230 – East Exterior Lighting

PM = Rycca Thacker, Mike Barth

07/29/26 – HCFD requests SOSS. DEG submits SOSS.
08/26/26 – DEG sends fixture model number to HCFD to get trades to check pricing and lead times. DEG finalizing the plans for permitting and trades to install.
09/23/26 – DEG submits drawings to IBI for approval and permit.
10/28/26 – Permit and plan review approved. HCFD trades has approved plans and permit. Trades to complete the install. DEG will call for inspections once work is installed.

230 – East Exterior Lighting Read More »

111 – Arc Flash Model and Labeling

PM Rycca Thacker, Mike Barth

06/23/26 – DEG receives PO and signed SOSS. Arc Flash Study initiated.
07/29/26 – DEG has nearly the entire single line from the KZF project modeled in SKM software. Next step is to field verify make/model numbers and serial numbers. DEG to schedule with the building manager.
08/26/26 – Study in progress.
09/23/26 – Study progress continues.
10/28/26 – Study complete. Labels to be printed and be scheduled with building manager to apply.

111 – Arc Flash Model and Labeling Read More »

230 – Plumbing Upgrades

PM: Megan, Terry Cannon,
04/30/26 – Project opened on website. DEG started fieldwork and is working on bid CD documents. Need to check on SOSS approval.
05/27/26 – Need to request meeting with new building manager before proceeding. Meeting June 4 at 9am for design meeting with Jesse.
06/25/26 – First review set probably ready in July.
07/30/26 – Plumbing ready for review, electric will be ready soon then to County for Owner review.
08/26/26 – Review sets sent to County and limited comments received back. Floor plans updated. The project will be ready to bid soon.
09/15/26 – Prebid
09/18/26 – Addendum 1 issued.
09/22/26 – Addendum 2 issued.
09/24/26 – Bid due Friday.
09/25/26 – Bids received. Triton and QCM Mechanical submitted bids. DK and others did not bid the project.
10/22/26 – Facilities notified DEG that the bids are not awarded due to contract technicalities. TTC informed Triton in person.
10/27/26 – TTC & Rycca discussed how to rebid the job with a few small changes and make it suitable for award. DEG will update the bid documents adn send back out for a price refresh from the same vendors.

230 – Plumbing Upgrades Read More »

230 – 11th Flr Training Rm Acoustics

PM: Rycca, Eryn
04/30/26 – SOSS to be submitted shortly.
05/28/26 – SOSS submitted.
06/25/26 – Acoustic testing occurred 06/19. Consultant will provide design recommendations based on report.
07/30/26 – Report provided by testing consultant to HCFD. Elevar to research other panel providers and will provide report in layman’s terms.
08/27/26 – Report and design options provided. Consultant working on final design images based on actual photos of the space.
09/24/26 – Rendering photo and samples provided to COA.
10/29/26 -Costs provided to COA.

230 – 11th Flr Training Rm Acoustics Read More »

111 – Employee Break Shelter (No ITB)

PM: Rycca, Eryn
eeagle@elevar.com;

04/30/26 – SOSS provided for CA.
05/28/26 – Awarded to Tumlin and Elevar receiving initial Div 01 submittals.
06/25/26 – No update.
07/30/26 – Submittals complete and unit moved into production planning. Contractor will provide stamped drawings soon.
08/27/26 – Contractor will provide stamped drawings soon with Elevar to follow up. Anticipated unit installation in Oct.
09/24/26 – Contractor provided stamped drawings. Anticipated unit installation in early Oct. Elevar/HCFD/GC to meet onsite prior to installation.
10/29/26 – Unit installed. Need closeout docs from GC.

111 – Employee Break Shelter (No ITB) Read More »

800 – Tower AHU Replacements

PM: Matt, Terry, Elevar
03/26/26 – Original SOSS rejected, need XBE on this job. DEG got proposal from Elevar last week and resubmitted on 3/25. Robert approved but need LOI for Elevar. DEG to provide and resend SOSS.
04/29/26 – More fieldwork completed last week with Tom and we have selected which units will be replaced. DEG working with Habegger on new unit selections and putting background drawings together. We will have a kickoff meeting in May with Elevar on electrical work for these units.
05/27/26 – Unit selections are made, we will be ready to meet with Elevar for electrical kickoff first week of June. No real surprises with new units other than they are all converted VVT to VAV units now. ALC controls kickoff meeting discovered that they cannot reuse any of the JCI VFD drives on this project.
06/25/26 – HVAC design progressing, Electrical kickoff meeting held with Elevar, more fieldwork next week. Owner planned end of July.
07/30/26 – Met with owner on design scope. Design continues, Owner review set still planned for end of July. Working on coordination with Emcor and Elevar on scope for VFD’s and electrical needs.
08/26/26 – Another field trip and final design concepts updated for several AHU.  We have meeting with Facilities Thursday afternoon to discuss budget, final scope, and asbestos abatement.  Then we are ready to bid.
09/15/26 – Project Issued for Bid. Bid opening scheduled for 11/12/26.
10/26/26 – Addendums issued bid opens on 11/12/26. Addendum 1 issued. No additional questions have been received as of 10/26.

800 – Tower AHU Replacements Read More »

525 – HVAC Retrocommissioning (No ITB)

PM: Rycca, Terry
Closeout Contact: Will Fisher wfisher@davieseg.com


02/24/26 – SOSS submitted for CX work.
03/25/26 – No updates.
04/29/26 – SOSS received last week. Internal kickoff meeting yesterday. Client kickoff meeting scheduled for Friday.
05/13/26 – DEG on site for initial fieldwork and discovery meeting.
05/20/26 – Internal meeting with Emcor & Habegger for RTU retro commissioning at 525. Commissioning is set for 5/28/ and 5/29 with Will Fisher, Emcor and Habegger.
06/25/26 – Bison currently repairing RTU-4, Triton currently upgrading economizers for RTU-2,3. Once complete CX will continue. Graphics updated to match other buildings.
07/30/26 – Bison repaired their units. Parts delayed on Triton units until 8/5. After economizers are programmed CX continues.
08/26/26 – Final parts came in yesterday and Triton is scheduled on site 8/27 to install missing parts for these units, then final commissioning will begin.
09/23/26 – DEG and Emcor met earlier this month and finalized the commissioning for this building and set final report to HC. Outstanding item are the exhaust fans in the main warehouse which are owner items to troubleshoot and repair.
10/26/26 – All work is complete the retro-commissioning is complete, final report sent to the County.

525 – HVAC Retrocommissioning (No ITB) Read More »

Colerain – Animal Shelter – (F037)

PM: John Millar/Emily Phillips
01/30/26 – THP issued SOSS for review.
02/17/26 – Hamilton County approved the SOSS.
02/18/26 – THP completed preliminary field survey.
02/26/26 – THP working on repair documents.
03/25/26 – THP finalizing document review set for review with HC early April.
04/27/26 – THP published Owner review documents.
06/25/26 – THP working on Bid Documents.
08/26/26 – THP working on Bid Documents with included demo walkway.
09/22/26 – THP published DD documents.
09/24/26 – Project plans to publish bid documents 9/28/26.
10/13/26 – Prebid meeting occurred.
10/16/26 – Addendum No. 1 issued (prebid meeting minutes).
10/29/26 – Project update – Bids due 11/23/26.

Colerain – Animal Shelter – (F037) Read More »

Comm Center – Electrical Assessment

PM = Rycca Thacker, Mike Barth

02/25/26 – HCFD requests SOSS. DEG to prepare SOSS for submission.
03/25/26 – No updates. DEG to submit SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – DEG receives signed SOSS and PO. Assessment underway.

Comm Center – Electrical Assessment Read More »

Comm Center – Electrical Device ID and Arc Flash

PM = Megan, Mike Barth

02/25/26 – HCFD requests SOSS for project. DEG to Provide SOSS.
03/25/26 – No updates. DEG to finalize and submit the SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – HCFD asked for revised SOSS with Electrical Sub included in price. DEG to receive quote from Edge Electrical Contractor by 10/30/2026 and will then resubmit.

Comm Center – Electrical Device ID and Arc Flash Read More »

TPC 9th Floor JFS and CoC Renovation

County: PM Rycca Thacker – Champlin PM: Sam Hofmann

02/26/26 – SOSS received for JFS portion of work. Design team verified existing conditions. SD plans and estimate in progress.
03/26/26 – SD plans and estimate in progress.
04/30/26 – SD plans and Estimate to be submitted to County next week.
05/28/26 – SD plan and estimate submitted to county for JFS work. CoC work is put on hold until further notice.
06/25/26 – No Update.
07/30/26 – No Update.
08/28/26 – CoC approved. SD plan and estimate to be uploaded to Archibus.
09/24/26 – Re-kick off to be scheduled.
10/29/26 – No Update.

TPC 9th Floor JFS and CoC Renovation Read More »

230 – Lobby Security Upgrades

PM: Rycca Thacker, Eryn Thamann
02/26/26: Added as new project. Need meeting with COA/Probate/HCFD to review scope.
03/26/26: SOSS provided for concepts/SD phase.
04/30/26 – No update.
05/28/26 – Will wrap into elevator project. Elevar to provide new SOSS and will work on design options.
06/25/26 – SOSSs in process for approval with HCFD now.
07/30/26 – Concepts reviewed at initial meeting and working thru final concept now. Will review with HCFD prior to scheduling full group meeting. 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
08/27/26 – A third option for the rear secure elevator area was discussed with Rycca and will be provided this week. Another meeting with the main group will then be scheduled. Exterior Lighting portion broken back out to separate project.
09/24/26 – A third option was provided to the entire group and another meeting was held. Another revision was sent to entire group for input and potential third meeting.
10/29/26 – Another mtg was just held and option 7 is under design.

230 – Lobby Security Upgrades Read More »

Colerain – Kitty City Electrical Upgrades

PM = Megan, Mike Barth

01/28/26 – HamCo request SOSS for Electrical Upgrades for Kitty City. DEG submits SOSS. DEG receives approved SOSS and PO on 01/28/26. DEG coordinating meeting with Duke.
02/25/26 – DEG meets with Duke to discuss power options. DEG proceeding with load calculations to send to Duke for service sizing.
03/25/26 – DEG develops drawings for electrical upgrades. Final field work scheduled for 03/31 at 7:30 AM to confirm final details.
04/29/26 – DEG submits 100% review drawings and OPCs to HCFD for comment/approval. Upon receipt of comments, ITB will be submitted.
05/27/26 – DEG meets with bldg mgr – adds a couple of alternates for additional outlets and also replace thru wall fans with new with humidistats.
06/23/26 – Drawings sent to HCFD for review.
07/29/26 – Upon receipt of HCFD review comments and/or approval, ITB package will be finalized and issued.
08/26/26 – Meeting scheduled for 08/28/26 with CARES to review and receive approval. Goal setting worksheet submitted (pending approval).
09/23/26 – Project issued for bidding. Prebid meeting occurred on 09/23. Bids are due on 11/12.
10/28/26 – Project in bidding phase. (1) addendum issued.

Colerain – Kitty City Electrical Upgrades Read More »

800 – HVAC Controls Upgrade (STS)

PM: Terry Cannon, Tony Matre
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com

 


08/19/25 – Kickoff discussion with Emcor.
11/18/25 – Emcor running low voltage at the building for new DDC network.
12/09/25 – Const Mtg and meeting minutes distributed.
01/08/26 – Const Mtg. Emcor making progress on equipment in the basement and on the first floor. They need help with access to some rooms that are under HCSO control.
01/20/26 – Const Mtg and new schedule released. Emcor gearing up for Chiller plant programming in March. Joe says they will take care of the 6th floor network cable. AM reports it is still not in the right place. The switches are in place and ready.
01/21/26 – Emcor shared missing submittals with DEG on VFD’s.
02/25/26 – Work continues as Emcor is planning on working on the chiller plant in March.
03/25/26 – Work continues, chiller plant programming in progress. Emcor ready to commission when building starts the chilled water plant for the season.
04/28/26 – Const progress meeting with Emcor held with DEG, Tom and Emcor. Small progress being made on new controls. Emcor asked to start boiler plant this week, it was decided to wait because of cold weekend temperatures. Tom had issues with chiller operation, Emcor found chiller in manual and released it. Emcor did some training with Tom to show him how to use new system but Graphics are not complete yet and the chiller plant is not fully programmed yet. Emcor to work on graphics, updated chiller programs and preparing for heating plant integration.
05/25/26 – Const Meeting held adn Emcor reported they started the boiler plant upgrades and they are making good progress. The communication infrastructure is in place for the future upgrades and the 800 Tower units can be added to it.
06/25/26 – Const meeting held last Tuesday, working out graphics updates and final controls work. Tom requested training.
07/30/26 – Project nearing completion, chiller sequences being updated.
08/26/26 – Project is complete and in commissioning. PCHWP-2 has an issues that DEG will be on site troubleshooting on Thursday.
09/23/26 – DEG met onsite to review chiller operations. DEG recommends to follow DK recommendation to replace thermal overloads on PCHWP-2. Tony said that Craig could perhaps replace these since they are less than $100. That is our recommendation as well. DEG updating the PID to new conditions after replacement of CH-2.

800 – HVAC Controls Upgrade (STS) Read More »

Winton – New Animal Shelter Building

PM: Rycca Thacker, Mike Murphy, Terry Cannon
12/11/25 – Land purchase is complete. The new building should be online by September 2029-ish.
02/26/26 – SOSS and PO received. Site investigation has begun. Kickoff to be scheduled sometime in March.
03/26/26 – Kick-off held with County, Cares and design partners. Geotech will begin investigation shortly. SPoA to send out programming survey shortly.
04/30/26 – Geotech beginning their scope. Needs assessment confirmation meeting on the calendar for 6/3.
05/28/26 – Data collection teams meeting held on 5/12. CARES needs to confirm some operational questions to prepare for the needs assessment on 6/3.
06/25/26 – Programming verification meetings complete. CARES will review and compare data to existing concept plan.
07/30/26 – SPoA to provide final program report.
08/28/26 – Programming report provided to CARES for review. Add services for Geotech approved. Additional testing scheduled for first week of september.
09/24/26 – Additional clearing needed for geotech. Approval pushed new borings until October. Program verification meeting held and concept plans incoming.
10/29/26 – Concept plan presented. CARES provided comments. SD plan in progress.

Winton – New Animal Shelter Building Read More »

All Buildings – Space Allocation Drawings

PM: Rycca Thacker, Eryn Thamann
12/11/25 – SOSS requested for space allocation drawing updates. Awaiting final building priority list from HCFD to finalize SOSS.
01/29/26 – Elevar working on SOSS.
02/26/26 – Elevar provided SOSSs.
03/26/26 – SOSSs approval pending.
04/30/26 – SOSS approved for three buildings. Need schedule from HCFD for access hours, building priority, and deadlines.
05/28/26 – Waiting for Elevar badging to be finalized.
06/25/26 – Started scanning of 1701 06/22 and will last the week. Drawings will be updated as scans come back and starting with JFS areas for leasing diagrams.
07/30/26 – Working thru 1701 set and met with HC IT Dept to review on 07/23. Scanning complete for 111 Tri-Co. Scanning scheduled at TPC for 08/10-08/14.
08/27/26 – Provided 1701 CAD and pdf files. Just received pdfs files of the parking garage and will bgin on those soon. Scanning completed at TPC and 111 Tri-Co. As staff area vailable, these drawings will be checked against scans.
09/24/26 – CAD files received of 1701 parking garage from Champlin to complete that portion of work. Files for 111 are almost complete and sent to HCFD for indications of tenant spaces. Templates for 138 are complete.
10/29/26 – Working thru TPC now.

All Buildings – Space Allocation Drawings Read More »

CH – B95 Office Suite Renovations

PM: Megan, Sam
10/30/25 – This project went out to bid this week. Sam will send out invites for prebid and bid opening.
12/11/25 – Triton is low bidder. Project in contract phase.
12/12/25 – Furniture and two drawer cabinets can be located close to the hot water radiators, they just have to be moved if we ever need to service the units.
01/28/26 – Contract goes in front of the board today. Bulletin #1 will go out next week with the changes requested from Rycca.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. Project mobilization to be scheduled by County.
05/28/26 – Project tentative start on 8/10/26.
06/25/26 – No update.
07/30/26 – Submittals are being returned. Project start has adjusted to 8/31.
07/30/26 – RT said we may get new direction on final design for this space. We may need another Bulletin for this project.
08/28/26 – Mobilization on hold until scope changes are settled.
09/24/26 – Scope changes received. Bulletin is being prepared.
10/29/26 – Bulletin will be issued to Triton upon approval

CH – B95 Office Suite Renovations Read More »

Dane – Security System and Exterior Lighting

PM: Matt Butz, Mike Barth
10/30/25 – Project was sent out for bid, DK sent in questions with options. Security lighting prebid also held.
12/10/25 – Project small projects bids received. Glenwood awarded the bid. Contract in finalization phase. Submittals and construction to commence once the contracts are approved.
01/28/26 – Project contracts and PO sent to subs. Meeting dates for KO meeting requested from contractor.
02/25/26 – DEG and HCFD meet with Glenwood on exterior lighting. Installation of drawings pending light fixture procurement (approx mid March).
03/25/26 – Exterior lighting installed. Play yard lighting levels requested to be increased. DEG performs lighting study to increase the lighting levels. DEG sends to HCFD.
04/29/26 – Play yard lights installed last week. All exterior lighting complete. Security cameras work to commence upon the completion of Central Campus work.
05/27/26 – Play yard lights permitted and inspected (final inspection passed). Cameras are kicking off beginning of June.
06/23/26 – DK has mobilized to the project site to install the cameras. installation is underway. Weekly project meetings scheduled.
07/29/26 – Installation underawy. Most of access control installed. Cameras are being installed and cabling installed with the GSA vendor.
08/26/26 – Installation will be finalized when ISWP installed at the location.
09/23/26 – ISWP installed by technical services. Installation finalization and connections scheduled with DK.
10/28/26 – Installation of cameras nearing completion.

Dane – Security System and Exterior Lighting Read More »

All Buildings – Emergency Switchgear PM

PM: Rycca Thacker, Mike Barth
10/30/25 – The project is out for bid, prebid is scheduled for November.
12/10/25 – Bid opening occurred. Zero bids received.
01/28/26 – HamCo asks DEG to re-package and resend out to bid.
02/25/26 – No updates this month. DEG will compile all data and send list of buildings that information is still pending.
06/23/26 – DEG contacts all building managers to confirm that there have been no modifications to the critical load lists for each building. A review set will be sent to HCFD end of June.
07/29/26 – DEG has not received responses from buildings.
08/26/26 – ITB pending the advertised estimate from HCFD and then goal setting worksheet approval.
09/23/26 – Project in bidding phase. Prebid meeting was held on 09/22. Bids are due 11/12/26.
10/28/26 – Project in bidding phase. (2) Addendums Issued.

All Buildings – Emergency Switchgear PM Read More »

TPC – Mechanical Room Door Replacement

PM: Jesse Estes, Sam Hofmann

08/28/25 – Field visit to confirm scope.
09/25/25 – Review set submitted to county. Project will be going out to bid next week.
10/30/25 – Project in Bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. County to schedule mobilization.
05/28/26 – Tentative start date of 7/6/2026.
06/25/26 – No Update.
07/30/26 – Tentative start has been pushed back to 9/8.
08/28/26 – No update
09/24/26 – Project has not started yet.
10/29/26 – 16 doors and frames have started. Project ongoing.

TPC – Mechanical Room Door Replacement Read More »

RSC – Regional Safety Complex Phase 2

PM: Rycca, Murphy, Toombs
09/25/25 – Design schedule has been updated such that final CD documents to be completed and bid in November 2025. Design documents are about 60% complete at this time.
10/29/25 – 90% Drawings, specifications, and cost estimates sent to Owner this week.
12/12/25 – Phase 2 drawings are in for owner comments. Bert said that he would get those back later this week. We are shooting for bidding first of January.
01/25/26 – MEP drawings and specification sent to Champlin Issued for Bid. They are stamped and signed. The targeted bid date is 02/02/26, Champlin reviewing all final documents in the set now. DEG is trying to onboard an AV and IT specialist for this job. We have not received his PO yet, Bright Technologies.
1/28/26 – THP submitted Bid & Permit set 1/21/26. will go out 2/3. Construction is expected to start in April.
02/26/26 – Budget has been approved and sent to Robert Bell for approval. Waiting on Cincy approvals to go out to bid. We are shooting for mid March issuance.
03/26/26 – Project is out to bid. Pre-bid scheduled for 4/2.
04/30/26 – Bid opening pushed back to 5/21. Sniper tower scope was pulled out as an alternate.
05/28/26 – Graybach was apparent low bidder. Bid vet to be scheduled in near future.
07/30/26 – A305’s requested from bidders. Waiting on direction from County. Not sure we have received them yet.
08/28/26 – Graybach awarded the project.
09/22/26 – THP – CA on going, reviewing RFI’s/Submittals.
10/29/26 – Permits submitted and almost ready. Dave commented that general waiting on fire inspector. Driveway permit is expiring next month. Plumbing submittals received and returned. Mechanical submittals received and returned.

RSC – Regional Safety Complex Phase 2 Read More »

JC – Cell Door and Frame Replacement (Phase 5)

PM: Matt Butz, Sam Hofmann

08/28/25 – Sheriffs provided scope of doors to be included in phase 5. Review set will be complete shortly.
09/25/25 – Review documents provided to county. Project will go out to bid on monday.
10/30/25 – Alpha is apparent low bidder. Bid vet occured 10/29. Alpha subbing out majority of the work to Cornerstone.
12/11/25 – Cornerstone is awarded the bid after contradictions in Alphas LOIs and Bid Vet statements came to light. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract signed. Kick off to be scheduled in near future.
03/26/26 – Cornerstone has taken field measurements. Submittals incoming.
04/30/26 – No update.
05/28/26 – Submittal received and returned. Schedule needs to be determined by Sheriffs.
06/25/26 – No update. Tentative fall start.
07/30/26 – Delivery scheduled for end of August.
08/28/26 – Mobilization in 2 weeks.
09/24/26 – two phases complete. Work ongoing.
10/29/26 – Project ongoing.

JC – Cell Door and Frame Replacement (Phase 5) Read More »

JC – Polished Concrete – Phase 2

PM: Jesse Estes, Sam Hofmann

09/25/25 – Project kickoff held and scope determined. Review documents will be ready for County next week.
10/30/25 – Project in bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – Bulletin #1 issued to include emergency L31 scope. Triton to provide schedule to begin work asap.
04/30/26 – Submittals approved. Triton to provide schedule.
05/28/26 – Triton mobilized 5/26. Epoxy demo ongoing.
06/25/26 – Half of South 3rd floor pods are complete. 5th floor Hall is next.
07/30/26 – First phase grinding and polishing is complete. Furniture will be installed next week.
08/28/26 – Furniture install ongoing. Backpunch scheduled for next wednesday.
09/24/26 – Phase 2 in progress.
10/29/26 – 2 pods complete in phase 2. Work ongoing.

JC – Polished Concrete – Phase 2 Read More »

800 – Fire Pump Replacement

PM: Matt, Terry Cannon
Engineers: Coty Groeschen, Wesley O’Hara
08/27/25 – Prebid held today, bids are due in September. Owner furnished equipment includes fire pump, jockey pump, low suction controller and fire pump controller.
08/28/25 – Issued for Bid 8/13 and bids open 9/24.
09/24/25 – Bid Opening today at 11AM.
10/03/25 – Post bid meeting held with Alpha and they are recommended for the project. Base bid no alternates accepted.
12/12/25 – Jesse reported contracts close to being sent to contractor for signature.
01/25/26 – Contract should have went to BOCC on Jan 19, no updates. Sending Permit Drawings Tuesday 2/3. Electrical RFI received and in the process of being answered.
02/12/26 – DEG starting pre-construction work with Alpha and subs.
02/25/26 – Contracts are back. DEG coordinating with Duke and IBI on power installation requirements for the MI cable. Alpha EC vendor being weird about MI cable requirements and cost.
03/25/26 – Alpha arranging EC vendor for this job. DEG working on necessary CFD details before work begins.
04/22/26 – FDC testing complete and 800 passes inspection. DEG checking with Alpha on starting this project and getting permits to begin. A project schedule should be ready to share with the owner in a couple of weeks.
05/27/26 – SOV was approved today. We are ready to set up the Pre-Const meeting. DEG sent mechanical drawings for permitting to Alpha last week adn IBI drawings are already in for permitting.
06/25/26 – Kickoff meeting held with contractors. IBI permit approved, City permit under review. Electric change order under review. Schedule, SOV, Site safety documents received and under review.
07/30/26 – Had meeting with vendors on electric change order. Third meeting scheduled today at 1PM. Prices are coming down but not going away. Met with CFD and received their thoughts on allowing the high rise fire pump to provide temporary service for both low and hi rise, they are amendable provided we provide a letter stating it will work. Griffith sent us that letter.
08/26/26 – CO-1 sent and signed by DEG and Alpha, returned to County for approval. Planning on scheduled work to begin in October after Duke power is stable.
09/23/26 – 9/26 shutdown pushed back to Veterans Day. Alpha agreed to January 2027 startup without the project incurring any additional cost.
10/26/26 – JTL requested site visit to start working on the electrical portion of the job. DEG informed them to coordinate with Facilities on access adn that we wanted to be cc’ed on all visits so we can stop in and check progress.

800 – Fire Pump Replacement Read More »

CH – Parking Lot Repair (F029)

PM: Matt Butz, Paul Bellman
06/03/25 – County, Kleingers and THP had a meeting to discuss scope of asphalt repair work.
07/24/25 – County and THP met to discuss project phasing.
07/30/25 – THP published preliminary opinion of probable cost for the project.
08/08/25 – THP published SOSS.
08/18/25 – County had kick off meeting with Tumlin, Champlin, THP, and Kleingers.
08/20/25 – County approved SOSS.
08/28/25 – Kleingers scheduled to survey the parking lot.
09/08/25 – Kleingers survey received
09/22/25 – Kleingers, THP, HC reviewed Courtyard lot for RFI #03 regarding overlay vs milling.
11/05/25 – THP, HC, and Tumlin reviewed milling conditions and full depth repair options.
11/14/25 – Kleingers provided updated striping plan.
11/18/25 – THP reviewed new asphalt in courtyard during heavy rain. Puddling and improper slope was observed on east portion of lot.
01/28/26 – No updates – weather pending.
02/26/26 – No updates – weather pending.
03/24/26 – No updates – Status of ponding in Courtyard area?
04/30/26 – THP to review on site conditions.
05/28/26 – No updates. Work in adjacent areas ongoing.
06/25/26 – Sink hole and active line was discovered in Courtyard lot. THP, Davies, and HC discussed scoping, filling void, and providing cleanout per supplied detail. Tumlin to get CO cost to repair.
07/30/26 – No updates from THP. Have not heard from Tumlin on the CO costs to repair sink hole in Courtyard Lot.
09/23/26 – No updates.
10/29/26 – No updates. Punchlist coming and cleanout addressed soon.

CH – Parking Lot Repair (F029) Read More »

TPC – BOCC Security Upgrades

PM: Matt Butz, Eryn Thamann, Mike Barth
06/26/25 – Fee estimates from Elevar/DEG were provided based on the Sheriff’s risk assessment document. ROM construction estimates were also provided.
07/31/25 – No update. The County commented that all has been submitted, waiting on comments.
08/28/25 – No update.
09/25/25 – No update.
12/11/25 – No update.
01/29/26 – No update.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – No update.
10/29/26 – Submitted SOSS for egress study.

