT has not confirmed Network architecture. Meeting schedule for 10/30/23 with all parties to finalize decision.
12/06/23 – Construction ongoing. Network architecture finalized and programmed. Glenwood has been working in non-housing areas first so that building staff can learn and get used to new VMS system.
01/31/24 – Working on floors. They have a computer in the room and are working on parallel system now, testing on two systems including the Valerus system for training.
02/28/24 – Construction continues on project. Training occurred on 02/28/24 on site with building staff. Ready to work on the PODs and move the residents.
03/27/24 – Work continues. Most of exterior cameras switched over. Close to working on 3rd floor (final housing units). Anticipated completion in next 30-60 days.
04/24/24 – Project nearing completion of original scope. CO cameras being installed.
05/29/24 – Glenwood has a hand full of interior cameras that remain to be installed, and then a few on the exterior.
06/26/24 – Glenwood ready for punchlist on all remaining areas. All main project cameras installed. CO cameras being installed. Demo complete and painted. Encoders being removed now.
07/24/24 – TEI and HCFD to finalize punch and issues on site in August.
08/28/24 – Glenwood has Cornerstone update the PLC system on site with new cameras to endure call ups are correct and working. TEI and HCFD will perform final walk thru once notified by Glenwood that everything complete.
09/25/24 – No Updates. Glenwood and Cornerstone working on scheduling modifications to the PLC.
12/11/24 – Glenwood notifies HCFD and TEI that PLC integration is complete. TEI and HCFD to perform final punchlist.
01/29/25 – Final punchlist completed and issued. Project complete pending closeouts.
02/26/25 – Project complete pending closeout.
04/23/25 – Project complete pending closeout.
05/28/25 – No updates.
05/29/25 – Barth has redlines, updating as-built drawings
06/25/25 – Record drawings complete. Project ready to close out.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
2020 – Security Camera System Upgrade Read More »
PM: Matt Butz, Mike Barth, Ken Orloff
09/26/22 – HCFD requests SOSS for project. TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project. TEI meets with Matt Butz to discuss project. Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design. Coordinating with Vendors and developing solutions to present to HCFD upon receipt of data from suppliers.
01/25/23 – TEI in receipt of product data from manufacturers. TEi meeting with rigging company on 02/01/23 to review scope of removing the egens and installing new in existing locations, and determine if any additional modifications are required to move the equipment in/out of the building.
02/23/23 – TEI meets with Rigging company, equipment vendors, and THP on site to confirm constructability of design. Design documents are progressing to a point where a review set will be sent to HCFD.
03/29/23 – TEI finalizing the coordination with multiple vendors for the equipment associated with this project. 80% complete project review meeting to be scheduled with HCFD.
04/27/23 – TEI has project ready to meet with HCFD and discuss final design direction. Meeting to be scheduled first week of May.
05/16/23 – TEI and THP discussed increasing scope of work for this project. Adding CMU partition walls and second means of egress in the existing gears rooms in both north and south buildings.
05/17/23 – TEI and THP met onsite to review the existing conditions at gears rooms in both the north and south buildings.
05/23/23 – TEI working on code required upgrades for this project. We are coordinating with IBI and THP on the redesign.
06/14/23 – THP sent Owner Review documents to ThermalTech.
06/28/23 – TEI submits review set of bid package to HCFD PM for review. TEI and PM review comments on 06/28/23. TEI to incorporate the review comments and develop final bid package for issuance after the 4th of July holiday.
07/10/23 – THP waiting to hear back from ThermalTech about Owner Review Comments, ITB #, and bid date in order to issue bid set.
07/26/23 – TEI holds issuance for updated XBE ITB package information. TEI to develop spreadsheet and work thru issuing with XBE requirements .
08/23/23 – THP has not heard any update on this project.
08/24/23 – TEI issues XBE package and gets approval. TEI finalizing project manual for HCFDF review and project issuance.
08/31/23 – Go ahead and get pre bid coordinated and final XBE items. Get out for bid.
09/27/23 – THP – Project tentatively out to bid on October 4th.
09/26/23 – TEI submits project manual to HCFD for final approval. will issue for bidding once manual is approved.
10/04/23 – Project advertised to bid.
10/18/23 – Pre-bid meeting occurred at the Justice Center.
10/26/23 – TEI issues project for bidding. Prebid meeting occurred on 10/18/23. Bids are scheduled to open on 11/09.
11/02/23 – Addendum #1 issued.
11/22/23 – Bid Opening.
12/06/23 – (1) bid received, in awardable budget range, but DEI determined XBE submission was not in accordance with requirements and recommended for rejection. Pending BOCC decision.
01/31/24 – No new updates from THP.
02/28/24 – THP no new updates from THP.
02/28/24 – Project to be re-bid with the fuel tank work bid as a separate project.
03/27/24 – TEI repackages project and will send to HCFD in next 2 weeks for review prior to ITB.
04/24/24 – No new updates from THP.
04/24/24 – TEI sends HCFD re-packaged documents for review. Upon receipt of review comments, and approval of GSWS from DEI – project to be re-issued.
05/13/24 – THP sent updated drawings and specs to ThermalTech for rebid on 05/15/24.
05/29/24 – Project issued for rebid. Project prebid meeting occurred on 05/29/24. Bids Due on 07/11/24.
06/26/24 – Project bidding.
07/24/24 – Project bid opening on 07/24/24. NO BIDS received. TEI contacts electricals to see why no bids.
08/29/24 – No new updates from THP.
08/28/24 – No Updates.
09/25/24 – No Updates.
09/26/24 – No new updates from THP. County requested new SOSS and include the underground tank with the scope again as an Alternate. Bring Terracon in for the Geotech in this SOSS.
12/11/24 – TEI submits SOSS and receives signed SOSS and PO for re-bid. Project to be re-packaged for re-bid starting in January.
01/29/25 – TEI repackaging the documents – send to Purchasing on on 2/10, available for bidding 2/11.
01/30/25 – Ready to Archive, start new Project file.
JC – Emergency Power System Replacement Read More »
PM: Matt Butz, Mike Barth
09/26/22 – HCFD requests SOSS for Upgrading the Hydraulic Elevators at the TPC. TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project. TEI meets with Matt Butz to discuss project. Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design. Working towards submitting owner review set to HCFD on or before 12/23/22.
01/25/23 – TEI issues project for bidding. Prebid Meeting scheduled for 02/09/23. Bids scheduled to open on 02/22/23.
02/23/23 – a single bid was received (graybach) and it was double the advertised estimate (nearly triple the cost bid 6 months ago as an alternate to the original elevator project). Bids were rejected.
03/29/23 – Project pending revised scope and/or revised budget discussions with HCFD.
04/27/23 – Project pending revised scope and/or revised budget discussions with HCFD.
05/23/23 – project has been re-designed with the scope of base bid being the aesthetic upgrades to match the traction elevators, and the mechanicals of the upgrades being bid as alternates. TEI sends drawing to HCFD for review. HCFD to update the AIA’s, and TEI to send project manual for final review. By June 1, issue dates, and ITB to be received from purchasing and project to be re-issued for re-bid.
06/28/23 – Project issued for bidding. Prebid meeting scheduled for 07/06/23 and bids are due on 07/19/23.
07/26/23 – Project bids received. (2) awardable bidders submitted bids (Alpha Const and Graybach). Alpha was apparent low bid, had clerical errors in bid and submitted a retraction letter for retract bid. TEI and Champlin vetted the Graybach bid and are recommending acceptance of the Graybach bid.
08/24/23 – Project in submittal phase and product procurement phase.
09/26/23 – BOCC approves project. Project to commence upon PO and kickoff with Graybach.
10/26/23 – project is in submittal approval phase. Once all submittals are approved, equipment will be procured. Upon receipt of equipment, installation schedule will be developed.
12/06/23 – All submittals have been returned. equipment in procurement phase.
01/30/24 – First Hydro unit (elevator #5) scheduled to begin the refresh work in mid February. To allow new Traction to be run (open to public) for 4-5 weeks prior to taking the second traction out of service for modernization.
02/28/24 – Schedule of elevator #5 pushed until after the second tractor elevator is completed. Materials received at American elevator, and ThermalTech to certify materials upon confirmation that Graybach and American have confirmed that the materials are the correct equipment.
03/27/24 – TEI certifies material. HCFD requests CO pricing for additional scope. Graybach pricing up the changes.
04/24/24 – Project progressing. Schedule pending inspections of Elev #2
05/29/24 – Hydro units scheduled to start Modernization upon completion of Freight elevator (approx Beginning of Aug)
06/26/24 – No Updates.
07/24/24 – The first Hydro elevator to be taken out of service for the modernization in next week or two (pending no issues with Freight Elevator inspections.
08/28/24 – Elevator #5 out of service being worked on. Graybach indicates that they are on schedule.
09/25/24 – Elevator #5 passes elevator inspection. Generator test completed during building power outage for switchgear cleaning.
10/30/24 – Final elevator nearly complete. Graybach requesting punchlist mid week of 11/04.
12/11/24 – Fianl elevator inspection passed and complete. Punchlist complete. Project pending final closeout documents.
01/29/25 – Graybach sends closeout docs to TEI for review. Pending MCB review.
03/26/25 – TEI reviews and submits closeout docs to HCFD.
04/23/25 – Project can be closed out.
TPC – Hydraulic Elevators Modernization Read More »
PM = Matt Butz, Mike Barth
08/24/22 – TEI authors SOSS for project. TEI receives Signed SOSS and PO on 08/23/22. TEI to develop project manual for bidding to have new agreement in place by 01/01/2023.
09/26/22 – TEI finalizing bid package, to submit for review and then will coordinate ITB with Purchasing department.
12/15/22 – TEI to submit to HCFD for final review on or before 12/23/22
01/25/23 – TEI issues for bidding. Bids received on 01/18/23. Service agreement bids turned over to HCSO.
JC – Security System PM Agreement Read More »
PM: John Nester, Mike Barth
05/26/22 – TEI submits SOSS for work. TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting. TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information. TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault. Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data. With new version of software, incident energy levels are less than threshold of 40 cal. TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD. TEI submits review set to HCFD. Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued. Bids open Friday 10/28/22.
12/15/22 – DK low bidder. TEI vets DK bid and sends recommendation to Hamilton County. Hamilton County drafts contract and sends to DK for signature. DK returns signed Contract.
01/25/23 – DK receives PO and signed contract. TEI and HCFD working to schedule pre-construction meeting with DK to kick off the construction.
02/23/23 – Pre construction meeting completed. DK has sent submittals to TEI for review. Submittals to be returned by end of week and equipment can be ordered.
03/29/23 – Materials have been ordered. Project to commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials. Material for TPC are at DK office, TEI to set up a meeting end of next week to talk install schedule, etc (pre-const).
06/28/23 – Pre construction meeting occurred. DK scheduling mobilization with other county projects and will coordinate with HCFD, Bldg Mgr, and TEI.
08/24/23 – DK to be on site next week to work on the gear modifications to expose the adjustable trip settings on the gear. door modifications are 1-day turn around. gate shall be locked out/tagged out with no admittance to the electrical swgr room while the covers are removed from the gear.
09/26/23 – Gear modifications are complete. grounding modifications are complete. VFD replacement and then re-labeling of building and project will be complete.
10/26/23 – TEI reaches out to DK to Schedule the installation of the VFD, now that the pneumatic controls were removed from the existing VFD. Installation schedule to be received early November.
12/06/23 – VFD installed, connect and programmed. Work associated in TPC is complete and ready to be punchlisted. Work at CH is not complete, so project can not be closed.
05/29/24 – No Updates.
06/26/24 – No Updates.
07/24/24 – No updates.
08/28/24 – New Arc Flash labels applied in the building.
09/25/24 – no updates.
10/30/24 – no updates.
12/11/24 – TEI delivers final AF reports to HCFD including tables and single lines from the model.
04/23/25 – Updates tied to CH Arc Flash project.
05/28/25 – No updates
07/30/25 – No updates, waiting on CH breaker to close out.
04/26/26 – Ch breaker received and delivered to HC. Ready to closeout. OK to Archive.
TPC – Arc Flash Remediation Upgrades Read More »
PM: John Nester, Mike Barth
05/26/22 – TEI submits SOSS for work. TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting. TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information. TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault. Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data. With new version of software, incident energy levels are less than threshold of 40 cal. TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD. TEI submits review set to HCFD. Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued. Bids open Friday 10/28/22.
