230 – Elevator Modernization

PM: Rycca Thacker, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (4) elevators in 230 East 9th Street Building. TEI and Elevar meet to discuss roles on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar SOSS provided to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD. SD meeting scheduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team meets with the Courts committee to review security and finishes. DD documents are progressing.
06/25/25 – Team meets with Court Admins. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027). The contract phase and procurement deposit caused the delay.