TPC – BOCC Security Upgrades Read More »

TPC – 3rd Floor Auditor Breakroom

PM: Megan, Sam Hofmann, Terry Cannon
05/29/25 – Added as new project.
06/25/25 – Checking dates for meeting.
07/24/25 – Design meeting conducted on site.
08/26/25 – Design continues, updated floor plans received from Champlin today.
09/24/25 – Prices and owner review documents submitted to Champlin. County to review budget and scope to determine if they have enough money to bid as is.
10/30/25 – Scope and Budget confirmed. Project will be issued for bid today.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No Update.
04/30/26 – Submittals are in process. County to schedule mobilization.
05/28/26 – Triton mobilized on 5/6. Construction and Bi-weekly meetings ongoing.
06/25/26 – Demo complete. Framing complete. Roughin inspections ongoing.
07/30/26 – Construction ongoing.
08/28/26 – Project nearing completion. Punch scheduled for next week.
09/24/26 – Punch walkthrough completed. Closeouts in progress.
10/29/26 – Backpunch complete. Closeouts received and being reviewed

TPC – 3rd Floor Auditor Breakroom Read More »

All Buildings – Fire Damper Testing & Inspection

PM: Tony Matre, Terry Cannon
05/22/25 – Tony Matre asked for an SOSS to rebid this project in 2025.
06/25/25 – SOSS submitted.
07/30/25 – SOSS approved this month. Internal meeting conducted for kickoff to collect as-builts and setup new drawings.
08/28/25 – Drawings are nearing review status. Coty and Luke made good progress, but we have a lot of as-built items to incorporate from the last bid.
09/24/25 – We are updating the drawings for the new buildings including 525, EMA, and Mercy. Drawings should be ready for review in a couple of weeks for the whole bid package.
09/25/25 – 525 does not have any fire rated walls. CHA answered Coty about Dane.
10/30/25 – Still putting new buildings together.
12/12/25 – Original building drawings updated. New building drawings added, ready for TTC review. We noticed that several fire dampers missed in the Justice Center because of the spline ceiling are open and accessible. TTC worked with NKYHC to get a quote to update the fire dampers in the JC lobby now before the new ceilings go back in. NKYHC working with Triton to use their lift.
01/25/26 – Review sets sent to Tony Matre for distribution and review. After comments are received, we will setup the bid schedule for this project.
02/25/26 – No comments received yet, ttc checked in a couple of times.
03/25/26 – We are waiting on green light from Tony before bidding. Review sets are in for comments.
04/26/26 – Project on hold awaiting green light from Tony.
05/27/26 – DEG needs to add to buildings to the the bid and then we will start putting together the ITB.
06/25/26 – Finalized scope for new buildings, updated and found missing data from previous bid and addendums, final items being added to scope for bid package.
07/30/26 – Talked to Tony and we are removing 1701 and 111 from scope. We don’t have to wait for any additional comments from Facilities, TTC can package this up for bidding.
08/26/26 – Coty reviewed drawings this month and made changes but said he needs to clean up some items from the Coop work and he will get that done this month for my final review.
09/23/26 – Review project with Tony, putting 2026 budget together for Tony, but he also said to get the job out for bidding in October 2027.
10/26/26 – TTC will review drawings before Partner meeting.

All Buildings – Fire Damper Testing & Inspection Read More »

SPHQ – Fall Protection Upgrade (F026)

PM: Matt Butz, Paul Bellman

04/01/25 – County requested SOSS for Fall Protection upgrade to the existing roof.
04/24/25 – THP to publish SOSS for review.
05/21/25 – SOSS approved.
06/25/25 – THP requesting roofing plans to start layout.
07/30/25 – THP working on DD drawings and plan to send draft to HC late next week.
08/27/25 – THP finalizing DD drawings and plan to send to HC at the end of the week.
09/24/25 – THP working towards CD drawings. Need to schedule a review meeting with HC.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
11/19/25 – THP issued summary letter to HC recommending NR Lee Restoration.
12/11/25 – HC finalizing paperwork for Contract approval.
01/14/26 – HC issued fully approved Contract to HR Lee Restoration.
01/27/26 – Preconstruction Meeting held virtual.
01/28/26 – THP issued Preconstruction Meeting Minutes.
02/19/26 – Preconstruction Meeting held On-site.
02/20/26 – THP issued Preconstruction Meeting Minutes.
03/25/26 – HR Lee is scheduled to deliver telehandler forklift 3/26 or 3/27 and material on 3/31. Work scheduled to begin shortly after.
04/08/26 – THP and HC reviewed on site substantial completion by HR Lee.
04/20/26 – HR Lee submitted Change Order for requested additional railing at small roof. THP to review with HC.
05/26/26 – HC issued signed and approved CO for additional railing. HR Lee placed order and updated schedule requested. Closeout documents in progress.
06/25/26 – THP is scheduling a final walk-thru with all parties. Closeout documents in process.
07/14/26 – On site final walk.
08/21/26 – THP sent CO #2 for requested safety line and final punch items to HR Lee for signature. Signed CO#2 returned to HC.
09/22/26 – On site review of final punch list items. HR Lee to schedule remaining work by next week.
10/08/26 – HR Lee completed final punch list items and THP and HC reviewed and approved.
10/15/26 – HR Lee submitted final closeout docs.
10/29/26 – HR Lee submitted paint touch up procedures from manufacturer for warranty work and would like to schedule paint touch up of bases.

SPHQ – Fall Protection Upgrade (F026) Read More »

TPC – NFPA Fire Door Upgrades

PM: Sam Hofmann, Jesse Estes

02/27/25 – SOSS returned. Kick off to be scheduled in near future.
03/27/25 – Drawings have been started. Kick off to be scheduled.
04/24/25 – Drawings in progress. To coordinate with Elevar on format.
05/29/25 – No update.
06/26/25 – Field visit to walk through all buildings to be scheduled.
07/31/25 – Field visit complete. Drawings to be finalized.
08/28/25 – Final review meeting to be scheduled.
09/25/25 – Door Hardware Consultant to visit doors on site to provide feedback and cost.
10/30/25 – Assa Abloy is working on specs and estimate.
12/11/25 – Assa abloy is finalizing scope.
01/28/26 – Finalizing cost estimate and base bid scope
02/26/26 – Completing bid set and project manual.
03/26/26 – No Update.
04/30/26 – No Update.
08/28/26 – County is cleaning paint off labels and will report back which locations will still need to be replaced.
09/24/26 – Confirmation required on labels able to be cleaned.

TPC – NFPA Fire Door Upgrades Read More »

800 – Façade Repair SD (F022)

PM: John Nester, John Millar
01/02/2 – Champlin reached out to THP to provide SD services for the new Animal Shelter.
02/25/25 – THP provided an SOSS for SD Services.
03/26/25 – Elevar pending approved PO. Truescan started scanning the building from the interior.
04/23/25 – Design team had internal kick off meeting. Project update – Scanning complete and THP working on base Revit model for the project.
05/28/25 – Elevar has site walk scheduled for 05/30 to review windows. THP completed initial surveys and plans to rappel 5/29 and 5/30.
06/26/25 – Elevar investigating window replacement vs restoration and window cleaning products.
07/31/25 – Window drawings are progressing and a set will be provided to THP for inclusion in the next checkset to HCFD.
06/30/25 – THP completed aerial platform surveys of the lower section of the building and interior surveys of the façade 6/30 to 7/3.
07/17/25 – Stone stabilization proposals received and AFR is the low bidder.
07/22/25 – THP sent 800 Broadway review set to County. Set included windows and fall protection.
07/30/25 – AFR installing supplemental anchors on north elevations. Anticipate being complete by 7/31/25.
07/30/25 – AFR completed installation of supplemental anchors and THP confirmed the work.
08/27/25 – THP published share file with SD review drawings. Drawing included stone, window, and safety package.
08/28/25 – Summary documents and initial estimate planned for week of September 2.
08/28/25 – Window SD set provided to THP 08/15.
09/25/25 – Elevar provided ROM estimate to THP.
10/30/25 – Review mtg with HCFD scheduled for 11/06.
10/23/25 – THP issued opinion of probable cost for all work.
10/30/25 – County review meeting scheduled for November 6th.
12/11/25 – Review mtg held with HCFD. Revised estimates and design schedule to be provided.
12/01/25 – Schematic Design meeting occurred. Scope, budget and next steps presented.
12/23/25 – HC requested an SOSS – DD through Bidding.
01/19/26 – THP published SD report for County project planning.
01/29/26 – THP/Elevar working on SOSS.
01/31/26 – THP and County working through project scope and design team services.
02/25/26 – THP published SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working through initial design phase planning.
05/27/26 – Design Kick off meeting completed.
06/08/26 – Project summary for security meeting published.
06/17/26 – Project placed on hold.
07/29/26 – THP published summary of conditions for use by the County.
09/24/26 – Project on hold.
10/25/26 – Project on hold

800 – Façade Repair SD (F022) Read More »

Elevar – General Services 2025 (F021)

02/25/25 – PO approved.
08/28/25 – CH fifth floor interior sign code summary provided to HC on 08/27.
12/11/25 – No updates.
01/29/26 – Combine with General Services F015.
03/26/26 – 230 exterior lighting study and 111 Tri-Co smoker’s hut performed under Gen. Services.
04/30/26 – Submitted SOSSs for additional PM and CA time to support HCFD and a Prevailing Wage Coordinator.
05/28/26 – SOSSs not approved for PM and PW Coordinator. Juvenile Assessment Center walkthru occurred and Elevar/DEG to issue report.
06/25/26 – Elevar SOSS not approved yet for Juvenile Assessment. Complete the report under Gen Services?
07/30/26 – 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
07/30/26 – Elevar Juvenile Assessment report complete and need DEG portion to fully integrate.
08/27/26 – 230 Exterior Lighting Project back to DEG for electrical design. Fixture options provided to Rycca.
08/27/26 – Does HCFD want Elevar’s Juvenile Assessment report without DEG’s report?
09/24/26 – Elevar assessment report provided to HCFD without DEG’s portion. Site visit was made to review potential relocation of operable partition but put on hold.
10/29/26 – No update.

Elevar – General Services 2025 (F021) Read More »

JC – Emergency Power Upgrade 2025

PM: Matt Butz, Mike Barth
11/06/24 – THP update – THP provided an email with budget to rebid the project.
01/30/25 – Restart post to track 2025 project for this project.
01/24/25 – THP update – THP provided a formal SOSS.
02/26/25 – Prebid Meeting occurred on 02/26/25. Attendance by DK, Dunn Electric and Driekast. Bids due on 4/10/25.
03/07/25 – Terracon on site for test boring. Preliminary results included sandy dirt findings. Official report coming later this month.
03/25/25 – Terracon invoiced project for work but final report not here yet.
03/26/25 – Project bidding. Lots of questions being submitted by Glenwood. Bids are due 04/10.
04/23/24 – Project bids received. (2) bidders. Glenwood and Alpha. Glenwood apparent low bidder. DEI approves bids. TEI vets bid ln 04/22/25 – TEI to submit letter of recommendation to start the contract phase.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase. Contract contacts TEI asking about status.
07/30/25 – DEG, HCFD, Bldg Mgr meet with Glenwood Electric for a pre construction KO meeting. at time of bid, the generators and switchgear quoted Glenwood 6-8 weeks for submittals, and then 40 weeks +/- for shipping of gear. Glenwood released the submittals end of last week. Likely startup of construction summer 2026.
08/27/25 – DEG has not received submittals to date.
09/24/25 – DEG receives equipment submittals. Submittals under review and approval.
10/29/25 – DEG working with contractors to get the permits in order.
01/28/26 – Issues with one switch that contractor and DEG working on.
02/25/26 – CO #001 issued. All gear should be on order. Estimated delivery June/July 2026.
03/25/26 – Glenwood submits several RFIs on the project. DEG reviewing RFIs.
04/29/26 – Glenwood submits pay applications for procured material. DEG to visit the crane yards to certify the equipment.
05/27/26 – Project construction pending material procurement.
06/23/26 – DEG speaks with Glenwood, and the gear manufacturer has production delays, the anticipated mobilization date has slid to 09/01. The existing equipment in the areas where the work is to occur needs to be relocated prior to mobilization.
07/29/26 – Project mobilization pending procurement of equipment.
08/26/26 – DEG meets with Glenwood at FDL and Ohio Cat to certify some of the equipment. Gen sets are on site in Dayton Crane Yard. Glenwood to schedule certifying the equipment trip with DEG.
09/23/26 – Pre-construction meeting occurred. glenwood site super has been on site to get knowledge of the building. Construction to begin around 10/01/2026
11/06/25 – THP issued permit drawings to be submitted with Davies set.
10/01/26 – Triton issued RFI No. 1.
10/05/26 – THP responded to RFI No. 1.
10/28/26 – Construction underway. Multiple meetings and discussions re fitting generator on oversized skid into the basement. Skid to be modified to fit into the building. ATS location for North tower is final coordination item at the time.

JC – Emergency Power Upgrade 2025 Read More »

800 – Exit Stair Security Cages

PM: Matt Butz, Eryn Thamann
01/29/25 – Met onsite 01/27 to review scope and SOSS requested.
02/25/25 – SOSS provided for Elevar/TEI. Pending approved PO.
03/26/25 – Pending PO approval. Onsite meeting with City AHJ is scheduled for 03/27 to walk spaces and review for any AHJ concerns.
04/24/25 – Elevar had site visit walk-thru AHJ to review life safety concerns. City concerns sent out in meeting minutes with sketches. HCFD needs to confirm additional scope as indicated by AHJ. Elevar will work on stair scope only for now.
05/28/25 – Elevar provided drawing backup to TEI on 05/28. After MEP design is DD level, a design review meeting will be scheduled with HCFD. Elevar to provide design schedule and will need to meet with HCFD to review Div 01 requirements.
06/26/25 – Design review meeting scheduled for 06/30 to review CD set.
07/31/25 – HCFD has 95% set. Waiting on approval prior to preparing final bid set. Elevar to provide clarification on fee per MB’s request.
08/28/25 – Discussing remaining fee with MB/TEI.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Elevar met with HCFD to review 90% set and provided overview sheet for security committee. Waiting on security committee approval before proceeding with CDs. Project needs to be bid/award in 2026.
02/26/26 – Waiting on security committee approval before proceeding with CDs. Elevar has picked up internal revisions and ready when HCFD obtains approval.
03/26/26 – HCFD to setup security committee approval before proceeding with CDs.
04/30/26 – On hold pending HCFD approval of bidding costs.
05/28/26 – Out to bid now with bids due June 30.
06/25/26 – No update.
07/30/26 – Contractor recommendation provided to HCFD and contracts are in process with Purchasing.
08/27/26 – In final stages of contracts with Purchasing.
09/24/26 – Contract was finalized.
10/29/26 – Procurement starting but no submittals yet.

800 – Exit Stair Security Cages Read More »

All Buildings – Life Safety Drawings

PM: Rycca Thacker, Eryn Thamann
01/29/25 – SOSS requested. JN to confirm what buildings are included in SOSS.
02/25/25 – Pending approved PO.
03/26/25 – First site walk 03/27 at 230. Other buildings shall be scheduled after initial 230 bldg walk.
04/24/25 – 230 Building progressing. Examples with a few questions sent to HCFD for review/approval on 04/22. Elevar is scheduling other buildings with onsite facility managers.
05/28/25 – Example of 230 building was approved by HCFD. Site walks for TPC, 800, CH buildings have also been performed. Need updated drawings for JC care pods and TPC to accurately show floor plans. Need facility manager contacts for remaining locations to schedule site walks.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – JC walk-thru occurred and Elevar has questions re: JC. Elevar received CH comments from Court Admin and an additional walk-thru is needed to confirm map orientation. Remaining buildings have not been walked yet.
08/28/25 – Evac maps for 230 building provided to HC on 08/27. Other buildings are ongoing.
09/25/25 – All maps will be provided before 11/01. Building 230 has been turned over.
10/30/25 – Evac maps are progressing and on schedule for 11/01 deadline except for a few floor plans where Elevar doesn’t have updated plans and can’t get updated plans.
12/11/25 – All buildings except Hillcrest campus and 6th Floor CH plans have been provided to HCFD with additional JC detainee-area evac plans.
01/29/26 – One floor of CH and Hillcrest to be completed by end of next week. Awaiting Tri-County drawings.
02/26/26 – Elevar working on final 111 Tri-Co drawings now and expect completion in approx. one week.
03/26/26 – Complete with 111 Tri-Co. Portion of Hillcrest remains until further notice.
04/30/26 – Complete. Keep project open for Hillcrest?
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – SOSS provided to complete 1701.
09/24/26 – No update on SOSS for 1701. CAD/pdfs provided to HCFD for other completed buildings.
10/29/26 – No update.

All Buildings – Life Safety Drawings Read More »

JC – Condenser Pumps Replacement

PMs: Matt Butz, Terry Cannon
01/17/25 – SOSS Requested.
02/26/25 – SOSS received, TEI starting preliminary engineering.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project design has begun, we should have preliminary review ready in a couple of weeks, and then we can meet and talk particulars for this project.
05/28/25 – First round of internal reviews complete. We are picking up TTC markups, creating a construction cost estimate, and filling out electrical coordination sheet. We will have the mechanical drawing issued for owner review on 5/30.
06/25/25 – No comments back from anyone that I know of, should we move to bidding?
07/28/25 – We sent drawings back for comment and requested AIA documents for bidding. Ready to bid but ITB not requested until budget is set.
08/28/25 – Budget set at $200,000. Comments and AIA contracts forthcoming from Facilities for this project.
09/24/25 – Prebid held last Friday, it was well attended. Addendum 1 due out this week.
10/29/25 – Pre Award meeting held with Geiler today and they can be recommended for this project.
12/12/25 – In contract approval stage.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed. We have reviewed submittals already and are waiting on project kickoff to send them back to Geiler.
02/25/26 – Contract and PO are ready. DEG preparing for project kickoff. Pump submittals are approved.
03/25/26 – No kickoff meeting yet, submittals are approved, awaiting go ahead from County to move on this one.
04/29/26 – Kickoff meeting held early this month. Geiler commented that pumps were bid to be replaced when entire chilled water system was down. We are going to get everything in place and start this project in November 2026.
05/27/26 – DEG approved first pay application for $5500 and will send to County. Project on hold until November.
06/25/26 – Payapp received. Equipment in town, DEG to review at Geiler warehouse.
07/30/26 – Equipment approved, waiting on next Payapp from Geiler.
08/26/26 – Hold till November start.
09/23/26 – On hold until November, TTC approved and sent in Payapp 1, Payapp 2 already paid.
10/23/26 – Payapp 1 has cleared at Geiler.
10/26/26 – Pre-const meeting November 5. TTC removed the tentative tag on the meeting and update the invite.

JC – Condenser Pumps Replacement Read More »

800 – 6th Floor Reno & Bsmt Plumbing Repairs

PMs: Sarah, Terry Cannon, Eryn Thamann
01/17/25 – SOSS Requested.
02/25/25 – SOSS submitted to HCFD. Pending approved PO.
02/26/25 – Awaiting approved SOSS.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. We will follow Elevar lead on first design meeting. TEI scope is in the basement and the 6th floor area. Elevar hasn’t received approved PO.
04/24/25 – PO provided and awaiting design kick-off meeting with Court Admin/team.
04/23/25 – Project setup and internal meetings underway. Elevar and ThermalTech setting up kickoff meeting.
05/28/25 – Awaiting kickoff meeting with Elevar and County. TTE ready to mobilize for design.
06/25/25 – Kickoff meeting in July.
07/30/25 – Drawings received from Elevar, ThermalTech working on MEP design, submitted questions about need for MSB in new restroom. Additional fieldwork done last week for basement repairs.
07/31/25 – Drawings are progressing for a bid review set Aug 8 and a bid set to HC Purchasing Aug 15. TTC changed name and assigned to Elevar and merged Plumbing Repairs and 6th Floor Reno.
08/28/25 – Project scheduled for bid advertisement on 08/29.
09/25/25 – Bids due 10/10. Last addendum due out 09/26 with final questions.
10/30/25 – Lowest bid was Triton and under advertised cost. Vetting mtg occurred and Elevar has recommended Triton for award.
12/11/25 – Project awaiting final contract award from purchasing.
01/29/26 – No update.
02/26/26 – Contract was approved but Elevar has seen no submittals or correspondence. Elevar to schedule construction kick-off mtg.
03/26/26 – Contract was approved but Elevar has seen no submittals or correspondence.
04/30/26 – Have reviewed some general trade submittals.
05/28/26 – Possibly complete with submittals but low on Triton’s priority list.
06/25/26 – No update as it’s low on Triton’s priority list. Not received change order pricing for flooring add.
07/30/26 – Construction kickoff meeting held 07/20. Recurring progress meetings scheduled.
08/27/26 – Triton likely back onsite now after ACM removal. Regular progress meetings to resume next Mon. We will keep the floor drain in the project based on today’s conversation.
09/24/26 – Working thru slab change order.
10/29/26 – New pricing is expected soon for slab work.

800 – 6th Floor Reno & Bsmt Plumbing Repairs Read More »

800 – Low Rise AHU Replacements

PM: Matt Butz, Terry Cannon
01/17/25 – SOSS requested.
02/26/25 – TTC still needs to submit this SOSS, this is the last one on my list to submit.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project underway. We have completed our first field trip to the building. TEI running load calculations to verify sizing, setting up existing drawings and working on ventilation calculations. After we get the preliminary design complete, let’s meet and discuss project particulars.
05/28/25 – We held a kickoff meeting with the Facilities in the last month and made another round of field trips to the building for additional information. We are trying to prove HVAC AHU sizing from original job and collect factory information from original install of the low rise units to verify coil sizing, heating and cooling loads and whether or not air side economizers make economic sense during this replacement.
06/25/25 – ThermalTech doing additional fieldwork to lock down actual ductwork in the mechanical rooms. We should be ready for bidding next month.
07/31/25 – Project submitted for Owner Review. Project Manual didn’t make it through TTC review, will be sent later. Look for prebid third week of August.
08/26/25 – Prebid meeting Wednesday 8/27. TTE invited many.
09/24/25 – Addendum 1 previously released. Bid opening today at 11AM.
10/29/25 – Project on hold pending official bid award. TTC answered Nester email inquiry this morning about award status. TEI/DEG has not advised either bidder the project has been awarded yet.
12/12/25 – in contract approval stage. TTC notified contractors that Triton received the bid and Alpha did not.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed.
02/12/26 – Contracts are back. Pre-Const meeting being set up now.
02/25/26 – Triton has been awarded the project. We are scheduling the project kickoff meeting soon. We do need to discuss what are we going to do with AH-71 and it’s proximity to the parapet wall.
03/25/26 – Submittals coming in, no kickoff meeting scheduled yet.
04/26/26 – DEG working on change order request drawing to relocate AHU-L71 to farther away from parapet wall. Once complete we will get a price from Triton for the change.
05/27/26 – DEG sent revised AHU-L71 location to Triton for pricing to rotate away from parapet to get 10 foot clearance.
06/25/26 – Awaiting project kickoff. AHU-71 change order not received yet.
07/30/26 – Pre Construction meeting held with Triton. Working on submittals, sent permit drawings to Triton, working on getting project n place for January start so unit can be replaced over long County weekend.
08/26/26 – Reviewing submittals preparing for January start.
09/23/26 – Still on track for January start, no new submittals in September from Triton.
10/26/26 – Had meeting with Triton and Emcor on HVAC Controls. We are awaiting the resubmittal of the controls package to DEG for full review. The controls have not been approved for this project yet. AHU submittals including curbs are approved. We are verifying current lead time for equipment.

800 – Low Rise AHU Replacements Read More »

JC – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after fist walk of 230 bldg. Need updated drawings from Champlin and door labels from HCFD that match fire door report.
04/24/05 – Walk-thru not scheduled yet.
05/28/25 – Elevar needs building info that matches between original LSS report and building plans. Current plans don’t have door numbers listed and LSS report has inaccurate photos of doors. Walk-thru on hold pending further info.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – Walk-thru performed but drawings have not been updated yet.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates almost complete but can review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – Paint removal will occur at JC. Elevar reviewed JC with Sheriff’s and a few items will be revised. No updates on progressing project into bidding.
07/30/26 – Elevar had questions regarding anti-ligature closer locations at JC and emailed to HCFD. List of doors needing paint removed sent to HCFD. Need final allowance amount from HCFD to add to bidding docs for door re-certificaiton/replacement if paint removal doesn’t work.
08/27/26 – Questions still remain for JC anti-ligature items but will be confirmed prior to bidding. HCFD to provide allowance figure for re-certification.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

JC – Fire Door Repairs Read More »

CH – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230.
04/24/25 – Walk-thru not scheduled yet.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

CH – Fire Door Repairs Read More »

800 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230 bldg.
04/24/25 – Walk-thru not scheduled yet but is next in line.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

800 – Fire Door Repairs Read More »

230 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and initial site walk scheduled for 03/27 with JN.
04/24/25 – Walk-thru occurred and drawings have progressed. Elevar to coordinate with Champlin on design in near future.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. Need to know if paint removal was successful on stickers.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

230 – Fire Door Repairs Read More »

230 – Elevator Modernization

PM: Rycca Thacker, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (4) elevators in 230 East 9th Street Building. TEI and Elevar meet to discuss roles on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar SOSS provided to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD. SD meeting scheduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team meets with the Courts committee to review security and finishes. DD documents are progressing.
06/25/25 – Team meets with Court Admins. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027). The contract phase and procurement deposit caused the delay.

230 – Elevator Modernization Read More »

800 – Elevator Modernization

PM: Rycca Thacker, Mike Barth, Lauren Schmitz
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (5) elevators in 800 Broadway. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed all field work and work is ongoing.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting was scheduled with HCFD. SD review meeting shceduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to schedule courts committee for design review.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/23/25 – THP – Davies, Elevar, County and THP met to review possible options for getting the elevators in 800 Broadway.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
07/29/25 – THP sent a proposed summary of elevator access plan and THP scope of work for review.
08/13/25 – THP sent an SOSS to Davies for review.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/08/26 – THP issued bid documents.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – THP sent questions for GC post-bid review in March.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay. Due to the obsolescence of the R-410A refrigerant, the Liebert units for the machine room cooling anticipated ship dates are 52+ weeks. The Skill-Aire alternate ($42k deduct) is 16-18 week ship time.

800 – Elevator Modernization Read More »

CH – Elevator Modernization

PM – Rycca, Mike Barth

09/25/24 – HamCo requests SOSS for Elevator Modernization project for (9) elevators in Courthouse. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI has design schedule. Field work ongoing.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to notify when courts committee are ready for review meeting.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule with RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Bids still under review by HC.
04/30/26 – Low bidder vetting meeting occurred. Contract in process with HC Purchasing. Notification of TKE buyout forwarded to HCFD.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay.

CH – Elevator Modernization Read More »

CH – Facade Repairs/Roof Replacement (F005)

PM: Matt Butz, John Millar, Eryn Thamann
06/26/24 – THP provided SOSS to Elevar.
07/25/24 – County approved SOSS.
08/14/24 – THP and Elevar completed a kick off meeting and general walk of the roofs.
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
09/26/24 – Truscan came out two days ago and modeled the building. Elevar will share with the partners, over one billion points scanned, CH and surrounding areas. More fieldwork needed.
10/30/24 – Model shared with THP and SD continues.
12/09/24 – THP working with model and performing site work.
10/30/24 – Model shared with THP and SD continues.
12/11/24 – THP completed initial field work to confirm model accuracy. THP provided review comments and has begun working on model joints.
01/29/25 – THP has performed several facade tests but weather limited site work; surveying still ongoing to document stone/terra cotta joints. Roof plans are developed; THP/Elevar coordinating on roof edge details now.
02/25/25 – Deliverable schedule sent to MB. Work ongoing.
03/26/25 – Met with HCFD to review SD status drawings. THP has additional site investigation to perform but still look on track for May SD deliverable.
04/24/25 – Team is progressing with design. Elevar to get masonry contractor under contract to complete destructive investigation.
04/24/24 – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
05/28/25 – Decision on mason expected 05/29. Elevar to schedule work with HCFD.
06/26/25 – Mason under contract and patiently awaiting their onsite schedule. THP/Elevar meeting to coord. designs. Final SD set expected to HCFD end of July.
07/31/25 – Mason walk-thru 07/24 with THP/HCFD and scheduled onsite start for 08/04. Badging will start if crew will be inside but will determine at walk-thru. Deadline pushed back to accommodate mason.
08/28/25 – Waiting for final mason contractor to get badged to start investigative demo.
09/25/25 – Mason onsite in Sept and design team finalizing drawings based on findings.
10/30/25 – Final SD set provided to HCFD along with cost estimate. Review mtg schedule for 11/06 with HCFD/THP.
11/06/25 – THP and Elevar met with HC to review SD set. HC requested updates to OoPC and schedule.
11/21/25 – THP sent final OoPC to Elevar, with requested updates from HC.
12/01/25 – THP reviewed design schedule with Elevar and HC during 800 Broadway meeting.
12/11/25 – Final cost estimate and design schedule will be provided to HCFD this week.
01/29/26 – Elevar/THP working on SOSS.
02/23/26 – THP published fee proposal to Elevar for Phase II of design work.
03/26/26 – SOSS approval pending.
04/24/24 – THP update – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
04/30/26 – SOSS approved. Need to schedule kick-off meeting with team and HCFD.
05/28/26 – Design kickoff mtg occurred 05/27. Elevar to send pdf presentation to team for review with Court Admins. Team will provide design schedule very soon.
06/17/26 – Project placed on hold.
06/25/26 – On hold. Design kickoff minutes and presentation provided to HCFD.
07/30/26 – No update. Remains on hold.
08/14/26 – THP provided recommended critical repair scope and budget.
08/27/26 – Priority list provided by THP to HCFD. Could restart after November with very limited scope.
09/24/26 – Project on hold.
10/25/26 – Project on hold

CH – Facade Repairs/Roof Replacement (F005) Read More »

EMA – Tornado Sirens Arc Flash Study

PM = Matt/ Trades, Mike Barth
08/28/24 – ThermalTech submits SOSS for all sirens in Zone 4.
09/25/24 – TEI receives signed SOSS and PO for project. TEI to schedule kick off meeting with HCFD.
10/30/24 – TEI contacts Duke Energy for available fault at each location. TEI coordinates with HCFD for addresses of each siren. Model in Progress.
12/11/24 – Zone 4 sirens are modeled and the labels are ready for printing. TEI will print and deliver to HCFD.
01/29/25 – TEI to deliver the labels to HCFD.
02/26/25 – TEI delivers Arch Flash Labels for Zone 4 sirens.
03/26/25 – TEI delivers SOSS for zone 5 sirens. TEI receives PO to start the Zone 5 package.
04/23/25 – TEI to start the arc flash study for zone 5 sirens.
06/25/25 – No updates this month.
07/30/25 – DEG receives available fault from Duke for Zone 5 sirens and modelling is in process.
08/27/25 – Modeling of all sirens in progress.
10/29/25 – Modeling complete. Pending MCB and CMI review.
12/10/25 – No updates
01/28/26 – HamCo requests SOSS for next zone (assuming Zone 6).
02/25/26 – DEG submits SOSS for Zone 6.
03/25/26 – DEG receives PO and signed SOSS for Zone 6. DEG gathering data from duke and developing model. Zone 5 arc flash stickers to HamCo Trades.
04/29/26 – DEG completes modeling of zone 6 sirens. On Barth’s desk for review and approval, and then send to CMI for approval prior to printing labels for trades.
05/27/26 – No updates.
06/23/26 – DEG reviews model with CMI (Charlie) and gets CMI approval of model. DEG prints all zone 6 labels and delivers to Trades Electricians.
07/29/26 – Project deliverables complete until next years zone 1 SOSS approved.