12/15/22 – DK low bidder. TEI vets DK bid and sends recommendation to Hamilton County. Hamilton County drafts contract and sends to DK for signature. DK returns signed Contract.
01/25/23 – DK receives PO and signed contract from HCFD. HCFD and TEI working to schedule preconstruction meeting to kickoff the construction.
02/23/23 – Preconstruction meeting completed. DK sends submittals to TEI for review. Submittals will be returned by the end of the week and equipment can be ordered.
03/29/23 – Materials have been ordered. Construction will commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials. DK has the VFDs in their shop. Scheduled ship date for the replacement MCC bucket is mid to late June. Scheduled ship date for the replacement MCC is mid to late October 2023. DK may install VFDs on wall sooner than MCC. Will schedule pre-const meeting next week to discuss options.
06/28/23 – Pre construction meeting was conducted. Once Bldg Mgr notifies that the compressed air lines that are in the location that the VFDs are scheduled to be installed have been relocated, DK will install the VFDs on the wall. Anticipate that all Chiller shutdowns will occur once the MCC arrives (November ish) when the CH is not in cooling mode.
08/24/23 – work pending equipment procurement.
09/26/23 – work pending equipment procurement.
10/26/23 – TEI requests status update from DK on the reciept of MCC. Upon receipt of MCC – the installation will be scheduled ASAP while not in cooling mode since the MCC serves chillers.
12/06/23 – DK indicates that ship date for MCC pushed by manufacturer from 11/1/23 to 03/14/24. TEI questions when it was ordered, and DK indicates the PO was issued on 03/17/23. DK questioned why the ship date delay? No response. TEI requests a meeting with DK, to develop an alternate plan for installation since it will now likely occur in cooling season.
01/30/24 – Waiting for equipment to arrive on site to schedule the installation (scheduled ship date = Mid March 2024).
02/28/24 – TEI has DK confirm ship date (=03/14/24) for equipment. HCFD and TEI schedule pre-const meeting with DK on 03/08/24.
03/27/24 – DK confirms receipt of MCC. VFDs are powered and the other MCC bucket already replaced. DK to schedule an outage to install the new MCC over a weekend and to coordinate with weather and CH schedules.
04/24/24 – MCC scheduled for installation on 05/04/24. Bucket to be swapped out during the same outage.
05/29/24 – MCC install did not occur. New date being coordinated (tentatively 06/22/24).
06/26/24 – Install of MCC occurred on 6/22. No issues reported back.
07/24/24 – TEI prints off the arc flash stickers for the CH. Planning to install starting Aug 1 – pending availability of HCFD to escort/open doors.
08/28/24 – Upon review – labels were not correct that were printed. TEI reprints labels and will install pending coordination with building manager.
09/25/24 – TEI scheduling applying labels with bldg mgr and will apply all labels in the building.
10/30/24 – TEI applies labels throughout the building
12/11/24 – TEI delivers final AF report to HCFD with the AF tables and the model single lines in the reports.
02/26/25 – HCFD reports issues with MCC replaced. DK indicates additional bucket requested by HCFD ship date of 08/2025.
04/23/25 – Project pending additional equipment shipping 08/2025.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No Updates. Breaker scheduled to ship next month.
08/27/25 – Breaker has arrived. DK working with HCFD to schedule the installation.
09/24/25 – Breaker is installed. Waiting on final phenolic labels to come in and be installed and then project will be complete after DEG and HCFD do a final final punchlist.
12/10/25 – DEG conducts final walkthrough. All work complete. Project complete pending closeout.
01/28/26 – Project in Closeout
04/29/26 – Breaker received and delivered to trades. Project can be closed out.
CH – Arc Flash Remediation Upgrades Read More »
PM = Matt Butz, Mike Barth
02/23/2022 – HCFD requests SOSS from TEI. TEI submits SOSS, and receives signed SOSS and PO. Project pending kickoff with HCRM and HCFD.
04/27/22 – Matt Butz and TEI meet with RM, and determine locations for adding the security cameras. Design documents are getting started now that Barth has returned from medical LOA. Will have review set for MButz upon his return form medical LOA.
05/26/22 – TEi and Matt to review the design documents for the camera locations. DK indicates that the materials are in inventory at their facility. TEI to certify equipment prior to approving the billing.
06/28/22 – HCFD, HCSO, HCRM and TEI meet with DK re status and DK provides tentative schedule. DK starts installation of cabling on the second floor.
07/27/22 – Installation continues with cabling and camera installation.
08/24/22 – Installation completed. TEI and Matt Butz perform punchlist. TEI issues punchlist to DK.
09/26/22 – HCFD issues DK change order for work associated access control on the second floor. Upon material procurement, and installation of access control equipment, TEI and HCFD will punchlist those items.
10/26/22 – Installation of access control pending procurement of materials.
12/15/22 – Installation of access control pending procurement of materials.
01/25/23 – Installation of access control pending procurement of materials.
02/23/23 – Installation of access control pending procurement of materials.
03/29/23 – DK indicates that the materials are in their shop and that the installation will be complete by 03/31/23.
04/27/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
05/23/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
06/28/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
08/31/23 – Work is complete, ready to close out the project.
12/06/23 – Pending final closeout documents from DK.
01/30/24 – TEI waiting on warranty letter from DK.
CH – 1st & 2nd Floor Security Cameras Upgrade Read More »
PM = Rycca Thacker, Mike Barth
12/13/21 – JFS issues RFQ and bids come in significantly higher than expected. TEI and HCFD to develop an ITB with a clearly defined scope for rebidding purposes.
01/25/22 – TEI working on RFQ – will submit to RT for review and comment.
02/23/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
04/27/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
05/26/22 – TEI and Rycca discuss scope items and TEI is finalizing the ITB for HCFD review and approval. TEI to submit to HCFD by June 10.
06/28/22 – TEI submits the final draft of RFP to HCFD for review. Issuance of ITB pending review comments and direction from HCFD.
07/27/22 – The project is currently in the bidding phase. Bids are due 8/26/22. Prebid meeting scheduled on 08/03/22.
08/24/22 – Prebid meeting conducted and addenda issued. Bids are due Friday 08/26/22.
09/26/22 – Bids received. Glenwood apparent low bid. TEI vets bid. Recommends Glenwood for the project. In contract phase.
09/29/22 – Archive next month.
A&D – Access Control Maintenance Agreement Read More »
PM John Nester, Mike Barth
10/26/21 – ThermalTech receives signed SOSS and PO for project. RFP in development.
13/13/21 – HamCo advises TEI to hold on the RFP development until a time when the county develops policy on the use/locations etc. of the EV Charging stations. TEI on hold until directed otherwise from county.
01/25/22 – TEI receives notice from JN that the project will move forward as originally discussed. TEI and JN to schedule kick off meeting the beginning of February
02/23/22 – TEI submits list of questions for RFQ to HCFD. Kick off meeting with HCES scheduled for 03/01/22 at 3:00 PM. Upon receipt of direction from the HCES, RFQ will be finalized.
04/27/22 – HCFD determines that the Infrastructure needs to be bid separately from the service contract. TEI develops infrastructure plan (SD level), includes power for the mobile coach, and has review meeting with HCES, HCPH, and HCFD on 04/26/22. CD phase and implementation pending funding approval from County.
05/26/22 – TEI finalizes the SD package after review with the end users (drawings and revised opinion of probable cost). TEI submits SOSS for CD thru CA phase of the work. Work pending SOSS approval and PO.
06/28/22 – Work pending SOSS approval and PO.
07/27/22 – Work pending SOSS approval and PO.
08/24/22 – TEI receives Signed SOSS and PO. JN states that funding for the install will be in 2023, and to work towards a first of 2023 issuance date for the project.
09/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
10/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
12/15/22 – Project documents in QC phase at TEI. Will be sent to HCFD once QC review complete for review and then issued for bidding.
01/25/23 – TEI to send final review set to HCFD for review by 02/10/23. Project bidding pending HC policy and procedures implementation decisions.
02/23/23 – Project bidding pending HC Policy and procedures implementation decisions.
03/29/23 – Project bidding pending HC Policy and procedures implementation decisions.
04/27/23 – Project bidding pending HC Policy and procedures implementation decisions.
06/28/23 – HC policy has been worked on by ES. Location for the EV charging stations has been moved from 250 WHT to Civic Center Drive (Comm Center), and also to include the Regional Crime Lab in Blue Ash (common provider). TEI and JN to discuss modifications to existing SOSS.
08/24/23 – TEI visits the site with the building manager and determines path/routing of power feeds for the EV charging equipment. Discusses with JN, and will modify new SOSS for new location.
09/26/23 – TEI develops plan for drawings and sends to HCFD for review/approval.
10/26/23 – TEI has Underground detective locate existing utilities on site, TEI shows on plan and HCFD submits to ODOT for approval.
12/06/23 – TEI submits documents to HCFD to submit to ODOT for approval. Pending ODOT approval.
03/27/24 – Tracking this on other project.
EV Charging Stations RFP Read More »
PM – Rycca Thacker, Mike Barth
10/26/21 – ThermalTech receives signed SOSS and PO. HCFD asking for design to be complete by 11/05/21.
12/13/21 – TEI submits drawings to TEI with to HCFD for review. RT returns drawings to TEI with additional scope changes. TEI to finalize drawings for issuance by EOY.
01/25/22 – TEI sends drawings to HCFD for review and final comments, to be issued upon receipt of comments.
02/23/22 – TEI sends drawings to Glenwood Electric to obtain quote (since Glenwood is under warranty for system). Upon receipt of quote from Glenwood, TEI and HCFD will determine next steps.
04/27/22 – TEI reviews quote with RT and Glenwood. Recommendations forwarded to JFS. Next steps pending approval from JFS.
05/26/22 – JFS approves the Glenwood quotation. HCFD executes CO for project and Glenwood is procuring materials. Install to occur upon receipt of materials.
06/28/22 – Install to occur pending material procurement.
07/27/22 – Install to occur pending material procurement.
08/24/22 – Install to occur pending material procurement. As of 8:00 PM on 8/24/22, Glenwood received materials at their shop on 08/24/22. Glenwood is coordinating resources and will contact Rycca Thacker in the next few days to schedule installation.
09/26/22 – Project in construction phase. Upon notification from Glenwood that install is complete, TEI and HCFD will perform punchlist.
10/26/22 – TEI and HCFD to perform punchlist.
12/15/22 – TEI and HCFD to perform punchlist.
01/25/23 – There were hardware issues on the stair tower doors. Glenwood ordered replacement hardware and tentative ship date is approx 3 weeks. TEI will finalize punchlist upon installation of pending hardware.
02/23/23 – Project completion pending installation of hardware.
04/27/23 – Project completed. RT and TEI perform punchlist walk through. Upon receipt of all close out materials, can be archived.
05/23/23 -Waiting on receipt of all close out materials.
A&D – 7th Floor Access Control Modifications Read More »
PM: John Nester, Mike Barth
08/26/21 – HCFD provides TEI with signed SOSS and PO for project.
02/23/22 – TEI reviewing current IEEE standards as they relate to the existing county procedure 7.0. Once all current standards are incorporated and approved by HCFD and CMI – the PMs in Archibus will be updated.
04/27/22 – No updates. Will move forward now that Barth has returned from medical LOA.
05/26/22 – No Updates this month.
06/28/22 – No Updates.
07/27/22 – TEI developing list of equipment for Nathan to put the procedures in Archibus.
08/24/22 – No updates this month.
09/26/22 – No Updates this month.
10/26/22 – No Updates this month.
TPC – Electrical PM Procedures. Read More »
PM: Matt Butz, Mike Barth
08/26/21 – HCFD send signed PO and SOSS to TEI. TEI contacts HCFD PM to set up design kick off meeting, date is pending.
10/26/21 – TEI has began the design process, setting up drawings and using archive drawings to show on demolition plans. Once kickoff meeting occurs, the field verification process will occur and the project will proceed.
12/13/21 – TEI develops demolition drawings from existing building plans from archives, and conducts design kick-off meeting with HCFD and building manager. Next step is to schedule field work to document/confirm existing conditions. TEI to work with building manager on schedule.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks returned and employees badges approved. TEI and HCFD to schedule the field work with building managers.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements). Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications. TEI fieldwork complete. Existing conditions documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system. New BDA system will be installed. TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 07/04/22 for review and comments. ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review. Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding. Available to bidders on 08/30/22. Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22. ITB # 075-22.