EMA – Tornado Sirens Arc Flash Study Read More »

CH – 6th Floor Sheriff’s Storage

PM: Eryn Thamann, Matt Butz
08/27/24 – Elevar SOSS approved. TEI to submit SOSS.
09/24/24 – TEI submitted SOSS to HCFD. Elevar requested design kick off meeting with HCFD.
10/30/24 – Drawings are setup and design team need to walk space for FV and finish discussions.
12/09/24 – Need to review finishes with HCFD. Will perform site work 12/12. BW said bring over finishes and he would like to maybe replaced tile in main hallways.
01/02/25 – TEI reached out for update on project progress.
01/27/25 – Kickoff meeting occurred 1/22, SD & Cost Due to John Nester 3-4 weeks after meeting.
02/26/25 – Elevar to gather full SD set for HCFD submission. Archibus project made and SD estimates can be added. ThermalTech will complete SD drawings by Friday 2/28.
02/27/25 – JN will bring in Sheriff Office for final review early March for this job.
03/26/25 – Team met with stakeholders to review SD options. Elevar will provide another round of SD options and storage options based on new info from meeting.
04/24/25 – Elevar provided second round of SD plan options and Sheriff storage options for selection. Upon plan and storage selections, the team can procced with design docs.
05/28/25 – No update.
06/26/25 – Elevar to update Archibus cost estimates.
07/31/25 – Elevar to update Archibus cost estimates.
08/28/25 – Estimates updated and new options uploaded.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Elevar to submit SOSS. Need final decision on Sheriff’s storage options or no storage included. Confirm no separate interior office for Sheriff’s IT group.
02/26/26 – Elevar has remaining fee and will start on this immediately.
03/26/26 – DEG to finalize MEP drawings and a final HCFD review set will be ready.
04/30/26 – Set is 95% and on hold for final bidding info.
05/28/26 – Need to prep documents for trades work. Elevar to submit building permit and DEG to submit IBI permit.
06/25/26 – Elevar to submit building permit and DEG to submit IBI permit this week.
07/30/26 – Kickoff meeting held 07/22. IBI permit approved. Building permit still under review.
08/27/26 – Kickoff meeting held with trades. IBI review approved and DEG will submit. Building permit paid for and wall bracing engineering change submitted.
09/24/26 – Will postpone construction start until approx. Nov 2026.
10/29/26 – Restart?

CH – 6th Floor Sheriff’s Storage Read More »

Hillcrest – Campus Long Term Strategic & Master Planning

PM: Eryn Thamann, Bert Watts, John Nester
08/27/24 – Initial meeting held with HCFD, Juvenile Court, Elevar.
09/24/24 – SOSS submitted for strategic planning efforts. Juvenile Courts waiting on larger funding of Hillcrest projects/programs before approving.
09/26/24 – On hold.
10/30/24 – No update.
12/09/24 – No update.
01/29/25 – No update.
02/25/25 – No update.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.

Hillcrest – Campus Long Term Strategic & Master Planning Read More »

Central – Office Consolidation Phase 1 & 2

PM: Bert, Mike M, Terry, John Millar
05/30/24 – ThermalTech submitted SOSS to Champlin for SD & Cost.
05/31/24 – Champlin sends TTE background material to start working on this project.
06/26/24 – Design Meeting started, Champlin sent agenda and latest drawings.
07/02/24 – Board Presentation Day.
07/10/24 – Fieldwork at site.
07/17/24 – Fourth Floor layout sent from Champlin to TTE.
07/25/24 – JFS Computer Room fieldwork setup for TTE.
07/31/24 – Bond Hill Due Diligence SOSS request sent.
08/01/24 – SD & Cost sent to Hamilton County for this project.
08/21/24 – Due Diligence SOSS questions came back from Champlin. Be ready to move on due diligence quickly if approved.
09/19/24 – THP update – Champlin/County request THP provide building envelope and garage restoration due diligence assessments.
09/26/24 – Due Diligence kicked off. Architectural, MEP and environmental site visits complete. Survey happening today. Structural and civil scheduled.
10/02/24 – Due Diligence – THP update – THP published proposal to Champlin.
10/03/24 – THP update – Champlin/County request THP provide structural footing design for the garden fencing as part of the larger project.
10/07/24 – Due Diligence – THP update – THP field teams completed building envelope and garage surveys.
10/10/24 – Due Diligence – THP update – THP completed roof thermal scans.
10/11/24 – THP update – THP published proposal to Champlin.
10/23/24 – Met onsite with Facilities, Environmental Services, Ameresco and ThermalTech on Netzero energy opportunities.
10/25/24 – Due Diligence – THP update – THP published building envelope and parking garage due diligence assessment to Champlin.
10/31/24 – Due Diligence draft submitted to county. SOSS for DD-CA submitted. DD review meetings have begun. Documentation ongoing.
12/12/24 – DD to be submitted for review on 12/23. Estimate to be submitted 1/6. Meetings ongoing.
12/23/24 – THP update – THP issued DD fence and moveable wall structural details.
01/27/25 – ThermalTech finalizing fieldwork at the site to continue design for HVAC, Plumbing, Electric, and Fire Protection beyond the DD phase into CD. We have received the server survey from Telecomm and have updated our calculations for each IDF and MDF room, we hope to have floor plans updated by end of this week with proposed rack locations and HVAC needs. We are on pace to make the CD deadline of February 28, 2025.
01/30/25 – Final meetings with each department ongoing. CD’s being developed. Bid review set to be submitted for review on 2/21.
02/27/25 – Review set submitted to county. Tentative bid issuance date is 3/6. DDS has been removed from bid package to be issued as a separate project.
03/27/25 – Drawings are ready for bid. Updated Estimate to be submitted this week.
04/24/25 – Bid phase ongoing. Pre-bid had light attendance. Bids open May 23.
05/29/25 – Graybach is apparent low. Bid vet to be scheduled when bid is determined acceptable.
06/26/25 – Bid vetting in process. A305s provided to county for consideration.
07/31/25 – Graybach will be awarded the bid. bid vet meeting held. contract has been signed and will be going in front of the board next week. Const meetings start week of August 11.4
08/28/25 – Graybach has mobilized and began demolition. Furniture move services bid issuance on 8/26. RFI received on plumbing and HVAC are being answered as they come in. We have officially access controls, but it has been resubmitted as individual components and AV cable, fiber and Cat6 is approved. Now we need to discuss what to do about the security camera system. We reinforced with the field foreman that we are pulling every cable back to the IDF rooms so it landed by floor. TTE to send IDF coordinate drawings to John for ordering and coordination ASAP.
09/23/25 – TTE met with DK yesterday on proposed HVAC changes at Bond Hill. DK has already performed all the work on the first floor, we negotiated changes and discuss field engineering changes methodology with Dustin and Dave. We agree on the material cost but feel strongly that the labor is more than what is needed to make the requested changes (as it was estimate at three additional men for one month). TTE suggested that this change order is enough to cover not only the 1, 2, 3 floors, but the entire building.
10/02/25 – THP – Champlin requested field support for cutting holes in precast panels.
10/23/25 – THP – after site trips and coordination with Champlin, THP issued field sketch for precast hole support.
12/11/25 – Graybach still confident they will get done by mid January with TCO in mid January for Phase 2. TCO expected next week for Phase 1 as most inspections are done for the TCO work. Design team still issuing Bulletins for changes for GC, EC, and low voltage. AT A&D they are getting ready to move to the new building. HC has weekly move meetings for coordination, Veteran Services move being coordinated. Osterman working with HC and Graybach coordinate move items. HC seeking additional funding for extra asks at the building and the low voltage items.
01/28/26 – Punch walk through completed. Exit sign issue has been solved.
02/26/26 – JFS has moved in to the first 3 floors. minor punch work ongoing. Floors 4 and 5 are ongoing. DDS awarded to Triton. Demo is complete for DDS.
03/26/26 – Floors 4 and 5 in progress. Punch tentatively scheduled for 3 weeks from now. Furniture scheduled to be compete 5/1. DDS portion is ongoing.
04/30/26 – Project to be complete in 2 weeks. Punch scheduled for next week. Move in mid may.
05/28/26 – Punch work nearly complete on 1, 2, & 3. Punch walk through on 4 & 5 minus DDS happened last week. Everyone (minus DDS) should be moved in by end of next week.
10/29/26 – Closeouts ongoing.

Central – Office Consolidation Phase 1 & 2 Read More »

EMA – Tornado Siren Conditions Assessment (No ITB)

PM: Matt/Trades, Terry Cannon
Closeout: Terry Cannon, tcannon@davieseg.com


06/25/24 – Proposal from ANS sent to Bert Watts for review.
07/24/24 – Submitted for 2025 budget. County may know in Q4 about viability.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
01/17/25 – SOSS Requested.
02/26/25 – Kickoff meeting on hold while TEI researches additional technologies.
03/19/25 – Preliminary conditions meeting held with EMA on SOSS modifications. TTC submitted revised SOSS with additional scope same day.
04/23/25 – MCP sent a very high proposal in to assist on this project. TTC to follow up with Nester on next steps.
05/28/25 – TTE release PO to ANS for Siren Assessment, scheduling the first kickoff meeting June 30 or July 2, this request out to Mike D at ANS. ANS says they will need about 45 days to perform the onsite analysis. MCP quote came back very high, looking for other specialist contractors to assist with assessment.
06/25/25 – ANS cannot make the July 2 date, TTC to pick another date.
07/18/25 – Kickoff meeting held at 525 with ANS and EMA. Project set to kickoff August 4.
07/27/25 – Nick commented that third party vendor not required for future recommendations of system and we can concentrate on the siren conditions first.
07/30/25 – Additional scheduling taking place, project set to kickoff August 11 onsite at Siren #414. EMA, TEI, HCDF and ANS.
08/28/25 – ANS has made two deployments to the County so far. Zone 4 was completed the first week of August. Zone 5 was addressed this week. We are not sure how far ANS will get this week but shadowing ANS, each siren was about one hours to 90 minutes of work with travel. We have questions out for what constitutes a FAILED siren, especially in regard to test 3.1.4 on the Audit worksheet. The Siren Tracking sheet was created and updated and implemented by ThermalTech and put to use in the OneDrive. The OneDrive folder is available for use on this project. We are on schedule for targeted completion.
09/24/25 – Vendor meetings continue. Zone 6 is complete. 26 audits have been uploaded, no failures for this group. Several sirens were skipped for access and traffic control. Joe is in town for Zone 1&2 at this time.
10/29/25 – ANS has completed their initial visit to all sites in all zones. ANS returning November 3 for Traffic Control sites. The traffic control sites and daily order was released today to all team members. Friday November 7 is a backup day to pick up remaining sites. Facilities has followed behind ANS nicely fixing and putting UNSAT sirens back into service.
12/12/25 – Traffic Control and Access impeded sites have been visited. DEG checks with ANS every day for final audits. We have received 8 of the final 37. TTC must submit 25% Draft Report by Friday.
12/31/25 – Draft report sent to Hamilton County Facilities & EMA for review.
01/12/26 – Received final 17 Audit reports from ANS and incorporated them into the report.
01/15/26 – Reviewed report with EMA and tabulated all siren conditions from ANS and presented these numbers to EMA as well.
01/25/26 – Updated report being sent to the EMA this week for second around of reviews.
02/25/26 – Rev-5 sent to the EMA for comment. This version includes the Acoustic Model from ASC. No comments received from Rev-4 yet.
03/25/26 – No comments received yet.
04/16/26 – Met with the EMA on comments on the report. They are extensive comments. DEG will begin working through the changed.
04/27/26 – DEG continues working on report updates. We’ve gotten though some of the proposed cost changes, most of the editing is complete, inventory changes picked up and now TTC has to contact Federal Signal and get their information for the report.
05/21/26 – Met with EMA and Facilities and sent back next revision of report to EMA for approval and review.
06/25/26 – TTC checked back with Morgan on comments or progress, no update yet.
07/30/26 – No updates on markups to final report.
08/26/26 – No updates, saw Nick at Sharonville Life Safety event, he didn’t mention.
09/23/26 – No updates but we are starting two siren relocations with Ben, Keith, and Zach.
10/26/26 – Waiting on next review meeting with EMA. Project is in closeout.

EMA – Tornado Siren Conditions Assessment (No ITB) Read More »

JC – Selective Cell Door Replacement 2024 (Ph. 4)

PM: Matt Butz, Sam Hofmann
03/28/24 – SOSS received. Sheriffs to locate doors included in this project.
04/25/24 – No update.
05/30/24 – Sheriffs provided doors to be included. Work in progress.
06/27/24 – Work in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. project to be bid in next couple weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Cornerstone is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project in contract phase.
01/30/25 – Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 3/31.
04/24/25 – No Update.
05/29/25 – Submittals received.
06/26/25 – Submittals to be returned and a schedule provided by Cornerstone.
07/31/25 – Submittals returned. Cornerstone to schedule mobilization.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Cornerstone to mobilize Monday to finish phase 3 work and begin phase 4.
12/11/25 – Phase 1 complete. Moving to phase 2 after the new year.
01/28/26 – Project ongoing.
02/26/26 – Project is ongoing. 2 pods left until completion.
03/26/26 – Project ongoing. second to last phase has been started. Final phase to pause for 1 month until Triton completes phase 2 work.
04/30/26 – No update.
05/28/26 – Cornerstone to complete this project after tritons project is complete.
06/25/26 – No update.
07/30/26 – Final pod is ongoing.
08/28/26 – Work is complete. Closeouts in progress.
09/24/26 – No update

JC – Selective Cell Door Replacement 2024 (Ph. 4) Read More »

230 – 10th Floor Marriage License Reno 2024

PK = Matt Butz, Mike Barth, Eryn Thamann
05/29/24 – TEI submits SOSS for approval.  Project pending PO and signed SOSS.
06/05/24 – Elevar submits SOSS for approval. Project pending PO and signed SOSS.
06/26/24 – Project pending PO and signed SOSS.
07/24/24 – TEI, Elevar and HCFD meet on site with end user. Scope changed and SOSS’s to be resubmitted for new revised scope.
08/27/24 – Elevar submitted new SOSS on 07/26 and awaiting approval.
08/28/24 – TEI receives signed SOSS and PO.
09/24/24 – Elevar scheduled a design kick off meeting for 10/01.
10/30/24 – Concepts provided to Probate for review.
12/09/24 – Finalizing concepts this week.
01/27/25 – ThermalTech awaiting schedule from HC/Elevar, HVAC SD level completed. In CD phase with 75% review in next few weeks. Electrical to finalize field confirmation after the partner meeting on 01/30/25.
02/25/25 – 75% review set sent to Probate for review and schedule of onsite meeting. Elevar still owes additional SOSS for lift removal/office add.
03/26/25 – Team met with Probate and has a few revisions. Still need finishes from HCFD. Elevar still owes additional SOSS for lift removal/office.
04/23/25 – Team is awaiting approval of lift/office SOSS to complete CDs.
05/28/25 – Progressing with CD drawings while waiting on final finishes approval.
06/26/25 – CD set was reviewed Probate and approved. Final finishes and systems furniture selected. Waiting for Probate to approved final SOSS for lift removal and additional office at which time they will be added to the drawings.
07/31/25 – Probate set to issue PO for additional work last wee/this week. Elevar to coordinate additional work and provide backgrounds. Need final approval for bidding from HCFD.
08/05/25 – THP received project authorization and signed agreement.
08/22/25 – THP – Elevar, County and THP reviewed field conditions for infill project.
08/28/25 – Additional SOSS approved and THP made site visit to field verify existing lift. Project will be ready to start HC review/bidding prep after this final scope is completed.
09/08/25 – THP issued infill repair detail for review.
09/25/25 – Drawings 95% complete and likely ready for a final review. ROM cost estimate sent to Probate for review.
10/21/25 – THP issued structural bid documents for project package.
10/30/25 – Project out to bid as of 10/22. Pre-bid mtg scheduled with team for 11/05.
12/11/25 – Post-bid vetting meeting scheduled for Alpha on 12/10 with Triton as next lowest.
01/29/26 – Permit/revisions applied for at City. Waiting on final contracts thru Purchasing.
02/26/26 – Contract awarded to Alpha on 02/19. Elevar to schedule construction kick-off mtg.
03/26/26 – Elevar to schedule construction kick-off mtg after Alpha provides construction schedule; expect this soon. HCFD to award special inspections SOSS.
04/30/26 – Construction kick-off meeting scheduled for end of May.
05/28/26 – Construction kickoff mtg occurred 05/27. Eryn to issue mtg mins and setup recurring progress mtgs. Construction to start June 1.
06/25/26 – Construction ongoing.
07/30/26 – Construction ongoing. Approx. carpet delivery is Aug 4. Phase 1 is waiting on carpet install prior to shifting to Phase 2.
08/27/26 – Construction ongoing in phase 2. Working on HVAC duct issue.
09/24/26 – Punch list for Ph. 2 occurred and contractor moved to Ph. 3.
10/29/26 – Approx. 2 weeks from Phase 3 completion. Furniture move is scheduled for 10/28. Closeouts will also remain.

230 – 10th Floor Marriage License Reno 2024 Read More »

RSC – City Water Main Extension

PM: Rycca, Terry Cannon
04/24/24 – Kleingers sent preliminary survey to County and ThermalTech for approval. Two items were tagged for review from the survey, the creek crossing and box culvert.
04/25/24 – SOSS approval going in front of the Board on May 2. BW needs all the TE paperwork by Monday for this work.
05/17/24 – Bert checked on status of submission to GCWW for water permit. TEI working on fire calculations for the load. We have the city water demand at 90 GPM.
05/28/24 – Colerain Township asked for the cost to extend the water line past the property. TEI and Kleingers will have to discuss additional cost.
05/29/24 – TEI to have preliminary application ready to discuss at Stated meeting this Thursday and completed by Friday.
06/26/24 – Preliminary application submitted this month. HC asked us to submit a SFHA permit too, which Kleingers is taking care of.
07/24/24 – Kleingers submitted both applications. TTE will check on progress with Doug.
08/28/24 – Update meeting scheduled for next week with County and City.
09/24/24 – Kleingers is currently working updating the drawings and its going well. It’s pretty straight forward except for the creek crossing, that might be tricky.
10/30/24 – Kleingers, ThermalTech and GCWW met onsite two weeks ago. TTE and Kleingers group sent out updates from meeting. The plan is agreed upon, Kleingers continue to design the routing and scope for new water line. GCWW says they will probably run a 12″ main in the street for current and future growth.
12/12/24 – Kleingers spoke with Bert this week and received the okay to proceed with the final construction drawings creating for the new water line.
01/28/25 – Kleingers sent an update to Bert. TTE sent review comments to Kleingers. Doug inquired if there was any progress on easement around bridge for new line.
02/26/25 – We had a progress meeting with GCWW, HamCo, Kleingers, adn ThermalTech and reviewed progress. TKG will follow up on easements and permitting. ThermalTech send load calcs to GCWW for use in their model.
02/27/25 – BW already made call on easements but believes the Engineer Office probably wants a Right of Way enlarge so the utilities can get back to maintain utility in the future. The routing of the line from the tap to down the road may change to meet GCWW needs for taps. TTC to check back with Doug on additional updates.
03/25/25 – Kleingers submitted an updated set of review drawings this week for review.
04/23/25 – Project in for review. Some emails are going around for coordination right now.
05/28/25 – Biweekly design meetings are now being held on Friday afternoons. ThermalTech hosting the meetings on Teams. Current work includes final approvals form GCWW, communication with Colerain Fire Dept about hydrant locations and finalizing HC Engineers Office comments. The Right of Way for the work around the bridge is in HC hands. Kleingers review drawings are up to date and distributed.
06/25/25 – Kleingers sent review drawings to the team yesterday. TTC to review and work on branch application. GCWW said the first shipment of piping will be delivered Friday.
07/11/25 – Design meeting to review County engineer comments
07/18/25 – Design meeting to review comments with GCWW. Kleingers to update and send new drawings for GCWW review to everyone.
07/30/25 – Next meeting is August 1 to comment on revised drawing sets and proposed budget. Bert sent easement requirements to Kleingers for their help with.
08/01/25 – Design Mtg #8 was held. The schedule was coordinated with the latest timeline. Kleingers will pick up latest markups and update the BOM on the dwgs for CWW. We are sending final review set to every for review the week of August 18. The easement work is underway.
08/04/25 – Kleingers sent latest drawings and materials list for final approvals.
08/22/25 – Final review project manual and drawings submitted to Bert Watts for approval. Budget and cost estimate finalized and coordinated with Bert. Comments sent to Kleingers by TTC for updates into final bid package. KEG working on easement with HCEO. Mylars sent to City for approval. New budget around $1.14M and we will publish at one million.
09/24/25 – Final review with City, GCWW and HamCo held on 9/12. We must wait until city/county agreement is signed and funds approved for bidding then TEI can publish the project.
10/29/25 – Kleingers has paid the OEPA bill and sent the City receipt. The project is nearly ready to bid but we await the City/County agreement to move forward with bidding. All the documents are ready to go minus final review and assembly.
12/12/25 – City/County agreement went to Board for Approval on 12/11, assuming that is approved bidding for RSC City Water Line will be in January.
01/21/26 – Received comments back from Bert Watts indicating that the City and County would have final comments back to DEG by Feb 6. Issuance pushed back to Feb 11 and bid date extended.
02/18/26 – Project Issued for Bid to County Purchasing.
02/25/26 – Prebid scheduled for March 4 on site. Bid opening schedule for April 1.
03/25/26 – The project is out for bid. Addendum 1 & Addendum 2 have been issued. Bids open April 1.
04/22/26 – Bids extended to April 22. Bids were opened and read. Four awardable bids.
04/24/26 – The low bidder has pulled his bid because they did not include the full paving requirements.
04/27/26 – The pre-award meeting is scheduled with the next low bidder QCM on Friday at 1:00 PM.
05/27/26 – QCM was recommended for the job. Their contract is in for review with the prosecutor office.
06/25/26 – Contract sent to QCM and signed. DEG met with QCM on SOV and schedule on 6/24. QCM to send SOV in for review and they are okay with schedule extension and August 1 start. They would like to have a pre-const ASAP.
07/30/26 – Early Pre Const and Pre Const meeting held, notes distributed. Next meeting August 4. QCM acquired ROW permit, survey complete, and had begun marking and cutting pavement.
08/26/26 – Const Mtg #1 & #2 held on site. QCM making progress to about 1200 LF of piping installed. FH 13 installed. 50 sticks of piping missing but we’ve tracked it down to a missing shipment. US Pipe working to provide missing lot to the project site for use. Payapp #1 received and approved.
09/23/26 – Payapp #2 approved and submitted. Next Const Mtg is next Tuesday at 8AM not 9AM. QCM working on CO cost for hydrant and culvert, we will have something by the end of the week. Things are going well.
10/19/26 – Project team met on site to review landslide condition at Station 4 where the water line goes down hill to creek. It was decided to bring Terracon out to review existing road conditions.
10/22/26 – Project team met Terracon on site to review existing conditions. Facilities, GCWW, Terracon, QCM, DEG and Kleingers discussed alternate routes and proposed solutions. GCWW is leaning toward keeping the line where design and shoring up the hillside and sharing that cost with HCEO. Facilities and HCEO has afternoon meeting to discuss next steps. Afternoon meeting reviewed original design and field conditions with HCEO, Facilities and DEG. Kleingers not at afternoon meeting. It was decided to do more investigation, look for previous soil boring and to reconvene with another HCEO and Facility meeting on 10/30/26 for updates.
10/26/26 – HCEO working on reviewing existing field conditions at and around original water line path so we can keep water line in original spot. Terracon submitted boring report to Facilities from 1970’s for this area. This report was shared with the project team. Follow up meeting on Friday.

RSC – City Water Main Extension Read More »

CH – Parking Lot Security

PM: Matt Butz, Sam Hoffman, Mike Barth
04/25/24 – Champlin has submitted SOSS, ThermalTech submitted SOSS recently.
05/30/24 – SOSS returned. Project kickoff to be scheduled in near future. BW said that this project on the fast track due to a recent incident in the parking lot.06/27/24 – Kickoff to be scheduled.
07/25/24 – Meeting held on site with County, Champlin, and several judges. Champlin is investigating fencing options and guard booth options for review. Plan will be modified based on comments in the field.
08/12/24 – THP completed a cursory field measurements for review of the proposed fencing.
08/12/24 – THP sent proposal to Champlin for review.
08/27/24 – THP sent SOSS to County for review.
08/29/24 – THP working on design with Champlin.
08/29/24 – Second meeting held for more investigation. THP found that additional structure will be needed for fence and guard booth.
09/25/24 – THP issued bid documents 9/20/24.
10/31/24 – Project is out to bid. Opening on 11/8.
01/30/25 – Tumlin was awarded the bid. Kickoff held. Permit submitted 1/29. Pending zoning and historical society approval. Submittals incoming.
02/27/25 – Submittals in progress. Tentative schedule received. Rejection received from the historical society.
03/27/25 – Submittals in progress. Zoning hearing scheduled for 4/2 for historical variance.
04/24/25 – Historical approval provided given some aesthetic changes to the project. Tumlin to provide pricing on the changes.
05/29/25 – Working with guard booth manufacturer to meet energy code requirements.
06/20/25 – THP submitted Bulletin #1. This covers the revisions that resulted from historic review board comments.
06/25/25 – THP received preliminary pricing from KT Holden for resurfacing lots: 250k.
07/31/25 – County approved moving forward with the Resurfacing project.
08/26/25 – THP modified the footing design to accommodate a continues concrete curb. THP preparing final sketch to be published on 8/30 with Bulletin No. 4.
09/24/25 – THP issued bulletin #4 on 8/29/25 to add grade beam for field conditions and new parking lot resurfacing work. Project in CA
10/30/25 – Grade beams installation onging. Guard booth will be lowered into place this weekend. Progress continues.
01/28/26 – Steel for door installed. Work ongoing.
02/26/26 – Cold formed steel going up in the next couple weeks. Fence material delivered. Phase 2 is pushed back slightly to align work.
03/26/26 – Phase 1 nearly complete. Cladding structure to begin weather dependent. Phase 1 fence installed. Phase 2 tentative date is 4/13.
04/30/26 – Phase 1 complete this week. Following for punch and commissioning. Phase 2 to begin 5/11. Parking on e court street and bus stop coordinated with city to prep for phase 2. Rycca, Mike and Derrick met onsite for security plants. SOSS incoming.
05/28/26 – SOSS for security plant beds submitted. Sheriffs have solved their booth connection issue and kicked off phase 2.
06/25/26 – Phase 2 to switch over mid July. Doors and booth to be tested to ensure seamless transition.
07/30/26 – Phase 2 has begun. Demo exposed some underground conditions that are being resolved. Phase 1 issues have been worked out, including new controls after being struck by lightning.
08/28/26 – Issues discovered below grade have been solved. Grade beams almost complete. Steel has been erected.
10/29/26 – Finishing fence this week. Programming second door. Ready for turn over next week.