09/26/22 – Project out for bids. Bids open 09/28/22.
10/26/22 – Bids received and opened. DK apparent low bidder. JCI/Simplex vender in bid. TEI vets bid and makes recommendation for award. Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD. Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives approved contract and PO. HCFD and TEI working to schedule preconstruction meeting to kick off the construction.
02/23/23 – Pre construction meeting completed. JCI developing submittal documents.
03/29/23 – TEI speaks with JCI about status of Submittal Package. JCI states that the submittals are tracking about 2-3 weeks behind the 800 Broadway submittals (anticipated receipt of submittals = late April to Mid-May).
04/27/23 – JCI indicates that the submittals for the JC shall be sent to DK by mid May. Still tracking same as indicated last month. TEI to review and turn around upon receipt of submittals.
05/23/23 – JCI indicated that the submittals will be sent to DK this week. DK has not received to date.
06/28/23 – DK has not sent submittals to TEI for review to date. Submittals will be reviewed by TEI upon receipt.
07/26/23 – TEI receives submittals for project. Reviewing and will return. Pre construction meeting (along with 800) is scheduled for 7/28.
08/24/23 – TEI, HCFD and DK meet (at 800) to discuss project. work in JC to mobilize late Q1/early Q2 of 2024. Matt Butz asks about the BDA equipment at the JC, and how quickly it can be installed (issues with the existing system). TEI reaches out to DK to request data about schedule.
09/26/23 – TEI reaches out to DK for CO cost to install the ERRS (BDA) ASAP versus waiting until the new JCI system is in the building. MobilCOMM states no issues with the plan. DK sending electrician to site to confirm existing system is compatible and will issue CO accordingly. TEI stresses with Gleason that time is of the essence.
10/26/23 – MobilCOMM has ordered to BDA for the JC and will schedule the installation upon receipt of the equipment. DK still on schedule to mobilize as previously identified.
12/06/23 – TEI asks DK to find status of BDA – should be at MobilCom per previous schedule. TEI will follow up with DK.
01/30/24 – Installation of BDA pending the background checks from MobileComm
02/28/24 – MobileCOMM cleared to work in building. TEI contacts DK and tells them that the install must be scheduled and we need to have install date by beginning of February partner meeting.
03/27/24 – MobilComm and DK to mobilize 4/1/24 to install and get the BDA installed ASAP.
04/24/24 – Work has began on the BDA upgrades, most work in basement complete and 1st floor is next. All areas with minimal/no coverage were addressed first.
05/29/24 – BDA installed and turned on in the lower levels of both buildings. Finalizing the install of the BDA in the next week or two. Started the install of the backbone for the JCI fire alarm system.
06/26/24 – BDA installed and complete. DK and Biederman working out PO issues to get permitted. Panels installed and backbone conduits being routed through the building. DK facing additional staffing issues.
07/24/24 – Staffing issues continue. Permits for BDA applied for – pending City approval. Work continues on backbone. DK developing means and methods and durations of timing needed in all inmate areas to coordinate with HCSO. JCI finalizing CO pricing for deluge system, but Jay at JCI tells TEI that the relays needed for the CO are currently on backorder and the scheduled ship date is 01/31/2038 (and this is NOT a typo!). TEI states this is NOT acceptable!
08/28/24 – Project in construction. Permits for BDA obtained, inspections completed (passed) and MobilComm to send approval paperwork to HamCo once received.
09/25/24 – Construction progressing in the building.
10/30/24 – Construction progressing in the building following behind the cell lock project.
12/11/24 – DK indicates that the backbone installation is nearly complete and that they will need to have JCI and Notifier at the next const meeting (01/08/25) for coordination of cross trip.
01/29/25 – Cross trip installed and working. DK to have JCI at next project meeting to review schedule and Deluge system (controlled on all floors).
02/26/25 – JCI, HCFD, and TEI meet to discuss deluge system on site. TEI sent JCI record dwgs of sprinkler system in building. Construction on-going.
03/26/25 – JCI has all parts for Deluge upgrade to DK. The Deluge upgrade to begin early April.
04/23/25 – Deluge work has started. Working in unit 1 of north tower, all floors. Then Unit 2 North, and so on.
05/28/25 – Side 2 of the north building to be completed in the next 2 weeks.
06/25/25 – Issues with the Deluge valves and water leaks. TTC attends FA meeting and evaluates the valves and to send in recommendations.
07/30/25 – Construction on the project progressing with availability of spaces. DEG submits memo with recommendations.
07/31/25 – TTC issued memo on the deluge valve issue in the North building. We will talk more about this after the meeting today.
08/27/25 – Construction progressing. Moving to south tower beginning of September.
09/24/25 – Construction progress continues. DK following the other projects as pods are made available.
10/29/25 – Construction progress ongoing. Anticipated completion April/May of 2026
12/10/25 – Construction progress ongoing. Change order issued at the OEC meeting today. JCI finalizing engineering change for the building department.
01/28/26 – All work (original Scope) in North tower near complete. JCI to submit documents to city by end of Janaury. Project ongoing. Anticipated completion Late April/Early May 2026.
02/25/26 – Project ongoing. Deluge work is being completed this week and next.
03/25/26 – Project ongoing.
04/29/26 – Pretest completed on 04/28 throughout both buildings. Consult with inspector to be scheduled to outline inspection process.
07/29/26 – 2 months of inspections completed and the CFD and CBD have approved all of the installations. DEG has assembled the punchlist for the project and issued to the EC. Most items were discussed at time of inspection and punchlist walk – and we anticipate that they have been completed. Training for building staff was 07/28/26.
07/30/26 – Electric issues at panel and distribution at fire pit shorted out. Wire ran in lighting conduit and DK has to do an emergency repair for the job. MB to investigate and report back.
08/26/26 – Project complete pending final IBI and Elevator inspections for JCI to sign off on permit. Scheduled for Week of 08/31. Closeouts requested from DK.
09/23/26 – All inspections except IBI complete. IBI pending renewal paperwork. Project pending final closeout.
10/28/26 – IBI final inspection passed and complete. Project pending closeout documents.
JC – Fire Alarm System Upgrades Read More »
PM: Matt Butz, Mike Barth
08/26/21 – HCFD sends TEI signed PO and SOSS. TEI contacts HCFD PM to schedule design kick off meeting. Date pending.
10/26/21 – TEI has begun the design process by setting up the CAD file drawings and using archive data to begin the demolition drawings. Once kick off meeting occurs, the field investigation will be scheduled and the design will proceed.
12/13/21 – TEI has taken the as-build documents to create demolition drawings. Next step is to field verify/document the existing conditions. Field work to be scheduled with building manager. design kick off meeting occurred with HCFD and building manager.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks approved and badges approved. TEI and HCFD to schedule field work with building manager. Note – there was an issues with the existing Simplex FA System panel (dialer power supply) and JCI sent a quote for a complete panel replacement. TEI and JCI investigating a more cost effective fix until a time when the system is replaced.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements). Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications. TEI fieldwork complete. Existing conditions documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system. New BDA system will be installed. TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 7/4/22 for review and comments. ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review. Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding. Available to bidders on 08/30/22. Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22. ITB # 075-22.
09/26/22 – Project bidding. Bids Due 9/28/22.
10/26/22 – Bids received and opened. DK apparent low bidder. JCI/Simplex vender in bid. TEI vets bid and makes recommendation for award. Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD. Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives contract and PO. HCFD and TEI working to schedule preconstruction meeting to kick of construction.
02/23/23 – Preconstruction meeting completed. JCI developing submittals.
03/29/23 – TEI speaks with JCI about submittal package. JCI estimates that the submittals for the 800 building will be completed and turned over to DK in the next 2-3 weeks (Mid April-ish).
04/27/23 – TEI follows up with JCI, submittals nearly complete. JCI indicated that the submittal package should be sent to DK on or before 05/01/23. TEI to review upon receipt.
05/23/23 – TEI receives, reviews, and returns submittals with minimal marks, asks for schedule from DK for commencement of work. JC sends photo of material that was shipped to DK for project. TEI to schedule pre-construction meeting first week in June.
06/28/23 – TEI requests schedule again from DK. Upon receipt of schedule, construction to commence pending procurement of materials.
07/26/23 – construction kickoff meeting scheduled for 7/28.
08/24/23 – DK to mobilize to project site and start construction on 9/5/23. Josh Querry from DK to PM/site Super the project.
09/26/23 – Construction has began. DK installing backbone of the system.
10/26/23 – Backbone installation complete. DK has started on upper floors and at the construction meeting on 10/25/23 stated that 18, 17, 16 and part of 15 is complete. DK also working in basement and installing devices there. Rooms are being identified that require either LEADs clearance or special access. DK to schedule work in these areas during day shift.
12/06/23 – Construction progressing. Working on installs in LB, B 1,2,3,3M. LB and B ready for change over. 2 will be by Christmas. 1, 3 and 3M will be nearly complete if not complete by Jan 1.
01/30/24 – DK submits CO request for portion of work changes. The beam detector CO still pending.
02/28/24 – Beam detector CO still pending.
03/27/24 – Beam detector for 3 beam detectors received ($41k). HCFD to determine if it is accepted or not. Smoke purge CO under review.
04/24/24 – Smoke purge CO verbally approved to DK at const meeting. Beam detector CO not approved at the meeting. Work continues through the building.
05/29/24 – The smoke purge CO has been approved and sent to DK. DK and JCI working on Drawing updates and will progress to install as soon as the revised install drawings from JCI complete. JCI indicated that all parts are readily available.
06/26/24 – No updates from JCI on this project.
07/24/24 – DK same staffing issues – staff being moved from 800 to JC and back. CO verbally approved (HCFD waiting on PO increase) for formal approval.
08/28/24 – JCI submits revised drawings wot city for approval. JCI states that there is no way (on existing system) to repair the amplifier card for the upper floors. TEI and HCFD directed JCI that the New system shall be turned on immediately and use the new devices for audio on the upper floors.
09/25/24 – TEI, DK and HCFD meet with inspector (Jeff Hinkel) to discuss inspection process and 3 and 3M. Inspections will proceed similar to CH and TPC, where we will have multiple teams and multiple inspections. Looking at options for the 3 and 3M area – inspector sympathized with the task and we developed possible workable solutions.
10/30/24 – The switchover of floors to the new system in the tower (top down) has commenced. Anticipate tower work to be completed in approx 2-3 weeks. then move to low rise floors. TEI recommends scheduling inspection of tower floors once tower complete.
12/11/24 – HCFD, CFD, CBD, JCI, DK and TEI participate in the first acceptance inspection at the building. Floors 7-18 were inspected and accepted, with minor tweaks. Construction continues, with the crews starting on 5th floor week of 12/16.
01/29/25 – Crews working on 2 right now. Next inspection scheduled for 02/12/25 at 5:00 PM. Planning for inspections of floors 2-6.
02/26/25 – Inspections for 2-6 went well. First floor complete and working in basement. Will be ready for next inspection in about a month. Then there will be the Flow/Tamper inspections, then AHU/smoke control inspections, then Elevators. Need resolution of elevator issues for the non-functioning elevators.
03/26/25 – Inspection for SB, B and 1 scheduled for 04/16/25. The tamper/flow inspection to be scheduled 2-3 weeks after the inspection on the 16th.
04/23/25 – All floors inspected for smokes, pulls, heats and AVs. Door holders were inspected. Tamper/flows inspection next – to be scheduled TBD.
05/28/25 – Tamper flow inspection occured and passed. Next is air handlers. Inspector allows the magna-helic results from the pre-test to be written on the covers for the inspection night.
06/25/25 – Installation nearing completion. Elevtor and Air Handler inspections scheduled for 07/16/2025
07/30/25 – Freight elevator and final air handler inspections scheduled for 07/31/25 at 0700. This is final building and fire and elevator inspections pending no issues during the inspections.
07/31/25 – Early morning inspection went well this morning. Three small electrical items are required to be updated to get the AHU-45 and Smoke Fans 14 & 15 did not start. The elevators are approved and the Chief Inspector approved the current smoke detector layout.
08/27/25 – follow up visits with CFD and CBD to inspect and approve the repairs made by HC. All inspections completed (other than IBI). IBI to be scheduled once the Bldg Dept and FD upload all their paperwork.
09/24/25 – All inspections passed. HCFD and DEG to schedule final punchlist for project.
10/29/25 – Punchlist completed and issued punchlist to DK.
12/10/25 – project tied to Justice Center PO. Closeout pending completion of JC FA project.
01/28/26 – Project tied to the JC FA PO, Closeout pending completion of JC FA project. Anticipated completion April/May of 2026.
02/25/26 – No Updates.
03/25/26 – No Updates.
04/29/26 – No Updates.
06/23/26 – DEG directs DK to assemble and submit closeout documents for 800 building.
07/29/26 – Project completion pending closeout documents.
08/26/26 – Project complete pending closeout documents.
09/23/26 – Project complete pending closeout documents.
10/28/26 – Project complete pending closeout documents.
800 – Fire Alarm System Upgrade Read More »
PM – Rycca Thacker, Mike Barth
08/26/21 – HCFD sends signed PO and SOSS to TEI. TEI to start immediately, as the switchgear cleaning work is contingent on the this work.
10/26/21 – TEI submits preliminary plans and opinion of probable cost to HamCo for review. Project pending project funding.
12/13/21 – TEI and HCFD gets quotation from CE Power to provide the install of the work. HCFD drafts and issues a PO for the work to be installed, and requests schedule from CE Power.
02/23/22 – All equipment has been ordered and anticipated delivery was end of February, early March. CE Power to notify TEI and HCFD upon receipt of all equipment and schedule installation and cleaning.
04/27/22 – Equipment is installed in the building. HCFD and TEI requesting dates from CE Power to perform Switchgear PM and Tie ins during same outage. Tie in pending CE Power availability.
05/26/22 – Tie in date tentatively scheduled for June 20 (Juneteenth Holiday). Pending approval from HCFD and JFS personnel. JFS requested that it move to as Saturday in case there were issues and needed the Sunday for repairs. Final date TBD.
06/28/22 – Date of tie in moved to 07/09/22. Tie in to be competed concurrently with switchgear cleaning (same power outage).
07/27/22 – Power outage cancelled by Duke energy due to tornados in the area, and unavailability of Duke crews. CE Power, HCFD, JFS and Duke to reschedule.
08/24/22 – Reschedule date is 09/10/22 pending no storms etc. in area.
09/26/22 – Installation complete. testing, training and punchlist to be scheduled.
09/29/22 – Work on SOSS for putting CRAC and Condenser on backup power.
10/26/22 – TEI submits SOSS for placing CRAC unit condensers on the backup power. project pending SOSS approval.
12/15/22 – TEI receives approved SOSS and PO. Project Design in progress.
01/25/23 – CE power punchlist incomplete. TEI sends follow up email to request that the work completed ASAP. Alex on site on 01/25/23 to confirm the existing power feeds to the condensing units, and a review set will be send to HCFD prior to bidding.
02/23/23 – TEI to submit to HCFD bid set for final review.
03/29/23 – TEI to submit review set to HCFD by 05/03/23.
05/23/23 – TEI submits review set to HCFD for comments. Upon receipt of owner review comments, project will be issued for bids (small projects method).
06/28/23 – TEI, RT and Kleeman meet on site and discuss project. Trades electricians to provide installation of the circuits. TEI to procure the permit from IBI for trades.
08/24/23 – Drawings are submitted to IBI for permit. Comments received and answered from IBI. Permit expected in next day or two.
09/26/23 – Plan review complete and permits ready to be picked up at IBI. TEI will deliver to HCFD for work to be completed by trades.
10/26/23 – TEI procures the permit for the work and sends to HCFD. Trades to install work.
12/06/23 – Trades to notify TEI when they are ready for inspections.
01/30/24 – Trades completes work. TEI and Trades have IBI inspect work and passed inspections on 1/30/24.
02/29/24 – Project complete, need as-builts to close out.
A&D – Computer Room Emergency Power Connections Read More »
PM – Matt Butz, Mike Barth
7/27/21 – TEI authors and submits SOSS. TEI receives signed SOSS and PO from HCFD. Design kick off meeting to be scheduled early August.
08/26/21 – Field work, pre construction meeting scheduled with DK at 1:30 PM on 08/26/21. Construction to commence thereafter.
10/26/21 – Project in construction. Issues with installation in process of developing repair plan.
12/13/21 – Project complete with the exception of wall path and painting. O&M manuals delivered to HCFD.
01/25/22 – Project complete pending receipt of closeout documents from DK.
JC – Card Access Control Read More »
PM – Matt Butz, Mike Barth
07/28/21 – Thermal authors and submits SOSS. TEI receives signed SOSS and PO from Hamilton County. TEI and HCFD to schedule design kick off meeting first week or two of August.
08/26/21 – HCFD PM and TEI schedule field work at all (4) buildings the afternoon of 09/02/21. TEI has coordinated with SecureTech and project is progressing.
10/26/21 – Project in contract phase. Construction to be completed once contract/PO is BOCC approved.
12/13/21 – Contracts sent to SecureTech. Pre-install training meeting with HCSO conducted last week. Parts are ordered and the will be available early January 2022. Install Scheduled to occur beginning MLK weekend 2022.
01/25/22 – Installation was completed on the weekend of 01/17/22. Securetech is working on getting closeout information to submit. TEI and HCFD to provide punchlist the beginning of February.
02/23/22 – All close out documents complete. Final pay application received. HCFD to provide TEI with mark ups of button locations to show on CAD drawings. Upon completion of the as-built conditions, project will be archived.
04/27/22 – TEI receives the mark ups for the CH for As-built documents 04/21/22. Upon completion of the as-builts (drawings complete, MCB to review final drawings), O&M manuals will be delivered to project can be closed out.
05/26/22 – TEI to provide HCFD with (2) full size sets to deliver to HCSO. Project complete upon turn over of full size drawings.
06/28/22 – Project complete.
07/27/22 – TEI Delivers thumb drive with electronic version of the drawings per HCSO request to Matt Butz.
CH/JC/TPC/800 – Panic Button System Upgrade Read More »
PM: Matt Butz, Mike Barth
05/27/21 – Project created.
06/23/21 – Project kick off meeting attended by TEI, HCFD, DK and HCSO. DK has began moving the doors over to the Vax system. Project construction continues.
07/28/21 – DK states that the project is substantially complete. TEI and HCFD provide punchlist site visit. TEI issues punchlist. DK addressing punchlist items.
08/26/21 – Punchlist items are picked up. TEI receives O&M manuals for review. No punchlist or warranty in O&Ms. Upon receipt, TEI will forward to HCFD.
10/26/21 – O&M Manuals delivered to HCFD. Project is complete.
800 – Access Control Read More »
PM: Bert Watts, Mike Barth
03/25/21 – New post started by TTC and assigned to MCB.
06/23/21 – TEI working on Study. Site visits to the buildings to be scheduled by TEI with building managers over the next few weeks. Study proceeding.
07/28/21 – TEI continuing to work on study, researching existing conditions and vulnerabilities.
08/26/21 – No updates.
02/23/22 – No updates per discussion with HCFD.
10/26/23 – TEI assigns work to EE Conn Gerard, who is reviewing the study and working on completing the study.
12/06/23 – Conn for TEI is continuing to work on study.
02/29/24 – Conn has report ready to review with Barth.
10/30/24 – Conn sends out questionnaire to bldg mgrs. If they are replying to conn, he on honeymoon and will address upon his retturn.
12/11/24 – Conn returned and finalized information from the buildings has report ready for my review. will send to HCFD once QC review complete.
Blackout Vulnerability Study 2021 Read More »
PM – Rycca Thacker, Mike Barth
03/24/21 – HCFD requests SOSS from TEI for an Electromagnetic Investigation of the first floor of the A&D building. ThermalTech soliciting venders to provide us a quote to measure the EM waves in the area, and will submit SOSS once we receive the quotation.
04/28/21 – TEI submits SOSS to HCFD. Project pending approval of SOSS and PO.
05/26/21 – TEI receives signed SOSS and PO. Study phase started.
06/23/21 – TEI, Rycca, Steve T, and Claude T perform walk through of space on 06/23/21 to document the EMF readings in the area of concern. Initial readings were higher than expected levels. Report and recommendations to follow.
07/28/21 – TEI working on report – with continued research for appropriate recommendations.
08/26/21 – TEI nearing wrapping up draft of report to deliver to HCFD. Will complete the report upon completion of 2022 estimates.
10/26/21 – TEI to deliver draft of report to HCFD 11/05/21.
12/13/21 – TEI submitted hard copy draft of report to HCFD for review and comments. Final report pending HCFD review.
01/25/22 – Final report pending HCFD review.
02/23/22 – Final report pending HCFD review.
04/27/22 – TEI receives comments from HCFD on 04/18/22. TEI incorporating comments and will deliver final draft to HCFD.
04/28/22 – Today’s discussion centered around adding to the study with a physicist recommendation on lead abatement protection. Champlin will lead collecting the information for the additional study and pulling in a third party person to help us update our report. Eventually, this will turn into a new report to the County. Meeting next Tuesday with THP, TEI and Champlin.
09/26/22 – TEI hand delivers (4) hard copies of the EMF report to HCFD.
10/26/23 – Project still on hold until further notice from HCFD.
12/12/24 – BW said to go ahead and send the final report to Rycca and close the project.
02/27/25 – OK to Archive.
A&D – First Floor EMF Study Read More »
03/24/21 – HCFD requests and TEI submits SOSS to provide Arc Flash Electrical System modeling and labeling at the Sheriff’s Heliport, the P&D Garage, and the Records Center. Project Pending SOSS approval and PO.
04/28/21 – Project Pending SOSS approval and PO.
5/26/21 – TEI receives signed SOSS and PO. TEI scheduling kickoff meeting with JN to begin field investigation and calculation phase of the study at all three facilities.
06/23/21 – TEI requests available fault information from Duke Energy for all 3 facilities. Upon receipt of data from Duke Energy, field work will be scheduled for each of the 3 facilities and studies will be completed.
07/28/21 – TEI receives data from Duke on Heliport and P&D garage, still waiting (and repeated requests) on Records Center Data. Upon receipt, we will schedule field work for input into models.
08/26/21 – Data from Duke still pending for record center. Multiple phone calls, when we talk to a rep, they pass along to someone else and the process starts over again.
10/26/21 – Data received from Duke. All buildings have been visited. Conn (EE on project) will schedule Phasor with Ian Zellner upon his return from vacation.
12/13/21 – site visits with EC to confirm feeder sizes etc. Finalize the model and submit to Charlie for final approval prior to application of labels.
02/23/22 – TEI submits finalized model calculations and report to CMI for review. We will schedule application of labels upon receipt of approval from Charlie.
04/27/22 – TEI receives CMI comments – and incorporated into the model. TEI printing labels on 04/27/22 and scheduling time with building manager to apply labels (week of 5/2/22).
05/26/22 – All labels complete and applied at building sites. Project complete.
Arc Flash – Heliport, P&D Garage and Records Center Read More »
03/24/21 – AKM requests SOSS for the installation of mini-split HVAC systems for (2) kennels. TEI is authoring and will submit by end of the day 03/26/21.
04/28/21 – SOSS submitted. Project completion pending SOSS approval.
05/26/21 – TEI receives signed SOSS and PO. TEI completes drawings and submits to IBI for Plan review. Plan review approved and TEI applies for permit. Installation work to be coordinate with Trades and building manager.
06/23/21 – Permits received. Work installed. Upon repair of boards in the units (due to pest infestation, electronics were compromised), final inspections will occur.
07/28/21 – Repairs have been completed and ready for TEI to call IBI and Schedule a final. TEI coordinating with Trades and IBI and will schedule in the next few days.
08/26/21 – IBI final inspection scheduled for 08/27/21. Time TBD, per IBI standards, must call day of the inspection to get timing. TEI coordinating with John Kleeman and John Nester.
10/26/21 – IBI required to have HVAC permit prior to the final for IBI. TEI developed HVAC documents and are awaiting permit approval and inspection to re-schedule the IBI final.
12/13/21 – Plan review and zoning have verbally approved. TEI was told full approval for the HVAC permit will be approved on 12/17/21. Once approved and picked up, we can have inspection, approval, and then have IBI final inspection.