CH – Parking Lot Security Read More »

JC – Lobby Ceiling Replacements

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. Project in progress. ThermalTech has been onsite and updated mechanical drawings for the potential future pans. Sam to setup kickoff project for this job.
06/27/24 – Kickoff to be scheduled in near future. BW asked to add the North Bldg Lobby to be added as an Alternate to this job, lower ceilings etc.
07/25/24 – Meeting held to discuss scope. Field visit to North building will take place soon. Bid set will be ready for owner review by end of August.
08/29/24 – Owner review set submitted. Project will be issued for bid in the next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kickoff to be scheduled in near future.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Submittals still in progress.
05/29/25 – No update.
06/26/25 – No Update.
07/31/25 – Submittals returned. Triton to schedule mobilization.
08/28/25 – Pre-mobilization meeting to be scheduled. Duration schedule received.
09/25/25 – Background checks approved. Triton mobilized this week. Demo to begin next week.
10/30/25 – Demo complete in both buildings. Installation has started.
12/11/25 – Plumbing and drain pan rework saved cost and simplified the system. Ceiling grid and pads to begin in North Lobby next week.
01/25/26 – Diffuser RFI answered earlier this month, should be an easy install. DEG reminded the county that they were working on Geiler replacing bad p-traps at ceiling before new ceilings are going back in. Fire dampers accessible only through this ceiling should be getting done by NKYHC (see Tony).
01/28/26 – North Building insulation tested for asbestos and came back negative. Triton providing pricing for insulation and mastic removal.
02/26/26 – CO#1 approved to remove insulation and mastic. Work is ongoing. Scheduled to be complete March 5th. Fire damper work is complete. Plumbing repairs being finalized. Fire alarm worker can use Triton lift to facilitate progress.
03/26/26 – Ceiling installation ongoing. CO Trap work to begin next week. Project tentatively to be complete mid april.
04/30/26 – Electric sub never got plan review approval. Issue has been resolved and inspections can be scheduled. Once inspections are passed, padding out ceilings will be final step.
05/28/26 – Final inspection passed. OKI to be on site for pad installation this week. Punch to be scheduled week of 6/8.
06/25/26 – Punch complete and final work to be complete this week.
07/30/26 – Punch work complete. Closeouts ongoing.
08/28/26 – Back punch complete. Closeouts received.
10/29/26 – No Update.

JC – Lobby Ceiling Replacements Read More »

TPC – Atrium Glass Replacement

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. work in progress.
06/27/24 – CDs in progress.
07/25/24 – No Update.
08/29/24 – Project will be issued for bid in next couple of weeks. Send to JN for review including the base bid and three alternates (bullet glass).
09/26/24 – Project is out to bid. Pre-bid scheduled for 9/30.
10/31/24 – No bids received. Project is back out today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future.
2/27/25 – Contracts finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals to be submitted.
04/24/25 – Submittals in progress.
05/29/25 – Pricing for frosted glazing received. We need to decide if spandrel glazing is remaining in the project.
06/26/25 – Change order cost to remove spandrel glazing and add frosted glazing to project received. Jesse to confirm.
07/31/25 – Changes confirmed. Scope will potentially be added to make use of deduct funds.
08/28/25 – Provided confirmation of scope change and permission to start. An offical cange order will be settled at the end of the project after any additional scope is added.
09/25/25 – No update
10/30/25 – Work is complete. Scaffolding removal and final cleaning to take place next week.
12/11/25 – Scaffolding removed and punch items addressed. Closeouts in review.
01/28/26 – County to provide scope for additional change order work.
02/26/26 – Field visit to determine additional work attended by Sam and Rycca. Bulletin #1 to be posted shortly.
03/26/26 – Bulletin #1 sent to Alpha to include glazing replacements on floors 5-10 and window cleaning of first floor windows.
04/30/26 – Alpha provided pricing. Waiting on clarification on pricing.
05/28/26 – No update.
06/25/26 – Change order approved. Schedule to be sent after submittals are approved.
07/30/26 – No firm delivery date yet.
08/28/26 – Tentative delivery date of 9/14
10/29/26 – Glazing installed. Windows washed this weekend.

TPC – Atrium Glass Replacement Read More »

TPC – Reentry Expansion

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in. We need the PO by mid-November and the project must be complete by 11/1/25, they are moving out of the lease space.
05/30/24 – Kickoff held with Thermaltech, County, Reentry and Champlin. Some minor redesign will be explored.
06/27/24 – New options will be provided to Trina this week.
07/25/24 – New options presented. Final plan confirmed. CDs in progress. Owner review scheduled for 8/14.
08/29/24 – Final owner review meeting held. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Submittals in progress. Kickoff meeting scheduled for next Wednesday.
06/26/25 – Demo for Phase 1 in progress.
07/31/25 – Demo complete for Phase 1. Re-entry to move to 4th floor space to give Triton full access to project area.
08/28/25 – Phase 2 demo is complete. Triton met with County and Champlin to discuss change orders. Adjusted COs provided. HC reported today that they would like to Triton to be completed in October 2025.
09/25/25 – Project on schedule to finish end of October. All change orders settled. Work continues.
10/30/25 – Project nearing completion. Furniture delivered to site. Triton will most likely get TCO approval early next week. Fire sprinklers are being added in a couple of pockets. We are keeping the window washing sprinklers heads as-is but Preferred will have to update their permit drawings after the TCO is approved.
12/11/25 – Fire protection work took longer than expected. Inspection to be scheduled for next week. Final CO expected before Christmas.
01/28/26 – Inspector will not provide CO until the exterior stair door is fixed. Trades is fixing the door starting on 2/2. Bulletin 2 for window shades and power issued and waiting pricing.
02/26/26 – Bulletin 1 pricing received. Work outstanding.
03/26/26 – Bulletin #2 pricing has been received and approved. Triton to begin electrical work.
04/30/26 – Blinds installation outstanding. All other work complete.
05/28/26 – Closeouts received and returned. Triton to submit outstanding items.
06/25/26 – No update.
07/30/26 – Hardcopies to be delivered to County.
08/28/26 – Hardcopies delivered. Access control programming complete.
10/29/26 – No update.

TPC – Reentry Expansion Read More »

CH – Law Library Stained Glass Window Repair

PM: Megan, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Initial field verification complete. We will need a second trip to take dimensions.
06/27/24 – Second trip complete. CDs in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30. ITB sent to multiple stained glass vendors.
10/31/24 – Bids received. One vendor had a bond issue, one bidder did not fill out XBE paperwork properly. Purchasing to provide direction.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in progress. Kickoff to be scheduled in near future.
02/27/25 – Contract Finalized. Kickoff to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Phase 1 windows are removed and taken back to the shop for refurbishment.
06/26/25 – Progress meeting at the shop scheduled for mid July.
07/31/25 – Windows still in progress.
08/28/25 – Phase 1 windows to be reinstalled in september. Phase 2 windows will be removed during the same time. Tentive completion date of end of october.
09/25/25 – Reinstallation of phase 1 began this week. Removal of phase 2 in progress.
10/30/25 – All storm windows have been installed. Stain glass installation of phase 1 to begin shortly. Phase 2 to be complete by end of november. County to request change order related to the plaster repair at window jambs.
12/11/25 – One section of stained glass installed. Second half of windows are still under repair. Background checks for installers have been over 90 days. County allowed stain glass to be reinstalled all at once when phase 2 windows are ready.
01/28/26 – No update.
02/26/26 – No update.
03/26/26 – Breilmeyer to mobilize this week. Installing half of glass and taking the other half to their shop.
04/30/26 – Half of stained glass is installed. Tentative completion at end of may.
05/28/26 – Breilmeyer to mobilize 6/8 to install the second half of the glass.
06/25/26 – Second half install ongoing.
08/28/26 – Installation complete. 1 punch item outstanding.
09/24/26 – No Update.
10/29/26 – Punch item complete. closeouts outstanding

CH – Law Library Stained Glass Window Repair Read More »

CH – North and South Riot Door Refurbishment

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Project to start once first phase is complete.
06/27/24 – Field verification completed. Drawings in progress.
07/25/24 – No Update.
08/29/24 – Owner review submitted. Investigating one more option for interior vestibule doors. Project will be ready to bid in next couple of weeks.
09/26/24 – Project will go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project was put back out to bid and opens on 12/19. Olek intends on bidding.
01/30/25 – Olek was awarded the bid. Contract is still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Doors have been removed and refurbishment is in progress.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – Call to discuss potential additional scope scheduled. Doors still in progress.
08/28/25 – Olek to reinstall riot doors in mid september. Electrical work to be complete during this visit. Any items that need to be taken to their shop will be removed and brought back after refurbishment.
09/25/25 – Olek currently onsite prepping for installtion of riot doors and interior doors.
10/30/25 – Door hardware supply issues pushed installation of riot doors back.
12/11/25 – Olek has been back on site. Ran into issues with the thresholds and pivots. Olek will be back mid january to continue work.
01/28/26 – Olek did not come back on site as first promised. Olek not responsive or timely. Champlin gave them a notice to be on site 1/19 or they would be referred to the prosecuter. Olek agreed they were in breach of contract but would not be on site until 1/26. The snow storm pushed that visit back until acceptable weather. County to provide prosecuter with letter.
02/26/26 – Olek to be back on site on March 9th to complete all remaining work.
04/30/26 – All work is complete. Closeouts are nearing completion.
05/28/26 – Closeouts outstanding. DK to complete a couple punch items.
06/25/26 – Close outs reviewed and several items still needed.
07/30/26 – Final punch item to be complete by Olek in August.
08/28/26 – Olek on site to complete punch work.
09/24/26 – Punch work complete. Olek sent official request for multiple change orders. Champlin has recommended denying request.
10/29/26 – Olek sent official request citing the contract. Champlin to provide official response.

CH – North and South Riot Door Refurbishment Read More »

SPHQ – Arc Flash Remediation 2024

PM = Matt, Barth

04/24/24 – TEI submits SOSS for approval.
05/29/24 – Project Pending SOSS approval.
06/26/24 – TEI receives signed SOSS and PO.  TEI has conversed with building manager re existing system and electrical needs.
07/24/24 – Project in progress.
08/28/24 – TEI to meet with building manager to discuss updated model and options.
09/25/24 – TEI meets on site with building manage and Matt Butz. A list of possible upgrades developed. TEI sends schematic dwg and costs to HCFD for review and direction.
10/30/24 – TEI issues project for bidding. Prebid meeting scheduled for 11/12/24 at 11:00 AM.
12/11/24 – Bids open at 11:00 AM on 12/12/24.
01/29/25 – No bids received. HCFD to advise if re-bid funds are available.
02/26/25 – No updates on rebid funding.
03/26/25 – No updates on rebid funding.
04/23/25 – No updates on rebid funding.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No updates on rebid funding.
08/27/25 – No updates on rebid funding
09/24/25 – Project pushed to 2026 project.
01/28/26 – DEG to submit SOSS for re-package and rebid for 2026 project.
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending approval of SOSS
04/29/26 – DEG receives signed SOSS and PO. Reaching out to bldg mgr to confirm scope.
05/27/26 – DEG meets with Ian Zellner – confirms scope. Finalizing drawings and OPC for HCFD review.
06/23/26 – DEG to submit 100% review set to HCFD by end of June.
07/29/26 – Per HCFD – Project on HOLD until further notice.
08/26/26 – DEG to update labels and apply then close out the project.
09/23/26 – No updates
10/28/26 – All labels have been applied to the gear on site. Project complete.

SPHQ – Arc Flash Remediation 2024 Read More »

EMA – Tornado Sirens Gen Services 2024

PM: Matt/Trades, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – TEI develops Clifton (#81 W Nixon) drawings and submits plans to IBI for permitting.  We will notify county trades once permit is approved.
06/26/24 – TEI secures permit for #81 West Nixon.  HCFD to notify when the work is completed and ready for inspections.
07/24/24 – No updates this month.
08/28/24 – No new work this month.
09/25/24 – IBI inspection passes and EMA and Duke to connect power. Work on Siren #81 complete.
10/30/24 – No updates this month.
12/11/24 – Ben (EMA) sends Alex GPS coordinates for siren that needs to be permitted. TEI working on the permit documents.
01/29/25 – No Updates this month.
02/26/25 – No updates this month.
03/26/25 – No updates this month.
04/23/25 – Wes and Ben (EMA) coordinate location. Upon approval of location and connections by Duke, permit drawings will be issued.
05/28/25 – TEI finalizes permit drawings and submits to IBI for plan review.
06/25/25 – Plan review passed. Permit applied for on line. Ready to schedule work with trades.
07/30/25 – Permit was delivered to HCFD (Electricians). Inspection pending installation. DEG will call for inspection when notified that the siren has been installed by trades.
08/27/25 – IBI inspection occurred and passed on 08/27/25.
09/24/25 – No updates.
10/29/25 – No updates this month.
12/10/25 – No updates this month. Pending issues with existing poles. etc.
01/28/26 – No updates this month. Pending issues with existing poles. etc.
02/25/26 – No updates this month. Pending issues with existing poles. etc.
03/25/26 – No updates this month. Pending issues with existing poles. etc.
04/29/26 – No updates this month. Pending issues with existing poles. etc.
06/23/26 – No updates this month. Pending issues with existing poles. etc.
07/29/26 – No updates this month. Pending issues with existing poles. etc.
08/26/26 – EMA reaches out to Wes about possible relocation of pole in Wyoming (Chisholm Park).
09/23/26 – EMA and DEG are working on (2) siren locations for 2026, and (1) for 2027.
10/28/26 – (2) Sirens are in for QC review. Then will be issued for installation.

EMA – Tornado Sirens Gen Services 2024 Read More »

CH – Common Pleas AV Upgrades

PM: Megan, Mike Barth, Mike Murphy
04/24/24 – TEI receives signed SOSS and PO.
5/29/24 – HCFD, TEI and Judge Jenkins Visits Montgomery County CH to see system in action.  Champlin and TEI visit all courtrooms to develop plans and take measurements of existing benches for install locations of equipment.
06/26/24 – Weekly meetings are conducted every Wednesday afternoon.   The most current EV equipment has been sent from BIS to the team.  TEI has Design documents well developed and will be conducting a final walk thru of each of the courtrooms on 06/27/24 as soon as the docket clears.
07/24/24 – TEI will provide HCFD a final review set on 7/26/24. HCFD will review and get comments back to TEI by 8/2/24. Project to be issued for bidding on 8/7/24.
08/28/24 – Project has been issued for bidding. Prebid meeting was held on 08/23 – (2) bidders attended. Bid opening scheduled for 09/19.
09/25/24 – Received (1) bid from DK, (39% over budget). Rejected the bid, repackaged and re-issued for REBID. Rebid Prebid meeting scheduled for 10/18 and Bid opening on 11/06. TEI reaching out to area ECs by phone and notifying of bid opportunity.
10/30/24 – Final addendum issued on 10/30/24. Bid Opening 11/06/24 at 11:00 AM.
12/11/24 – Bids open. DK low bid. TEI vets the DK bid and sends letter or recommendation to HCFD. project pre-const meeting to occur upon contract approval.
01/29/25 – DK, HCMC, HCFD, BIS and TEI are in the pre-construction/procurement phase of the project. DK to provide project schedule.
02/26/25 – DK, HCFD, BIS, TEI and HCCPC have weekly meeting to update status and tracking.
03/26/25 – Work on CR 580 has started. Next CR’s were discussed at the meeting this week. BIS to ship the next 2 rooms equipment week of 4/10.
04/23/25 – Work continues in CR 580. End of this week DK to be ready for carpet install (HCFD covering carpet install). Floor slab xray scheduled for 04/26/25 (Saturday).
05/28/25 – BIS sends technician to CR 580 today for coordination with DK. All DK field issues/concerns addressed. Field visit to fire up the system on 05/30 at 1:00 PM.
06/25/25 – CR 580 complete, pending training on equipment and demo to other Judges.
07/30/25 – CR 580 training completed. CR 580 in use and DK is now working on CR 320. Tweaks are happening as the systems are being placed into service. Rycca asked if we should order the AV equipment and set it back in the Archive room and they can use them out of the boxes on the sixth floor. Punchlist scheduled for 8/5 at 3PM.
08/27/25 – Punchlist for room 580 completed. DEG issues the Punchlist to DK. Installation of BIS equipment installed this week.
09/24/25 – Finalizing CR320. Moving on to CR 380 next. At const meeting, it was discussed to ship all equipment as soon as ample storage space for 16 more rooms equipment. Arpa funds must all be spent by 12/31/2026.
10/29/25 – Programming installed in Room 320. Work starting in rooms 300 and 380.
12/10/25 – Work continues with CR 300 and 380. Punchlist scheduled for 12/10/25 cancelled due to court session running long.
01/28/26 – Project continues.at the meeting today discussed the next 2 rooms to be worked on (340 and 360). This will finish the CRs on the 3rd floor.
02/25/26 – Project continues. Work on 3rd floor progressing. Speakers swapped out in 580 and sound quality substantially improved. DK brings in “sound expert”, Leo Little form ICS, to evaluate rooms. Leo to provide quotation to DEG for sound engineering services.
03/25/26 – Electrician changes necessitated for the project. DK to update situation ASAP. finishing CR 330 and moving to 360 and 340 next.
04/29/26 – Work continues in Rooms 340 and 360. Walk for 485 and 496 scheduled for 5/5.
05/27/26 – work continues in room 340 and 360. Rooms 485 and 495 are next (waiting on floor boxes to be fabricated). Walking locations on the 5th floor 05/27/26.
06/23/26 – Sound Guy (Leo Little) models room 485 and returns proposed layout with the speakers that were purchased from BIS.
07/29/26 – Sound guy visits room 300, modelling the room. HC directs Leo to only use the bill of materials for the rooms, and to not give recommendations for improved sound quality with equipment not in the original BOM.
08/26/26 – Room 300 sound recommendations installed. Sound quality greatly improved. ICS states that next 2 rooms are scheduled to be sent today.
09/23/26 – Work continues on the installation. ICS completes all room sound models and recommendations. There are 2 rooms (320 and 380) that HCFD sent comments back to ICS for tweaks.
10/28/26 – All sound models received on all rooms. Punchlist walk occurred on 10/26/2026. Work starting on Jenkins CR on Monday 11/02.

CH – Common Pleas AV Upgrades Read More »

Hillcrest – Campus Repairs Phase 1

PM: Megan, Mike Murphy, Terry Cannon
12/20/23 – THP – Champlin request SOSS for incidental structural support work.
12/21/23 – THP submitted SOSS to Champlin for review.
01/30/24 – Kickoff meeting with Facilities, Juv Court, Champlin and ThermalTech.
01/31/24 – Meeting notes distributed, TE started drawings packages for Phase 1.
02/28/24 – Scope for phase 1 finalized. Meeting scheduled for March 13, 10AM to review finishes and answer any remaining questions.
03/22/24 – ThermalTech Phase 1 drawings and cost estimates pretty close for final review. TTC working through individual items with Facilities. TTC requested meeting with Facilities to coordinate final scope of each building to nail down equipment repairs, replacement, upgrades. Verified that the four cottages are Elm, Evergreen, Hickory and now Maple is an Alternate.
03/22/24 – Champlin close to complete with review set as well. Final review meeting set for 4/3. Estimates to follow on 4/12.
04/24/25 – Final review drawings sent this month. Revised estimates were sent to Bert for review. Breakouts were formatted so they can see the assessment vs final design.
05/30/24 – County approved funding. Drawings modified accordingly. User requested a meeting to be scheduled in near future. BW said that the project can go out for bid as soon as we are ready to bid this project. TTC, MCB, and SH said the drawings and specifications are ready. BW and MM discussed the fence alternate around the building. Be ready to bid June 11-13 timeframe.
06/27/24 – Project is out to bid. Pre-bid scheduled for 7/9. Partners to invite local contractors for bidding on July 9.
07/25/24 – Project is still in bid phase. Final addendum to be posted by next Wednesday.
08/29/24 – Bids came in awardable. Accepting different alternates will determine lowest bid. County to decide what they are accepting.
09/26/24 – Project is in contract phase. County still finalizing alternates. Champlin to send recommendation letter for recommended bidder and note we have not finalized the accepted Alternates.
10/31/24 – Contract in process. Variance package for the fence is nearly complete.
12/12/24 – Contract awaiting on PO approval. Submittals incoming. HVAC and Plumbing submittal are done, TTC needs to approve and send along. BW said to go ahead and submit permit and fence variance for this job.
01/02/25 – ThermalTech starting on submittals this week for Phase 1.
01/30/25 – Kick-off held 1/29. Submittals are in progress. Zoning is complete. Permit has been submitted. Zoning application for fence to be submitted this week. Graybach ready to mobilize by mid February.
02/26/25 – We met with Aramark on Tuesday to review kitchen operational needs. TTE has been reviewing and working on HVAC, Plumbing and Electrical submittals on an ongoing basis. We are in good shape. Two AHU’s have delayed ship dates because the manufacturer is not producing R-454B refrigerant yet.
02/27/25 – Submittals in progress. Notice to proceed will be provided to allow Graybach to start on site work. Zoning application for fence to be submitted this week
03/27/25 – Submittals ongoing. Demolition ongoing. Permits approved and picked up. Fence application in HC lawyers hands.
04/24/25 – Bulletin #1 released. Already received a $25,000 add for the window changes. The rest of the pricing is outstanding.
05/21/25 – Met with Graybach, Champlin, Facilities on Change Order log, we do not have EC cost yet. Review deducts and approved a couple of them. Verbally approved Windows change order.
05/28/25 – ThermalTech regularly meeting contractors on site working on RFI and Change Orders for this project. The big items are the R-454B units for School and Dining, Water Closets on new tile walls, ductboard repairs and controls for the Admin building.
05/29/25 – Change order #2 for the windows is approved. Several potential change orders have pricing submitted. Rycca needs to finalize which will be approved or not. Change orders 3 and 4 approved. The remaining items have been priced and submitted to the board for a PO increase. Work may have to pause while this process takes place.
07/31/25 – Request for funding all change orders went before the board. No update on their decision yet. Work is in progress. Rycca reported that LaForce found a control key and it is getting cut and shipped to our site. The hope is to stay with the existing manufacturer. Rycca further said that they need final change order cost for all remaining COR so she can take final numbers to the BOCC. HVAC final cost, plumbing underground cost, electrical final change order needed. Sam is working on the frosted glass specs but must be ligature proof. TTC to confirm if County self performs repair if warranty is intact.
08/26/25 – Construction meetings continue. We agreed on the items to be included in Change Order 5 and now we are working on reconciling the cost associated with them. TTE sent two items for HC plumbers to fix, but while on site they had questions. TTC to meet them on site to review.
08/28/25 – County requested $800k for Phase 1 repairs. Plus CO#5 is approved and sent to Josh for approval.
09/24/25 – TTE sent a long list of field conditions to Graybach after last const meeting for them to address before the project gets to the punchlist phase. Graybach responded with action items and concerns over some of the comments. One item was that the County agreed to allow the return diffusers to remain as installed but they should be changed out before occupancy.
09/25/25 – Change order request goes in front of the board this week.
10/30/25 – Change order request was approved by the Board. Work continues in full force. No word on the fence yet.
12/11/25 – More change order requests came in. Scope removal to cover permit required work is being considered. Project competition is tentatively scheduled for end of February.
12/12/25 – DEG met onsite to review lighting change order and work out several nice compromises with the EE and GC. MCB to send Rycca and proposed update. Parks & Graybach to update and send in revised change orders for review.
01/23/26 – Const Mtg. DEG walked the site, check plumbing, heating, and electric. Chris Hofmeister called us back to the cottages to ask about external conduit adjacent to the receptacles. This turn out to be communication wiring not power wiring. Habegger will be out Tuesday to check temperatures in school, the two wings felt cold, but the core was warm. HVAC and plumbing are released to perform their punchlist.
01/28/26 – Campus is nearing completion. Bulletin to address change in fence scope to be issued in near future and variance submitted.
02/26/26 – Work ongoing. Waiting on approval for change in fence height to issue bulletin. Mechanical punch completed.
03/26/26 – Fence bulletin issued. Waiting on pricing to determine exact scope. Punch of school and admin building complete. Punch for remainder of buildings to be scheduled in near future.
04/30/26 – Punch work in progress. Fence application still in County hands.
05/28/26 – Variance application submitted. Hearing scheduled for 6/16. Owner punch walk through school. The rest of the buildings will be walked on 6/5.
06/25/26 – Variance approved. Survey to be scheduled in near future. Majority of punch work to be complete by mid July.
07/13/26 – TTC on site working on plumbing and HVAC items all week.
07/20/26 – TTC on site working on plumbing and HVAC trends all week.
07/22/26 – DEG on site doing back punchlist work.
07/23/26 – DEG on site doing back punchlist work.
07/24/26 – DEG on site doing back punchlist work.
07/30/26 – Final back punch complete. Minor items outstanding. Fence location needs final approval.
08/28/26 – Punch items have been progressing. Fence location not yet approved.
09/24/26 – 3 items remaining according to Graybach. Fence location has been approved, just waiting on confirmation of supposed easement.
10/29/26 – Back punch complete. Fence work ongoing.