01/25/22 – HVAC plans approved. Need to schedule final HVAC inspection and also final IBI
02/23/22 – Per building manager – 3 out of 4 units not functioning currently due to rodent issues. building manager will contact TEI when the units are operational so that we can schedule the finals.
04/27/22 – inspections pending units being operational.
05/26/22 – HVAC inspection complete/passed. IBI pending repairs to work by NK heating and Air. Building manager to notify TEI when we can schedule final.
06/28/22 – IBI pending repairs to work by NK heating and Air. Building manager to notify TEI when we can schedule final.
07/27/22 – IBI PASSES inspection! Project complete!
Animal Shelter – Kennel HVAC Modifications Read More »
PM: John Nester, Mike Barth
03/24/21 – HCFD requests SOSS for project. TEI submits SOSS and receives approval of the SOSS and the PO. kickoff meeting with facilities and building manager to be scheduled week of 03/29/21.
04/28/21 – TEI and HCFD meet with building manager and kick off design of the project. Project in design process.
05/26/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
06/23/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
07/28/21 – TEI submits drawings to HCFD for review comments. Receives comments from JN, awaiting comments from building manager. Package will be issued upon receipt of all comments.
08/26/21 – TEI and HCFD PM finalize bid set. Project out to bid date is 08/31/21, and bids due on 09/22/21. ITB # = 081-21
10/26/21 – Bids received. Fujitek is low bidder. TEI vets their bid, and the contract and PO was approved. Materials are on order, and upon receipt, installation will be scheduled.
12/13/21 – Installation pending arrival of parts.
01/25/22 – Installation pending contractor background checks.
02/23/22 – Preconstruction meeting scheduled for 02/22/22 – cancelled due to vendor having C-19. Pre Construction meeting re-scheduled for 3/8/22 at 9:00 AM.
04/27/22 – Project construction has began. Work occurring in the penthouses.
05/26/22 – Construction completion pending materials arrival.
06/28/22 – Construction completion pending materials arrival.
07/27/22 – Fujitec, HCFD and TEI meet to discuss the existing software and the proposed software, and the incompatibility issues. TEI and HCFD to develop response and plan moving forward.
09/26/22 – Fujitec to install updated software.
10/26/22 – Waiting on install from Fujitec.
12/15/22 – Waiting on Install from Fujitec.
01/25/23 – John Nester receives notice from Fujitec that all project personnel are no longer working for Fujitec. TEI and HCFD working to get new contact information to have Fujitec complete the project.
02/23/23 – Fujitec new personnel working to complete project.
03/29/23 – Fujitec experiencing a lot of personnel turn over. This project still pending. There are issues with one of the elevators on the monitoring system and until that is repaired, Fujitec not comfortable taking down the other cabs.
04/27/23 – No update from Fujitec.
05/23/23 – No updates from Fujitec.
06/28/23 – No updates from Fujitec.
07/26/23 – Fujitec!!!
08/31/23 – Fujitec and Kone working together to repair obsolete equipment in the building. Billing is not right.
10/26/23 – TEI works with Fujitec to correct billing (several attempts). TEI certifies pay application and delivers to HCFD for payment.
12/06/23 – No updates from Fujitec.
06/27/24 – No updates. Fujitec needs Kone aftermarket group to furnish some missing parts so they can continue working.
07/24/24 – HCFD, TEI and newer Fujitec regional sales mgr meet in B-90. Speak of issues. Fujitec asks for 3-4 weeks to look into issues and solutions.
08/28/24 – No Updates from Fujitec.
07/30/25 – This will be picked up in the elevator modernization project.
08/28/25 – OK to Archive.
800 – Elevator Monitoring System Upgrade Read More »
PM – John Nester, Mike Barth
03/24/21 – HCFD requests SOSS from TEI for SD/Estimating. TEI and HCFD conduct phone call with Greg Varner of Public Health to clarify scope on 03/24/21 and then TEI will finalize and submit SOSS.
04/28/21 – TEI and HCFD meet with Greg Varner and walk the space. TEI authors and submits SOSS. Project pending SOSS approval and PO.
05/26/21 – Project pending SOSS approval and PO.
06/23/21 – TEI receives approved SOSS and PO. Project field work to be scheduled with JN of HCFD
07/28/21 – TEI develops SD drawings and estimates for HCFD review. TEI to send to JN for review and comments by 08/06/21 – then finalize for official submission upon receipt of JN comments.
08/26/21 – TEI sends SD package to HCFD to send to public health. TEI sends HCFD PM estimate of fees for taking project through CD’s and CA. Project pending approval funding.
10/26/21 – Project pending approval of SOSS and PO.
10/28/21 – SOSS approved and work can continue.
12/13/21 – Final review documents to be sent for owenr review on 12/17/21. Review teams Meeting scheduled for 12/20/21 at 2:00 PM.
01/25/22 – Project has been issued for bids. Prebid meeting is scheduled for February 2, 2022
02/23/22 – Project issued for bidding per HC small project bidding process. Bids due to TEI on 02/25/22.
04/27/22 – Project re-bid per ITB process. (1) bid received from Triton. TEI vets bid and recommends Triton for project. Contracts drafted and at prosecutors office for review. Construction to commence upon approved contracts and PO issuance.
05/26/22 – Construction to commence upon approved contracts and PO issuance.
06/28/22 – Construction to commence upon approved contracts and PO issuance.
07/27/22 – Project to commence upon material procurement.
08/24/22 – Project to commence upon material procurement. All submittals retturned.
09/26/22 – Project to commence upon material procurement.
10/26/22 – TEI, HCFD and HCPH have kick off meeting with Triton. Materials on order and project schedule being developed by Triton.
12/15/22 – Walls and door frames installed. DK to mobilize Monday 12/19/22 to begin the Electrical install.
01/25/23 – Construction progressing. Upon approved inspection, walls can be closed up. Final door hardware not arrived yet. Powered door operator not on site yet. Construction completion pending materials arrivals.
02/23/23 – Ready to Archive.
03/29/23 – HCFD and TEI provide preliminary punchlist. Items being addressed and waiting on final inspections.
04/27/23 – HCFD and TEI to perform final punchlist.
05/23/23 – Once punchlist is complete, the project is complete, with the exception of the door outside of the scope of the project that the inspection agency wants panic hardware installed on.
06/28/23 – Triton working to resolve final panic hardware issues, and then will have final inspection.
237 WHT – HCPHD TB Clinic Entrance Security Access Control. Read More »
PM: Matt Butz, Mike Barth
12/09/20 – TEI submits SOSS for approval from HCFD. Project to commence upon receipt of approved SOSS and PO.
01/26/21 – TEI receives signed SOSS and PO for project. Project kickoff to be scheduled with facilities and project work to commence.
02/23/21 – TEI requests times/days to meet and have a design kick-off with HCFD and Champlin. Meeting to be scheduled as soon as availability is coordinated.
03/24/21 – TEI meets with Champlin, HCFD and building manager. kick off the meeting. lobby beautification project to determine the interiors for the elevators #2,3,4, and 5. project in design phase.
03/25/21 – We talked about phasing of the elevator work and TTC shared the HVAC smoke evacuation procedures for this building as they may be related to the work being done on the AHU, elevators and fire alarm systems.
04/28/21 – Project in design process.
05/26/21 – Project in design process. Interiors shall be coordinated with the lobby beautification project.
06/23/21 – Project design continues.
07/28/21 – Project design continues, will be completed once interior finishes are finalized with lobby beautification project.
07/29/21 – Finishes are selected and the job can go forward with bidding. Keep bronze colors intact, Murphy is working on selections. We have enough information from equipment vendor to give to the Admin committee to move this forward. MB to setup a design meeting for next steps.
08/26/21 – No update
10/28/21 – MCB updating elevator package based on JC learnings, low voltage, coordination issues into the TPC work. County requested elevator cab rendering with new finishes to use with the Lobby Renovation. Keep and polish up the existing mailbox.
05/26/22 – Final review sent to county. To be determined if this will be bid as one project with the lobby renovation.
06/28/22 – Project HCFD review completed and received. Drawing pack schedule coordinated with Champlin for the Lobby Beautification project. Drawings to be sent to Purchasing on 07/05/22, available for bidding 07/07/22, with bids opening on 08/04/22.
07/27/22 – Project bidding. Bid opening on 08/04/22. Prebid completed and addendum #1 and #2 issued.
08/24/22 – Bids opened. Graybach is apparent low bidder. Project contracts drafted and sent to Prosecutors office. Project to commence upon contract approval and PO.
10/26/22 – Bids opened. Graybach is apparent low bidder. Project contracts drafted and sent to Prosecutors office. Project to commence upon contract approval and PO.
12/15/22 – Preconstruction meeting occurred on 12/14/22 with Graybach, HCFD, TEI. Submittal are starting to arrive. Graybach to submit a project schedule.
01/25/23 – Submittals are arriving slowly. Electrical and Elevator submittals still pending.
03/29/23 – Submittals are arriving slowly. Electrical and Elevator submittals still pending.
04/27/23 – Submittals reviewed and returned. There are a couple of submittals (floor base, etc) that Champlin has requested samples and are still pending. Anticipated start of construction is around the beginning of July ’23. Graybach instructed to not make sure all materials are procured and received prior to starting actual construction so that there are no material delays once construction begins. Basement door selected for mock-up of door finish. mock up to be installed in next 2-3 weeks.
05/23/23 – Sill plate painted. The door mock up materials arrived at site damaged. Upon receipt of undamaged materials, the mock up will be installed for approval.
06/28/23 – TEI, Graybach, and HCFD meet on 06/28/23 to discuss schedule. Door frame finish selection is critical path item. Prior to taking an elevator off line, all materials for that elevator shall be on site. Door frame wraps are a 4-6 week lead time item.
07/26/23 – Door frame selections have occurred. Sent to Graybach and American Elevator. Permit applications have been submitted. Graybach anticipates starting on 1st elevator mid/late August.
08/24/23 – Graybach and subs are getting ready to start the project.
09/26/23 – Construction commencing on project. first elevator to be taken from service early October.
10/26/23 – Elevator #3 (Right hand Side Passenger Elevator) has been taken out of service and machine is being disassembled. There is a crane lift scheduled for 10/28/23 to remove Machine #3 from the penthouse, and lift the new equipment for #2 and #3. A second lift will be scheduled once Cab #2 is complete and ready to work on cab #1 (freight).
12/06/23 – Work continues on Cab #3. Old equipment is removed and new equipment is set in place in penthouse. work in shaft, cab and landings ongoing. new doors on multiple floors.
01/30/24 – First cab (cab #3), nearly complete. Graybach tentatively scheduling inspections for approval on week of 02/05, and pending approved inspections, will turn cab #3 over for use by end of week.
02/28/24 – First CAB turned over and in use. Working on second cab (Elev #2).
02/29/24 – Graybach sent email about air pressure in the lobby affecting for the doors, TTE advised them to check elevator door settings first before we change the HVAC and Smoke Evac fans in this building.
03/27/29 – Work continues on Elevator #2 (second passenger elevator). Graybach indicates that they are “on schedule”.
04/24/24 – Elevator #2 inspection scheduled for 05/01/24. Upon approved inspections and turn over – then #3 (the first one modernized) will be taken out of service for approx 1 week to address manufacturer’s recall on components. Then both lobby elevators will be returned to service for the building occupants.
05/29/24 – Elevator #2 passes inspections and is placed back into service. Elevator #3 recall work completed ahead of schedule and placed back in service. Freight elevator taken out of service and is being worked on. Anticipated completion late July/beginning of August.
06/26/24 – Project work progressing on the Freight. No schedule delays indicated by American Elevator or Graybach.
07/24/24 – Pretest of the FA connections on 07/24/24. Elevator inspection on 07/26/24. Turnover immediately after the approvals.
08/28/24 – Freight elevator complete, inspected and returned to service.
09/25/24 – Project complete pending closeouts from Graybach.
12/11/24 – Project complete pending closeouts from Graybach.
02/27/25 – Ready to Archive.
TPC – Elevator Modernization 2020 Read More »
12/09/20 – Fire pump and fire alarm are having multiple trouble signals (excessive amount). HCFD had SA Comunale investigate, and also JCI/Simplex, both stated that their systems are working correctly. TEI suggests that a logging meter be installed to determine if it is an incoming voltage issue to the fire pump since the alarm is a single phase alarm. Meter on pump and more data to follow once results from the metering are reviewed.
01/26/21 – Meter data indicated voltage variations and excessive rapid voltage changes. TEI reported to facilities the voltage issues. Facilities requests SOSS for study to determine options for power quality correction. SOSS submitted and approved by facilities. Study in progress.
02/23/21 – HCFD sends TEI email stating that the existing phase loss monitor on the existing fire pump does not have adjustable ranges. Study to develop “clean” power supply to fire pump continues.
03/24/21 – TEi continues working on project, no new developments to report.
04/28/21 – TEI Finalizing owner review draft, will send to HCFD by 5/5/21 for initial review. TEI identifies issues from previous report also associated with the fire pump that possibly may required to be addressed if implementations occur.
05/26/21 – TEI submits draft for owner review. TEI and HCFD evaluating additional options. TEI suggests a temporary solution, and requests a quote from DK (since they did fire alarm project and are working on another project in building). Solution pending pricing from DK.
06/23/21 – The temporary solution was installed on the system, and it was reported to TEI that there are no longer the troubles on the FACP. TEI to finalize report to HCFD with results of solution included.
CH – Fire Pump Electrical Investigation Read More »
12/09/20 – AKM called ThermalTech to develop Opinion of Probable cost and opinion of engineering fees to communicate to Animal Shelter personnel. AKM to advise TEI if the Animal Shelter wants to proceed with project, at which point AKM to ask for an SOSS. TEI sent opinions of cost to AKM on 12/04/20.
01/26/21 – Trailer delivered to site. TEI speaks with AKM about moving forward. AKM requested revised cost data based upon the location where the trailer was placed. TEI sends AKM data requested and asks about next steps
01/28/21 – Discussed having Duke pulling a separate service for this trailer to keep it separate from the main building’s supply. TEI stated that is how it is planned at this time.
02/23/21 – AKM requests SOSS for design work for the trailer install. TEI sends to AKM.
03/24/21 – Project pending SOSS approval and PO.
Animal Shelter – Trailer Power and Signal Read More »
09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – Approved SOSS has been received. Arc Flash to begin.
12/09/20 – Duke Energy information finally received from Duke, and model is developed. Site visit to coordinate and confirm existing conditions to be scheduled ASAP (post quarantine).
01/26/21 – TEI conducts field survey, develops model and is finalizing the model. Model results to be sent to Charlie at CMI for review no later than 01/29/21.
02/23/21 – TEI completes model and sends to Charlie at CMI for review and comments. Upon receipt of Charlie’s comments, TEI will implement, print and apply labels.
03/24/21 – TEI receives and incorporates comments from CMI. Model completed and labels are printed and TEI is scheduled to apply labels week of 03/29/21.
04/28/21 – Labels applied. TEI to submit printed results to HCFD and the project is complete.
05/26/21 – Project complete. OK to Archive
Animal Shelter – Arc Flash Study Read More »
08/21/20 – TEI submits SOSS, project pending SOSS approval and PO.
09/23/20 – TEI receives PO and signed SOSS for project. TEI to schedule project kickoff with HCFD.
10/27/20 – TEI Develops costing and recommendations for system replacements. TEI final report pending receipt of Russelectric report from outage for inclusion in final report.
12/09/20 – TEI received Russelectric report – to complete report and send to HCFD final draft.
01/26/21 – Still in Progress.
02/23/21 – No updates on this project this month. TEI to complete prior to next partner meeting.
03/24/21 – No updates this month. TEI to complete prior to next partner meeting.
04/27/22 – No updates.
JC – Emergency Electrical Service Upgrade Study Read More »
02/26/20 – TEI authors and submits SOSS for project per HCFD request. TEI receives PO and approved SOSS. TEI and HCFD meet with CE Power for site investigation of existing conditions and remains of the disconnect switch that failed/caught fire. CE power providing forensic’s report to TEI.
03/26/20 – CE Power has sent TEI forensics report. TEI adding CE Power findings to TEI report to send to Hamilton county.
04/30/20 – TEI finalizes report draft to send to facilities for review.
05/27/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
06/23/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
07/29/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
08/21/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments
04/14/21 – TEI incorporates owner’s comments into report and emails JN and BW final report for approval. Upon approval from HCFD – TEI will issue deliverables to HCFD.
04/28/21 – Report finalized, and (5) hard copies delivered to HCFD. Project complete.
TPC – Power Loss/Fire Event Study Read More »
01/28/20 – TEI authors and submits SOSS for lighting upgrades in the 6th floor board room area to eliminate the large “beam me up” light fixtures per the request of facilities and the Commissioner. TEI has sent facilities an option with costs, lighting calc and a rendering of the space.
02/26/20 – Commissioner rejects initial selection. TEI and HCFD send commissioner lighting selection data sheets and commissioner selects a fixture that is acceptable. ThermalTech sends HCFD revised rendering and lighting calculations for approval. TEI and HCFD discuss benefits/drawbacks of removing wall sconces in the room versus replacing the wall sconces. Pending commissioner approval.
03/26/20 – Project pending review an approval of rendering.
04/30/20 – Project pending review and approval of rendering.
05/27/20 – Project pending review and approval of rendering.
06/23/20 – Project pending review and approval of rendering.
07/29/20 – Project pending review and approval of rendering.
08/21/20 – Project pending review and approval of rendering.
01/28/21 – Archive for now.
TPC – 6th Floor Lighting Upgrades Read More »
PM – John Nester, Mike Barth
01/28/20 – TEI authors and submits SOSS for approval as requested by facilities.
02/26/20 – TEI receives signed SOSS and PO for the project. TEI to set up kickoff meeting with HCFD.
03/26/20 – Project pending COVID-19 restrictions.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI has kick off meeting with Bryan Collins. TEI and Bryan visit all sites to review gear that is included in the scope of the project. Upon receipt of questionnaires from the building managers, the specifications will be drafted for HCFD to review.
08/21/20 – TEI issues request for information from building managers to include in the specifications. Upon receipt of the information from the building managers, specifications can be completed and issued for bidding, once HCFD says to issue.
09/23/20 – TEI waiting on completed forms from building managers. Upon receipt of the information from the building managers, specifications can be competed and bid package issued.
12/09/20 – Project bids received, CE Power apparent low bidder, and contract sent to Prosecutors office for review and approval. Building priority and schedule TBD once contract is returned and PO cut.
01/26/21 – JN with facilities sends CE Power PO and contract, with instructions for background checks. Upon receipt of approved BGCs, pre-construction meeting to be scheduled. CE Power contacts TEI to request walk through of all facilities prior to evaluate the building and access issues to be prepared to speak intelligently at the pre-construction meeting. TEI instructs CE Power to start the BGC process, and then send request in email.
02/23/21 – Upon notification from JN that CE power has BGC’s completed and passed, a pre-construction meeting will be scheduled to prioritize and develop an anticipated project schedule.
3/24/21 – Background checks are coming back for CE Power staff. HCFD and TEI meet at P&D garage with CE Power to discuss first building to get work completed on. P&D garage work to occur on 03/27/21.
04/28/21 – P&D Garage work completed. 2020 is next – and meetings have occurred at the site to develop plan of execution of work at the 2020 facility.
05/26/21 – TEI and HCFD have meetings with 2020 staff to discuss options with performing the PM. HCJC looking at options to make the PM work. Facilities and HCJC working together with TEI to develop plan.
06/23/21 – work at 2020 facility pending approval of plan from HCJC.
07/28/21 – work at 2020 facility postponed till later in the year (cooler weather). HCFD and TEI walks A&D and 800 Broadway with Bldg managers and CE Power. CE Power to submit outage schedules and durations for both facilities and then PM to be scheduled.
08/26/21 – TEI, HCFD, and CE Power met at A&D to review the project. A solution to make the PM procedures easier in the future was suggested. RT and MB spoke with JFS, and decided to work on the solution to keep the computer room powered (see A&D computer room emergency power). Discussing 800 Broadway now with CE power to keep project moving.
10/26/21 – CE power has sent several of thermal scans for review. 800 Broadway work still to be scheduled. CE power to provide availability.
12/13/21 – CE power reviewed 800 Broadway for outage plan. No outage plan submitted from CE Power to date. CE power receives PO for emergency power and HCFD requests schedule for this work and 800.
01/25/22 – Outage plan received and under review with TEI and HCFD for 800 Broadway.
02/23/22 – Outage plan approved for 800 Broadway – TEI and JN reach out to CEPower for schedule.
04/27/22 – HCFD and TEI pushing CE Power to schedule work. Pending CE Power Availability.
06/28/22 – 222 cleaning scheduled on 07/09/22. meetings for balance of buildings to be scheduled the week of 07/11/22.
08/24/22 – CE power to provide proposed schedule for balance of buildings. CE Power stated that they will be providing load monitoring (proposed dates are 09/01/22 and 09/02/22). The proposed schedule for the balance of the buildings is due to John Nest and Mike Barth by end of day on 08/25/22.
09/26/22 – A&D building work site work performed. Duke issues with identifying the location of the emergency feed, caused a re-schedule of the outage.
10/26/22 – Next building (2020) outage plan meeting with users scheduled for 10/31/22.
01/25/23 – 2020 work completed with minimal issues. Pre-outage walk throughs occurred for the CH and for the TPC. Outage plans are in development with CE Power and outages will be scheduled upon approval of outage plans.
03/29/23 – CH work completed. There were issues with one server circuit not backed up and 120 gear maintenance was aborted. 480 gear completed. TPC gear remains to be PM’ed.
04/27/23 – TEI places to call to Qualus to discuss TPC. Qualus not returned call to date.
05/23/23 – TEI and HCFD meet with Qualus on site to discuss the project, alternates to the project, and the possibility of moving the Duke Energy bus duct. Pending quotes from Qualus.
06/28/23 – Pending quotes from Qualus.
10/26/23 – TEI and HCFD working to get Qualus to coordinate and work with Beam repair in basement. Once the coordination is complete, the work at TPC will be scheduled and project will then be complete.
12/06/23 – HCFD send Qualus CO for additional work. Upon receipt of CO the final work to be scheduled.
03/27/24 – TPC work to be completed likely in June/July of 2024. NOTE – add the Emergency generator gear on loading dock to list of gear to be maintained.
05/29/24 – HCFD, TEI and Qualus coordinating dates for final building. Once scheduled, website will be updated with date scheduled.
08/28/24 – TPC work scheduled for 09/07/24. Project will be complete once TPC work is completed and all reports and closeout documents received for Qualus.
09/25/24 – Switchgear cleaning occurred at TPC. Project complete pending final closeouts.
Electrical Switchgear PM Specs – 2020 Read More »
PM – John Nester, Mike Barth
01/28/20 – TEI authors and submits SOSS for project upon request of Facilities Department.
01/30/20 – This in in the approved projects list.
02/26/20 – TEI receives PO and signed SOSS for project. TEI to schedule kickoff meeting with facilities and building manager to kick off the project.
03/26/20 – TEI, County Facilities, and building manager to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI met with Bryan Collins and Ian Zellner to re-kick off the project. TEI contacting Joey Downs at Buckeye Power to re-evaluate the proposed solutions and add any updated recommendations/parts-pieces to develop the drawings and specifications.
08/21/20 – TEI contacts Buckeye Power to follow up on the initial quotation that Buckeye submitted. Design has commenced and coordination with EMI equipment supplier. We will notify HCFD once design review is ready.
09/23/20 – TEI, HCFD, and Ian meet with BPS, review the two options for the HMI replacement that BPS submitted. TEI and HCFD requested Sole Source letter from BPS. TEI developing Construction Documents for permitting and construction.
10/27/20 – TEI receives Sole Source letter from BPS. Working on permitting package – will provide draft of package for HCFD review once funding is released for the project.
12/09/20 – TEI wrapping up permitting package, and will send HCFD a review set prior to holiday break for review and to prepare for a January 2021 issuance.
01/26/21 – TEI sends JN at facilities a review set for the project. Upon facilities department review – TEI to finalize bid package and send to get costs.
02/23/21 – TEI and JN establishing final design review meeting with Ian Zellner and Comm Center Staff (within the next week), and will discuss dates for walkthroughs, etc at the meeting, then the project will be sent out for bidding.