Hillcrest – Campus Repairs Phase 1 Read More »

JC – Fire Pump Replacement (085-24)

PM: Matt, Terry Cannon
Closeout: Haeli Johnson, hjohnson@tritonservicesinc.com, Dayna O’Brien, dobrien@davieseg.com

 


01/24/24 – Post created for tracking.
02/01/24 – TE to submit SOSS for this project.
02/23/24 – Coty will be working on this job.
03/22/24 – Initial fieldwork started this week. SOSS submitted. Electrical review scheduled for next week to ensure fire pump feeders meet current code. Life safety code updates may apply to this upgrade.
04/08/23 – Met with our electrical group this week to discuss the power feeders to the fire pump. We decided the best course of action that saves the County the most money is to let the Emergency Power project go first and update the MCC disconnects to isolate the fire pump disconnect in its tub so that it meets current code. Once that work is complete, we can bid out the replacement of the fire pump with out running into issues with the new NEC requirements for feeders in concrete or the fire pump being fed first before ancillary equipment.
04/24/24 – The preliminary drawings are ready for TTC review.
05/29/24 – TTC marked up drawings for owner review. TEI working with Fire Marshal on component required for replacement versus new NFPA code. This has to be bid this year even though it will be installed after the Emergency Gen update.
06/26/24 – Final drawings are ready for review, changes have been made from our field trip with Andy earlier this month. CFD not willing to provide pumper truck for weekend, we are checking on rental fire pumps and fire watch. SA believes a fire watch can be used.
07/24/24 – We were waiting on the JC Emergency project to be awarded so we could move forward with bidding our design out. The FPC will provide the fire watch as needed to make these piping changes and replace the pump vs using the CFD. I have not seen any CFD response in writing to our design request.
08/28/24 – Final internal review scheduled Friday.
09/24/24 – Project is out for bid. Prebid scheduled for Oct 8 at 9am. Bid Opening is Oct 30.
10/30/24 – Bids opened with four bids under budget, two of which were non-awardable due to a bond issue. TTE to interview KFI on Friday for compliance to bid specs.
12/12/24 – Triton was the low bidder via the base bid and Alternates accepted, we await the contract and PO to have the kickoff meeting.
01/30/25 – Contract going to commissioners tomorrow for approval.
02/26/25 – Contract is back, we are setting up Pre-Const meeting.
03/25/25 – Pre Const meeting was held and meeting notes distributed. Schedule, SOV, and equipment submittals have been requested.
04/23/25 – Construction Meetings started. Stamped permit drawings have been sent to Triton for submissions. Submittals have been requested. Other project startup documents have been requested.
05/28/25 – ThermalTech received written direction on suction valve controller which is not required on this replacement as long as we have the low suction cutoff report as a supervisory back to the FACP. We are approving the Fire Pump Controllers and rejecting the Fire Pump and Jockey pump due to under sizing and rotation issues.
06/25/25 – Equipment ordered and waiting on equipment delivery. The latest ship date is September 18, 2025.
07/30/25 – Pump submittals are finally approved. Bulletin #1 drawings sent for pricing to fix test header.
08/28/25 – Latest update is that the fire pump will arrive 9/19. Triton to coordinate replacement with Owner.
09/24/25 – Work being scheduled now including fire watch requirements.
10/29/25 – The fire pump has arrived. The test header was repaired by SA Comunale, now the wall and patching work needs to be completed. A new test ring needs to be installed on the outside FDC. Quality Fire has two people badged, checking on TJ Williams badged contractors. We need to iron out Fire Watch details with Triton.
12/12/25 – Triton and Quality ready to begin the project. Final fire watch details being negotiated. Inspection test header has been repaired, outdoor placard spacing is loose.
12/22/25 – Construction meeting held, we are working out details of shutdown, fire watch and submittal approvals.
01/12/26 – Const Mtg, finalizing shutdown details, fire watch, and schedule for work. Fire Watch must be provided by Triton for non-secure areas, DEG to issue drawings for scope. Electrical shutdown may require Courthouse to provide steam for Justice Center based on weather.
01/21/25 – Adding additional details and scope to the shutdown and next phase of work. USPA does not have background checks complete for fire watch yet. Electrical changes submitted to IBI. Feb 3 will be electrical emergency crossover and Feb 10 will be the primary crossover. Pump replacement scheduled for Feb 23.
02/25/26 – Emergency power is connected. Normal power has become a power struggle between Duke and IBI and DEG is working through those requirements and obstacles with both parties. the pump install will be coordinated after the power requirements are resolved.
03/25/26 – Normal & Emergency power are connected and ready to go. CFD required paperwork submitted & 3 of 4 FDC did not pass inspection. March 23rd replacement rescheduled until FDC are repaired. SA coming in on Friday to begin repairs and assessment.
04/29/26 – 3 of 4 of the FDC are repaired. The fourth FDC is currently under repair but SA is having trouble sourcing an access panel for the wall opening. TTC asked to open the wall now and repair the FDC which should only take a day, temporarily install a wall covering to keep the fire pump job moving along. The fire pump is currently scheduled to be replaced May 18-22.
05/18/26 – Replacement started on the fire pump today. Triton and DEG providing 24/7 fire watch.
05/19/26 – Repairs and fire watch continues.
05/20/26 – Repairs and fire watch continues. 99% of electrical and mechanical work is complete. Corporate equipment pre-inspected the fire pump installation and it passed. We are trying to move up final inspection to Thursday at 1:00PM.
05/21/26 – Replacement complete. Fire pump tested at 1:00PM with full water test, manual and automatic starts with City of Cincinnati and Cincinnati Fire Department in attendance. All system passed, the new fire pump was put online about 4:00PM and the fire watch was completed.
05/27/26 – DEG provided the punchlist for the project and will distribute later this week.
06/25/26 – Project in closeout.
07/30/26 – Working on latest change orders for this project. COR-1.
08/26/26 – Change Order #2 in the works? Working on other closeout documents.
09/23/26 – Change Order #2 COR #1 data all updated and sent in for approval to County.
10/26/26 – Final change order approved and signed the project is in closeout. TTC reached out to Triton to get all closeout documents by 10/31.

JC – Fire Pump Replacement (085-24) Read More »

JC – Server Room Access Control Upgrades 2023

PM: Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS.  Design Kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to discuss project objectives and kick off project on 01/30.  Options and existing conditions were discussed.  Card reader to be connected to the VAX system in the building managed by Risk Management.  Door across the hall from Lincoln Base to be added to access control system as an alternate.
02/28/24 – TEI developing plans for this project.   Based on kick off meeting for Council Rooms – the VAX controller may be upsized to accommodate additional doors that are desired to be on VAX system.
03/27/24 – TEI Proceeding with documents.   Upon VAX confirmation, will complete documents.
04/24/24 – Documents in progress.   Review set to be sent to HCFD upon completion.
05/29/24 – no updates.
06/26/24 – Documents near complete.  TEI will send HCFD review set in next couple of weeks.
07/24/24 – TEI to deliver review set by end of week of 8/5/24.
08/28/24 – TEI sends documents to HCFD for review. Will issue bid package once review comments received and included in documents.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Documents sent to DK for GSA Pricing.
02/26/25 – DK sends GSA pricing for project to HCFD and TEI. Project pending contract.
03/26/25 – Pending contract approval.
04/23/25 – Pending contract approval.
05/28/25 – Project in contract phase.
06/25/25 – DK, DEG and HCFD have construction KO meeting. Construction to commence approx 06/27.
07/30/25 – DEG reaches out to DK for installation update.
08/27/25 – All equipment installation nearly complete.
09/24/25 – Base bid work complete. Pending CO work (added door).
12/10/25 – Change order issued for additional work. Pending procurement and installation of additional devices.
01/28/26 – Project pending the completion of the CO work.
02/25/26 – No update
03/25/26 – no update.
06/23/26 – Project closeout and final pay apps requested from DK.
07/29/26 – DEG follows up with DK for Closeouts.
08/26/26 – no updates
09/23/26 – Grant extended. Additional security measures drawing by DEG and priced by DK.
10/28/26 – Installation of additional items in progress.

JC – Server Room Access Control Upgrades 2023 Read More »

JC – LC Server Rack Upgrades 2023

PM = Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS.  Project kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet on 01/30 to discuss project objectives and kick off the project.  Network switches for the Kiosks and Camera systems shall be put in a lockable rack that will prevent local CO’s from tampering with them.   The outlets that serve the overhead rack and the floor mounted Telecor Intercom racks will have lockable covers over them such that they can not be unplugged.
02/28/24 – Project is ongoing.
03/27/24 – Project is ongoing with documentation.
04/24/24 – Review set to be sent to HCFD upon completion.
05/29/24 – no updates
06/26/24  –  TEI selects lockable racks.  TEI recommends racks with solid doors (versus glass doors), but the glass doors are slightly less costly.  ($100-$150 per rack).
07/24/24 – TEI to deliver review set to HCFD end of week of 08/05.
08/28/24 – TEI submits documents to HCFD for review and comments. Project will be issued for bidding upon receipt of comments.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Small projects bid to be issued on 01/31/25
02/26/25 – Project in bidding phase.
03/26/25 – Received (2) bids. Dunn Electric and DK. Dunn apparent low bidder. TEI vets Dunn bid.
04/23/25 – Project in contract phase with prosecutors office.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase.
07/30/25 – Const KO to be scheduled with Dunn and HCFD.
08/27/25 – HCFD, HCSO and DEG have const kick off with Dunn Electric. Materials roughly a month out.
09/24/25 – DEG approves submittals. Dunn Electric orders equipment. Dunn sends an email to DEG re equipment cost increase from bid time.
12/10/25 – All LC racks are installed, except G22. Ceiling by rack needs to be raised for the proper NEC clearances for the existing solenoid panels.
01/28/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
02/25/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
03/25/26 – Triton on site moving ceiling 03/25. Dunn to install new enclosed rack upon completion of ceiling work.
04/29/26 – All work completed. Punchlist completed. Contractor to submit closeouts.
07/29/26 – Project in closeout. DEG discusses with EC closeout docs needed.
08/26/26 – no updates.
09/23/26 – Project complete – pending closeouts.

JC – LC Server Rack Upgrades 2023 Read More »

CH – Law Library Text Room Renovation

PM – Jesse Estes, Sam Hofmann, Terry Cannon
12/07/23 – Signed SOSS received. Kickoff meeting requested.
01/22/24 – Load calculations are complete, fieldwork is started and mostly complete. Initial findings for AHU and HVAC needs sent to project team. In subsequent discussions it was decide to upgrade the unit for what we need in this space and do not try to “make” existing unit work if its undersized. TTE will design with that in mind.
01/31/24 – Review drawings to be ready in two weeks. TE to finish MEP review for that issuance.
02/29/24 – Final review meeting ready to be scheduled.
03/28/24 – Review meeting to be scheduled for first week of April.
04/25/24 – Review meeting held. Notes from Library received and changes have been made. They need to approve budget.
06/27/24 – Budget is still being worked out. Mothers room to be listed as an alternate. CDs in progress. Pull Mother’s Room out as an alternate. Laura got more money but not all of it. RR Alternate #1, Mother’s Room Alternate #2.
07/25/24 – No Update.
08/29/24 – Voting on new budget today and it should go forward soon.
09/26/24 – Budget was approved. Project to continue in October.
10/31/24 – Project goes out to bid today.
12/12/24 – Bid opens today.
01/30/25 – Alpha was awarded the bid. Contract still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 4/2. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Pre-mobilization meeting held. Alpha to provide schedule.
06/26/25 – Demo in progress. Freight elevator is down and has stopped work. RTU submittals were returned and we are working on an electrical requirements on the submittal with the vendors now. We have had several meetings trying to lock this down. Lead times range from 6 to 10 weeks.
07/31/25 – Demo is complete. Abatement of flooring to begin this week. Alpha to submit PCO related to plaster repair. AHU submittals have been received and approved with a new manufacturer. It took a long time to get there and there may be a credit to the project when all is said and done (Carrier/CaptivAire to York).
08/28/25 – Abatement will begin 9/2. Work paused during abatement delay. County is requesting more funds for plaster repair CO. Alpha was released to work up to cost of deduct from flooring removal.
09/25/25 – Framing has begun. Bathrooms to be turned over by end of October.
10/30/25 – Bathrooms to be turned over before 11/4. Asbestos concern to be investigated by the county. Work continues.
12/11/25 – Abatement of above ceiling pipe is complete. Alpha to remobilize and continue work.
01/28/26 – Bathroom back punch complete. Several items outstanding. Mid february completion.
02/26/26 – Library punch complete. Punch work outstanding.
03/26/26 – Back punch complete and work verified. Waiting on closeouts.
04/30/26 – Minor additional backpunch items sent to Alpha. Waiting on closeouts.
05/28/26 – No update.
06/25/26 – Closeouts outstanding. Shelf collapsed and new pins are being installed.
07/30/26 – No Update.
08/28/26 – Trades to fix all shelves. Alpha to come fix damaged shelves and adjust doors.
09/24/26 – Alpha to fix damaged shelves and conceal fasteners. Dehumidifier running to remedy door issues.
10/29/26 – Alpha to fix shelves and plaster in conference room.

CH – Law Library Text Room Renovation Read More »

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone)

PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/30/23 – Kickoff held on site. Sheriffs chose 7 doors for base bid and another 4 as an alternate. They will provide a few more doors to be added into the scope as alternates.
04/27/23 – Still waiting on additional doors from sheriffs.
05/25/23 – No update.
06/29/23 – List of doors and alternates has been provided. Drawings can be complete by end of month.
07/27/23 – Drawings will be complete by end of August.
08/31/23 – Drawings will be complete by end of September.
09/28/23 – Meeting held with Captain Wilson to confirm scope. Project will be out to bid 10/10.
10/25/23 – Project is out to bid.
12/07/23 – Bids returned. Cornerstone is lowest bidder. Bid review meeting held 12/5. Project now in contract phase.
02/29/24 – Cornerstone to send submittals in near future.
03/28/24 – Still waiting on submittals from Cornerstone.
04/25/24 – No Update.
05/30/24 – Submittals received and returned.
06/27/24 – Cornerstone field verification completed this week. Doors to be ordered.
08/29/24 – No Update.
09/26/24 – Cornerstone placed order. Pre-con meeting to be scheduled in near future.
10/31/24 – No Update.
12/12/24 – Cornerstone has material in hand. Coordinating best time with sheriffs and ongoing lock project work.
01/30/25 – Work to be scheduled in line with lock project corrections.
02/27/25 – No update.
03/27/25 – No Update.
04/24/25 – First Pod began. All frames installed but doors did not fit. New doors shipped immediately to finish the first pod. The rest of the doors will ship end of May.
05/29/25 – Pod complete and back punched. Next pod to begin next week.
06/26/25 – Next phase punch scheduled for tomorrow. Final phase to begin in 3 weeks.
07/31/25 – Next set of frames and Phase 4 frames to be manufactured together. 12 week lead time for delivery.
08/28/25 – Frames to be delivered mid september.
09/25/25 – Frames will be delivered next week.
10/30/25 – Cornerstone to remobilize monday.
12/11/25 – Phase 2, 3 and 4 have effectively merged into one project. All material is on site. Scope has been scheduled per unit with phase 2 and 4.
01/28/26 – Work Complete. Closeouts outstanding.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – Closeouts reviewed and missing items requested.
08/28/26 – No update.
09/24/26 – No update.
10/29/26 – No update.

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone) Read More »

525 – EMA/JFS/513 Office Renovations

PM: Bert Watts, Mike Murphy, Paul Bellman, Terry Cannon

01/25/23 – SD and Cost complete.  Created new category and started tracking EMA renovation.  CD documents have been started.  THP and TTE starting overhead door early project.  BW sent information for design.
02/22/23 – User meetings complete. DD in progress from user meeting changes.
03/30/23 – Met with JFS last week. Need to get approval on design from users.
04/27/23 – Meeting on site with JFS scheduled for 5/5. Design development to proceed after that. Update old estimate with new cost for revised design. Cost is due in two weeks. Champlin to send revised plans. Include owner required items in the new cost including blue brick screen wall that is coming down, new sidewalk, plus other owner items.
05/11/23 – Champlin requested updated opinion of probable cost with updated scope of work.
05/17/23 – THP provided updated opinion of probable costs for structural scope of work.
05/17/23 – THP provided SOSS for DD through CA services based on new scope of structural work.
05/21/23 – ThermalTech DD cost updated in Archibus and shared with the team. Drawings are being updated this week.
05/25/23 – Drawings and estimate have been uploaded to Archibus. Landlord improvements have been marked with a (C).
06/12/23 – THP – Champlin returned executed Contract for DD-CA Services.
06/29/23 – No updates from THP.
06/29/23 – Final plans have been approved by users. follow up information to be provided to County this week. CDs in progress.
07/27/23 – 95% Review set submitted to County. Page turn with users to be scheduled.
08/09/23 – THP updated structural work and fees to the Archibus project estimate.
08/31/23 – Updated department breakdown plans and estimate. User page turn to be scheduled in near future.
09/27/23 – THP waiting to hear from Champlin about the page turn meeting with Hamilton County.
09/28/23 – Review meeting held with EMA. minor changes to plans made. JFS and 513 meetings to be scheduled.
10/25/23 – THP sending bid set to Champlin. Meetings held with all users. Final owner review sent to County for landlord approval.
11/22/23 – Building owner has approved the Phase 2 renovation plans. THP to send Bid Set to Champlin once bid date has been set.
12/06/23 – THP to send Bid Set to Champlin for 12/15/23 issuance.
12/07/23 – Received final approval from landlord and County. Bid issuance on 12/15.
01/04/24 – Project advertised to Bid.
01/18/24 – Pre-bid meeting on site.
01/25/24 – Addendum #1 issued.
01/29/24 – THP sent stamped permit set to Champlin.
02/07/24 – THP Addendum #2 issued. Unit prices and details for CMU tuckpointing and CMU replacement were included.
02/22/24 – THP – Bid Opening. 4 bids received (Alpha Construction, John P. Tumlin & Sons, Leo J. Brielmaier, and Triton Services). Champlin to evaluate bids.
03/28/24 – Contract phase ongoing.
04/19/24 – THP – Approved construction contract approved by the Board of County Commissioners and sent to project team.
04/23/24 – THP – County issued PO for the project to the team. Pre-construction meeting tentatively scheduled for 05/03/24 afternoon.
04/25/24 – Contracts finalized. Project kickoff tentatively scheduled for 5/3.
05/03/24 – Pre-construction meeting with full team at project site.
05/30/24 – Kickoff held. Submittals in progress.
06/27/24 – Pre-mobilization meeting scheduled for 7/12. RTU submittals have been rejected, TEI trying to get submittals on approved manufacturers.
07/12/24 – THP reviewed front entry slab drainage issue with Hamilton County.
07/12/24 – Pre-mobilization meeting with full team at project site.
07/25/24 – Construction to begin Monday.
08/28/24 – THP returned structural shop drawings to Champlin.
08/29/24 – Construction ongoing. More abatement to be completed next week. Demo almost complete.
09/26/24 – Construction ongoing. Main sewer line underslab is damaged beyond use. Tumlin to report on extent of damage. CO2 is being discussed and finalized. THP will return approved Masonry Lintel shop drawings to Champlin on 9/26. Water test is complete and Fire Protection calculation underway.
10/29/24 – THP responded to Champlin regarding Masonry repairs. Hamilton County to determine extent of repairs.
10/31/24 – Construction ongoing. Change order 2 and 3 approved for sanitary line work and fire protection changes.
12/06/24 – THP visited the site to coordinate supplemental steel with Thermal Tech and Tumlin to help with the response to RFI 23. THP issued a field report for review by Thermal Tech.
12/12/24 – Work ongoing. Forest Park has provided report stating that any combustible material will need to be removed. We believe the wood studs would be grandfathered in compliance. Champlin to investigate.
01/27/25 – Work progressing, Tumlin stated they would be complete at the end of February. ThermalTech (TTC) trying to schedule a coordination meeting between Emcor, Bison, and KW about final controls scope between project and state term work. Rooftop units not onsite yet but should be arriving soon. Plumbing rough-in mostly complete. Forest part has approved our fire protection permit and Preferred Fire should mobilize soon to the site for sprinkler work. According to Tumlin, we will not have to move all the trucks parked in the warehouse for the sprinkler work (all sprinklers in the Northeast Warehouse must be replaced with 11.2 sprinkler head).
02/26/25 – Work continues in space. GC, MC, EC, FPC are all on site performing work daily. PC coming back soon when the fixtures will be installed. TTE bringing Wi-Fi plan to Friday meeting. Several COR have come in this week, HC asked for the Fire Pit cost too, the permit needs to be amended for the additional inspection. We will get a scheduled update this Friday.
03/11/25 – HVAC Engineering Change drawing sent to Tumlin for their submission to FP for the return air openings on the first floor.
03/23/25 – TTE returned another set of controls submittals to Emcor for the ALC controls. Bison has not confirmed if we can get BACnet thermostats or now. ALC planning on interfacing through the SystemVu controllers in the RTU units.
03/25/25 – Plumbing Engineering change drawing set to Tumlin to give to Carrigan to give to FP for the natural gas adjudication letter received last week. ThermalTech continues to answer questions from the contractors working towards permit approvals.
03/27/25 – Pricing for Bulletin#3 received. Substantial completion date set at May 9th.
04/24/25 – RTUs delivered a month ahead of schedule and have been installed. Fire pit work ongoing. Railings will not be delivered and installed before May 9. Signage quote approved.
05/19/25 – THP visited the site to review supplemental steel.
05/29/25 – Punch list sent last week. Railing scheduled for delivery this week. Tumlin to schedule final inspection. Signage to begin install tomorrow.
06/24/25 – ThermalTech onsite this week working on HVAC issues. We are scheduled to come back for troubleshooting with MC and CC Friday at 7am. Emcor video was sent out from Ben.
06/25/25 – Final inspection complete. CO will be signed when Rafic returns. Ribbon cutting tomorrow.
07/31/25 – Ribbon cutting ceremony held. Several punch items still outstanding. Tumlin to begin closeouts. As-Builts not received yet. Emcor controls out this week for finalizing the new DDC controls..
08/28/25 – Tumlin confirmed all work is complete. Back puch to be scheduled. Closeouts outstanding.
09/25/25 – Backpunch complete. As-builts received. closeouts outstanding.
10/30/25 – Closeouts outstanding. Official CO received.
12/11/25 – No update.
01/28/26 – Closeouts in review.
02/26/26 – Waiting on closeout corrections.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
08/28/26 – Tumlin provided update on missing items.
09/24/26 – No Update.
10/29/26 – Closeouts received

525 – EMA/JFS/513 Office Renovations Read More »

525 – Warehouse Doors and Ramp (F072)

PM: Rycca Thacker, Paul Bellman
12/07/22 – THP submitted SOSS to Hamilton County.
01/08/23 – THP spoke with City and have verbal confirmation a new curb cut is allowed.
01/10/23 – THP proposed initial layout to Hamilton County.
01/19/23 – THP and Thermal Tech met Hamilton County and EMA personnel onsite to review site layout and get field measurements.
02/10/23 – THP sent owner review documents to Hamilton County.
02/21/23 – Owner has approved the warehouse improvements. Hamilton County getting funding put in place.
02/24/23 – THP and Kleingers meeting with Hamilton County and EMA personnel to measure vehicles for final ramp layout and design.
03/16/23 – THP sent bid documents to Hamilton County Purchasing Department.
03/20/23 – Bid Documents released by Hamilton County Purchasing Department.
03/29/23 – Prebid meeting completed.
03/30/23 – Project opening scheduled for 4/13/23.
04/13/23 – Bid opening occurred with John P. Tumlin & Sons being the apparent low bidder and under budget.
04/21/23 – THP published a bid summary letter, recommending the County proceed with Tumlin.
05/21/23 – Permit drawings created and sent last week.
04/21/2023 – THP published a bid summary letter, recommending the County proceed with John P. Tumlin & Sons.
05/15/23 – HC sent contract to John P. Tumlin & Sons and requested their insurance certificates.
05/31/23 – HC waiting on Board of Commissioners for contract approval.
05/31/23 – John P. Tumlin & Sons working on schedule of values, schedule, site specific safety plan, material submittals, background checks, etc.
06/29/23 – THP receiving submittals from John P. Tumlin & Sons.
07/12/23 – HC notified THP that the construction contract will be presented to the Commissioners at their public meeting on 07/27/23.
07/27/23 – TTE returned the PTAC submittals again (second time) for changes.
07/28/23 – HC sent approved contract, PO, and Notice to Proceed to THP and Tumlin.
08/22/23 – Pre-Construction meeting set for Wednesday, August 30.
08/30/23 – Pre-construction meeting with THP, Hamilton County, Tumlin, ThermalTech Engineering, and Kleingers.
09/27/23 – Tumlin submitted construction schedule. Tentative date for mobilization set for October 2.
10/02/23 – Tumlin mobilized to site to begin construction.
10/25/23 – Interior overhead doors installed, masonry repaired at office, PTAC installed in office, interior slab on grade has been removed and replaced, interior man door has been installed, steel framing and masonry work at exterior door openings has started. Gas line has been relocated and additional gas line repairs have been approved via change order.
11/27/23 – Steel framing and masonry work for exterior openings has been completed. Both exterior overhead doors have been installed. Electric work and painting continuing inside. All mechanical/gas line repairs associated with this project have been completed. Exterior ramp (grading, forming, rebar/mesh, etc.) has been started. Concrete ramp pour scheduled for the week of 11/27/23.
12/06/23 – Electric work continuing inside. First two concrete ramp pours completed on 11/30/23 and 12/06/23.
01/02/24 – Last concrete pour for ramp completed.
01/24/24 – THP, ThermalTech, Hamilton County, and Forest Park met onsite to walk through and discuss required life safety items to get temporary certificate of occupancy for Phase 1. Team to address issues.
01/26/24 – Punchlist Walk Through with Bert Watts. Sent list to Tumlin.
01/30/24 – Additional Overhead Doors in back of warehouse started to get installed.
02/26/24 – THP, ThermalTech, and Champlin met onsite to review the vehicle layout. Champlin and ThermalTech to update Life Safety drawings and Electrical drawings, respectively, for in place vehicle layout with egress, emergency and exit lighting, etc to address issues that were discussed with Forest Park Building Department and Fire Department.
04/18/24 – THP received updated electrical drawings with emergency/exit lighting from ThermalTech. Request for change order pricing and updated drawings sent to Tumlin for installation.
04/24/24 – THP waiting to receive change order pricing from Tumlin. Installation of emergency/exit lighting required to close out phase 1 and building permit.
05/10/24 – Change Order for Emergency/Exit Lighting approved.
05/14/24 – Fully executed Change Order sent to all parties.
05/21/24 – Emergency/Exit Lighting submittal received. Waiting on review from ThermalTech to send approval. Installation to follow after submittal approval.
06/26/24 – ThermalTech reviewed Lighting submittal – Approved as Noted.
08/29/24 – Safety electrical items being installed.
09/26/24 – Pay Application #7 received for review.
10/11/24 – THP returned Pay Application #7 to Hamilton County.
10/31/24 – Closeout Process needs to be initiated.
12/11/24 – Closeout Process needs to be initiated.
01/23/25 – Closeout Process initiated with Tumlin.
02/26/25 – Closeout Process in progress by Tumlin.
03/26/25 – THP to follow-up with Tumlin on Closeout.
04/08/25 – THP sent Tumlin email on Closeout documents.
04/22/25 – Tumlin responded to email and indicated another request was sent out to subcontractors for closeout documents.
05/16/25 – Fire Alarm testing caused a short in the new fire alarm control panel. A fire watch was required for this weekend and was provided by a third party firm. TTE helped HamCo on first session until fire watch company arrived.
05/20/25 – Cin-Day installed the new FACP and replaced one address module, tested the existing system and found it to be working with no Trouble. We still need to work out warranty requirements.
05/19/25 – THP received close-out documents from Tumlin.
05/28/25 – THP started review of close-out documents.
06/25/25 – THP to return comments on close-out documents to Tumlin.
07/30/25 – THP reviewed close-out documents and sent Tumlin final comments/documents.
08/27/25 – Tumlin is sending final closeout documents to Hamilton County.
02/20/26 – Preconstruction Meeting held for Generator Plug-In Relocation.
02/23/26 – THP issued Preconstruction Meeting Minutes.
03/11/26 – On-site meeting held to review logistics of panel relocation.
03/24/26 – THP verified panel had been removed from the existing Blue Ash location. Status of permit drawings, IBI Inspection, closeout?
04/28/26 – Tumlin is working on final PW info for HC for Closeout Documents.
05/27/26 – County said do not archive until we get all closeout documents.
06/25/26 – Tumlin submitted requested Closeout Documents.
07/30/26 – Need IBI Inspection report for Closeout Documentation for Plug-in Electrical relocation. Davies to submit.
08/20/26 – THP sent project Meeting Minutes to HC.
08/27/26 – Rycca believes they have paid out this project.

525 – Warehouse Doors and Ramp (F072) Read More »

800 – Arc Flash Mitigation 2023

PM: Matt, Mike Barth

01/25/23 – TEI Submits SOSS.  Project pending SOSS approval and PO.
02/23/23 – Project pending SOSS approval and PO.
03/29/23 – TEI receives signed SOSS and PO.  Project kickoff to be scheduled with TEI and HCFD.
04/27/23 – TEI performs preliminary review of existing model.  TEI and HCFD to meet to discuss next steps.
05/23/23 – TEI to set up meeting with HCFD to discuss next steps.  Proposed time of 9:00 AM, on 6/8.
06/08/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
07/26/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
08/24/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC
09/26/23 – TEI develops drawings and submits to HCFD for review.
10/26/23 – TEI issues project for bids.  Prebid meeting occurred on 10/25/23.  Bids are scheduled to open on 11/22.
12/06/23 – Bids received and opened on schedule.  Stem Electrical is apparent low bid.  TEI vets bid and submits letter of recommendation.  Contracts are at prosecutors office for approval.
01/30/24 – Project awaiting BOCC approval
02/28/24 – Stem Electric receives signed contract and PO.  Preconstruction meeting to be scheduled in the next couple of weeks.
03/27/24 – Pre-construction meeting scheduled for 04/15/24
04/24/24 – Pre construction meeting occurred.  submittals receieved , and approved.  Project pending procurement of materials (approx 12 month ship date).  Stem electric to confirm shipping schedule.
05/29/24 – Project pending material procurement.  TEI requests Stem Electric to send in Ship date.
06/26/24 – No Updates. Project pending material procurement.
07/24/24 – No Updates.
08/28/24 – No Updates, project pending procurement of materials.
09/25/24 – Project pending material procurement.
12/11/24 – Project installation pending material delivery.
02/26/25 – Project installation pending material delivery.
04/23/25 – Project installation pending material delivery.
05/28/25 – No updates.
05/25/25 – No updates.
07/30/25 – Stem electric and DEG and HCFD meet to KO project. Gear has arrived and DEG certifies at Crane yard.
08/27/25 – Stem to begin the construction phase of this in first week or two of September.
09/24/25 – Gear is rigged into place. Outage/tie in to be coordinated.
10/30/25 – MCB to call Stem to schedule a shutdown meeting.
12/10/25 – DEG to follow up with Stem again to schedule the shutdown.
01/28/26 – Stem ready for the outage. John Nester requested pricing on refurbish breaker in the main gear. Stem is sending email of availability to DEG for meeting to discuss/schedule outages.
02/25/26 – Stem to send in proposed schedule and timelines.
02/25/26 – Stem sends in multiple proposed dates in May for tie in schedule. DEG, HCFD, Tech Svrcs, and Juv Courts to meet to discuss outage plans and select date.
04/29/26 – DEG and HCFD meet with all building tenants and discusses power outage plans. Tentative dates for outages are 5/30 for the 2nd floor and 6/19 for the sub-basement gear.
05/27/26 – 5/30 outage cancelled due to the contractor not having BGC staff. 6/19 outage still on the schedule.
06/23/26 – Second floor switch tied in on 06/19. TJW Electric provided staff that had current BGC and badge to perform the work. Basement level work to be scheduled.
07/29/26 – DEG has a virtual meeting with HCFD and Stem Electric. A list of possible Saturdays was emailed to HCFD and Stem to coordinate the next outage. HCFD to confirm the procurement of bad breaker for the distribution panel serving the computer room to be replaced by trades during the outage.
08/26/26 – HCFD states that the replacement breaker has been purchased by trades. Stem has confirmed 09/26/26 date with ESI, still pending confirmation from TJW. DEG states lets work towards making outage #2 happen on 09/26/26 so not to delay other projects. Stem to confirm with TJW and finalize the date.
09/23/26 – 9/26 date was postponed due to staffing issues with Stem Electric. New Date is 11/11/26 – starting at 07:00 AM. Pre-outage conference call scheduled for 10/28/2026.
10/28/26 – Outage is scheduled for 11/11/26. Meeting held with courts, HCSO and HCFD to discuss outage on 10/28/26.