03/24/21 – TEI receives sole source letter (modified as requested by Hamilton County). TEI and HCFD meet with the staff at Comm Center, and can issues the project once the procurement method is determined (sole source or ITB). purchasing approves sole source letter on 3/24/21. TEI and HCFD to conduct final meeting to finalize bidding documents ASAP.
04/28/21 – Per HCFD request – TEI requests a current quote from BPS, that has not expired. BPS confirms on 4/28/21 the latest version that we have recieved. Project to be issued upon receipt of this information from BPS and HCFD approval.
05/26/21 – TEI Submits Package to HCFD – who sent to prosecutors office for review and comments. Will issue to BPS upon prosecutor approval.
06/23/21 – Contracts mailed to BPS for signature and return to HCFD. Upon receipt of signed contracts, project will be approved and PO issued.
07/28/21 – PO issued to BPS for project. TEI and HCFD to schedule meeting with BPS to kick off construction and get leadtimes, etc.
08/26/21 – Construction pending procurement of equipment.
10/26/21 -Construction pending procurement of equipment. Anticipated to be Nov/Dec work.
12/13/21 – BPS on site starting today to install upgrades in the gear. Anticipate project work completed by end of the week.
01/25/22 – Work completed on the original contract work. HCFD requests quote from BPS for a replacement breaker to use incase of a breaker failure. BPS issues the quote and HCFD issues a PO for quote. BPS to purchase breaker.
02/23/22 – Upon receipt of breaker from BPS, project will be complete.
04/27/22 – Breaker received. Training completed. work from BPS completed. Upon receipt of closeout documents (AIA) from BPS – project complete.
05/26/22 – Upon receipt of closeout documents (AIA) from BPS – project complete.
06/28/22 – Project complete.
Comm Center – Electrical Service Upgrade Read More »
PM – John Nester, Mike Barth
01/28/20 – TEI authors and submits SOSS for the project requested by Facilities.
02/26/20 – TEI receives PO and signed SOSS. TEI and Jessica Powell request design kickoff meeting with 2020 staff. Project kickoff meeting to be scheduled ASAP and design to commence thereafter.
03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project Pending COVID-19 restrictions.
05/27/20 – Project pending COVID -19 restrictions.
06/23/20 – Project Pending COVID-19 restrictions.
07/29/20 – TEI meets with Rycca and Joe Houlihan to re-kick off the project. TEI re-booted the design process. Design fieldwork to be scheduled in the next 2 weeks or so.
08/21/20 – TEI completes field work and is working on completing design. TEI reaching out to Darryl Meadows (CFD) to schedule 85% complete review meeting with CFD and Bldg Department to get buy in on design with the AHJs prior to sending to HCFD for design review.
09/23/20 – TEI meets with Darryl Meadows, at the facility to review the design documents. Darry indicated that there is no BDA in the building presently, and that the City Ordinance requires a 3rd Party company (i.e. MobilCOMM) perform a spectrum analyzation of the building. TEI contacted MobilCOMM to obtain a quotation for the analysis. TEI will schedule a meeting to review design documents with HCFD – discuss option of Mass Notification, and latest Code changes that have been issued by NFPA 72, but that have not been adopted by the City of Cincinnati to date.
10/27/20 – TEI receives quotation from MobilCOMM for spectrum analysis for the building. TEI to schedule the test at a date that is approved by building manager. Upon receipt of the results of the testing – documents will be finalized and a review set will be sent to HCFD once funding for the project is secured.
12/09/20 – Spectrum Analysis scheduled for 12/15/20 with MobilComm. Upon receipt of results of analysis, TEI can send 99% set to HCFD for review in preparation for a January 2021 issuance.
01/26/21 – MobilComm provides spectrum analysis of the building, and a BDA for the project is not required for the building. TEI requests final design review meeting, and upon notification that funding is secured for project, will finalize ITB and issue for bidding.
02/23/21 – Project has been issued for bidding as ITB# 029-21. Pre-bid meeting scheduled for 03/09/21 and bids are due to purchasing on 03/24/21.
03/24/21 – Bids opened on 03/24/21 – and apparent low bidder is DeBra Kuempel, Inc. ThermalTech is vetting bids at 1:30 on 03/25/21 and will make recommendation ASAP to facilities upon completion of vetting process.
04/28/21 – Construction pending approval of contract by BOCC.
05/26/21 – PO and contract sent to DK on 05/25/21 – kickoff meeting to start submittal process requested with DK.
06/23/21 – JCI/Simplex developing submittals for the project. Upon approved submittals, construction will commence.
07/28/21 – TEI rejects (revise/resubmit) original submittals for the project. TEI receives revised submittals on 07/28/21. TEI to re-review and send approved submittals to DK for project. Project construction kickoff meeting can be schedule in next 2 weeks.
08/26/21 – HCFD and TEI host pre-construction meeting at the project site with Bldg Mgr, Brian Bell and Wayne McFarland. DK has PO and permits have been submitted for at are pending review comments from JCI Simplex. Materials from JCI have been released and are pending mid September delivery. DK tentatively scheduling mid/late September mobilization to the project site.
10/26/21 – TEI requests timeframe from DK for mobilization. Accoriding to JCI and DK, nearly all materials have be shipped to DK and work can commence.
01/25/22 – Project is in construction. Backbone installed and DK has been working to pull second conductor to the notification appliances. Work continues and in the next couple weeks will be working in the housing areas where residents will need to be temporarily relocated.
02/23/22 – Construction continues. There are issues with the current Siemens smoke control system that the building manager is working with Siemens to resolve. by first of next week, will be ready to start cutting over the units to the new system. Meeting scheduled on 02/28/22 with housing unit staff to discuss and plan for relocation of residents during the installation.
04/28/22 – Met this week on site to do more fieldwork, Project should be complete in June 2022.
05/26/22 – Project nearing completion. Inspections will be scheduled mid-late June for CFD and building department.
06/28/22 – Pretesting of smoke control system scheduled on 06/29/22. Upon successful completion of smoke control system, inspections to be scheduled.
07/27/22 – Inspections to start next week. Smoke control system work completed and tested.
08/24/22 – Inspections going well. Building Department on site 08/25/22 (during this meeting) finishing inspections. Will need to return once sampling tubes are replaced with correct tubes. Then training and closeout can occur.
09/26/22 – All inspections complete and passed! Finalized. Upon completion of installation of access panels in the ceiling, project will be complete.
10/26/22 – Project completed. Project pending close out documentation.
12/15/22 – TEI performs punchlist. Still pending closeout documents.
01/25/23 – TEI receives close out documents from DK and reviews. TEI requests minor updates. Upon receipt of minor updates, Closeout documents will be submitted and project will be complete.
02/23/23 – Project ready to archive next month.
2020 – Fire Alarm System Upgrade Read More »
02/26/19 – Facilities requests SOSS for WiFi System Design based upon Study that was completed in May 2016. TEI authors and Submits SOSS.
07/24/19 – TEI completes design. TEI has 100% design review meeting with HCFD, CMSNet, and Bradley Bedacht (Courts) and delivers copies of completed drawings and project manual for review. TEI inquires on 07/23/19 with BB if there are any comments. Upon receipt of comments, TEI will contact purchasing to establish ITB # and bidding dates.
08/27/19 – ThermalTech recieves final comments from the owner. Project was issued for bidding. The pre-bid meeting is scheduled for 09/04/19 at 10:00 AM. final bids will be due through the purchasing department at 11:00 AM on 09/20/19.
09/25/19 – The bids opened on 09/20, Glenwood Electrical Services is the apparent low bidder. ThermalTech is vetting the bid to make recommendations for a contract.
10/30/19 – ThermalTech has vetted the bids, and made recommendations to the HamCo for moving forward. Once contracts are completed, a pre-construction meeting will be scheduled with the contractor and the design team.
12/11/19 – Project executed and the purchase order delivered to Glenwood electric for the project. Glenwood sends TEI submittals for review on 12/10/19. Glenwood developing site specific safety plan and schedule for review. Glenwood submits list of employees for BGCs. upon approval of BGCs, will mobilize to the project. Anticipate mobilization early January 2020.
01/28/20 – ThermalTech rejects the submittals for non compliance – waiting for Glenwood to re-submit. According to Glenwood – the BGCs are in progress. Mobilization date is TBD.
02/26/20 – TEI approves and returns all re-submittals – Glenwood stated that their LV guys have the BGCs completed and returned, but the electrical crew has no BGCs returned yet. Materials have been ordered and Glenwood to contact HCFD to schedule mobilization. Glenwood has not gotten badges yet for any of their crew – I said to look closely at the info from HCFD – as there are only specific hours that badges can be made.
03/26/20 – Construction progressing, through the building. Glenwood began construction in the basement and are working their way up through the building. Glenwood’s Electrical guys will be complete by 04/01/20. Glenwoods low voltage guys are currently working on the 2nd floor.
04/30/20 – Project installation nearing completion. Glenwood schedules heat mapping of new system for May 15. TEI and facilities perform punchlist. TEI issues Punchlist.
05/27/20 – Heat mapping postponed until May 29 due to none communicating ports. Once heat mapping is complete, TEI and HamCo (Facilities and courts) to review and make comments for any final adjustments.
06/23/20 – Heat mapping completed on 05/29. There were multiple areas in the building where the heat mapping company did not scan the areas and marked on the report that the levels were below acceptable/expected levels. Upon review, all parties including Glenwood agreed that the heat mapping in those areas would be re-scanned. The re-scan was scheduled for 06/19, and floors 1 and 2 were re-scanned prior to a failure of the scanning device. The heat mapping company is scheduled to return to the courthouse on Friday 6/26 for floors 3 and 4. New reports will then be issued and reviewed by the team (Courts/Facilities and TEI).
07/29/20 – TEI reviewed revised heat maps with HCFD and Bradley Bedacht from Courts. There are a few minor modifications that need to take place, and the courts have been asked if there are any additional modifications that they would be interested in prior to project closeout. Bradley to coordinate the rollout of the new wifi system with telecom.
08/21/20 – TEI, HCFD, Telecom and Bradley Bedacht meet to roll out new system. New system turned on and running on 08/14/20. Glenwood scheduled to train on 08/24/20, and swap the (7) APs that are on the hcpub SSID to the CHPublic on the same day as training. Courts has published the passwords for the SSIDs and after the change over, the hcpub network will be shut down in the courthouse and demo of old system components can occur.
09/23/20 – Project nearly complete – switched over to new system. TEI issues request for CO pricing to add a WAP in room 415, and relocate (2) WAPs for better coverage. TEI receives email from BB stating that there may be a couple additional adds. Glenwood requests walkthrough to confirm understanding of changes. TEI to schedule the week of 9/28.
10/27/20 – Glenwood electric is scheduled to be on site 10/27/20 at 4:00 PM to make the final connections for the Change Order work. Once completed, as-builts and close-out document will be turned in and project can be closed out.
12/09/20 – Closeout documents and as-builts submitted to HCFD. final Pay applications submitted to HCFD. Project complete.
12/10/20 – Courts said so far so good. Proejct ready to archive.
CH – WiFi System Design Read More »
06/26/19 – TEI authors and submits SOSS for project. Project pending approval of SOSS and PO.
07/24/19 – TEI receives approved SOSS and PO. TEI to establish kickoff meeting with facilities and begin project.
08/27/19 – TEI to kick off this project once server room project is issued for bidding
09/25/19 – TEI is gathering data from the other projects for this report. TEI to schedule meeting with HCFD for kick off meeting.
10/30/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
12/11/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
01/28/20 – TEI has report well in process and will submit draft upon completion.
02/26/20 – TEI has report near completion – pending one manufacturer (GE) responses. Draft report to be submitted upon receipt and review of GE data.
03/26-20 – TEI to send to Facilities draft of report by 04/01/20.
04/30/20 – TEI send draft report to facilities for review. TEI receives comments from facilities. TEI modifying final report.
05/27/20 – TEI to finalize report for submission to facilities.
06/23/20 – TEI to finalize report for submission to facilities.
07/29/20 – TEI to finalize report for submission to facilities.
08/21/20 – TEI to finalize report for submission to facilities.
04/28/22 – Ready to archive.
Electrical Findings Study and Report Read More »
05/29/19 – ThermalTech authors an SOSS for the project – pending SOSS approval and PO.
06/26/19 – Project Pending approval of SOSS and PO.