800 – Arc Flash Mitigation 2023 Read More »

JC – 2022 Cell Door Replacement (Ph 2 Triton)

PM: Matt Butz, Sam Hofmann
01/21/22 – Signed SOSS Received.
03/23/22 – Meeting with Sheriffs to define scope. Number of doors defined. Hold pending door lock replacement project scope.
06/30/22 – Scope to be defined at project kickoff meeting for current set of doors.
07/28/22 – Scope to be defined at project kickoff meeting for current set of doors.
08/23/22 – Scope finalized. Plans to be sent and confirmed with sheriffs.
09/29/22 – Project out to Bid
10/27/22 – Triton won bid.
12/15/22 – Contracts signed and returned.
01/26/23 – No update.
02/25/23 – No update.
03/30/23 – Triton has subbed Jails Products again. Submittals to arrive shortly.
04/27/23 – No Update.
05/25/23 – No Update.
06/29/23 – No Update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – Kick off to be scheduled close to delivery.
03/28/24 – Triton asked question. Site visit to confirm to be scheduled for next week.
04/25/24 – Waiting on sheriffs to answer keying questions.
05/30/24 – Questions sent to Triton. Triton has not responded.
06/27/24 – New project manager assigned to project. Doors to ordered in near future.
02/27/25 – Doors are ordered and scheduled for delivery the last week of April.
03/27/25 – No update.
04/24/25 – Mobilization scheduled for early May.
05/29/25 – Delivery was delayed. mobilization scheduled for mid June.
06/26/25 – Mobilization scheduled for Monday.
07/31/25 – Frames came in with incorrect dimensions. They will all be modified by Triton and remobilized in a couple weeks.
08/28/25 – Modified frames were manufactured for thicker wall dimension. Triton to provide correct frames as soon as possible.
09/25/25 – Corrected frames will arrive with Cornerstones delivery.
10/30/25 – Frames to be delivered monday. Triton to mobilize and complete their scope.
12/11/25 – Triton discovered that the doors were the wrong thickness. Cornerstone doors can be used to cover all but one of their doors. The one door has been ordered and will be delivered shortly.
01/28/26 – Door delivery date has been pushed back. Work has been paused.
02/26/26 – Door still not delivered. Door suppossedly will be delivered tomorrow. two more doors in this project once the door delivered is completed.
03/26/26 – Final phase to begin next week.
04/30/26 – Frames came in the wrong size. Frames to be delivered next week. Project to be complete end of May.
05/28/26 – Cornerstone to complete final pod for Triton. 6/24 install date.
06/25/26 – Demo revealed damage to block walls. Change order accepted. Cornerstone to complete work. Mobilized this week.
07/30/26 – Work is complete. Closeouts ongoing.
08/28/26 – No Update.
09/24/26 – Change order to order new millenium pac units submitted. No update on closeouts.

JC – 2022 Cell Door Replacement (Ph 2 Triton) Read More »

CH – HVAC Control System Replacement (081-22)

PM: Matt Butz, Terry Cannon, Will Fisher
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com


02/19/22 – ThermalTech submitted SOSS for the project.
03/04/22 – Met with Emcor on Ameresco pricing and scope exercise.
03/09/22 – Met with SBS on new technology and ALC interfacing capabilities
03/10/22 – TEI has created all the background drawings and base specifications for the project in the new CSI format.
03/11/22 – SOSS received and work begins. TTC setting up kickoff meeting on this project.
03/15/22 – Met with Honeywell onsite today and reviewed scope of Chiller controls and scope of this project in more detail. Two new corporate guys met us onsite and review past history and what they plan going forward.
03/22/22 – TTE met and review the action item list for bidding this out in 2022. We need to get background checks complete, BDS coming down tomorrow for BGC, Fisher has his badge, Constable BGC is complete and needs his badge. We’ve agreed to meet with Honeywell and JCI as the additional manufacturer’s for this project. We also want some time to sit with the con
03/23/22 – Started specs in new CSI format. Set up meeting with Honeywell for April 8 and JCI for April 11. We are trying to meet with Barth to review acceptable communication paths in the CH. We will schedule fieldwork soon.
03/31/22 – Meeting updated with JCI for 4/7. The badge process is started for 3 guys.
04/15/22 – Final controls meeting with vendors held this day. All said they can bid this job and meet the requirements.
04/28/22 – Project design schedules distributed. Fieldwork and design in April, May, June, July. Bidding in August, September. Award and contracts are October, November. Fieldwork started last Tuesday with Bracken and Matt. Basement, sub-basement, and roof equipment was verified.
05/25/22 – ThermalTech has been on the building finalizing equipment locations and needs for the last month. Our review drawings for all the equipment including VAV boxes will be out the County on June 3. We are also developing airflow diagrams for the control sequences based on our findings and Honeywell existing information. We are on schedule to bid in August.
06/30/22 – This month we finished up equipment takeoffs and sent them back to the County for review. Comments came back in a day and we have scheduled another field trip to check out additional equipment. JN asked for us to check our equipment against the archibus database, however, I cannot see the equipment database in archibus yet. Ask HC for help at meeting.
07/27/22 – A full equipment set of drawings was submitted to the County for review. TEI scheduling another field trip for final equipment information next week. We want to be on site with Randy so we can finalize sequences on standalone equipment and missing equipment in the sequences.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 & 2 issued. Bid was extended to Nov 15. At least one more addendum before bid opening.
12/15/22 – Bids were opened on schedule and the apparent low bidder is Debra Kuempel. A full pre award meeting was held and the recommendation sent to the County for Base Bid and several Alternates for this job that were still under the published estimate. Project is moving forward, Emcor called for an update yesterday.
12/20/22 – County sent the contract to Emcor for signature.
01/24/23 – Contract was sent, not sure if the PO is back yet. Ready for kickoff.
01/30/23 – John checked back with Steve on contract status.
02/23/23 – Project is in front of the board for approval. DK putting together their project team and was instructed to run all communications through the County PM.
03/29/23 – All contracts are in place and we are ready to have pre-const kickoff meeting. TTC to schedule and reach out to ZH commissioning for their background checks.
04/25/23 – The Pre-Const meeting was help and Emcor was introduced to the project team. After the meeting, we walked one AHU and DK spent time on site surveying the existing building and equipment. We are in submittal and background check phases.
05/21/23 – It Meeting was help this month. DK putting together proposed network locations for our review. The County is working on ordering 7 network switches for the new Control VLAN inside the Courthouse.
06/28/23 – DK continues to work on background checks. Initial network switch location rejected, looking for new locations. TTC & MCB to suggest locations, then will give to DK to review, we may need additional network switches.
07/26/23 – Emcor still working on getting staff background checked for this job. Net network locations reviewed and sent to County for their review. We may potentially meet and go over them at Partner Meeting on Thursday. TTC invited IT and Telecom.
08/16/23 – Met with DK and have new prices for the fiber backbone change order. Steve Yockey sent them to TTC who will review and send to County.
09/27/23 – We are very close to finalizing the change order for the fiber infrastructure for this job. TTE will create a final room location drawing for DK after we receive comments from Jack, Steve and the County. Any issues with what is on the our change order markups for VE options? Controls Submittals have arrived for TTE review.
10/25/23 – Background and LEAD checks underway. DK working with JN. Network location finalized with County and Debra and Change Order #1 for network infrastructure sent to DK for signatures, we are accepting the Value Engineering proposal for this work. Controls submittals returned to DK Revise and Resubmit. We’ve incorporated ZH commissioning comments, WF, BDS and TTC comments into specifications. DK and TTE have coordination meeting on Thursday to review in details to ensure resubmittal is correct.
11/03/23 – Bi-Weekly Construction meetings begin. Emcor working on schedule. TE working on submittal review. Team working on network infrastructure. Jack can’t make Friday meetings until 2024.
11/17/24 – Const Meeting. Working on Background Checks and LEAD checks. Emcor low voltage working on cable runs.
12/01/23 – Const Meeting. Start working on deficiency report format, LEADS checks, low voltage routes.
12/15/23 – Const Meeting. Continue with Submittals work, background check and low voltage routes.
12/20/23 – Submittals returned for equipment and sequences. We still have a couple of outstanding items.
01/05/24 – Const Meeting. Work continues and is making progress.
01/19/24 – Const Meeting #6. Emcor and DK working on after hours progress, TE working on missing piece of equipment and getting ZH in Leads checks program.
01/26/24 – Deficiency List and Honeywell Scope meeting in Room 608.
02/23/24 – Const Mtgs continue. DK running new fiber continues. Deficiency list is begin worked and updated. Honeywell contacted for their portions. Emcor pricing up actuator replacements from deficiency report. Submittals are being updated, penthouse controls are being updated.
03/22/24 – Biweekly meetings continue. This month Honeywell got the chiller plant online, the secondary chilled water pumps VFD’s are online and working, Bacnet has been added to three of the four chillers. DK submitted change orders for four pneumatic upgrades to four units. TTE reached out to Honeywell for pricing on these same four units plus their deficiency list items. Emcor has many of the fibers ran to the server room, they need to repair the walls where they brought items into the room and finishing punching down the cabling. The DDC server is installed in the Rack.
04/24/24 – Next Const Mtg tomorrow is this Friday. Will is out this week and Bracken will cover the meeting. Emcor is being pushed to provide a best guess schedule. AH-52 has been submitted. TTE is reviewing sequences for the new equipment, we will have a design meeting with Emcor to go over sequences and make sure they can do what we have asked for in the Project Manual.
04/25/24 – Biweekly meetings continue. The fiber and CAT6 installation is scheduled to be finished by April 30th. The new network and front end are scheduled to be online during May and equipment changeover to the new controls system shall begin immediately afterwards. Emcor will begin with changing smaller equipment in the basement that is less disruptive to everyday operations. Emcor is beginning to work on replacing the approved pneumatic valve actuators that were deficient.
05/28/24 – Biweekly meetings continue. Low voltage wiring will be completed in the next 2 weeks, only the fourth floor remains incomplete. The new ALC controls database will be uploaded to the old server by Emcor this week. The database will then be transferred over to the new server once HAMCO brings the new server online. Emcor will be starting the first equipment change overs next week, once the database is uploaded. Emcor will begin with the smaller equipment in the basement that is less disruptive to everyday operations. CO#3 has been approved to add AHU-52 to the scope of the project, changing that unit to ALC controls. Emcor and ThermalTech have reviewed the controls sequences and are working to finalize the sequences.
06/24/24 – Biweekly meetings continue. Low voltage wiring on the fourth floor will be completed this week and the new network switch will be installed. Emcor has uploaded the new ALC controls database to the new server. Emcor has begun bringing materials to the site and are planning to begin work in the next 2 weeks to change over equipment in the basement. ThermalTech, Emcor, and ZH are working to finalize the controls sequences based on the latest comments provided by ThermalTech.
07/22/24 – Biweekly meetings continue. Emcor has begun to change over equipment in the basement to ALC controls. Emcors graphics department has begun work on the graphics for the front end. CO-01 is nearing completion, ThermalTech will be creating a punchlist to close out the work. Emcor and ZH Commissioning are coordinating to commission the equipment that’s been changed over. ThermalTech is coordinating a controls sequence meeting with ZH and Emcor. ThermalTech is also coordinating a deficiency list review meeting to close/address any open deficiency list items.
07/24/24 – Met with Dale and Ben today on sequences, they should be finalized before end of next week. Met with ZH commissioning today and ALC not ready with graphics for them to star CX, so we are pushing them back a week.
08/26/24 – Biweekly meetings continue. Emcor continues to change over equipment in the sub-basement and basement to ALC controls. Emcor has changed over the south central VAV’s on the first floor, further work on the first and second floor will begin in the next 2 weeks. Emcor continues to develop the graphics, expecting to complete them by the end of August. A preliminary BAS training took place this month to get Tyler Laws and his team familiar with the new system; another training will be scheduled once the graphics are complete. Commissioning by ZH Commissioning will take place once the graphics are completed. Controls sequences have been finalized by ThermalTech and Emcor, the sequence submittal is expected to be submitted by Emcor within August. Work for CO-01 is almost complete, Emcor will provide a punchlist and ThermalTech will verify it. The deficiency list is nearing completion, with a few items being addressed by HAMCO and a few items still to be investigated by Emcor.
09/23/24 – Biweekly meetings continue. Emcor continues to change over equipment in the basement and first floor to ALC controls and has begun work on the second floor. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session will take place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning has begun starting with the basement equipment. The fiber and CAT6 installation is nearly complete; Emcor has turned over a punchlist that ThermalTech has started to review. The deficiency list is nearing completion with a few items being addressed by HamCo and some items requiring Honeywell assistance.
10/28/24 – Biweekly meetings continue. Emcor continues to change over equipment on the second and third floors to ALC controls. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session has taken place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning is ongoing and currently focused on the basement equipment. The fiber and CAT6 installation are complete. Once the record network submittal drawings are received, ThermalTech and HAMCO will review and walk down the punch list items. The deficiency list is nearing completion with the last few items being addressed by HAMCO once the steam system is turned on for the winter.
10/29/24 – ThermalTech scheduling change order review meeting with HamCo. We need to work out some scope issues on the drawings vs reality of what is in the space.
12/12/24 – Emcor is mostly complete with the basement and moving up through the building to floors 1 thru 4 as well. They are onsite every day and working towards the April deadline. ZH commissioning has started creating an CX list that Emcor will have to help correct the CX issues as we move forward and complete the work. VPN seems to be working.
12/23/24 – Biweekly meetings continue. Emcor has completed all changeovers on the second floor and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement, basement, and first floor. Emcor has a few small items to update in the BAS per HAMCO preference. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. The fiber and CAT6 installation are complete. Record network drawings have been received from Emcor. ThermalTech and HAMCO will review and walk down any network related punch list items. The deficiency list will be checked again in January, no deficiencies have been checked on in December. Change order #2 work for AHU-21, AHU-22, OAHU-1, and AHU-B2 has begun. All of the AHU’s mentioned previously have new valves installed per CO#2, only the damper work remains to be completed.
01/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls; these floors should be completed in January. Emcor will begin the sixth floor in early February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. Most equipment in the basement that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The few remaining items on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for AHU-21, AHU-22, OAHU-1, and AHU-B2 should be completed in January, closing out CO#2 work. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
02/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, and fourth floor. Emcor continues to change over equipment on the fifth and sixth floors to ALC controls. The fifth floor should be completed in February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover will begin in February. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The one remaining item on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going and should be completed in February, closing out CO#2 work. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
03/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to change over equipment on the sixth floor as well as wrapping up the equipment in the basement and beginning on the chilled water system and large AHU’s. AHU-82 is the first large AHU that has been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover is on-going. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 85) have been changed over. March will focus on the large systems in the courthouse, the chilled water system and the remaining large AHU’s.
04/23/25 – Work is progressing with about about 84% of the project complete. Emcor has asked for a two month extension for completion. ZH is following behind Emcor and catching up on commissioning. The County has some decent request for front end modifications that Emcor needs to work through. The large AHU’s are being converted now. The Chilled Water plant is current under integration and Emcor has been asked to provide a boiler plant integration cost outside of the scope of this project (see TTC & AKM).
04/28/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the sixth floor, seventh floor, and the chilled water system. All large AHU’s (AHU-68, 75, 82,85) have been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement (Pending deficiency item repairs). Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning will be next. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. A schedule extension change order is in progress. May will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the few remaining items and the chilled water system. The following are the remaining items to be changed to ALC controls for the project: Chilled water system, AHU-B, AHU-B16, EF-71, and misc. (4) condensing units. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Change order #4 is closed. Change order #5 has been signed, extending the schedule to June 13 and adding in the changeover of FCU-8 and AHU-B to full ALC controls. June will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/28/25 – Emcor did not submit a payapp for January. Payapps 12, 13 and 14 are wrong. We are working on corrections. We received corrected copies of 13 & 14 today but 12 is still wrong.
06/23/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for the chilled water system and (4) misc. condensing units, which are on-going. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HamCo and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Emcor is back checking all of their work, currently expecting to be done and ready for ThermalTech to punchlist on August 1. Basement, first, and second floors are largely complete and functioning correctly. HamCo is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. July will focus on checking all equipment and resolving any commissioning deficiencies identified by ZH Commissioning to prepare for August 1 punchlist.
07/25/25 – Const Mtg held with HamCo, TTE, and Emcor. ZH not present.
07/28/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for (4) misc. condensing units in the basement, which are on-going. The chilled water plant is now changed over and running in automatic mode. Emcor is focusing the majority of their time back-checking the commissioning items found by ZH and resolving any issues with the large AHU’s (85R has some pressure sensor issues being worked on). All change order work is completed. CO#6 is being drafted to give credit to HAMCO for systems that have been removed from scope and to extend the schedule. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is completed. State contract work is on-going for misc. repairs. Commissioning by ZH is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network (CO#1) related punch list items. Emcor is back checking all of their work, revised date for ThermalTech to begin punchlist is now August 15. Basement, first, and second floors are largely complete and functioning correctly. HAMCO is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. County wants to make sure that DK is doing the t-stat touch up plates. Make sure the County knows when.
08/25/25 – The project has entered the punchlist phase. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing the majority of their time backchecking the commissioning items found by ZH and resolving any issues with the large AHU’s. All change order work is completed. CO#6 is being drafted to give credit to HamCo for systems that have been removed from scope and to extend the schedule. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HC and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Punchlist walk with ThermalTech and HC is scheduled for early September.
08/26/25 – We are having a hard time narrowing down the graphics for the generators in the Courthouse. EGEN is the emergency generator in the basement. GEN-1 is the standby generator on the platform.
09/22/25 – The project is in the punchlist phase. Punchlist was developed during a one-day site walk with HAMCO and ThermalTech. Draft punchlist was supplied to Emcor, punchlist will be submitted to Emcor as final once ZH’s commissioning is completed. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing on completing items on the punchlist or checking the commissioning items found by ZH and resolving any issues. All change order work is completed. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is nearing completion. All equipment (except for heating equipment) has been commissioned. ZH has commissioned the chilled water plant. ZH is coordinating with HamCo and Emcor to resolve any issues found. The Punchlist has been issued, and we are ready to enter the closeout documents phase.
10/29/25 – The second training session was held earlier this month with the operators. I think it started our rough but was better received by the end of Training. More use will make the end user more comfortable with the new product. The Project punchlist still being completed. ZH Commissioning has a few days left to complete their work on the deficiency list for this project. We found that the free cooling HTX was not on the graphics yet, DK fixed yesterday and the heating plant is not working correctly yet, DK to assist Tyler in making this right.
12/12/25 – Functional testing deficiencies list meeting held today to review progress from Dec 3-5. Some items complete, many are not. DK needs to devote resources and technician to site to complete the CX work. DEG will have to setup owner internal review meeting later this week to review our outstanding resolution items. TTC pushing for 02/28/26 drop dead date for all the outstanding work, requested basic progress scheduled for DK too address final items.
12/22/25 – Punchlist completion is on-going. Site visits in December discovered that there are numerous open items on the resolution tracking form to be resolved. Resolution tracking form items are planned to be resolved by the end of February. HAMCO has given a PO to Emcor to replace HX-1 and HX-3 steam valves to DDC on state contract terms. Weekly meetings have been scheduled to check on the progress of the resolution tracking form items.
12/23/25 – HTX-4 Meeting scheduled for Jan 7 with County, DK and Davies.
01/25/26 – Emcor and DK making good progress, we are hopeful that this project will complete by the end of February. Ethan making good progress knocking out all final items and coordinating with HamCo and ZH Commissioning. VPN access requested for Will Fisher, Anthony said they will send him application. Smell and temperature on sixth floor better but not gone all the way that I know of. Weekly meeting continue with DEG, Emcor, DK and Facilities.
02/25/26 – Weekly Const meetings continue. Emcor has completed the TE punchlist and ZH resolution tracker except for the chiller plant which they are working on this and next week. The HTX will be taken apart and tested in March or April. TTC reached out to Emcor for a full PW download directory as requested.
03/25/26 – Emcor working on Chiller and Cooling tower plant controls. Emcor commissioning ready to start as soon as chillers are started. DEG and ZH met on commissioning deficiencies. DEG issued Punchlist #2, ZH working on revised resolution tracker worksheet. We are scheduled to inspect the HTX next month.
04/20/26 – Emcor, DEG and ZH reported for final commissioning and worked through the final punchlist and functional testing markups this week.
04/28/26 – Checked in with Tyler and everything seems to be working well.
04/29/26 – Tyler reported this morning at the cooling tower overflowed with water this morning and the penthouse was flooded. Investigation showed that some equipment was commanded off and a second condenser water pump started causing the overflow condition. DEG asked Emcor for an additional logic step to prevent this from happening in the future. Emcor also asked that equipment be release to operated in automatic mode so this does not happen.
05/27/26 – All punchlist and resolution tracker work is reported as complete. DEG requested closeout documents from Emcor for project closeout.
06/25/26 – Project in closeout.
07/30/26 – Working on closeout documents. Emcor collecting OM’s and paperwork. We check back every Friday.
08/26/26 – Almost all closeout documents received including releases. We are working on full closeout.
09/23/26 – After months of work, coordination, and emailing Emcor, we have the final closeout documents and TTC will hand delivery to Ted and Mat ton 9/24. We have requested final payapp for processing.
10/26/26 – Project is in Closeout.

CH – HVAC Control System Replacement (081-22) Read More »

CH – Bronze Door Repair

PM: Matt

02/15/22 – Signed SOSS received.
03/31/22 – Field investigation completed. Preliminary drawings completed. We have been in contact with several historic door restoration companies.
04/28/22 – Drawings at 75% complete. Need to schedule a review meeting.
05/10/22 – Review meeting with Rycca. Determined more documentation per door is needed.
06/30/22 – Bid package to be finalized and submitted for final review.
07/28/22 – Additional site visit performed. detailed scope photographs added to drawing set.
08/24/22 – 95% check set sent to HC.
09/29/22 – Project out to Bid
10/27/22 – Olek won bid. West doors and Cleaning awarded. Contracts in progress.
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Call with Olek, County and Champlin to discuss details of kickoff meeting. kickoff meeting to be scheduled by end of February.
02/22/23 – Kickoff meeting to be scheduled in near future. Champlin has reached out to Olek twice for dates.
03/30/23 – Kickoff held on site. Preliminary schedule received. Olek to provide firm dates as we near demolition.
04/27/23 – Doors have been removed and sent to New Jersey for refurbishment.
05/25/23 – Doors have been taken apart and analyzed. Doors are in better shape than anticipated. Submittals to come soon.
06/29/23 – Photographs received. Work in progress.
07/27/23 – Restoration ongoing. restoration revealed that the door pulls were originally nickel plated. Change order to nickel plate the door pulls in progress.
08/31/23 – Olek to return to site 9/11. Test fit of closer complete.
09/28/23 – Olek cleaned existing bronze and prepped hardware installation. No crocs in sight.
10/25/23 – Construction ongoing. County requested pricing for additional bonze cleaning.
12/07/23 – Installation scheduled tentatively for march. Olek returned pricing for all items requested.
02/29/24 – Change orders approved. Several doors are complete. Still on schedule for late March Install.
03/28/24 – Doors to be installed first week of April. Site and prep work will continue into the following week.
04/25/24 – Doors to be installed in may. Firm dates to be determined.
05/30/24 – Olek is on site. Two doors are in. One Torchiere was blown over in a storm. Olek is shipping damaged parts to their shop.
06/27/24 – Work on site complete. Olek will need to come back for punchlist work. Matt ask Murphy to review final retainage payment submit.
08/29/24 – Olek needs to come back out to complete punchlist.
09/26/24 – No Update.
10/31/24 – Olek was back on site for the punch work. They did not complete the list and will need to come back.
12/12/24 – Olek came back for the back punch work but did not complete their work. They will be back for the punch and for a closer warranty issue.
01/30/24 – Olek still has punch work to complete. close outs to be submitted.
2/27/25 – Scott reached out to olek to request closeouts and a timeline for punch work. The closeouts are in progress. The punch work will be done in tandem with the first phase of the north and south doors.
03/27/25 – No Update.
04/24/25 – No Update.
05/29/25 – No Update.
06/26/25 – No Update.
10/30/25 – No Update.
12/11/25 – No Update.
01/28/26 – Olek to complete punch work when on site next.
02/26/26 – Olek onsite March 9th to finish punch work.
03/26/26 – Olek is onsite. Punch work is in progress.
04/30/26 – Work is complete. Closeouts nearly complete.
06/25/26 – No update.
07/30/26 – No update.
08/28/26 – No update.
09/24/26 – No update.

CH – Bronze Door Repair Read More »

JC – Cell Door Lock Replacement (Cornerstone)

PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received
01/26/22 – Plans and Schedule created. Will be discussed at JC Door Replacement Kickoff.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress.
06/30/22 – Documentation in progress.
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Bid opening is pushed to 3/3. Final addendum to be issued before 2/28.
03/30/23 – The bid has been cancelled. An invitation for manufacturers to demo their products has been put out for 4/5.
04/05/23 – Manufacturer presentations held. Willo, Airteq, and Habersham displayed their products to the county and sheriffs.
04/27/23 – Revised bid sent to the prosecutors office for review. Once approved, the project will be ready to rebid.
05/25/23 – Project has been rebid. Pre-bid meeting is 6/2.
06/29/23 – Bids received. Project is awardable.
07/27/23 – Lowest Bidder – Jails – bid is under review with prosecutor to determine if bid is awardable. Second lowest bidder – cornerstone – vetted.
08/31/23 – PO is approved and contract has been sent. Kickoff meeting to be held in the near future.
09/28/23 – Kickoff meeting held. Site visit to measure existing conditions scheduled for week of 10/9. 4 cell mock up to be scheduled at site visit.
10/25/23 – Site visit occurred. Mock up submittal returned. Mock up installation to be scheduled in near future.
12/07/23 – Mock ups to be installed 1/9.
02/29/24 – Mock ups ran into trouble connecting with the PLC. Cornerstone could not figure it out onsite. They sent locks to be tested by Stanley. Locks have not been successfully programmed yet.
03/28/24 – Stanley determined that the locks can be used with modification to the PLC system. Cost of the upgrade is around $500,000. Conversation of next steps ongoing.
04/25/24 – Working mock-ups installed. Schedule to be determined for Securitas to be on site for upgrading power.
05/30/24 – Work to begin 6/17. Work is expected to take 2-3 weeks per floor.
06/27/24 – Locks delivery was delayed. The locks had to be re-programed. Cornerstone to overnight one re-programed lock to ensure functionality. Prep work on George 51 is complete.
07/24/24 – Matt punchlisted project last Sunday. They met the State on Monday. One door hitting the wall, so we need to add a new bumper.
08/29/24 – Installation ongoing. Cornerstone getting to a unit per 2 weeks.
10/31/24 – Installation ongoing. No issues have been resolved by airteq regarding quality control. Meeting to discuss issues with Cornerstone and Airteq will take place next week.
12/12/24 – Installation ongoing. Power upgrade is complete. Rewiring lock power is in progress. New switches to be installed at end of January.
01/30/24 – Last unit work ongoing. Cornerstone and Airteq VPs to attend a meeting in February to work out warranty issues.
02/27/25 – Meeting held with VPs of Airteq and Cornerstone to finalize warranty discussion. 5 year warranty agreed upon. Medical unit to be complete this week. outstanding work will be repairing damaged locks.
03/27/25 – All contract work complete. Closeouts to be submitted and correction work to be done.
04/24/25 – Replacement housing and attic stock to be delivered in near future. Cornerstone will begin correcting outstanding punch items.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – No Update.
08/28/25 – No Update.
09/25/25 – Attic stock and corrected housings delivered and replacement process has began. Closeouts outstanding.
10/30/25 – Still have a couple of things left to do. We need a list of lock boxes left to do.
12/11/25 – List of outstanding punch items provided. Closeouts under review.
01/28/26 – Punch work complete. Attic stock is outstanding. Closeout corrections requested.
02/26/26 – Closeouts will be delivered next week. Attic stock needs to be replenished from warranty work orders.
03/26/26 – Still waiting on closeout docs. Attic stock is still not on site. Warranty period has not began.
05/28/26 – No update.
06/25/26 – No update.
08/28/26 – Phillip onsite to review rust damage. Champlin to provide report.
09/24/26 – Report submitted. No update on solution.
10/29/26 – Roller bolts have been discovered missing on several doors. Sheriffs to provide report.