07/24/19 – Project pending approval of SOSS and PO.
08/27/19 – Project pending approval of SOSS and PO.
09/25/19 – Project pending approval of SOSS and PO.
10/30/19 – Project pending approval of SOSS and PO.
12/11/19 – Project pending approval of SOSS and PO.
01/28/20 – Project pending approval of SOSS and PO.
02/26/20 – Project pending approval of SOSS and PO.
03/26/20 – Project pending approval of SOSS and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
06/25/20 – Latest discussion was to just archive this project as it is not needed at this time. OK to archive.
Comm Center – Lower Level Quiet Room Read More »
05/29/19 – Hamilton County requests SOSS for the project.
06/26/19 – TEI submits SOSS to facilities. Project pending SOSS approval and PO.
07/24/19 – TEI receives signed SOSS and PO for project. TEI, Facilities and JFS to conduct project kickoff meeting on 07/25/19 to begin project.
08/27/19 – ThermalTech emails Claude T to request 100% review meeting for a time on (or around) 09/11/19. After final review comments, project will be issued for bidding.
09/25/19 – ThermalTech, HCFD, and JFS meet to review 100% documents. HCFD send TEI federal procurement requirements. TEI adds to the project manual and submits to HCFD for review by prosecutors office. Project will be issued for bidding upon receipt of comments from the prosecutors.
10/30/19 – Project will be issued for bidding upon receipt of comments from the prosecutors.
12/11/19 – Project bids received, Glenwood Electric is apparent low bid on the project. TEI vetted bid and submitted recommendation that HamCo proceed with authoring the contract with Glenwood.
01/28/20 – Upon approval of contract and issuance of PO to Glenwood Electric, a pre-construction meeting will be scheduled and the project construction will commence.
02/26/20 – Glenwood’s PO and contract approved. Construction kickoff meeting scheduled for 02/27/20 at 1:00 PM.
03/26/20 – Construction kickoff pending the return of the background checks.
04/30/20 – Construction began – paused due to non-shipment of parts from MFGR. Glenwood clarifying scope and working to get actual ship dates.
05/27/20 – Construction underway. Control cabinets installed in basement through 7th floor on west end of the building. Controllers installed on 6,5, and 4 on the est end of the building. power supplies ordered and pending on time delivery, power supply install anticipated to start on or around June 1. Anticipated project completion is end of June.
06/23/20 – All controllers are installed. All power supplies have been installed and powered. Glenwood and Claude Toulsen are working to develop new badgeing standards (photos, logos, facility codes, etc). Upon completion of the badge standardization process, and all of the JFS data is updated to new standard, the database will be imported to the Kantech system and the system will then be migrated over to the new system.
07/29/20 – JFS is working with Glenwood to transition old database into the new database, and upon completions of the development of the new database, new system pretty much ready for rollout. The door on the southwest corner of the Parkhaus Garage is on the old system, and will not be functional after change over without adding to system. Glenwood provided pricing for changeover. HCFD, JFS, AMB and A&S to determine next steps.
08/21/20 – Glenwood waiting on Pictures from JFS to include in the software before they can transition over to Kantech system. Glenwood working to respond to punchlist information that the installation is not in compliance with the specification.
09/23/20 – JFS completes their preparation work with the new employee photo database. Discussion occurred when Glenwood stated there was no additional expandability in the new system. TEI provided documentation of the basis of design product had substantial expandability built into the system. Glenwood ordered additional cabinets to provide the expandability that was included in the specifications. Glenwood to begin installation of additional cabinets and the associated programming on 9/28. Estimating 2 additional weeks from then for completion of installation. Upon completion of installation, TEI will perform final Punchlist and process closeout documents.
10/27/20 – Glenwood is on site programming all cards and integrating the new database. Additional batteries are on site, however, additional power supplies were back-ordered, and are scheduled to ship 10/30/20. Will be installed upon receipt.
12/09/20 – Glenwood on site doing switchover to new system. All upper floors are on the new Kantech system, and the new doors in the basement and sub-basement are installed and on the new system. Exterior doors are scheduled to be switched over on 12/14/20, and building staff and Sheriff’s office has been notified and is planning for the switchover.
01/26/21 – TEI and Matt Butz performs punchlist for project. Upon completion of Punchlisted items and closeout, project will be complete.
02/23/21 – TEI and Rycca Thacker perform punchlist back-check. TEI requests final closeout documentation from Glenwood to close out the project.
03/24/21 – TEI receives and is reviewing the O&M manuals from Glenwood. Upon approval of O&M Manuals, TEI will deliver to HCFD. TEI and Glenwood working to provide all close out paperwork for the project.
A&D – Access Control System Design Read More »
05/29/19 – Hamilton County requests SOSS for the project.
06/26/19 – TEI submits SOSS for approval. Project pending approval of SOSS and PO.
07/24/19- Project pending approval of SOSS and PO.
08/27/19 – Project pending approval of SOSS and PO.
09/25/19 – Project pending approval of SOSS and PO.
10/30/19 – Project pending approval of SOSS and PO.
12/11/19 – Project pending approval of SOSS and PO.
01/28/20 – Project pending approval of SOSS and PO.
02/26/20 – Project pending approval of SOSS and PO.
03/26/20 – Project pending approval of SOSS and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
07/29/20 – Project pending approval of SOSS and PO.
08/21/20 – Project pending approval of SOSS and PO.
JC – Parking Lot EV Charging Station Study Read More »
05/29/19 – Hamilton County requests SOSS for the Project.
06/26/19 – TEI submits SOSS to facilities. Project pending approval of SOSS and PO.
07/24/19 – Project pending SOSS approval and PO.
08/27/19 – Project Pending SOSS approval and PO.
09/25/19 – Project Pending SOSS approval and PO.
10/30/19 – Project Pending SOSS approval and PO.
12/11/19 – Project Pending SOSS approval and PO.
01/28/20 – Project Pending SOSS approval and PO.
02/26/20 – Project Pending SOSS approval and PO.
03/26/20 – Project Pending SOSS approval and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
07/29/20 – Project pending approval of SOSS and PO.
08/21/20 – Project pending approval of SOSS and PO.
10/28/20 – Okay to Archive.
800 – 4th and 5th Floor Security Read More »
05/29/19 – Hamilton County requests SOSS for project.
06/26/19 – TEI submits SOSS to facilities. Project Pending SOSS approval and PO.
07/24/19 – Project pending SOSS approval and PO.
08/27/19 – Project pending SOSS approval and PO.
09/25/19 – Project Pending SOSS approval and PO.
10/30/19 – Project Pending SOSS approval and PO.
12/11/19 – Project Pending SOSS approval and PO.
01/28/20 – Project Pending SOSS approval and PO.
02/26/20 – TEI receives signed SOSS and PO for project. TEI contacts Jessica Powell and requests project kickoff with 2020 staff. Kickoff meeting to occur ASAP and project to commence thereafter.
03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project Pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI meets with Bryan Collins to re-kickoff project. TEI contacts sub contractor to schedule field investigation to incorporate into the SKM model. field investigations to be coordinated with building manager.
08/21/20 – TEI has Phasor Electric perform field investigation of all of the gear and feeders at the building. Field work notes were sent to TEI on 08/20/20, and the data will now be entered into the model for running calculations.
09/23/20 – TEI processing data from Phasor – and will complete the modeling upon receipt of follow up data requested from Phasor.
10/27/20 – Phasor scheduling back visit to the building to get missed information and then the model will be completed and sent to Hamilton County Safety Consultant for review.
12/09/20 – Phasor returned to site to gather missed information. Finalizing model, and will send through internal review, and then forward to Charlie for his review.
01/26/21 – Model to be sent to Charlie at CMI for review by 01/29/21.
02/23/21 – Model completed and sent to Charlie at CMI for review and comments. Upon receipt of review comments from Charlie, labels will be printed and applied at the building.
03/24/21 – ThermalTech receives comments from CMI and incorporates into the model. Labels printed and building manager contacted to schedule installation of labels – proposed to be installed week of 03/29/21.
04/28/21 – Labels installed on all equipment. TEI to over report to HCFD and project complete.
05/26/21 – Project Complete.
2020 – Arc Flash Modeling and Labeling Read More »
04/24/19 – HCFD requests SOSS from TEI for the project. TEI submits SOSS and receives signed SOSS and PO. TEI requests kickoff meeting the HCFD and all parties . Project start pending project kickoff meeting.
05/29/19 – Design progressing and TEI anticipates that 100% documents will be issued to HamCo no later than mid week (week of June 3).
06/26/19 – Drawing submitted to HamCo for review and no comments received. TEI submits to IBI for plan review and permit on 06/28/19.
07/24/19 – TEI receives plan review approval from IBI, and secures the electrical permit for trades to work on the project. Core drills complete and trades working on electrical modifications for the project. Hamilton County trades to notify ThermalTech when they are ready for the rough in inspection.
08/27/19 – work completed , inspections passed, and the security scanners have been relocated.
CH – West Entry Security Screening Renovations Read More »
01/15/19 – TEI talked to Tony Matre about a new project to power up a new overhead door that will be installed on the attorney entrance on the back of the Courthouse including access control for the door after hours. Mike Barth will lead this project for ThermalTech since it appears to be mostly electric in nature. Overhead door will be allowed to provide equipment for this job. ThermalTech will coordinate this with facilities and the vendor and we can reach out to GBBN for door support as needed. ThermalTech to provide SOSS for this (hand delivered at the 01/31/19 partner meeting).
02/26/19 – Project pending the SOSS approval and PO.
03/26/19 – Project pending the SOSS approval and PO.
04/24/19 – Project pending the SOSS approval and PO.
05/29/19 – TEI receives Approved SOSS and PO. TEI contacts AKM for project kickoff.
06/26/19 – TEI has meeting with AKM, RM, and HCSO to kick off project. RM indicated long range card reader was proposed, but only works with Bluetooth, which the HCSO does not want to use Bluetooth. TEI sends HCFD options to discuss with team and upon reciept of direction will complete drawings for owner review.
07/24/19 – TEI gets quote from DK to install work with Overhead Door as a sub to them and sends to AKM for review/approval. AKM to have install work per the approved design concept (issuance of RF clickers for vehicles that park in the garage, and card reader access control for those not in vehicles with approved credentials in the system.
08/27/19 – DK awarded contract to complete the work. DK scheduling install through Rob Edwards and Tony Matre. This all to be installed as soon as possible. Risk Mgmt is upgrading the access control system in the CH to a Vax system by Vicon. This new system to be Vax, and may be installed before Vax head end.
09/25/19 – DK moving forward with installation. Ramp was trenched on 09/20 and 09/21 with conduit installed to locate reader on the east ramp wall. DK to submit schedule to AKM.
10/30/19 – Overhead Door Company is scheduled (again) to install the door on 10/31/19. Upon installation of the door, DK to coordinate with Risk (who is in having the new access control system installed) to tie in the new card access to the new door.
12/11/19 – Overhead door installed, and DK missed an internal CR. TEI calls DK to inform them to install it. AKM states that there are items on the project that are not installed. Instructs TEI to advise DK that all work associated with his PO to be completed. SK states that the VAX system is incomplete, and AKM says get his PO worth of work installed, and he can close out his work and then the operation of the system is dependent on the completion of the VAX project.
01/28/20 – According to DK – the install of the work associated is complete with the exception of the VAX connections. DK has the door able to be operated with Pushbutton in the guard booth until a time when the VAX system is fully operational.
02/26/20 – HCFD stated that the door shall be interlocked with the FA system to maintain accessible egress path in the event of a FA situation. TEI requests timing and pricing from DK for modifications to the system to interlock with the FA system.
03/26/20 – DK sends in the pricing for the fire alarm interface. AKM asks for cost breakdown.
04/30/20 – Project pending FA interface.
05/27/20 – Project pending FA interface and over ride switch installation.
06/23/20 – Project pending FA interface.
07/29/20 – Project completion pending access control system completion and fire alarm interface.
08/21/20 – DK has been directed that all pending items to be completed prior to Labor Day weekend. The man-trap features will not be active until the entire VAX system is up and running and programmed. All construction work not associated with the VAX turnover to be completed.
09/23/20 – DK installs keypad and card reader so walk-ups (with appropriate access) can operate man trap doors. DK on site on 09/23 working on programming and finalizing the issues with the system.
CH – Overhead Door Project Read More »