JC – Cell Door Lock Replacement (Cornerstone) Read More »

2020 – Roof Replacement (F034) and Davit Upgrade (F027)

PM: Rycca Thacker, John Millar
07/29/21 – THP Submitted SOSS to County.
08/23/21 – SOSS approved.
02/2321 – THP completed roof cuts and assessments. THP scheduling masonry survey for repairs, anticipated week of 2/28.
03/07/22 – Week of March 7th, THP Surveyed interior for masonry distress and slab settlement.
03/24/22 – THP and County reviewed field findings from THP survey.
04/27/22 – THP developing DD documents.
06/30/22 – THP developing DD documents. Plan to bid mid August.
07/28/22 – THP proposed design schedule update DD issue 8/30/22 and CD issue 9/15/22
10/27/22 – THP to publish 90% drawings 10/28/22.
01/10/23 – County provide review comments.
01/26/23 – THP anticipates CD documents issued 2/3/23.
02/23/23 – Finalizing documents. Plan to issue bid documents week of 2/26.
03/24/23 – Bid documents anticipated the week of 4/3/23.
05/31/23 – Documents advertised for bid.
06/07/23 – Prebid mtg occurred.
06/16/23 – Addendum No. 1 issued.
06/27/23 – Bid opening occurred. Two submitted bids received with low bid 16% above advertised budget. THP to review with County next steps.
08/31/23 – June bids rejected. County requested roof and masonry project be separated and bid this fall. THP published review documents 8/31/23.
10/06/23 – Roof Repair project approved for KEE system. AIA documents issued to THP. Slab and Masonry Repair project approved. AIA documents issued to THP.
10/0923 – County comments to the review documents published to THP.
10/09/23 – Inclusion goals published.
10/12/23 – Review Bid Documents published for both the Roof and Slab Lifting Projects.
10/13/23 – Final Bid documents published for both the Roof ITB 116-23 and the Slab Lifting and Masonry Repairs ITB 117-23 projects.
10/16/23 – Roof and Slab projects advertised for bid.
10/25/23 – Prebid meeting occurred for both projects.
10/26/23 – Bid opening scheduled for November 30, 2023.
11/09/23 – Slab and Masonry Repairs Addendum No. 1 issued.
11/13/23 – Roof Repairs Addendum No. 1 issued.
11/14/23 – Slab and Masonry Repairs Addendum No. 2 issued.
11/17/23 – Roof Repairs Addendum No. 2 issued.
11/20/23 – Roof Repairs Addendum No. 3 issued.
11/30/23 – Slab and Masonry Repairs Bid opening. No submissions.
11/30/23 – Roof Repairs Bid opening. Five contractors submitted bids with a range of $1,761,452 to $2,103,895. One bid was below advertised bid amount and the remaining bidders were within 10%. Bids sent to the economic inclusion department for review.
12/23/23 – Kelly Brothers Roofing found responsive and THP notified to review the bid.
01/08/24 – THP and Kelly Brother’s reviewed the bids.
01/15/24 – THP published bid summary recommending Hamilton County contract with Kelly Brothers for the roof project.
02/06/24 – Hamilton County sent AIA contract to Kelly Brothers Roofing.
03/02/24 – Kelly Brothers returned contracts to Hamilton County.
03/25/24 – THP published conform and permit drawings to Kelly Brothers and Hamilton County. Drawings updated with 2024 code review and requirements.
03/27/24 – Project contract goes before the board on April 4th for final approval.
04/11/24 – Executed contract sent to KBR.
04/29/24 – Preconstruction meeting completed.
05/30/24 – Project update – THP processing submittals and shop drawings.
05/31/24 – Initial scaffolding installation for roof access to start.
04/29/24 – Preconstruction meeting occurred.
05/31/24 – Project mobilization occurred.
06/27/24 – Contractor working on Roof D, E, and F. Existing roofing removed, repairs started and installation of the complete system started on roof D south end. Roof work on hold until July 1.
07/25/24 – KBR working on Roof D installing system south to north. Temporary scaffolding stair tower at roof F extended to roof D. Temporary stair tower and bridge installed to Roof C.
08/16/24 – THP published Bulletin No. 1.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
09/12/24 – THP published walk mat layout review drawing.
09/16/25 – THP sent SOSS for additional services for Roof Safety Design.
09/19/24 – KBR completed main installation on roof D and E and working on detailing on both. Preparation for Roof F has started.
09/19/24 – THP published roof safety review drawings.
09/24/24 – THP published roof safety review drawings, Rev. 1.
09/25/24 – Hamilton County, CMI and THP had a MS Teams meeting to review the roof safety drawings and proposed approaches.
09/26/24 – KBR completed main installation of Roof F.
10/25/24 – THP released initial safety package for pricing by KBR. THP working on platform design to finalize complete package.
10/31/24 – KBR completed Roof D,E, &F including initial punch work. Roof A,B, & C and punch trip review complete. All lightning protection work scheduled to start early November.
10/30/24- KBR completed the work on lower roofs A,B and C and THP completed the initial punch review with KBR and HC for these roofs. THP needs to review the final fibertite’s punch review for the final confirmation.
11/06/24- HP approved pay App No.4 from KBR and send it to HC for the final review
11/07/24- THP send out the Bulletin No.2 to KBR for Pricing.
11/15/24- THP had a visit to KBR’s warehouse to confirm the walk mat materials purchased by KBR.
12/03/24- KBR send the Pricing for Bulletin No.2 to THP for review.
12/05/24- THP requested the breakdown of cost and resubmitting the CO No.2 from KBR.
12/09/24- HP approved pay App No.5 from KBR and send it to HC for the final review.
12/10/24- KBR sent the breakdown of costs for CO#1 for THP’s review.
12/11/24 – THP forwarded breakdown of cost and backup review to Hamilton County.
12/18/24 – County and THP approved KBR pricing. Final change order to be coordinated with safety upgrade work.
01/29/25 – County sent KBR AIA Change Order No. 2 for signature.
01/30/25 – Project status – Roof installed. Change order No. 2 waiting for execution and weather to install new safety platforms, RTU removal, and roof reconfiguration.
02/04/25 – Change Order No. 2 executed.
03/06/25 – Lightning protection work is complete, KBR is still waiting on the certification letter from Maxwell.
03/21/25 – THP reviewed the shop drawings for the platform and sent it back with comments to KBR. KBR Believed it should be roughly 7-8 weeks from getting them on-site for install.
03/26/25 – THP/LJB’s proposal for roof in progress.
04/24/25 – LJB provided updated proposal on 4/17/25. THP sent final proposal to County for review.
05/21/25- KBR confirmed that fabrication for the ladder and platforms is completed and they are at their site ready for deliver and install. KBR are getting themselves put on the schedule and will follow up with THP once they have a date.
06/18/25 – KBR will begin roof work on 07/07, including installation of ladders, platforms, and fall arrest systems on the ladders. Remaining work includes installing walk mats, replacing drain rings and cages on all roofs, and capping abandoned curbs on Roof C. KBR anticipates completing the Change Order #2 (CO#2) work within approximately two weeks from the start date.
06/24/25 – KBR submitted the lightning protection certification for THP’s review.
07/11/25- KBR completed 90% of the CO#2 works including installing walk mat on roofs, platform installation on both roof C and E, installing drain ring & strainers and caping abounded curb.
07/30/25 – KBR will provide CO#3 and CO#4 for remaining work including safety railing on roof D and E, Hatch guard, stair tower rental and all the work regarding removing old davits and installing new fall protection system. (the fall protection system work will be based on LJB design)

HC Juvenile Justice Center Davit Upgrade (F027):
THP PM: Rycca Thacker, John Millar
03/27/25 – County identified a number of safety concerns with roof operations. THP and the County had follow up meetings.
04/17/25 – THP received proposal from LJB for design of the safety davit system.
04/18/25 – THP published SOSS for County review.
05/07/25 – SOSS approved.
05/29/25 – THP coordinating design with LJB. Initial design discussions/meetings complete and formal SD to be submitted mid-June.
06/23/25 – LJB sent the preliminary drawings for the fall arrest system upgrade to THP. The design will be discussed with HC on 06/26. If there are no major changes, the final design is expected to be completed by the end of July.
07/11/25 – LJB sent the 90% drawings set and it was approved by THP and HC. LJB planning to provide the final design by August first.
08/22/25 – KBR completed remaining work on the ladder at roof F.
08/27/25- THP requested an updated cost estimate from KBR for CO#4 with a labor and material breakdown on the few Items including ( Safety Railing Roof D and Roof E, Hatch Guard, Flash New Davits and New Fall Protection) per county’s request and deducting the Terrecon cost from the list since that will be through THP.
08/27/25 – LJB send final review documents to THP. THP to review then forward to the team.
09/10/25- Terracon conducted a site survey to inspect the platform and ladder on roofs. They have noted that (2) attachments bolts on the top of the ladder at Roof E were loose. THP has reached out to KBR regarding this matter, and they are planning to have the steel crew back on site to complete the work.
09/19/25- LJB adjusted few items in their drawings per THP request and THP has sent the final drawings to KBR and HC for their review. KBR is waiting on CO#4 approval to start the rest of the work.
09/26/25 – County requested a breakdown of CO #4 work to be completed with railing material costs provided by the County.
10/09/25 – KBR provided updated pricing for CO #4 with the County providing the railings.
10/10/25 – THP reviewed pricing and noted one item to update.
10/16/25 – KBR provided an updated CO #4 breakdown pricing.
10/16/25 – THP approved pricing.
10/20/25 – County sent fully executed CO #4 to all parties.
10/26/25 – County received pricing for railings for CO #4 work with KBR. THP to review once cut sheets and product information is provided.
12/10/25 – KBR had the crane on site for delivering the roof railing on Friday 12/5 and were planning to complete the work the week of 12/8 weather depending. The work will include the installation of the railing at the roof edge on roof D and E and railing around the hatch at roof D.
01/08/26 – The railing installation on both roof has been completed and installed safety railing at roof hatch needs to be replaced. KBR and LJB will begin the installation of the new fall arrest system at the beginning of march and all remaining work and miscellaneous items will be completed at that time. THP will schedule a meeting before starting the work on March to go over all items with KBR and LJB.
02/23/26: KBR has installed the new railing around the roof hatch and planning to start the work on March 2nd with LJB for installation new fall arrest system. The Crane will be on site on 03/2/26 and contractors are estimating the work will be completed by end of the March.
03/18/26: THP has reviewed the new design layout with LJB, KBR and HC and approved the layout for Roof E, and then the partial section of roof D on 3/20. The rest will be reviewed by THP on the first week of April.
04/30/26: Project summary – LJB and KBR have installed 95% of the fall arrest system. At roof D an assembly needed to be adjusted and fall arrest for the ladder system has a back ordered component. Contractor anticipates finishing end of May.
09/24/26 – Work reported to be complete. THP and KBR coordinating final punch review by Fibertite and Terracon.
10/07/26 – THP completed formal punch trip with KBR. Missing gates noted.
10/29/26 – KBR ordered gates.

2020 – Roof Replacement (F034) and Davit Upgrade (F027) Read More »

JC – Fire Alarm System Upgrades

PM: Matt Butz, Mike Barth
08/26/21 – HCFD send signed PO and SOSS to TEI. TEI contacts HCFD PM to set up design kick off meeting, date is pending.
10/26/21 – TEI has began the design process, setting up drawings and using archive drawings to show on demolition plans. Once kickoff meeting occurs, the field verification process will occur and the project will proceed.
12/13/21 – TEI develops demolition drawings from existing building plans from archives, and conducts design kick-off meeting with HCFD and building manager.  Next step is to schedule field work to document/confirm existing conditions.  TEI to work with building manager on schedule.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks returned and employees badges approved.  TEI and HCFD to schedule the field work with building managers.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 07/04/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project out for bids.  Bids open 09/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives approved contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick off the construction.
02/23/23 – Pre construction meeting completed.  JCI developing submittal documents.
03/29/23 – TEI speaks with JCI about status of Submittal Package.  JCI states that the submittals are tracking about 2-3 weeks behind the 800 Broadway submittals (anticipated receipt of submittals = late April to Mid-May).
04/27/23 – JCI indicates that the submittals for the JC shall be sent to DK by mid May.  Still tracking same as indicated last month.  TEI to review and turn around upon receipt of submittals.
05/23/23 – JCI indicated that the submittals will be sent to DK this week.   DK has not received to date.
06/28/23 – DK has not sent submittals to TEI for review to date.  Submittals will be reviewed by TEI upon receipt.
07/26/23 – TEI receives submittals for project.   Reviewing and will return.  Pre construction meeting (along with 800) is scheduled for 7/28.
08/24/23 – TEI, HCFD and DK meet (at 800) to discuss project.  work in JC to mobilize late Q1/early Q2 of 2024.  Matt Butz asks about the BDA equipment at the JC, and how quickly it can be installed (issues with the existing system).  TEI reaches out to DK to request data about schedule.
09/26/23 – TEI reaches out to DK for CO cost to install the ERRS (BDA) ASAP versus waiting until the new JCI system is in the building.  MobilCOMM states no issues with the plan.   DK sending electrician to site to confirm existing system is compatible and will issue CO accordingly.  TEI stresses with Gleason that time is of the essence.
10/26/23 – MobilCOMM has ordered to BDA for the JC and will schedule the installation upon receipt of the equipment.  DK still on schedule to mobilize as previously identified.
12/06/23 – TEI asks DK to find status of BDA – should be at MobilCom per previous schedule.  TEI will follow up with DK.
01/30/24 – Installation of BDA pending the background checks from MobileComm
02/28/24 – MobileCOMM cleared to work in building.  TEI contacts DK and tells them that the install must be scheduled and we need to have install date by beginning of February partner meeting.
03/27/24 – MobilComm and DK to mobilize 4/1/24 to install and get the BDA installed ASAP.
04/24/24 – Work has began on the BDA upgrades,  most work in basement complete and 1st floor is next.   All areas with minimal/no coverage were addressed first.
05/29/24 – BDA installed and turned on in the lower levels of both buildings.   Finalizing the install of the BDA in the next week or two.  Started the install of the backbone for the JCI fire alarm system.
06/26/24 – BDA installed and complete. DK and Biederman working out PO issues to get permitted. Panels installed and backbone conduits being routed through the building. DK facing additional staffing issues.
07/24/24 – Staffing issues continue. Permits for BDA applied for – pending City approval. Work continues on backbone. DK developing means and methods and durations of timing needed in all inmate areas to coordinate with HCSO. JCI finalizing CO pricing for deluge system, but Jay at JCI tells TEI that the relays needed for the CO are currently on backorder and the scheduled ship date is 01/31/2038 (and this is NOT a typo!). TEI states this is NOT acceptable!
08/28/24 – Project in construction. Permits for BDA obtained, inspections completed (passed) and MobilComm to send approval paperwork to HamCo once received.
09/25/24 – Construction progressing in the building.
10/30/24 – Construction progressing in the building following behind the cell lock project.
12/11/24 – DK indicates that the backbone installation is nearly complete and that they will need to have JCI and Notifier at the next const meeting (01/08/25) for coordination of cross trip.
01/29/25 – Cross trip installed and working. DK to have JCI at next project meeting to review schedule and Deluge system (controlled on all floors).
02/26/25 – JCI, HCFD, and TEI meet to discuss deluge system on site. TEI sent JCI record dwgs of sprinkler system in building. Construction on-going.
03/26/25 – JCI has all parts for Deluge upgrade to DK. The Deluge upgrade to begin early April.
04/23/25 – Deluge work has started. Working in unit 1 of north tower, all floors. Then Unit 2 North, and so on.
05/28/25 – Side 2 of the north building to be completed in the next 2 weeks.
06/25/25 – Issues with the Deluge valves and water leaks. TTC attends FA meeting and evaluates the valves and to send in recommendations.
07/30/25 – Construction on the project progressing with availability of spaces. DEG submits memo with recommendations.
07/31/25 – TTC issued memo on the deluge valve issue in the North building. We will talk more about this after the meeting today.
08/27/25 – Construction progressing. Moving to south tower beginning of September.
09/24/25 – Construction progress continues. DK following the other projects as pods are made available.
10/29/25 – Construction progress ongoing. Anticipated completion April/May of 2026
12/10/25 – Construction progress ongoing. Change order issued at the OEC meeting today. JCI finalizing engineering change for the building department.
01/28/26 – All work (original Scope) in North tower near complete. JCI to submit documents to city by end of Janaury. Project ongoing. Anticipated completion Late April/Early May 2026.
02/25/26 – Project ongoing. Deluge work is being completed this week and next.
03/25/26 – Project ongoing.
04/29/26 – Pretest completed on 04/28 throughout both buildings. Consult with inspector to be scheduled to outline inspection process.
07/29/26 – 2 months of inspections completed and the CFD and CBD have approved all of the installations. DEG has assembled the punchlist for the project and issued to the EC. Most items were discussed at time of inspection and punchlist walk – and we anticipate that they have been completed. Training for building staff was 07/28/26.
07/30/26 – Electric issues at panel and distribution at fire pit shorted out. Wire ran in lighting conduit and DK has to do an emergency repair for the job. MB to investigate and report back.
08/26/26 – Project complete pending final IBI and Elevator inspections for JCI to sign off on permit. Scheduled for Week of 08/31. Closeouts requested from DK.
09/23/26 – All inspections except IBI complete. IBI pending renewal paperwork. Project pending final closeout.
10/28/26 – IBI final inspection passed and complete. Project pending closeout documents.

JC – Fire Alarm System Upgrades Read More »

800 – Fire Alarm System Upgrade

PM: Matt Butz, Mike Barth
08/26/21 – HCFD sends TEI signed PO and SOSS. TEI contacts HCFD PM to schedule design kick off meeting. Date pending.
10/26/21 – TEI has begun the design process by setting up the CAD file drawings and using archive data to begin the demolition drawings. Once kick off meeting occurs, the field investigation will be scheduled and the design will proceed.
12/13/21 – TEI has taken the as-build documents to create demolition drawings.  Next step is to field verify/document the existing conditions.  Field work to be scheduled with building manager.  design kick off meeting occurred with HCFD and building manager.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks approved and badges approved.   TEI and HCFD to schedule field work with building manager.  Note – there was an issues with the existing Simplex FA System panel (dialer power supply) and JCI sent a quote for a complete panel replacement.   TEI and JCI investigating a more cost effective fix until a time when the system is replaced.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 7/4/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project bidding.   Bids Due 9/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick of construction.
02/23/23 – Preconstruction meeting completed.  JCI developing submittals.
03/29/23 – TEI speaks with JCI about submittal package.   JCI estimates that the submittals for the 800 building will be completed and turned over to DK in the next 2-3 weeks (Mid April-ish).
04/27/23 – TEI follows up with JCI, submittals nearly complete.   JCI indicated that the submittal package should be sent to DK on or before 05/01/23.  TEI to review upon receipt.
05/23/23 – TEI receives, reviews, and returns submittals with minimal marks, asks for schedule from DK for commencement of work.  JC sends photo of material that was shipped to DK for project.  TEI to schedule pre-construction meeting first week in June.
06/28/23 – TEI requests schedule again from DK.  Upon receipt of schedule, construction to commence pending procurement of materials.
07/26/23 – construction kickoff meeting scheduled for 7/28.
08/24/23 – DK to mobilize to project site and start construction on 9/5/23.  Josh Querry from DK to PM/site Super the project.
09/26/23 – Construction has began.  DK installing backbone of the system.
10/26/23 – Backbone installation complete.  DK has started on upper floors and at the construction meeting on 10/25/23 stated that 18, 17, 16 and part of 15 is complete.  DK also working in basement and installing devices there.   Rooms are being identified that require either  LEADs clearance or special access.  DK to schedule work in these areas during day shift.
12/06/23 – Construction progressing.  Working on installs in LB, B 1,2,3,3M.  LB and B ready for change over.  2 will be by Christmas.  1, 3 and 3M will be nearly complete if not complete by Jan 1.
01/30/24 – DK submits CO request for portion of work changes.  The beam detector CO still pending.
02/28/24 – Beam detector CO still pending.
03/27/24 – Beam detector for 3 beam detectors received ($41k).  HCFD to determine if it is accepted or not.  Smoke purge CO under review.
04/24/24 – Smoke purge CO verbally approved to DK at const meeting.  Beam detector CO not approved at the meeting.  Work continues through the building.
05/29/24 – The smoke purge CO has been approved and sent to DK.  DK and JCI working on Drawing updates and will progress to install as soon as the revised install drawings from JCI complete.  JCI indicated that all parts are readily available.
06/26/24 – No updates from JCI on this project.
07/24/24 – DK same staffing issues – staff being moved from 800 to JC and back. CO verbally approved (HCFD waiting on PO increase) for formal approval.
08/28/24 – JCI submits revised drawings wot city for approval. JCI states that there is no way (on existing system) to repair the amplifier card for the upper floors. TEI and HCFD directed JCI that the New system shall be turned on immediately and use the new devices for audio on the upper floors.
09/25/24 – TEI, DK and HCFD meet with inspector (Jeff Hinkel) to discuss inspection process and 3 and 3M. Inspections will proceed similar to CH and TPC, where we will have multiple teams and multiple inspections. Looking at options for the 3 and 3M area – inspector sympathized with the task and we developed possible workable solutions.
10/30/24 – The switchover of floors to the new system in the tower (top down) has commenced. Anticipate tower work to be completed in approx 2-3 weeks. then move to low rise floors. TEI recommends scheduling inspection of tower floors once tower complete.
12/11/24 – HCFD, CFD, CBD, JCI, DK and TEI participate in the first acceptance inspection at the building. Floors 7-18 were inspected and accepted, with minor tweaks. Construction continues, with the crews starting on 5th floor week of 12/16.
01/29/25 – Crews working on 2 right now. Next inspection scheduled for 02/12/25 at 5:00 PM. Planning for inspections of floors 2-6.
02/26/25 – Inspections for 2-6 went well. First floor complete and working in basement. Will be ready for next inspection in about a month. Then there will be the Flow/Tamper inspections, then AHU/smoke control inspections, then Elevators. Need resolution of elevator issues for the non-functioning elevators.
03/26/25 – Inspection for SB, B and 1 scheduled for 04/16/25. The tamper/flow inspection to be scheduled 2-3 weeks after the inspection on the 16th.
04/23/25 – All floors inspected for smokes, pulls, heats and AVs. Door holders were inspected. Tamper/flows inspection next – to be scheduled TBD.
05/28/25 – Tamper flow inspection occured and passed. Next is air handlers. Inspector allows the magna-helic results from the pre-test to be written on the covers for the inspection night.
06/25/25 – Installation nearing completion. Elevtor and Air Handler inspections scheduled for 07/16/2025
07/30/25 – Freight elevator and final air handler inspections scheduled for 07/31/25 at 0700. This is final building and fire and elevator inspections pending no issues during the inspections.
07/31/25 – Early morning inspection went well this morning. Three small electrical items are required to be updated to get the AHU-45 and Smoke Fans 14 & 15 did not start. The elevators are approved and the Chief Inspector approved the current smoke detector layout.
08/27/25 – follow up visits with CFD and CBD to inspect and approve the repairs made by HC. All inspections completed (other than IBI). IBI to be scheduled once the Bldg Dept and FD upload all their paperwork.
09/24/25 – All inspections passed. HCFD and DEG to schedule final punchlist for project.
10/29/25 – Punchlist completed and issued punchlist to DK.
12/10/25 – project tied to Justice Center PO. Closeout pending completion of JC FA project.
01/28/26 – Project tied to the JC FA PO, Closeout pending completion of JC FA project. Anticipated completion April/May of 2026.
02/25/26 – No Updates.
03/25/26 – No Updates.
04/29/26 – No Updates.
06/23/26 – DEG directs DK to assemble and submit closeout documents for 800 building.
07/29/26 – Project completion pending closeout documents.
08/26/26 – Project complete pending closeout documents.
09/23/26 – Project complete pending closeout documents.
10/28/26 – Project complete pending closeout documents.

800 – Fire Alarm System Upgrade Read More »

Archibus

11/30/19 – Worked with County to add IGS accounts for gas accounts.06/24/20 – Lots of work on Archibus this month. We’ve trained Sharon and Ryan to help with bill entry. Added the missing constellation bills to 264, 1033, 2611 accounts from the CCAO change. Fixed a myriad of IGS issues from missing accounts and bills. Reconciled the JC account from a missing gas bill in Nov 2019. Fixed 250 WHT from estimated electric bills that showed up in May 2020 for March and April 2020. Provided the regular monthly reports for Bert and Tim.
12/27/19 – Finalized bills and updated monthly reports.
01/31/20 – Finalized bills and updated monthly reports. CH gas has some issues.
02/28/20 – Finalized bills and updated monthly reports.
03/31/20 – TTC working more on Monthly reports and Archibus due to Covid. final reports sent to Bert late.
04/30/20 – TTC continues to work on Archibus with Bracken due to Covid. Final reports were missing data, ttc updated and re-sent reports to bw.
05/27/20 – TTC working on Archibus approval all month. TTC and BDS working on CH gas issues for Dec 2019 and Feb 2020, data and bills need to be updated.
06/24/20 – Archibus was updated this month. We spent time getting up to speed on the new updates, we spent a good deal of time manually creating header blocks for the Bert monthly reports due the Archibus update and we trained some additional people in Archibus usage. A&D and 250 WHT have Covid related billing issues and Comm Center was found to get missing IGS gas bills entered.
07/29/20 – The DOC addin is not online yet so we updated headers manually this month. The A&D was finally reconciled so we will need to input June bill and then unarchive April and May so we can fix these bills. The good news is that the County is getting money back. Courthouse IGS and Duke IT rate bills are goofy but we will figure them out.
08/26/20 – All estimated bills are corrected. Tim contacted TEI about adding the SPCA to the Archibus list of buildings.
09/18/20 – TTE owes county SOSS for SPCA, Courthouse EDI bill messed up again. AD building was estimated.
10/28/20 – Archibus is up to date. 222 Water estimated, 230 water is estimated, Courthouse Water is estimated, JC water is estimated, 800 gas estimated, 2611 Water missing, 2611, 2377, 264 IGS gas August missing. Bert monthly reports are ready for review.
12/10/20 – Archibus reports are being sent out on a monthly basis as usual. The Courthouse gas is being switched to the FT account and should start coming in on the regular IGS bills. several water and gas accounts are estimated presumably because of Covid. This month’s bills are caught up in the queue, several water bills are estimated.
12/28/20 – Monthly Reports sent to Bert.
01/26/21 – Monthly Reports are ready minus the IGS bills for November.
02/24/21 – CH gas bills not right end of 2020, working on EDI tax roll ups, approving regular bills.
03/25/21 – Most EDI bills missing this month. IGS and Duke gas bills are a mess, overbilled in November 2020, TTE to download Animal Shelter bills from Myduke and then enter them as part of last year SOSS.
04/29/21 – 2021 SOSS approved. ThermalTech entered all Animal Shelter bills through February. We are catching up on monthly bills.
05/26/21 – All bills for the last two months and Monthly Reports resolved except the Courthouse gas bill from October.
06/25/21 – This month has had a lot of Archibus activity. The EDI process has been in testing, TTE working on $15,000 utility credit from Duke and IGS finally resolved and the Crime Lab bills were added, checked, and approved in Archibus.
07/28/21 – Meeting with County went well. ThermalTech ready to start entering Water and IGS bills.
08/25/21 – Archibus Water and IGS bills entered and uploaded by ThermalTech this month. TEI uploaded all-electric and gas bills for all accounts this month too. Monthly reports already complete.
09/30/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report emails.
10/29/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report sent late by TTC.
11/30/21 – Electric, gas, and water bills updated. Bills were downloaded and uploaded to Archibus by TEI for Duke elec & gas. Monthly report sent by TTC.
01/22/22 – We have been working on the EDI integration with Duke this month and now have weekly meetings on the new EDI process. 29 bills are missing from December at this time and we are having a hard time getting them reimported from Duke. Duke sent a new text file to BRG for import, I don’t know if that is going to work. TEI stands ready to enter them manually if the import does not work.
02/25/22 – Lots of work on EDI bills in new format, fixing and entering new bills.
03/31/22 – meeting with Duke and County bi-weekly for new EDI process. Attended EDI training with County.
04/28/22 – New EDI bills are coming in and they are wrong; too many line items, usage is doubled and we can not access the Duke Portal. This was relayed to the Duke EDI team this morning during out bi-weekly meeting.
05/25/22 – Several Archibus and EDI meetings trying to resolve new billing issues. it’s better but not fixed. TEI manually updating all bills that come in at this time.
07/27/22 – We are still working with Duke trying to EDI billing resolved with BRG and Duke EDI and currently we are still entering most bills manually. After they are approved we are updating almost all lines, and we are entering water bills directly.
10/26/22 – Archibus bills updated as much as possible and Duke billing issues sent to Duke and IGS, big meeting next Monday.
02/22/23 – Archibus being updated monthly and TEI is fixing almost all EDI inputs from Duke.
03/30/23 – Working on final EDI resolution for double counting usages, fixing CH gas and electric bills, Record Center. Working with BRG to fix EDI input adn stop queueing issues. Dane and 111 will not work for EDI.
04/26/23 – BRG updated the macro for importing usage from EDI and the double usage has been eliminated. We have as a group decide not to import the EDI data from small accounts that have combined gas and electric. ThermalTech will enter these directly.
05/21/23 – Many problems still exist in Archibus from Duke bills or EDI entries from Duke but we are down to handling them on 3 or 4 projects. CH, 5035, 250 and Animal Shelter.
06/28/23 – Most problems have been worked out with the module. EDI billing is starting to smooth out. BRG requested to fix new billing lines last month. Combination electric and gas accounts will have to entered manually.
07/26/23 – Met with BRG and County this month to discuss Archibus updates and new version rollup.
10/25/23 – SPHQ and 5035 gas bills reconciled and records unarchived for approval. TTC approved modifying 18 months of SPHQ bills back to April 2022. 5035 corrected bill not as easy to approve, TTC sent question to Duke about rebill estimates. David Hiser is processing a billing records check for us.
01/31/24 – Archibus updates continue to be made on billing and modules. We are still waiting on final updated gas bills for IGS for 2023.
06/26/24 – Some bills still have issues but we are 99% back on track with Duke billings.
07/24/24- No major reported issues this month in billing.
09/24/24 – Duke EDI issues resolved, several bills have late charges and under billed, we continue to roll with the punches.
01/28/25 – Billing errors are begin reconciled with Duke and Dynegy and IGS. Monthly reports are being sent on schedule with specific data.
05/28/25 – Bill entry continues and errors are reducing, I dare say we are almost back to normal. Except JC reported no gas usage in April, Duke and IGS have been contacted.
06/25/25 – Bill entry continues and we are working out problems with EDI. The JC has an errant gas meter reading.
07/30/25 – Bill review going well. Dynegy and Duke have an issue on a bill and Hillcrest has an gas cost recovery issue.
08/26/25 – Dynegy cost misses being worked on with Duke and Dynegy. Duke received approval to recovery missing Gas Recovery cost for a large part of 2025. TTE tracking and predicting cost recovery for HamCo.
09/24/25 – JN asked to update the Siren procedures to start in March 2026.
10/29/25 – Siren PM was rescheduled to March.
12/12/25 – 111 Archibus entered in DEV and ready for review. DEG working on 1701.
01/25/26 – 111 submitted for review on Jan 26. 1701 will be started once 111 feedback is returned and worked on until complete. New access to past PM procedures will help greatly in crafting the new PM’s.
02/18/26 – 111 submitted. 1701 submitted for review and we met twice on conforming the 1701 PM’s into County standard format. Vogt working on updating the worksheet template for this and future project.
02/20/26 – Duke has agreed to separate and create new accounts for 111, 525, 1701 locations. This will eliminate the EDI issues with BRG. We are not sure when this will happen.
02/25/26 – Commodity usage getting double in 2026 again just like 2025, probably a BRG fix.
03/25/26 – DEG & BRG working on Archibus billing issues with Duke. 111, 525, and 1701 bills have been separated into electric and gas bills. We are working on organizing and getting into EDI the data and processed through BRG.
04/29/26 – We are working on March bills now for reports. Hillcrest access was granted this month and Duke fixed access to the newly separated bills for 111, 525, and 1701. Those should be entered soon. We will verify.
05/27/26 – Working on revised 1701 PM list with Robert and Tim. All other reports submitted on scheduled. Good month for billings.
06/25/26 – DEG to update1701 PM import, working with Tim on fixing bad data import. DEG to verify more equipment in field, need more time at building and with BMS to get additional data.
08/26/26 – 1701 Import template sent to County for final review. Working on Hillcrest export for Hillcrest start of work.
10/26/26 – 1701 has been finalized with edits and tweaks along the way. It should be final, final, final, final now.

Archibus Read More »

Champlin – General Services

02/14/19 – County invites Champlin for MSA agreement
02/21/19 – County sent MSA Contract to Champlin
03/13/19 – County sent revised MSA Contract to Champlin
03/18/19 – Champlin sent proposed revisions to MSA Contract
03/29/19 – County sent final MSA Contract
05/23/19 – General Services P.O. approved
05/30/19 – Kru and Mike from Champlin attended Monthly Partners Meeting
06/03/09 – Bert requests code interpretation for safe room locks on certain areas within the 911 Communications Center.
06/07/19 – Champlin provides 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/14/19 – Champlin provides further clarifications on 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/27/19 – Kru from Champlin attended Monthly Partners Meeting
07/31/19 – Christy from Champlin attended Monthly Partners Meeting.
08/29/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
09/26/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
10/30/19 – Champlin visited Auto Title and currently working on space layout.
12/12/20 – Mike and Sam from Champlin attended Monthly Partners Meeting and Updated website
01/02/20 – Bert reached out to Mike and Kru for CAB signage replacement
01/10/20 – Kru and Sam from Champlin visit Taft Center for potential Alley Door Upgrade
01/24/20 – Champlin reached out to multiple vendors for information on existing conditions
01/28/20 – Champlin received CAD files of CAB elevations from THP.
01/30/20 – Mike and Sam attended Monthly Partners Meeting and updated website.
01/30/20 – CAB signage project to be added to an existing facade repair job currently active at the CAB
02/04/20 – Signage drawings sent to THP to give to AFR
01/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
02/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
03/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
04/08/21 – Sent County options for casework refresh.
04/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
05/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
06/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
07/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
08/26/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
10/25/21 – Final Facilities kitchenette drawings sent to County for review.
10/28/21 – Sam Hofmann attend monthly partner meeting.
12/03/21 – SOSS approved for Design and consulting services.
12/14/21- Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
01/26/21 – Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
02/09/22 – Met with County, Triton, Thermaltech and Champlin to review scope of TPC 6th Floor ceiling replacement.
03/31/22 – Sam Hofmann attends Monthly Partner Meeting.
04/28/22 – Mike Murphy attends Monthly Partner Meeting.
05/26/22 – Mike Murphy and Sam Hofmann attends Monthly Partner Meeting.
06/30/22 – Sam Hofmann attends Monthly Partner Meeting.
07/28/22 – Mike Murphy attends Monthly Partner Meeting
08/25/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/15/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
01/26/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
02/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
03/30/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
04/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
05/25/23 – Sam Hofmann attends Monthly Partner Meeting
06/29/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
07/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
08/31/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
09/28/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
10/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Evac plans for TPC 10th Floor returned . Champlin to correct 250 WHT plans.

Champlin – General Services Read More »

Master Planning 2019

04/09/19 – Champlin receives request for Master Planning proposal
06/24/19 – Master Planning Kick-Off meeting held at Courthouse
07/02/19 – Champlin sends initial Master Planning Form to County Facilities
07/22/19 – Champlin sends revised Master Planning Form to County Facilities
08/05/19 – Master Planning Form and Master Planning Department Meetings reviewed at meeting held at Courthouse with County Facilities
08/20/19 – Champlin met with Moira Weir and Michael Patton, JFS
08/20/19 – Champlin met with Todd Lang, County Engineer
08/22/19 – Champlin met with Greg Brush, Clerk of Courts
08/23/19 – Champlin met with Dave Pittinger, Recorder
08/27/19 – Champlin met with Michael Lonneman, Treasurer
08/27/19 – Champlin met with Ray Faller, Public Defender
08/29/19 – Champlin met with Adult Probation
08/30/19 – Champlin met with Frank Spatero & Sarah Irwin, HR
09/03/19 – Champlin met with Trina Jackson, Re-Entry
09/03/19 – Champlin met with Paula Drake, Auditor
09/05/19 – Champlin met with James Noyes, Planning & Development
09/05/19 – Champlin met with John Hetzel & Dale Wittmer, Sheriff (800 Broadway & JFS)
09/06/19 – Champlin met with Carla Guenther & Steve Rokich, Juvenile Court
09/06/19 – Champlin met with Lisa Gorrasi & Bev Davis, Domestic Relations Court
09/12/19 – Juvenile Courts tour as follow up to 09/06 meeting
09/12/19 – Champlin met with Joann Cramer, Purchasing
09/13/19 – Champlin met with John Hoffman, Telecommunications
10/25/19 – Master Plan Draft Presentation and Review with Master Planning committee
11/12/19 – Champlin met with Bert Watts and Tony Matre to discuss Master Plan Draft.
11/26/19 – Champlin submitted Master Plan Document. Financial review section still under review.
12/08/19 – Champlin received comments on the 11/26 document from Bert Watts.
12/13/19 – Champlin submitted final version of Masterplan to County
02/20/20 – Champlin received final comments. Updated master plan accordingly
05/12/20 – Final draft submitted to Bert.

Master Planning 2019 Read More »

Energy Manager

04/03/18 – TTC updated the Duke Proposed Rate increase in the Energy Outlook section and incorporated all of RWL notes into the Rev 2 file and created Rev 3 and sent to Ralph and Tony for approval.
04/04/18 – Rev 3 of the 2017 Energy Report is complete. The editable Word file was sent to Ralph for approval by Judi prior to submission to the BOCC. 04/26/18 – Ralph reported that the final report is in the editing stage and he will return as soon as Judi has markups.
07/04/18 – All Energy Impact Studies updated and sent to Bert and Tony for approval and use.
07/14/18 – All Energy Star submitted to the EPA for approval.
08/01/18 – All buildings Energy Star Reports are complete. We were able to get SPHQ certified this year with some good work with the EPA folks on how to model the building. 230, 800, Admin, A&D, Courthouse, 250 and SPHQ all qualified this year.
08/29/18 – Bracken review the Archibus versus Watchdog reports this week and there are some discrepancies we need to fix.
09/24/18 – Verified the first six months of 2018 in Watchdog and Archibus this month, started putting together the 2019 Energy Report format, pulled all the Watchdog data down into TEI excel forms. Grace, Bracken and Laurie have updated pretty much everything from Watchdog into our forms for future use.
10/23/18 – ThermalTech has created a excel file database to mimic Watchdog data given the vast changes in the Watchdog database format, I may recommend that we abandon the Energy Watchdog Website if its too complicated to use and doesn’t display the data as Tony likes – we will either give it to him manually or use the Archibus Watchdog Reports. We also reconciled the first six months of 2018 for all energy data and fixed a multitude of smaller errors and reports. It is very important to keep two database of the information to ensure Archibus reports the data use accurately so we can’t abandon the manual entry or Watchdog entirely in our opinion. I have also met with Bracken and Amy Crousey to cross train more TEI people on the energy manage duties to assist me in my efforts to keep up with the data.
11/29/18 – We have started the 2018 Energy Report and are waiting on an updated SOSS for next years activities.
01/09/19 – Spoke with Tony and we are shooting for a draft report of the Energy Report to Ralph at the Ohio Energy Conference on Feb 19, 2019. Final report due in March 2019.
01/22/19 – TTC and AEC working on final report, requested curtailment from the County for report.
02/28/19 – TEI attended the 23rd annual Ohio Energy Conference with Ralph and Tony Feb 19/20. TEI also send the draft Energy Report to Ralph to make edits for this year final report yesterday.
03/11/19 – Ralph returned comments to ThermalTech on final report updates. TTC received Ameresco M&V data for report. TTC to make final edits and finalize report for printing.
04/24/19 – TTC started final edit soon Energy Report for Ralph and Tony.
05/03/19 – Printed final copy for Facilities and dropped off downtown for distribution.
05/10/19 – Terry met with Ralph and picked up final round of comments, made edits, printed final and returned final set to Facilities this day.
06/18/19 – Talked to Tony and mgrs about getting access to data rooms for modify the energy star model for new data center requirements. Those field trips can probably happen next week for Ryan J.
06/27/19 – Worked with Duke to get 230 meter converted to remote reader. They installed new devices on 6/21/19 and sent a new bill showing non estimated readings yesterday to our accounts.
07/25/19 – TTE attended RFP for new energy savings last week. Collecting data and preparing for more work.
08/28/19 – This month had some billing issues for us to work one. Admin water was unusually high which we worked on with Tony and in the field at the meter. Data was sent to Tony with TTC review of existing conditions. Coroner Gas was zero creating several issues in Archibus and for billing. We contact David Hiser and discovered that Duke will rebill several accounts. We have decided to wait until the new bills are entered into Archibus to approve and correct these bills. However the usage was not out of historical norms.
09/19/19 – Coroners bills retroactively getting updated by Duke due to a metering issue. ThermalTech will update the Archibus database. Admin Water bill had high usage one month but apparently back down to previous usages. The low water meter side of the meter does not seem to be registering low water usage at this time based on TTC fieldwork.
09/25/19 – The CCAO is apparently changing gas suppliers in November 2019 to IGS. TTE preparing for these changes in Archibus and approving bills.
10/04/19 – TTC meets David Johnson on site and collects data from Courthouse PLC system. TEI prorates missing dates and months for CH steam usage from last three year. Amy populates the district heating plan in Energy Star. Courthouse only increases to 59. TTC informs County that the Courthouse will not qualify this year for the Energy Star Award.
10/11/19 – Ryan, Terry, and Amy are working on Energy Star submissions for 230, 800, Admin & A&D.
10/22/19 – Energy Star submission are uploaded to the EPA.
10/29/19 – Energy Star approvals come back for 230, 800 Broadway and A&D Building.
10/30/19 – Admin Building Estar is signed and uploaded.
12/12/19 – We are performing end of year work and preparing the Energy Report for next year.
01/24/20 – ThermalTech started compiling the worksheets for the Energy Report for Calendar Year 2019 in an effort to have a preliminary draft ready for OEC with Ralph and Tony. Archibus bills for IGS still getting entered and sorted out, Admin electric bills still need fixed for 2019 estimated and new meter data.
01/28/20 – Ralph sent TTE work on sharing Energy Star with the Green Umbrella people.
02/17/20 – Mark and Terry finish draft Energy Report for Tony and Ralph to review. Great progress this year and we are farther along then usual. Executive Summary write up and calculations not done yet.
02/18/20 – TTC, Ralph and Tony at the Ohio Energy Conference this year and several items will find their way into the Energy Report this year. This was a two day seminar on a variety of topics related to energy futures and managing energy and renewables in Cincinnati.
02/20/20 – Three main things to work on this week for Energy Report. (1) securing the rebate for the wrong tariff at the Courthouse, (2) Opting out of the Duke Energy EE riders and (3) exploring the Building Performance for Energy Star.
03/23/20 – Sent final copy Rev 5 to Ralph and Tony for final review.
03/24/20 – Got comments back from Ralph, picked up comments and send final Rev 6 to Ralph for approval.
03/25/20 – Got approval to print 16 color copies of the final Report and two thumbs up from Tony and Ralph. I’m going to send this one out to Phipps because we are not in the office to print this year.
03/30/20 – Submitted full package to Energy Star for Audit for Dec 2019 submission for Energy Star.
04/20/20 – 250 Energy Star Certification was sent to Ralph and Team. energy Reports were delivered by Phipps to the County.
05/27/20 – Updated Energy Star website with latest data from bills, trying to reconcile some bills from Duke and found the JC gas usage was very high last month but that turned out to be the exercising of the hot water boilers.
06/11/20 – Met JCI on site for Facility Explorer training and to work on 800 Chiller scheduling issues. Worked about half the day on site and finished updating the control book back at the office. Followed up with Tom and JCI about changes made onsite.
06/24/20 – Updated all the Watchdog reports at ThermalTech this month for electricity, gas, water. Found some accounting errors and fixed those. Updated links in the master worksheet and updated data for the 2020 Energy Report worksheets on our network. Work with 800 Broadway and chiller scheduling and water issues on the 16th floor. Followed up with Tom at 800 several times to verify chiller schedule is off on nights and weekends. After a couple of more tweaks, removing override and delete exception schedules, the chillers as of yesterday are off when unoccupied. JCI did not have the service contract in place yet.
07/29/20 – Performed some minor work this month on Energy Manager, check Ralph’s emails and read up on HB 6 for County implications. Duke finally gave the A&D an actual bill and reconciled the estimated months; county gets money back.
08/26/20 – Not a whole lot going on with Energy Management this month. TTE keeping up with RWL emails and reading reports. Energy Star webinars basically say to hold until October November for resubmissions.
09/18/20 – JC bills are coming in too high. TTE figured out this is related to a rider from Duke but it doesn’t make sense because the riders appear to be equal or less than last year. We created a worksheet to share with Duke of mind out why this is happening.
10/28/20 – Worked with Duke on the Opt-Out program this month and got all accounts over 200,000 kWh annually should be out of the program by November 1, 2020. TEI to confirm.
12/10/20 – Started end of year EM work and County issue request for several new PO for additional work. Energy Stars are started, TTC waiting to review.
12/30/20 – 2020 Energy Star SEP underway for TTC review.
01/26/21 – All Energy Star SEP are complete and printed. TTC to review and send to Ralph for signature. The deadline is February 10, 2021 for 2020 submissions.
02/24/21 – Bracken helping with 2020 Energy Report, made good progress this week, hopefully turn around on Friday.
03/25/21 – Ralph and Tony reviewing final report this month, they are submitting final edits today EOB.
04/29/21 – TTC assisted in edits on the BOCC Energy Report PowerPoint for Ralph.
05/26/21 – Still working on the refund from Duke or IGS on double billing back in October.
06/18/21 – Work Thursday and Friday creating 2022 budget estimates for Tony.
06/25/21 – Rebate from IGS on its way, just waiting on paperwork.
07/26/21 – Budget sheets created and sent to Tony Matre.
08/25/21 – Energy Star getting started for buildings.
12/15/21 – Five buildings certified for Energy Star in 2021. 230, 250, 800, Admin, and the A+D building.
01/25/22 – Utility bills are being verified for 2021 for the Energy Report 2021. TTC registered for the Ohio Energy Conference in person along with Tony and Ralph.
02/24/22 – Just got back from OEC with Bert, Tony, Ralph. Decarbonization.
03/31/22 – Final edits and calculations were completed yesterday, the final report will be sent to Tony and Ralph this week.
07/22/22 – Assisted Ralph with edits on PowerPoint for BOCC presentation. Sent final edits.
07/27/22 – Working with Tony on high water usage at 800, CH and 250. 250 building Duke bills are currently under investigation by Duke for billing issues with the Duke electric rates. The last three months may have to be corrected and rebilled.
10/26/22 – Energy Star for 2022 to be completed in early November.
01/24/23 – Courthouse electric bill was corrected March to December for new meter but billed on the wrong tariff. ThermalTech asked Duke to credit $26,000 and rebill the county.
02/22/23 – TTE working on Energy Report and calls for rough draft next week OEC.
05/01/23 – Report is complete and sent to Ralph for comments. Ralph texted back wrong version. TTC sent actual 2022 report.
05/21/23 – Tony asked for budgeting information for 2023 for T+D and Commodity.
06/28/23 – Received final edits from Ralph two weeks ago. Jimmy picked up half of the comments, TTC needs to pick up remainder.
07/26/23 – 2022 Hard copy reports delivered to Ralph today, quantity 15.
01/31/24 – 2023 Energy Report about 50% complete.
05/28/24 – Ralph received Impact Energy Award for Facilities on May 2, 2024.
06/26/24 – Forecasting for 2025 sent to Tony, including the Master work files.
07/24/24- Energy Star up to date, working on new City aggregation request from BW email.
10/30/24 – Energy Star work fieldwork complete. SEP sent to Tony for signature.
01/27/25 – Energy Report 2024 has been started. We are proposing a new coversheet to celebrate Mr. Bert Watts taking over the the Directorship of the Facilities Department. I will send to Tony and Bert for voting on the best new coversheet 🙂
04/23/25 – The first draft of the Energy Report is ready for Tony and Bert Review.
05/28/25 – Waiting on comments back from Tony and Bert on Energy Report.
06/25/25 – Waiting on comments from Bert before finalizing the Energy Report and printing.
08/26/25 – TTC updated and sent back for comment Final Energy Report in PDF. Hard copies have not been printed yet.
09/24/25 – No comments or updates on front end sections. Report has been submitted for final approval.
10/29/25 – Energy Star SEP are complete and sent to Tony for signatures.
12/12/25 – Five buildings received the Energy Star award for Hamilton County this year 250, 230, 800, A&D and TPC. Congratulations!
01/15/26 – Send Tony utility forecast to electric, gas and water for 2026. Had to take a stab at 111 and 1701 because they are not occupied.
01/19/26 – DEG going to self print two energy reports and send to Tony for 2025. We are still planning on created a 2025 report this year.
01/21/26 – TTC talked to Anthony about getting access to 1701 on our myduke1@davieseg.com account and hopefully to move 111 and 525 to the same account.
01/25/26 – SPHQ currently qualifies for Energy Star, but we have to verify the gas data is correct because for months Duke listed 0 usage. Once that is verified, we may certify this building early in 2026.
02/25/26 – 2025 utility reconciled in the DEG master files. The 2025 Energy Report is ready for first Draft Mode. the Performance Guarantee sections has been removed because Ameresco is not keeping that data any longer. TTC in printing two copies of the 2024 Energy Manager report to give to Tony Matre.
03/25/26 – 2025 Energy Report Draft ready for review.
04/29/26- Small changes requested on Energy Report, going to Tony soon.
05/27/26 – Report ready for TTC review then to Tony.
06/25/26 – Energy Star for Courthouse and SPHQ completed and sent in for approval. 525 and 1701 also have scores above 75 but must wait to be certified for occupancy and working equipment.
08/26/26 – We are closing work on the A&D building. Final bills mean we need to unarchive bills from March so we can fix them.
09/23/26 – Working on updated all locations for electrical, water, gas, and getting bills for new sites. We are also trying to navigate the changes on CCAO and IGS from coming in on the new Duke bills.
10/27/26 – TTC sent Energy Report to Tony in email per his request. We are working on integrating Hillcrest and 1701 into the future Energy Modules

Energy Manager Read More »

TEI – General Services

01/26/21 – Website updated, jquery issued addressed, 3 plugins updated, PHP security issued researched.
02/25/21 – Updated all proejcts for virtual partner meeting. Updated PW rates.
03/25/21 – TTC archived previous contract general service post to the TEI-General Services- Archive.
04/29/21 – Domain Name renewed with locking. Website updated. New scripts updated but TTC still to update more features this month after meeting.
05/26/21 – Updated the website this month, uploaded the PW rates for the month, udpated the legal wrap for Jill becoming the Interim Purchasing Director.
06/25/21 – Website updated, Partner meeting moved to Friday and it will be in person this month.
07/29/21 – Partner meeting. Website updated.
08/05/21 – Website down, TTC working repairs.
08/12/21 – Website restored through Doteasy, although WebFeat was also contacted.
08/16/21 – TTC backing up website locally in the hopes of moving to the WordPress.com servers, website down again. TTC working on restoring.
08/18/21 – TTC restored the website from my local backup and will start backing up monthly after the partner meeting. I need to address jquery degradation soon.
10/04/21 – Bert contacts TTC informs him the website is down again. TTC restores but the website keeps crashing again daily.
10/25/21 – TTC spends most of the day troubleshooting and restoring website backups, isolates issues to plugins on the website. I disabled all plugins and started enabling them one a time. Eventually got the website working, but the formatting was not quite right. I reached out to WebFeat to fix formatting by partner meeting.
10/28/21 – Website crashes again and TTC restores website. TTC and MCB attend Partner Meeting.
02/24/22 – Website updated. Scripts need to be updated soon. PW rates uploaded.
03/31/22 – Attended PM meeting.
04/28/22 – Attended PM meeting in person.
05/25/22 – Final Energy Report sent to Ralph for sharing with Holly and Jeff.
05/26/22 – Afternoon meeting. Website update last two days.
06/30/22 – Website updated for meeting.
07/28/22 – Website updated for meeting.
08/25/22 – Website updated for meeting.
09/29/22 – Website updated for meeting.
10/26/22 – Website plugin not working, TTC reached out to WebFeat for repairs, now we have a security issue in items, TTC reached out again with screenshots.
04/26/23 – Elementor plugin needs updated, TTC to do when after Partner Meeting.
12/15/23 – TTE to provide JC and CH CAD Background updates for Archibus. Start conversation with new partner for this work.
03/28/24 – Go Reds, Opening Day 2024. Barth wins Design Partner of the Month! Hahahaha.
04/12/24 – Webfeat finished updates on the HamCo website. Fixes Elementor, Jquery and other pending updates. Backs up website and gets rids of all update prompts.
04/20/24 – TTC creates access for Elevar on website.
07/17/24 – Website hacked. Support ticket submitted. Website repaired in two days and additional securities added.
07/24/24 – New website securities added and users edited with new system. Target Range not working, new support ticket submitted by TTC. I disabled GBBN access to website but left all their post intact.
08/01/24 – Updated Prevailing Wage Rates.
08/01/24 – Updated Prevailing Wage Rates.
09/01/24 – Updated Prevailing Wage Rates.
10/01/24 – Updated Prevailing Wage Rates.
11/01/24 – Updated Prevailing Wage Rates.
12/01/24 – Updated Prevailing Wage Rates.
01/01/25 – Updated Prevailing Wage Rates.
01/09/25 – Updated Prevailing Wage Front End document shared with everyone.
02/01/25 – Updated Prevailing Wage Rates.
03/01/25 – Updated Prevailing Wage Rates.
04/01/25 – Updated Prevailing Wage Rates.
05/01/25 – Updated Prevailing Wage Rates.
05/19/25 – Downloaded new MEP RFQ.
06/01/25 – Updated Prevailing Wage Rates.
07/31/25 – All Partners were instructed to reinforce the County requirements for construction including but not limited to no parking onsite, Badges displayed at all times, do not visit HC spaces outside of the project scope, no using county tools, no using county supplies.
12/11/15 – Website updated, PW rates updated and sent, mid-month updates being sent by Ted.
08/27/26 – New County Bid Advertisement & Front End Released
09/04/26 – Small Project Quotes packet updated by Kerry and Jill.
09/23/26 – DEG getting badges updated Q4 2026.
10/27/26 – Worked on creating a new category parent category to separate projects into Active, Closeout and Archived. Category is created, navigation is updated, but operation is not quite right yet.

TEI – General Services Read More »